Sei sulla pagina 1di 14

Vol

.1I
ssue3,Oct
ober2016
Int. J. Civil Engg. Conc.Structs 2016 Hatkar K B and Hedaoo N A, 2016

ISSN 2455-7714, www.trpubonline.com


Vol. 1, No. 3, October 2016
© 2016, www.trpubonline.com. All Rights Reserved

DELAY ANALYSIS BY USING RELATIVE


IMPORTANCE INDEX METHOD IN
INFRASTRUCTURE PROJECTS
Hatkar K B1* and Hedaoo N A1

*Corresponding Author: Hatkar K B,  ketanh99@gmail.com

One of the most common problems in the infrastructure project is delay. Delay in a construction
project can be defined as the late completion of works as compared to the planned schedule or
contract schedule. Construction projects can be delayed due to so many factors. It may be due to
consultant, contractor, material, equipment, finance etc related factors. The aim of this paper to
identifying the causes and effects of delays in infrastructure projects (road, bridge and flyover). This
has been achieved by undertaking a critical analysis of the literature and carrying out a questionnaires
survey. The twenty questionnaire surveys were completed by taking interviews of the respondent, i.e.,
consultants and contractors who works on infrastructure projects. Then the causes of delay assessed
using Relative Importance Index (RII) so as to rank the factors. Also use the Spearman’s Rank Correlation
Coefficient test to determine significant correlation between contractors and consultants perspective.
The most significant factors of construction delays were identified as: (1) Local political interference;
(2) Inadequate fund allocation; (3) Improper project planning and scheduling; (4) Delay in progress
payments by client; (5) Escalation of material prices. Also major effects of delay were identified that
are (1) Time overrun; (2) Cost overrun; (3) Disputes. The results also include the most effective methods
for minimizing construction delays.

Keywords: Infrastructure projects, Delay, Relative importance index, Spearman’s rank, Correlation coefficient

Introduction has been a popular topic in construction


The construction industry is a very important management research, and various delay
sector for the development and economic studies have been carried out for different
growth of developing country (Haseeb et al., purposes (Abdullah AlSehaimi et al., 2013).
2011). A construction project is commonly Infrastructure projects in India are infamous
acknowledged as successful, when it is for delays and cost overruns. Very few
completed on time, within budget and in projects get delivered within time and within
accordance with the specifications (Murat cost. The delays and cost overruns have
Gunduz et al., 2013). Over many years, delay become hallmark of infrastructure projects
1
College of Engineering, Pune, India.

This article can be downloaded from http://www.trpubonline.com


9
Int. J. Civil Engg. Conc.Structs 2016 Hatkar K B and Hedaoo N A, 2016

in India. Bandra-Worli Sea Link was planned of Baldwin et al. (1971) was carried out to
as a Rs. 300 Crore project to be completed determine the causes of delay in the
by 2004; but its actual cost is Rs. 1,600 crore construction process in the United States.
along with five years delay. Indeed, very few Mansfield et al. (1992) which investigated the
projects get delivered in time and on cost. causes of delay and cost overruns that affect
Delays on construction projects are a completed highway projects in Nigeria.
universal phenomenon. They are almost Murat Gunduz et al. (2013) identified the
always accompanied by cost and time total 83 different delay factors and addressed
overruns (Sadi Assaf and Sadiq Al-Hejji, the most significant factors and groups of
2006). Project delays have a debilitating effect causes of delays through ranking results.
on all parties (owner, contractor, and Sadi Assaf et al. (2006) identified seventy
consultant) to a contract in terms of a growth three causes of schedule delay exist in Saudi
in adversarial relationships, distrust, construction projects. They found that the
litigation, arbitration, cash-flow problems, most important causes of schedule delay as
and a general feeling of apprehension seen by contractors were: delay in progress
payments by owner, late approving design
towards each other (Abd. Majld and Ronald
documents by owner, change orders by
McCaffe, 1998). Several factors can contribute
owner during construction. Abd El-Razek
to delays on a project and analyzing the
et al. (2008) identified the thirty two causes
causes of delays is an essential task for
of delay in construction projects in Egypt.
ameliorating any potential conflicts or claims
The overall results indicated that the most
(Muhwezi and Otim, 2014). The study is to
important causes are: financing by contractor
identify the major causes of delays in
during construction, delays in contractors
construction projects in construction
payment by owner and non utilization of
industry through a survey and to find the
professional contractual management.
perception of the different parties towards
Muhwezi et al. (2014) studied the effects of
the problem, what their responsibilities are delays on building construction projects in
and how they carry them out. It is expected Uganda, using Kampala as the case study
that this study will provide some good so as appropriate mitigation measures are
empirical data on the extent and type of put in place to ameliorate the effects of delay.
delays in construction projects. Abdullah Al Sehaimi et al. (2013) studied
simple analysis and evaluation of the
Literature Review findings and recommendations of published
Several articles have discussed causes of studies of construction delay in developing
delay in construction projects in numerous countries.
manners; some studies identified the main
causes of delay in several countries and Research Methodology
various project types, while other studies The research methodology will explain how
discussed the delay analysis methods and the objectives of this study can be achieved.
the proposed ways to mitigate it. The study Firstly, questionnaire was divided into two
This article can be downloaded from http://www.trpubonline.com
10
Int. J. Civil Engg. Conc.Structs 2016 Hatkar K B and Hedaoo N A, 2016

main parts. Part A includes the details of the equipment, Frequent equipment breakdown,
respondents and organizations in order to Slow mobilization of equipment and
get the information about the respondent Shortage of equipment parts. Contractor
s details and organization as well. Part B related group includes thirteen factors which
includes three sub-sections, Section I are: Inadequate contractor experience,
includes the questionnaire of factors causing Inappropriate construction methods, Poor
delay, Section II includes the questionnaire site management and supervision, Site
of effects of delay and section III includes management, Improper technical studies by
the questionnaire of method of minimizing the contractor during the bidding stage,
delay. Improper project planning and scheduling,
Incompetent project team, Delays in sub-
In Section I, seventy six factors causing
contractors work, Poor communication and
delay were identified from in-depth
coordination with other parties, Rework due
literature studies and discussing with some
to errors, Inaccurate time estimate,
construction practitioners. These factors then
Inaccurate cost estimate and Obsolete
grouped into eight major groups which are
technology. Consultant related group
Material related delays, Labour related
includes eight factors which are: Lack of
delays, Equipment related delays,
experience of consultant in construction
Contractor related delays, Consultant related
projects, Poor design and delays in design,
delays, Client related delays, Finance related Delay in approving major changes in the
delays and External related delays. Material scope of work by consultant, Slow response
related group includes ten factors which are: and poor inspection, Inaccurate site
Shortage of construction material in market, investigation, Incomplete drawing/detail
Late delivery of materials, Changes in design, Poor communication and
material specification during construction, coordination with other parties and
Poor procurement of construction materials, Inadequate project management assistance.
Imported of construction materials, Delay in Client related group includes ten factors
manufacturing materials, Unreliable which are: Slow decision making by client,
suppliers, Damage of sorted materials, Poor Change orders by the owner during the
quality of construction materials and construction, Delay in progress payments,
Escalation of material prices. Labour related Conflicts between joint-ownership, Lack of
group includes eight factors which are: experience of client in construction, Client
Strike, Labour supply, Personal conflicts interference, Delay in site delivery, Lack of
among labour, Labour productivity, capable representative, Lack of
Shortage of skill labour, Slow mobilization communication and coordination and
of labour, Low motivation and Absenteeism. Improper project feasibility study. Finance
Equipment related group includes seven related group includes seven factors which
factors which are: Insufficient numbers of are: Inadequate fund allocation, High
equipment, Equipment allocation problem, interest rate, Monthly payment difficulties,
Inadequate modern equipment, Improper Delay payment to suppliers/subcontractors,
This article can be downloaded from http://www.trpubonline.com
11
Int. J. Civil Engg. Conc.Structs 2016 Hatkar K B and Hedaoo N A, 2016

Unreasonable constraints to client, Client’s subcontractors and suppliers, Complete


financial difficulties. Finance related group and proper design at the right time,
includes thirteen factors which are: Local Competent personnel of consultant/
political interference, Weather condition, designer, Competent and capable of client’s
Changes in government regulations and representative, Site management and
laws, Loss of time by traffic control and supervision, Use of proper and modern
restriction at job site, Natural disasters construction equipment, Proper project
(flood, hurricane, earthquake), Accidents planning and scheduling, Accurate initial
during construction, Unexpected geological cost estimates, Use of appropriate
condition (Such as high water table, etc.), construction methods, Proper material
Inflation/Prices fluctuation, Delay in procurement, Effective strategic planning,
providing services from utilities (such as Systematic control mechanism, Perform a
water, electricity), Slow site clearance, preconstruction planning of project tasks
Conflict, war and public enemy, Problem and resources needs, Absence of
with neighbors and Unforeseen ground bureaucracy, Allocation of sufficient time
condition. and money at the design phase, Accurate
initial time estimates, Frequent
Section II of B questionnaire included the
coordination between the parties involved,
six effects of delays which are: Time overrun,
Developing human resources in the
Cost overrun, Dispute, Arbitration,
construction industry through proper
Litigation and Total abandonment.
training, Clear information and
Section III of B questionnaire included the communication channels and Project
total thirty two methods of minimizing management assistance.
construction delays which are: Competent D
These questionnaires were based on the
Capable project manager, Ensure adequate
Likert Likert’s scale of five ordinal
and available source of finance,
measures from 1 to 5 (very low effect to very
Multidisciplinary/competent project team,
high effect) according to level of
Availability of resources, Commitment to
contributing.
projects, Adopting a new approach to
contract award procedure by giving less
Data Analysis and
weight to prices and more weight to the
capabilities and past performance of Discussion
contractors, Complete and accurate project The procedure used in analyzing of data was
feasibility study and site investigation, aimed at establishing the relative importance
Acceleration of site clearance, of the various factors that contribute to
Comprehensive contract documentation, causes of delays, effects of delays and
Frequent progress meeting, Awarding bids methods of minimizing construction delays.
to the right/experience consultant and There are three steps used in analyzing the
contractor, Use up to date technology data: calculating the relative importance
utilization, Use of experienced index; ranking of each factors based on
This article can be downloaded from http://www.trpubonline.com
12
Int. J. Civil Engg. Conc.Structs 2016 Hatkar K B and Hedaoo N A, 2016

relative importance index, and to determine RII = W/(A x N)


degree of correlation on ranking the factors where
among the two groups.
W = Weightage given to each factor by the
Relative Importance Index respondents
The contribution of each of the factors to A = Highest weight (i.e., 5 in this case)
overall delays was examined and the
N = the total number of respondents
ranking of the attributes in terms of their
criticality as perceived by the respondents Table 1 shows the ranking of top ten
was done by use of Relative Importance factors that causes delay from seventy six
delay factors. That means these ten factors
Index (RII) which was computed using
causing delay are more contributing into the
equation and the results of the analysis are
infrastructure projects.
presented in Tables 1 to 3. To determine the
ranking of different factors from the Table 2 shows the ranking of various
viewpoint of contractors and consultants, the effects of delay. Top effect indicate very high
Relative Importance Index (RII) was frequency of occurrence in infrastructure
computed using RII Equation (Abdalla Odeh projects.
and Hussein Battaineh, 2002; Murat Gunduz Bar Chart 1 shows the time overrun is the
et al., 2013; and Muhwezi and Otim, 2014). top most significant effect of delay among

Table 1: Most Important Factors Causing Delays

This article can be downloaded from http://www.trpubonline.com


13
Int. J. Civil Engg. Conc.Structs 2016 Hatkar K B and Hedaoo N A, 2016

Table 2: The Common Effects of Delays

Table 3: Methods of Minimizing Construction Delays

six effects of delay. It also indicates the cost The Spearman’s Rank Correlation
overrun and disputes are also major effects
Coefficient Test
of delay.
The Spearman rank correlation is used to
Table 3 shows the ranking of the relative
know whether there is disagreement or
importance of top ten methods of
minimizing construction delays from total agreement between the two groups on
thirty two methods. It indicates that these ten ranking factors. This test is used to find and
methods are more effective methods for compare how well the contractors and
minimizing construction delay. consultants agree on the relative
This article can be downloaded from http://www.trpubonline.com
14
Int. J. Civil Engg. Conc.Structs 2016 Hatkar K B and Hedaoo N A, 2016

Figure 1: Effects of Delays

importances of the delay causes. A perfect Assaf and Sadiq Al-Hejji, 2006; and
positive correlation (r s = +1) indicates that Abdullah AlSehaimi et al., 2013).
the two samples rank each object In order to determine there is significant
identically, whereas a perfect negative correlation of the ranking of factors that
correlation (rs = -1) indicates that the ranks causes delays, effects of delays, and methods
of the two samples have an exactly inverse of minimizing construction delays between
relationship. It might be said then that contractors and consultants perspective, the
sample estimates of correlation close to Spearman’s Rank correlation coefficient was
unity in magnitude imply good correlation, computed as following equations and the
whereas values near 0 indicate low or no results of the analysis are presented in Table
correlation (Sadi Assaf et al., 1995; Sadi 4 (Abdalla Odeh and Hussein Battaineh,

Table 4: Results of Spearman’s Rank Correlation Coefficient Test

This article can be downloaded from http://www.trpubonline.com


15
Int. J. Civil Engg. Conc.Structs 2016 Hatkar K B and Hedaoo N A, 2016

2002; Abd El-Razek et al., 2008; and Ibrahim Alternative hypothesis: H1: Agreement in
Mahamid et al., 2012): rankings among the two groups.
rs = 1 – [(6d2)/(N3 – N)] Compare the value against the critical
r s = Spearman’s Rank correlation value. Reject the null hypothesis, if rs is
coefficient greater than the critical value.

d = the difference in ranking between the Table 4 shows the results of tests of
contractors and consultants Spearman’s Rank Correlation Coefficient for
different groups of construction delay. This
N = the number of variables Table 4 indicates Material, Contractor,
This calculated value of rs is compared Client, Finance and External related delay
with critical value of rs from the standard groups agree on the ranking given by both
table for n samples. contractors and consultants.
Null hypothesis: Ho: No significant Contractor related group causing delay
agreement in the rankings among the two and finance related group causing delay are
groups. the top most significant group that

Figure 2: Groups of Causes of Delays

This article can be downloaded from http://www.trpubonline.com


16
Int. J. Civil Engg. Conc.Structs 2016 Hatkar K B and Hedaoo N A, 2016

contributed to causes of delays among eight of project tasks and resources needs,
groups shown in bar Chart 2. Accurate initial cost estimates, Ensure
adequate and available source of finance,
Conclusion Multidisciplinary/competent project team,
In a construction project where time truly Use of proper and modern construction
equals money, the management of time is equipment, Proper project planning and
critical, thus predicting the likelihood of scheduling, Use of appropriate construction
schedule delay may play a key role towards methods, Use of experienced subcontractors
project success. There existed a need to and suppliers and Site management and
develop a probabilistic schedule delay supervision.
analysis model in construction projects as a
decision support tool for contractors before Recommendations to
the bidding stage. Minimize Delays
Based on this study, some recommendations
From total seventy six factors causing
are given as follows:
delays, top ten most important factors have
been identified which are: Local political We divide the recommendations into
interference, Inadequate fund allocation, three groups:
Improper project planning and scheduling 1) Recommendations for the clients,
by contractor, Delay in progress payments
2) Recommendations for the consultants,
by client, Escalation of material prices,
and
Weather condition, Delay in payment to
suppliers/subcontractors, Insufficient 3) Recommendations for the contractors.
numbers of equipment, Incomplete Recommendations for the Clients
drawing/detail design and Natural disasters
• Appropriate funding levels should
(flood, earthquake, etc.).
always be determined at the planning
Total seventy six factors causing delay stage of the project so that regular
were identified and grouped into eight payment should be paid to contractors for
major groups. The major delays groups were work done. Therefore, clients should
identified are: Contractor related delays and work closely with the financing bodies
Finance related delays. and institutions to release the payment on
The major effects of delays have been schedule.
identified which are: Time overrun, Cost • Clients should not interfere frequently
overrun and Disputes. during the execution and keep making
From total thirty two methods of major changes to the requirements. This
minimizing construction delays, the top ten can cause inordinate delays in the project.
effective methods have been identified • While selecting the contractors, clients
which are: Competent/Capable project have to make sure that the contractors are
manager, Perform a preconstruction planning not selected based only on the lowest bid.
This article can be downloaded from http://www.trpubonline.com
17
Int. J. Civil Engg. Conc.Structs 2016 Hatkar K B and Hedaoo N A, 2016

The selected contractor must have continuous work training programs to


sufficient experience, technical capability, update their knowledge and be familiar
financial capability, and sufficient with project management techniques and
manpower to execute the project. processes.
• Communication and Co-ordination • Contractors should appoint experienced
should be proper with the other parties. and reputed subcontractors.
• Site should be delivered as soon as • Contractors must plan their work
possible after project is awarded. properly and provide the entire schedule
to the clients
Recommendations for the
Consultants • Proper work as per specification to avoid
• All working drawings must be clearly rework due to error.
drawn indicating all the dimensions and • Contractors must make sure they have a
scale so as to avoid ambiguity during sound financial backing.
construction.
Recommendations for Future
• Avoid the redesign of the project once
submitted. Studies
More research on construction delays should
• Accurate site investigation should be
be done in order to develop guidelines, or
done in order to avoid errors in design.
methods of minimizing construction delays.
• Establish control system to control and Furthermore, similar research should be
evaluate variation in orders initiated by performed in various provinces or cities of
owner. India. In order to providing more reliable
• Consultants should prepare and approve data it is required to carry out studies for
drawings on time. each specific type of construction projects,
including highways, dam construction
Recommendations for the projects, utilities, etc. Surely, detailed
Contractors
surveys required to be performed to find out
• Contractors should not take up the job in cash flow problems on delays in construction
which they do not have sufficient projects.
expertise.
• Development of good system for site References
management and proper supervision 1. Abd El-Razek M E, Bassioni H A and
develops project planning and Mobarak A M (2008), “Causes of Delay
scheduling. in Building Construction Projects in
• Initially calculate optimistic duration to Egypt”, Journal of Construction
execute the project. Engineering and Management, November,
• In order to improve contractors’ pp. 831-841, ASCE.
managerial skills there is need for 2. Abd. Majld M Z and Ronald McCaffe
This article can be downloaded from http://www.trpubonline.com
18
Int. J. Civil Engg. Conc.Structs 2016 Hatkar K B and Hedaoo N A, 2016

(1998), “Factors of Non-Excusable Kuwait Chapter of Arabian”, Journal of


Delays that Influence Contractors’ Business and Management Review, Vol. 1,
Performance”, Journal of Management in No. 4, pp. 18-42.
Engineering, Vol. 14, No. 3, pp. 42-49. 9. Haseeb M, Xinhai-Lu, Aneesa Bibi,
3. Abdalla M Odeh and Hussein T Maloof-ud-Dyian and Wahab Rabbani
Battaineh (2002), “Causes of (2011), “Problems of Projects and Effects
Construction Delay: Traditional of Delays in the Construction Industry
Contracts”, International Journal of Project of Pakistan”, Australian Journal of Business
Management, Vol. 20, pp. 67-73. and Management Research, Vol. 1, No. 5,
4. Abdullah AlSehaimi, Lauri Koskela and pp. 41-50.
Patricia Tzortzopoulos (2013), “Need for 10. Ibrahim Mahamid, Amund Bruland and
Alternative Research Approaches in Nabil Dmaidi (2012), “Causes of Delay
Construction Management: Case of in Road Construction Projects”, Vol. 28,
Delay Studies”, Journal of Management in July, pp. 300-310, ASCE.
Engineering, October, pp. 407-413, ASCE. 11. Muhwezi L and Otim G (2014), “An
5. Ali Tarhini, Muhamad Fakih, Mahir Assessment of the Factors Causing
Arzoky and Takwa Tarhini (2015), Delay on Building Construction Project
“Designing Guidelines to Discover in Uganda”, International Journal of
Causes of Delays in Construction Construction Engineering and Management,
Projects: The Case of Lebanon”, Vol. 3, No. 1, pp. 13-23.
International Business Research, Vol. 8,
12. Mulenga Mukuka, Clinton Aigbavboa
No. 6 (Canadian Center of Science and
and Wellington Thwala (2013), “A
Education).
Theoretical Assessment of the Causes
6. Chan D W and Kumaraswamy M M and Effects of Construction Project
(1996), “Reasons for Delay in Civil Delay”, International Conference on
Engineering—The Case Study of Hong Civil and Environmental Engineering
Kong”, Inst Eng Trans., Vol. 2, No. 3, (CEE’2013), November, pp. 27-28.
pp. 1-8. 13. Murat Gunduz, Yasemin Nielsen and
7. David Arditi and Thanat Mustafa Ozdemir (2013),
Pattanakitchamroon (2006), “Selecting a “Quantification of Delay Factors Using
Delay Analysis Method in Resolving the Relative Importance Index Method
Construction Claims”, International for Construction Projects in Turkey”,
Journal of Project Management, Vol. 24, Journal of Management in Engineering,
pp. 145-155. Vol. 29, April, pp. 133-139, ASCE.
8. Haseeb M, Xinhai-Lu, Aneesa Bibi, 14. Sadi A Assaf and Sadiq Al-Hejji (2006),
Maloof-ud-Dyian and Wahab Rabbani “Causes of Delay in Large Construction
(2011), “Causes and Effects of Delays in Projects”, International Journal of Project
Large Construction Projects of Pakistan, Management, Vol. 24, pp. 349-357.
This article can be downloaded from http://www.trpubonline.com
19
Int. J. Civil Engg. Conc.Structs 2016 Hatkar K B and Hedaoo N A, 2016

15. Sadi A Assaf, Mohammed AI-Khalil and Overruns in Saudi Arabian Construction
Muhammad AI-Hazmi Assaf (1995), Industry”, International Journal of Scientific
“Causes of Delay in Large Building & Engineering Research, Vol. 7, No. 2,
Construction Projects”, Journal of pp. 555-560.
Management in Engineering, March/April, 17. Terry Williams (2003), “Assessing
pp. 45-50, ASCE. Extension of Time Delays on Major
16. Shabbab Al Hammadi and Sadique Projects”, International Journal of Project
Nawab M (2016), “Project Time Management, Vol. 21, pp. 19-26.

This article can be downloaded from http://www.trpubonline.com


20
1120 S Walton Blvd, Suite 138, Bentonville,
Arkansas - 72712-0077, USA.
www.trpubonline.com

Potrebbero piacerti anche