Pipeline Project

1 message

Makesh, Arjun <AMakesh@kockw.com> Sat, Jun 13, 2020 at 11:47 AM


To: sksameeruddin@gmail.com <sksameeruddin@gmail.com>

                4. CONSTRUCTION  

                                                i. Pipeline Projects

                                                                1) Civil Activities

                                                                                a) Site Survey & ROW

                                                                                b) Excavation

                                                                                c) Bedding

                                                                                d) Padding

                                                                                e) Backfilling & Bern Preparation

                                                                                f) Open cut road crossing

                                                                                g) HDD road crossing backfilling 

                                                                2) Mechanical Activities

                                                                                a) Stringing

                                                                                b) Welding

                                                                                c) NDT

                                                                                d) Coating

                                                                                e) Lowering

                                                                                f) Tie-in

                                                                                g) NDT & Coating for Tie-in

                                                                                h) Open cut road crossing

                                                                                i) HDD road crossing

j) Road Crossing Tie-in & Coating

With Regards,

Arjun M

Planning Engineer

EXTN: 21605