BIHAR STATE POWER TRANSMISSION COMPANY LIMITED

Agenda No. /- 2017-18

Subject: - Agenda note of restoration of collapsed towers during cyclone in the month of May 2017.

1. During month of May 2017, following cases of tower collapse in BSPTCL system were observed

SL. Name of Line Date and time of Date of


no. damage Restoration/Charging
1. 132 kV BSF- Hatidah 15.05.2017/ Night 28.05.2017/ 01:00 Hrs
D/C Tr. Line
2. 132 kV Jamui- 15.05.2017/ Night 24.05.2017 at 18:15 Hrs
Sheikhpura S/C Tr.
Line
3. 132 kV BTPS- 15.05.2017/ Night 20.05.2017 at 20:00 Hrs
Naugachiya- Purnea [DD +6]
D/C Tr. Line
4. 132 kV Lakhisarai- 15.05.2017/ Night 21.05.2017 at 13:04 Hrs
Sultanganj Tr. Line
5. 220 kV Gaya (PG)- 17.05.2017 at 22.05.2017 at 17:52 Hrs
Dehri Tr. Line 16:02 Hrs
6. 132 kV Kahalgaon- 23.05.2017 at 26.05.2017 at 16:05 Hrs
Sultanganj Tr. Line 20:30 Hrs
7. 132 kV Jamui- 25.05.2017 29.05.2017 at 19:19 Hrs
Sheikhpura S/C Tr. at around 14:00 [Line charged on NO
Line Hrs LOAD]

2. The cyclonic storm has caused large scale damage in BSPTCL system. Total seven nos. of tower
collapsed in four transmission lines of BSPTCL on 15.05.2017 (Night), Two (2) nos. of tower on
17.05.2017 (evening) in one transmission line, one no. of tower on 23.05.2017 (evening/night),
25.05.2017, 19.06.2017 in one transmission line each. A large no. of trees uprooted & fallen on
the road/ vehicle causing massive damages in DISCOM system also.
3. In PGCIL many towers also collapsed in three no. of transmission lines of PGCIL system i.e. 400
kV Kodarma- Bokaro D/C line, 400 kV Kahalgaon (NTPC)- Farakka I & II & 765 kV Bodhgaya-
Banaras line. Certain S/Y equipments at PGCIL also damaged. e.g. 400 kV B-Ph LA of 200 MVA
ICT-II at Banka (PG), CVT & BPI of 400 kV BSF- Banka ckt-I.
4. As step of immediate restoration, three nos. of ERS in 132 KV Biharsharif – Hathidah
ckt-1 were erected after collapse of towers at location no. - 421, 422 & 423.
5. In case of power failure from alternate source, might have caused power
restriction/ TPF in nearby areas.
6. In other lines, keeping in view the emergency work, towers were erected by
arranging nearby available different agencies without inviting tender.
7. The expenditure incurred in restoration of above lines are as follows:
SL.
Name of Line Claimed Amount Name of Agency Nature of urgency
no.
M/s RS Shukla
construction and It affected power reliability at GSS
132 kV BSF- Hatidah D/C company Hathidah. Any power failure from
1 9,91,000
T/L (loc. No. 421,422,423) alternate source might have caused
M/s RS Infra projects pvt.
power restriction/ TPF in nearby areas.
Ltd.
It affected power reliability at GSS
Jamui and GSS Sheikhpura. Any power
132 kV Jamui- Sheikhpura M/s RS Infra projects pvt.
2 11,75,874/- failure from alternate source might
S/C T/L (loc. No. 54,55) Ltd.
have caused power restriction/ TPF in
nearby areas.
Due to collapse of tower power
availability at GSS Dehri on Sone
restricted to 140 MW against total
220 kV Gaya (PG)- Dehri
demand of 230 MW causing load
T/L M/S Bhojpur Engg works
3 20,00,000/- shedding of 132/33 kV GSSs. In a failure
(Dismantling of tower) pvt. ltd.
in alternate source ( Pusauli PG S/C old
(loc. No. 84, 85)
T/L ) might have caused TPF/Load
restriction at GSS Dehri on Sone and
connected 132/33 kV GSSs.
It affected power reliability at GSS
Jamui and GSS Sheikhpura. Any power
132 kV Jamui- Sheikhpura M/s KRR Transmission
4 5,80,581/- failure from alternate source might
S/C T/L (loc. No. 67) and project pvt. Ltd.
have caused power restriction/ TPF in
nearby areas.

It affected power reliability at GSS


132 kV BTPS- Naugachiya- Naugachiya and GSS Purnea. Any power
M/s KRR Transmission
5 Purnea D/C T/L (loc. No. 29,05,247/- failure from alternate source might
and project pvt. Ltd.
308 ) have caused power restriction/ TPF in
nearby areas.

It affected power reliability at GSS


132 kV Lakhisarai- Sultanganj and GSS Lakhisarai. Any
M/s KRR Transmission
6 Sultanganj D/C T/L 8,78,747/- power failure from alternate source
and project pvt. Ltd.
(loc. No. 77) might have caused power restriction/
TPF in nearby areas.

It affected power reliability at GSS


132 kV Kahalgaon- Sultanganj and GSS Kahalgaon. Any
M/s KRR Transmission
7 Sultanganj D/C T/L (loc. 7,78,410/- power failure from alternate source
and project pvt. Ltd.
No. 217) might have caused power restriction/
TPF in nearby areas.

8. 220 kV Muz(PG)- Hajipur 17,70,727 /- ABN

Total Rs. 11080586/-

This for kind information of The Board

(Kriti Kiran)
(S. B. Prasad) Company Secretary
Chief Engineer (Trans. O&M) BSPHCL
BSPTCL, Patna