ACARREO DE MATERIAL PRODUCTO DE EXCAVACION A PRIMER KM.

, INCLUYE CARGA CON EQUIPO

DATOS

VOLUMEN EXTRAIDO DEL CONCEPTO ANTERIOR


594 M3

PROCEDIMIENTO
ABUNDAMIENTO 801.9 M3
CAMIONES:
114.6
CAP. 7M3:

TIEMPO QUE TARDA LA RETRO CARGANDO UN CAMION:


15-25 MIN
PROPUESTA MEDIA: 20 MIN/CAMION (7M3)
2291.1 MINUTOS TOTALES
1 RETRO + 1 CAMION 4.8 DIAS SOLO CARGANDO

1 RETRO+ 3 CAMIONES 21 M3/HR


168 M3/DIA
TIEMPO EN ACARREO 4.8 DIAS
REDUCIENDO DIAS
2 RETRO+ 6 CAMIONES 42 M3/HR
336 M3/DIA
D.R. 2.4 DIAS

COSTOS:
RETROEXCAVADORA 250 HR 2000 DIA
CAMION VOLTEO (7M3) 250 HR 2000 DIA

PRESUPIESTO RETROEXCAVADORA (2) 9546.4


CAMION VOLTEO (6) 28639.3
SUBTOTAL DE RENTAS 38185.7

UTILIDAD 10-15 5727.9

TOTAL 43913.6