Supply, Customization& Implementation of Online Automated Building Plan Scrutiny and
Approval System at various Development Authorities and UP Housing Board.
TECHNICAL BID
Critical Dates
SN Particulars Date Time
1
RFP for Online Building Plan Scrutiny and Approval System
Table of Contents
1 Section I: LETTER OF INVITATION..................................................................................................................... 6
7.12 Lucknow Development Authority’s right to vary Quantities at the Time of Award . ............................. 25
3
RFP for Online Building Plan Scrutiny and Approval System
8.3 MINIMUM SPECIFICATION FOR HOSTING THE APPLICATION FOR ONE DEVELOPMENT AUTHORITY ... 34
4
RFP for Online Building Plan Scrutiny and Approval System
For
Supply, Customization & Implementation of Online Automated Building Plan Scrutiny and
Approval System at various Development Authorities and UP Housing Board.
RFP bid are invited from experienced Service Providers, for “Supply, Customization &
Implementation of Online Automated Building Plan Scrutiny and Approval System at various
Development Authorities and UP Housing Board ” from 17/7/2016 to 1/8/2016 till 3.00 P.M. and RFP
bid shall be opened on the 3/8/2016. The details of submission of RFP bid are available in the RFP Bid
document uploaded on the website http://www.ldalucknow.co.in . The Authority reserves the right to
cancel any or all the RFP bid or annul the Bidding process without assigning any reason thereof.
5
RFP for Online Building Plan Scrutiny and Approval System
Lucknow Development Authority is a nodal agency with top ranking among all housing agencies of the
state. During the course of time Lucknow Development Authority has progressed with various landmarks
in the field of housing.
Besides normal housing projects board has diversified its activities to planning, designing, construction
and development of almost all types of urban development projects. Lucknow Development Authority
has planned and executed various projects for the development of health and education. It is also
handling new district headquarters projects with the execution of large number of schemes. Lucknow
Development Authority has attained capability of executing large residential colonies and townships.
at LDA office up to the date and time mentioned in the table below:-
Last date for submission 1st August 2016 till 3.00 P.M.
of RFP Bid’s
Website address http://www.ldalucknow.co.in
e-mail address ldacecivil@gmail.com
7
RFP for Online Building Plan Scrutiny and Approval System
8
RFP for Online Building Plan Scrutiny and Approval System
In order to allow prospective Bidders a reasonable time to take the amendment into account in
preparing their RFP bid, Lucknow Development Authority at its discretion, may extend the deadline for
the submission of RFP bid. Such extensions shall be posted / up-loaded on the RFP Bid website
www.ldalucknow.co.in
The RFP bid prepared by the Bidder shall comprise the following components:
RFP bid will comprise of:
a. Technical proposal submission form
b. Financial proposal submission form
The bid documents needs to be submitted physically until Date: - 1st August 2016 before 3.00 P.M.
Bid’s submitted later than the date and time will be not be accepted.
RFP bid submission date and time is over, the Bidder cannot submit his/ her Bid. Bidder has to submit
the RFP Bid well in advance considering the above factors. The Bidder only, will be held responsible if
his/ her RFP bid are not submitted in time due to any reasons.
11
RFP for Online Building Plan Scrutiny and Approval System
a. Supply, Customization and Implementation of Online Automated Building Plan Scrutiny and
Approval System at 27 Development Authorities.
b. To send an SMS to mobile phones of citizens/ Architects/ employees etc., reminding them about
payment/ status/ alerts/reminders etc. Thus the system should have the facility to send SMSs
wherever required e.g. site visit information, proposal status, payment reminders and any other
updates
c. Hosting the Application at 3rd party secured Data Center.
d. Provision of Manpower for operation of Project for a period of three year.
e. Maintenance of Application for a period of three year after Go-Live.
f. The system should have built in integration with and SMS gateway and the payment gateway for
payments of development charges and other demand generated by the system.
g. The bidder will be responsible for provision of Payment and SMS Gateway.
h. The system shall be integrated with digital signature.
Study the existing method for the approval of building plan proposals in 27 Development
Authorities including the method, software and formats being used currently for sanctioning
the building plans.
Preparation, submission and approval of the System Requirement Study (SRS) of proposed
solution for Automating the Building Plan Approval System for various Development
Authorities.
The Bidder will prepare an SRS and suggest a system to incorporate best methods and
practices to enhance/augment present of flow of data and mapping of the approval and
occupancy process.
12
RFP for Online Building Plan Scrutiny and Approval System
Provide 15 user license of the proposed software for each Category AS Development
Authority, 10 user license of the proposed software for each Category A Development
Authority, 7 user license of the proposed software for each Category B Development Authority
and 5 user license of the proposed software for each Category C Development Authority
(Total 226 Licenses) There are total development authorities under category AS are 4, total
development authorities under category A are 4, total development authorities under
category-B are 5, total development authorities under category C are 14.
To train the officials and other stake holders of 27 Development Authorities for one week one
time at their respective locations
Providing one trained Technical Person with minimum qualification of Diploma in Civil
Architecture for support and Operation of application for a period of 3 year after award of
contract.
Deliverable (s): Test and deploy Automated Building Plan Scrutiny & Approval System
The system should provide sufficient base to ensure security of the plan approved by 27
Development Authorities using the system. This will include storing approved files which will be non-
13
RFP for Online Building Plan Scrutiny and Approval System
editable, storing the approval information in database in secured manner. The system should also
provide facility to print the approved drawings for the system and only those will be considered as
approved drawings by the system.
Activity-IV:
The bidder shall provide Maintenance support for three year after approval of SRS by the authority.
Scope of annual maintenance will be as follows.
Maintain rule database and implementation of changes in the values of the existing DC
Regulations/ By-Laws.
14
RFP for Online Building Plan Scrutiny and Approval System
Authorization The Bidder should be either manufacturer or The bidder should submit
Authorized dealer of the proposed COTS solution. MAF(Manufacturers
Authorization Form) from
OEM
15
RFP for Online Building Plan Scrutiny and Approval System
The Proposed COTS solution should fulfil following criteria for eligibility (the credentials from bidder/
manufacturer should be enclosed) Please submit relevant documents/evidence in your technical proposal in
response to the eligibility criteria mentioned above..
COTS product should have been successfully implemented and Declaration Letter from OEM with names of
running for last 2 years in at least 20 ULBs (Urban Local Bodies) clients(enclosed Certificates from the Client)
in India.
At least online 50000 building plans has been processed through Declaration Letter from OEM with names of
the proposed COTS solution implemented in various ULBs in clients and number of building plans
India processed through system.
COTS Product should have been deployed in more than 15 Declaration Letter from OEM with names of
Municipal Corporations in a single state order in India. clients (enclose Work Order Copies)
Minimum 5 Crore sq. ft area is processed through system using Declaration Letter from OEM and MIS reports
proposed COTS product. of various ULBs
The COTS OEM’s total turnover for the last 3 financial year i.e.
2013-14,2014-15& 2015-2016 should be minimum INR 100 (CA certificate to be submitted for the same),
crores from the software sales and Consulting. For FY 2015-16, Management books would
be considered with self-certification.
16
RFP for Online Building Plan Scrutiny and Approval System
A Evaluation of Bidder 10
17
RFP for Online Building Plan Scrutiny and Approval System
If number of 5
drawing
scrutinized
between
5000 to
25000
C COTS Functionality 15
18
RFP for Online Building Plan Scrutiny and Approval System
1. Scrutiny System
2. Document Management
System
3. Web based approval flow
4. Online Payment
integration & approval
through digital signature
5. State-wide Approach
Total Marks 100
Only the bidders, who score a total Technical score of 70 (Seventy) or more, will qualify for the evaluation
of their commercial bids.
Consequent upon the evaluation, each Technical bid will be assigned a Technical Score out of a
maximum of 100 points. The bidder with highest Technical Score (Tmax) will be awarded 100% score.
Technical Scores for other bidders will be evaluated using the following Formula:
Technical Score (TS) = (Total Technical Score of the Bidder /Tmax) X 100
The Commercial Bids of only the technically qualified consultants will be opened for evaluation. The
consultant with lowest Total Commercial Quote (L1) will be awarded 100% score.
Commercial Scores for other consultants will be evaluated using the following Formula:
Commercial Score (CS) = (Total Commercial Quote of L1/ Total Commercial Quote of the Consultant)
X 100
In determination of the best value bid, the following weightage shall be given for the technical and
commercial scores of the consultants in a Quality and Cost Based Selection methodology (QCBS):
Technical Score: 80%
Commercial Score: 20%
For every Consultant the Final Total Score (FS) will be calculated using the formula
FS = 0.8 X TS + 0.2 X CS
The consultant with the highest value of FS shall be selected as the successful consultant.
19
RFP for Online Building Plan Scrutiny and Approval System
20
RFP for Online Building Plan Scrutiny and Approval System
21
RFP for Online Building Plan Scrutiny and Approval System
The system should have the ability and flexibility to design suitable workflow for the approval
process as per the requirements of the Development Authority. The approval workflow should be
as per the work flow being followed by Development Authority’s hierarchy and workflow rules
should be flexible enough to change as desired.
System should generate automatically the fee memo/ demand notes based on the submitted
Building plan. System should have necessary interfaces for Fee collection and receipt
generation. System will be integrated with Payment Gateway provided by bidder.
Plans approved
Pending proposals
Delayed approvals
All the required changes would be provided by this committee in writing to the bidder.
Any development authority requiring any modification in the system need to represent
their case to the committee and only after approval of the committee the same would be
implemented.
The decision of the committee would be final and acceptable to bidder as well as the
development authority.
22
RFP for Online Building Plan Scrutiny and Approval System
23
RFP for Online Building Plan Scrutiny and Approval System
24
RFP for Online Building Plan Scrutiny and Approval System
The Lucknow Development Authority reserves the right at the time of Contract award to increase or
decrease the quantity of goods and services originally specified in the Schedule of Requirements without
any change in unit price or other terms and conditions.
If any such change causes an increase or decrease in the cost, or the time required for, the Supplier’s
performance of any provisions under the Contract, an equitable adjustment shall be made in the Contract
Price or delivery schedule, or both, and the Contract shall accordingly be amended. Any claims by the
Supplier for adjustment under this clause must be asserted within seven (7)days from the date of the
Supplier’s receipt of the Purchaser’s change order.
25
RFP for Online Building Plan Scrutiny and Approval System
3 Supply and installation of State wide application at the 30% of Sr. No. A1 &A2
hosted Central Server
4 On Deploying State Wide Application and UAT as per 40% of Sr. No. A1 & A2
Specifications
Supply of User Licenses (Work Flow & CAD based) at 50% against delivery of Sr.
5
each development authority of Lucknow Development No. A3 & A4
Authority
9 Hosting of the complete automated building The payment for the AMC
permission application as per the provided hardware shall be made on a
specification. Quarterly advance basis
within 15 days after raising
invoice
26
RFP for Online Building Plan Scrutiny and Approval System
Manpower & Maintenance for a period of Three year (Sr. No. C&D)
7.15 Assignment/Sub-contracting
The Service Provider shall not assign / sub-contract, in whole or in parts its obligations to perform under
27
RFP for Online Building Plan Scrutiny and Approval System
the Contract to any other firm except with the Lucknow Development Authority’s prior written consent, but
not absolving of Sub- Provider's ultimate responsibilities to successfully implement the project in totality
in proper functional performance.
/end-customer and implement all the activities. The Service Provider shall abide by the job safety
measures prevalent in the country and will indemnify the Lucknow Development Authority from all
demands or responsibilities arising from consequences, accidents or loss of life and property due to
negligence of the Service Provider. The Service Provider will pay all indemnities arising from such
incidents and will not hold the Lucknow Development Authority responsible or obligated. The Service
Provider is responsible for managing the activities of its personnel and will hold itself responsible for any
misdemeanors. The Service Provider will treat all data and information as confidential about the Lucknow
Development Authority and end-customer, obtained in the execution of his responsibilities, in strict
confidence and will not reveal such information to any other party without the prior written approval of the
Lucknow Development Authority/end-customer.
Service Providers in the performance of the allotted job. Disclosure to any such employed person shall
be made in confidence and shall extend only as far as may be necessary for purpose of such
performance.
2. For purpose of this Clause, “Force Majeure” means an event beyond the control of the Service
Provider and not involving the Service Provider’s fault or negligence and not foreseeable. Such
events may include, but are not limited to, acts of the Lucknow Development Authority either in
its sovereign or contractual capacity, wars or revolutions, fires, floods, epidemics, quarantine
restrictions and freight embargoes. If a Force Majeure situation arises the Service Provider shall
promptly notify the Lucknow Development Authority in writing of such conditions and the cause
thereof. Unless otherwise directed by the Lucknow Development Authority in writing, the Service
Provider shall continue to perform its obligations under the Contract as far as is reasonably
practical, and shall seek all reasonable alternative means for performance not prevented by the
Force Majeure event.
be commenced prior to or after delivery of the Goods and services under the Contract.
7.27 Arbitration
1. In case of dispute or difference arising between the Lucknow Development Authority and a
Service Provider relating to any matter arising out of or connected with the award of contract,
such dispute or difference shall be referred to Sole Arbitrator, the Principal Secretary/Secretary,
UP Housing Board, Govt of U.P., to decide the dispute both in case of foreign supply as well as
Indian supply. The provision of Arbitration and Conciliation Act, 1996 shall apply.
2. Arbitration proceedings shall be held at Lucknow and the language of the arbitration proceedings
and that of all documents and communications between the parties shall be in English.
3. The decision of the Sole Arbitrator or its nominee shall be final and binding upon both parties.
The cost and expenses of arbitration proceedings will be paid as determined by the Arbitrator.
However the expenses incurred by each party in connection with the preparation, presentation
etc. of its proceedings shall be borne by each party itself.
a. The parties shall continue to perform their respective obligations under the Contract unless they
otherwise agree ; and
b. The Lucknow Development Authority shall pay the Service Provider any money due to the Service
Provider.
All disputes shall be subject to the jurisdiction of the Courts at Lucknow only.
31
RFP for Online Building Plan Scrutiny and Approval System
languages.
Subject:-
Dear Sir,
Having examined the Bidding Documents, we, the undersigned, offer to <Name of Work>in
accordance with the terms and conditions of the contract mentioned in the RFP
We undertake, if our bid is accepted, to commence work as per the schedule and to achieve the
effectiveness of the contract within the respective time period stated in the Bidding Documents.
We have read the provisions of bid and confirm that these are acceptable to us.
We undertake, if our bid is accepted, to commence the work as per the schedule immediately
upon your Notification of Award to us, and to achieve Completion within the time stated in
the Bidding Documents.
If our bid is accepted, we undertake to provide Performance Security in the form and
amounts, and within the times specified in the Bidding Documents.
We undertake that, in competing for (and, if the award is made to us, in executing) the above
contract, we will strictly observe the laws against fraud and corruption in force in India
Signature:
32
RFP for Online Building Plan Scrutiny and Approval System
• Certificate of Incorporation
Name of Bidder:
Signature of Bidder:
33
RFP for Online Building Plan Scrutiny and Approval System
If centralized Hosting for all the development authorities at single location is decided by the department, then the
requirement of the servers and other computing capacity would be optimized by the department for further reducing
the hosting and management cost of the proposed solution and bidder has to comply with same.
34
RFP for Online Building Plan Scrutiny and Approval System
Sr.No. Item
Data Center(DC) and Disaster Recovery(DR) Compliance
1 DC infrastructure IPv6 Compliant
2 DC and DR should physically reside in India and all application, data, and all its
supporting infrastructure should reside within India only
3 DC and DR should be managed and monitored 24x7x365 days in the Cloud Service
Provider’s Network Operation Centre(NOC)
4 Firewall with IPS, IDS for both primary and DR servers should be provisioned
5 Hosting Service provider should ensure 24x7x365 security monitoring of OBPS
solution to detect attacks and alert about suspicious events that may lead to breach
of security
6 Should have dynamic load balancing capability
7 The Bidder should ensure OBPS application and all its related Information hosted in
the DC and DR should be under secured environment based on GoI regulatory
requirements if any.
8 DR should be indifferent Seismic Zone with different fault line than the DC.
Business Continuity and Resiliency
9 DR drill is required to be conducted as per Business Continuity and Resiliency Plan
once in every one year, and a detailed report of the same should be submitted by
the bidder.
10 Cloud/ Hosting Service Provider should provide a detailed Business Continuity
and Resiliency Plan for effective disaster management, to handle disaster situations.
CSP should also provide periodic test reports to UVAVP as per the Business
Continuity & Resiliency Plan
Governance Model
The governance policies around OBPS application, all its related data, and storage
11 And retention policies adopted should be informed.
35
RFP for Online Building Plan Scrutiny and Approval System
Software Compliance
12 Bidder should procure, install, configure and maintain licensed software required for
proper hosting of OBPS solution with latest anti-virus.
13 Bidder to ensure all antivirus software and programs are updated timely and
Regularly in the Cloud / Hosted server and kept up-to-date
14 The bidder should test the patches for OBPS application compatibility
Information Security Management
15 All application security concerns like HTML/SQL Injections, application of Stored
Procedures etc. should be quarterly tested for, and report for the same should be
submitted quarterly.
16 Bidder should ensure appropriate information security, anonymity, and encryption
for OBPS application over Cloud / Hosting to avoid any unauthorized access
17 Ensure there is no data or information leakage
18 Ensure secure disposal and complete removal of all unutilized data and information
Related to OBPS application from all storage media
19 Ensure that data from live OBPS application(Production data)is not replicated or
used in non-production instances without UVAVP permission
Vulnerability and penetration testing should be performed on information security
20 Management on a quarterly basis. CHSP is responsible to submit a report for the
same on a quarterly basis
Creation & maintenance of the directory server integrated with security modules like
Authentication, Authorization & Auditing capabilities, Web single sign on, OTP
21 management for critical components and the usage of Digital signature to ensure
web based signage of documents. The SI should also employ the usage of a log co-
relator system to ensure centralized collection and analysis of log files.
Data, Information and Backup Policy
22 Backup or redundancy mechanisms implemented to ensure compliance with
regulatory, statutory, contractual or business requirements
36
RFP for Online Building Plan Scrutiny and Approval System
23 Services provided should include appropriate data anonymity and encryption over
Cloud
24 Data Disposal should be secure and mechanisms should be for complete removal
Of data from all storage media, ensuring data is not recoverable by any computer
forensic means
37
RFP for Online Building Plan Scrutiny and Approval System
1 Gaziabad AS
3 Kanpur AS
4 Lucknow AS
Total AS Category 5
1 Agra A
2 Allahabad A
3 Meerut A
4 Muradabad A
Total A Category 4
1 Aligardh B
2 Baraille B
3 Gorakhpur B
4 Mathura B
5 Varanasi B
Total B Category 5
1 Banda C
2 Bulandshar C
3 Faizabad C
4 Firozabad C
5 Hapud-Pilkua C
38
RFP for Online Building Plan Scrutiny and Approval System
6 Zansi C
7 Muzaffarnaagar C
8 Raibareli C
9 Saharanpur C
10 Unnav C
11 Rampur C
12 Urai C
13 Khurja C
Total C Category 13
39