Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
5-i
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
5-ii
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
The equipment shall be used for control and protection of 230 kV Pakse
substation. The 230 kV Pakse substation shall be of the breaker and a half
arrangement, outdoor air insulated type, consisting of two (2) 230 kV lines to
230 kV Xe-Namnoy switchyard of Xe-PianXe-Namnoy hydroelectric power
project, two (2) 230 kV lines to EGAT 230 kV Ubon Ratchathani 3 Substation
and one (1) 230-22 kV 10 MVA transformer bay for station service with OLTC
at low voltage side and complete with one (1) 22000-400/230 V, 3ø, 500 kVA
distribution transformer.
The two (2) 230 kV outgoing lines shall be designed, constructed and made a
detour around the 500 kV substation area which is reserved for future
construction. The two (2) 230 kV lines will be connected with 500 kV
transmission line from Pakse to Ubon Ratchathani 3 substation at the 500 kV
deadend tower located outside the reserved area. The 500 kV transmission
line will be energized at 230 kV voltage level.
2. SCOPE OF SUPPLY
The following control and protection system equipment shall be furnished,
mounted and completely wired with any necessary devices to accomplish the
necessary control, protection and metering system functions as specified in
the Specification.
5-1
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
Twp (2) 230 kV control switchboard shall be furnished with control equipment
complete with integral accessories mounted and completely wired on and
inside the control switchboard as indicated on the above drawing.
(a) Panel No. 1F, 230 kV Line No. 1 and No. 2 to Xe-Namnoy Switchyard and
230 kV Line No. 1 and No. 2 to Ubon Ratchathani 3 substation
(i) Four (4) indicating voltmeters, semiflush mount, 110 mm square face,
with 250° scale arc, range 0-300 kV, 50 Hz, VT ratio
230,000 / 3 : 115 / 3 , as per Sub-Clause 3.2.17, for 230 kV line No.
1 to Xe-Namnoy switchyard and 230 kV line No. 2 to EGAT Ubon
Ratchathani 3.
(ii) One (1) voltmeter phase selection (VS), four-position “OFF, 1-3, 2-3,
3-1 for use with item (i), as per Sub-Clause 3.2.16.
(iii) Four (4) discrepancy control switches (DCS), for operation of motor
operated disconnect switches (80115), (80114), (80124) and (80111)
via the output contacts of interposing relays mounted inside the
panel, which represent the contacts of the discrepancy control
switches (DCS), as per Sub-Clause 3.2.16(b) and as per Sub-Clause
3.2.30 for interposing relays.
(iv) One (1) electrically operated mimic ground switch device (80111G),
rated 220 VDC, to automatically itself in accordance with its
respective line ground switch (8014G), complete with an amber light
assembly of light-emitting diode (LED) suitable for use with 220 VDC,
as per Sub-Clause 3.2.15.
The amber light will be “on” when the line ground switch (80111G) is
open.
This synchronizing switch (SS) shall be used with main bus No. 1 the
breaker control switch (CS) for closing of power circuit breaker
(80112). Each synchronizing switch (SS) shall use the interposing
relays of the latched-in type for mode selection functions. The output
contacts of the interposing relay shall represent “Local Control Mode”
of the contacts of the synchronizing switch (SS) for use in conjunction
with the output contacts of other interposing relays which represent
the contacts of the breaker control switch (CS) in item (vi). The other
output contacts of the interposing relay which represent the contacts
of the synchronizing switch (SS) shall also switch the relevant
incoming voltage and the running bus voltage to initiate the common
synchro-check relay (25-27/59) for closing the 230 kV line power
circuit breaker (80112).
5-2
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
(vi) One (1) main bus No. 1 breaker discrepancy control switches (CS),
as per Sub-Clause 3.2.16(a). The breaker control switches (CS) shall
be furnished with interposing relays which are mounted inside the
panel. These interposing relays shall provide output contacts to
represent the breaker control switch (CS) for control of power circuit
breaker (80112) through output contact of interposing relay which
represent the synchronizing switch (SS) in item (v) for both mode
selection functions of synchronizing switch (SS) and switching of
incoming voltage and running bus voltage to initiate the common
synchro-check relay (25-27/59) which provided in the Panel No. 1F at
“Local Control Mode” for closing of 230 kV line breaker when the
synchronism condition is met.
(vii) One (1) light box, engraved with “230 kV Line No. 1 to Xe-Namnoy”,
as per Sub-Clause 3.2.11.
(viii) One (1) potential and current test switch complete with multi-pole test
plug as per Sub-Clause 3.2.12, for item No. (ii), 230 kV line No. 1 to
Xe-Namnoy.
(ix) Four (4) discrepancy control switches (DCS), for operation of motor
operated disconnect switches (80123), (80133), (80135) and (80121)
via the output contacts of interposing relays mounted inside the
panel, which represent the contacts of the discrepancy control
switches (DCS), as per Sub-Clause 3.2.16(b) and as per Sub-Clause
3.2.30 for interposing relays.
(x) One (1) electrically operated mimic ground switch device (80121G),
rated 220 VDC, to automatically itself in accordance with its
respective line ground switch (8014G), complete with an amber light
assembly of light-emitting diode (LED) suitable for use with 220 VDC,
as per Sub-Clause 3.2.15.
The amber light will be “on” when the line ground switch (80121G) is
open.
One synchronizing switch (SS) shall be used with the center breaker
control switch (CS) (80122) and the other shall be used with the main
bus No. 2 breaker control switch (CS) (80132). Both synchronizing
switches (SS) shall each be used with the relevant breaker control
switch for closing the relevant power circuit breaker via a common
synchro-check relay (25+27/59). Each synchronizing switch (SS)
shall use the interposing relays of the latched-in type for mode
selection functions. The output contacts of the interposing relay shall
represent “Local Control Mode” of the contacts of the synchronizing
switch (SS) for use in conjunction with the output contacts of other
interposing relays which represent the contacts of the relevant
breaker control switch (CS) in item (xii). The other output contacts of
the interposing relay which represent the contacts of the
synchronizing switch (SS) shall also switch the relevant incoming
voltage and the running bus voltage to initiate the common synchro-
5-3
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
check relay (25-27/59) for closing the 230 kV line power circuit
breaker (80122).
(xii) Two (2) breaker discrepancy control switches (CS): one center
breaker control switch (CS) and the other for main bus No. 2 breaker
control switch (CS) as per Sub-Clause 3.2.16(a). The breaker control
switches (CS) shall be furnished with interposing relays which are
mounted inside the panel. These interposing relays shall provide
output contacts to represent the breaker control switch (CS) for
control of the relevant power circuit breaker through output contact of
interposing relay which represent the relevant synchronizing switch
(SS) in item (xi) for both mode selection functions of synchronizing
switch (SS) and switching of the relevant incoming voltage and
running bus voltage to initiate the common synchro-check relay (25-
27/59) which provided in this Panel No. 1F at “Local Control Mode”
for closing of 230 kV line breaker when the synchronism condition is
met.
(xiii) One (1) light box, engraved with “230 kV Line No. 1 to Ubon
Ratchathani 3 Substation”, as per Sub-Clause 3.2.11.
(xiv)One (1) potential and current test switch complete with multi-pole test
plug as per Sub-Clause 3.2.12, for 230 kV line No. 1 to EGAT-Ubon
Ratchathani 3 Substation.
(xv) Four (4) discrepancy control switches (DCS) for operation of motor
operated disconnect switches (80215), (80214), (80224) and (80221)
via the output contacts of interposing relays mounted inside the
panel, which represent the contacts of the discrepancy control
switches (DCS), as per Sub-Clause 3.2.16(b) and as per Sub-Clause
3.2.30 for interposing relays.
The amber light will be “on” when the line ground switch (80221G) is
open.
This synchronizing switch (SS) shall be used with Main bus No. 1 the
breaker control switch (CS) for closing of the main bus No. 1 230 kV
power circuit breaker (80212). Each synchronizing switch (SS) shall
use the interposing relays of the latched-in type for mode selection
functions. The output contacts of interposing the relay shall represent
“Remote Control Mode-Normal-Local Control Mode” of the contacts
of the synchronizing switch (SS) for use in conjunction with the output
contacts which represent the contacts of the breaker control switch
(CS) in item (xviii). The other output contacts of interposing relay
which represent the contacts of the synchronizing switch (SS) shall
5-4
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
also switch the relevant incoming voltage and the running bus voltage
to initiate the common synchro-check relay (25-27/59) for closing the
230 kV line power circuit breaker (80212).
(xviii) One (1) main bus No. 1 breaker discrepancy control switches (CS),
as per Sub-Clause 3.2.16(a). The breaker control switches (CS) shall
be furnished with interposing relays which are mounted inside the
panel. These interposing relays shall provide output contacts to
represent the breaker control switch (CS) for control of power circuit
breaker (80212) through output contact of interposing relay which
represent the synchronizing switch (SS) in item (xvii) for both mode
selection functions of synchronizing switch (SS) and switching of
incoming voltage and run bus voltage to initiate the common synchro-
check relay (25-27/59) in item (vii) at “Local Control Mode” for closing
of 230 kV line breaker when the synchronism condition is met.
(xx) One (1) light box, engraved with “230 kV Line No. 2 to 230 kV Ubon
Ratchani 3 Substation”, as per Sub-Clause 3.2.11.
(xxi)One (1) potential and current test switch complete with multi-pole test
plug as per Sub-Clause 3.2.12, for 230 kV Line No. 2 to EGAT Ubon
Ratchathani 3 Substation.
(xxii) Four (4) discrepancy control switches (DCS) for operation of motor
operated disconnect switches (80223), (80233), (80235) and (80211)
via the output contacts of interposing relays mounted inside the
panel, which represent the contacts of the discrepancy control
switches (DCS), as per Sub-Clause 3.2.16 (b) and as per Sub-Clause
3.2.30 for interposing relays.
One (1) synchronizing switch (SS) shall be used with the center
breaker control switch (CS) (80222) and the other shall be used with
the main bus No. 2 breaker control switch (CS) (80232). Both
synchronizing switch (SS) shall each be used with the relevant
breaker control switch (CS) for closing the relevant power circuit
breaker via a common synchro-check relay (25+27/59). Each
synchronizing switch shall use the interposing relays of the latched-in
type for mode selection functions. The output contacts of interposing
relays shall represent “Remote Control Mode” and “Local Control
Mode” of the contacts of the synchronizing switch (SS) for use in
conjunction with the output contacts of other interposing relays which
5-5
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
(xxiv)Two (2) breaker discrepancy control switches (CS), one for center
breaker control switch (CS) and the other one main bus No. 2 breaker
control switch (CS) as per Sub-Clause 3.2.16(a). The two breaker
control switches (CS) shall be furnished with interposing relays which
are mounted inside the panel. These interposing relays shall provide
output contacts to represent these two switches (CS) for control of
the relevant power circuit breaker through output contact of
interposing relay which represent the relevant synchronizing switch
(SS) in item (xxiii) for both mode selection functions of synchronizing
switch (SS) and switching the relevant incoming voltage and running
bus voltage to initiate the common synchro-check relay (25+27/59)
for closing the relevant 230 kV line circuit breaker until the
synchronism condition is met
(xxv) One (1) light box, engraved with “230 kV Line No. 2 to Xe-Namnoy”.
(xxvi)One (1) potential and current test switch complete with multipole test
plug, as per Sub-Clause 3.2.12, for 230 kV Line No. 2 to Xe-Namnoy.
(xxvii) One (1) lot of providing brackets, mounting, and wiring of four (4)
remote inputs/outputs (I/O) module which are parts of the Distributed
Control and Monitoring System (DCMS). The DCMS system shall be
furnished and mounted in the 230 kV Pakse substation equipment
under the control selector switch (43 DCMS) in the “Remote Control
Mode” by the operator work station located in the control building.
However in this mode, it can be performed by the Programmable
Logic Controller (PLC) mounted on Panel No. 5R which is mounted
between protective relay board panel 4R and 6R.
The remote I/O module shall interface with the Programmable Logic
Controller (PLC) which is mounted on the swing rack board Panel No.
5R. The remote I/O module will received the command from the PLC
and then send this command via the output contact of interposing relay
in item (xxviii) which represent contact of the remote I/O module to
operate 230 kV power circuit breaker or motor operated disconnect
switch or closing the 230 kV power circuit breaker through
synchronizing switch in “Remote Control Mode”
The power supply for remote I/O module shall be rated 220 VDC.
(xxviii) One (1) lot of interposing relays shall be furnished, mounted and
wired on the brackets inside the Control SwitchboardEquipment
Layout, at the top view plan of the respective drawing. The
5-6
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
(xxix)One (1) lot of loss-of-DC alarm relays (27XB, 27XR) for control
schematic circuits of circuit breaker control, motor operated
disconnect switch control, interposing relay control circuits for breaker
control, interposing relay circuit for disconnect switch control,
interposing relay for synchronizing selector switch control and etc.
Loss-of-DC alarm relays shall be as for Sub-Clause 3.2.19(j).
(xxx) One (1) lot of wiring for control from this panel to 230 kV substation
equipment and to interface the remote inputs/outputs (I/O) module in
this panel. The wiring shall also be provided between this remote I/O
module to interface with the Programmable Logic Controller (PLC)
panel No. 5R for remote operation of 230 kV substation equipment.
(xxxi)One (1) lot of miniature circuit breaker (MCB) for power supply
disconnects to isolate the devices from power supplies in the tripped
or open conditions, as per Sub-Clause 3.2.6.
(xxxii) One (1) lot of engraving nameplates for designations of the panel
and all devices mounted on the front face of the panel and mounted
inside of the panel shall be assigned the designations, as per Sub-
Clause 3.2.7 and 3.2.14.
(xxxiii) One (1) lot of painting mimic buses, devices and symbols on the
panel, as per Sub-Clause 3.2.15.
5-7
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
(i) One (1) indicating voltmeter, semiflush mount, 110 mm square face,
with 250° scale arc, range 0-300 kV, 50 Hz, VT ratio
230,000 / 3 : 115 / 3 , as per Sub-Clause 3.2.17.
(ii) One (1) voltmeter phase selection (VS), four-position “OFF, 1-2, 2-3,
3-1 for use with item (i), as per Sub-Clause 3.2.16.
(iv) One (1) main bus No. 1 discrepancy control switches (DCS) for
operation of motor operated disconnect switch (80215A) via the output
contacts of interposing relays mounted inside the panel, which
represent the contacts of the discrepancy control switches (DCS), as
per Sub-Clause 3.2.16(b) and as per Sub-Clause 3.2.29 for interposing
relays.
(v) One (1) main bus No. 1 breaker discrepancy control switches (CS),
as per Sub-Clause 3.2.16(a). The breaker control switches (CS) shall
be furnished with interposing relays which are mounted inside the
panel. These interposing relays shall provide output contacts to
represent the breaker control switch (CS) for control of the main bus
No. 1 power circuit breaker (80212A).
(vi) One (1) on load tap changer (LTC) selector switch (43AMDCS),
maintained contact type, three-position “Auto-Manual-DCS Control”.
This selector will be furnished by the transformer manufacturer.
(viii) One (1) Automatic Voltage Regulating relay (AVR), flush-mount type
for automatic LTC control in “Auto-Mode”.
5-8
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
Contractor.
(x) One (1) symbol of Dropout fuse cutout, as per Sub-Clause 3.2.15.
(xii) One (1) light box, engraved with “Station Service Distribution Board”.
(xiii) Two (2) light boxes, one box, engraved with “230 kV Main Bus No. 1”
the other engraved with “230 kV Main Bus No. 2”.
(xiv) One (1) potential and current test switch complete with multi-pole test
plugs, as per Sub-Clause 3.2.12, for use with item (ii).
(xv) One (1) lot of providing brackets, mounting, and wiring of one (1)
remote inputs/outputs (I/O) module which is part of the Distributed
Control and Monitoring System (DCMS). The DCMS system shall be
furnished and mounted in the 230 kV Pakse substation control
building to provide remote control and monitoring of the 230 kV
substation equipment by operator work station located in the control
building. However, the “local automatic mode” can be performed by
the Programmable Logic Controller (PLC) which is mounted on Panel
No. 5R between protective relay board Panel No. 4R and 6R.
The remote I/O module shall interface with the Programmable Logic
Controller (PLC) which is mounted on the swing rack board Panel No.
5R. The remote I/O module will received the command from the PLC
and then send this command via the output contact of interposing
relay in item (xiii) which represent contact of the remote I/O module to
operate 230 kV power circuit breaker or motor operated disconnect
switch or closing the 230 kV power circuit breaker through
synchronizing switch in “Remote Control Mode”
The power supply for remote I/O module shall be rated 220 VDC.
(xvi) One (1) lot of interposing relays shall be furnished, mounted and
wired on the brackets inside the panel as indicated inside the Control
SwitchboardEquipment Layout at the top view plan, drawing No.
71.2119.27.206. The interposing relays shall be rated 48 VDC in
according to Sub-Clause 3.2.30.
5-9
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
(xvii) One (1) lot of loss-of-DC alarm relays (27XB, 27XR) for control
schematic circuits of circuit breaker control, motor operated
disconnect switch control, interposing relay control circuit for breaker
control, interposing relay circuit for disconnect switch control,
interposing relay for synchronizing selector switch control and etc.
Loss-of-DC alarm relays shall be as for Sub-Clause 3.2.19(i).
(xviii) One (1) lot of wiring for control from this panel to 230 kV substation
equipment, and to interface remote inputs/outputs (I/O) module in this
panel. The wiring shall also be provided between the remote I/O
module to interface with the Programmable Logic Control (PLC)
Panel No. 5R for remote operation of 230 kV substation equipment.
(xix) One (1) lot of miniature circuit breaker (MCB) for power supply
disconnects to isolate the devices from power supplies in the tripped
or open conditions, as per Sub-Clause 3.2.6.
(xx) One (1) lot of engraving nameplates for designations of the panel and
all devices mounted on the front face of the panel and mounted inside
of the panel shall be assigned the designations as per Sub-Clause
3.2.7 and 3.2.14.
(xxi) One (1) lot of painting mimic buses, devices and symbols on the
panel, as per Sub-Clause 3.2.15.
Thirteen (13) swing rack type protective relay switchboard and one (1) swing
rack type Programmable Logic Controller (PLC) and interposing relay board
shall consist of the following equipment and integral accessories mounted and
completely wired on the swing rack type switchboard as indicated on the
drawing entitled: “230 kV Protective Relay Switchboard–Equipment Layout”
drawing No. 71.2119.27.207 as follows:
(a) Panel No. 1R, Primary Pilot Relaying System No. 1 (LP1) for 230 kV Line
No. 1 to 230 kV Xe-Namnoy Switchyard shall comprise:
5-10
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
The primary pilot relaying system No. 1 (LP1) shall initiate single-pole
and three-pole tripping and reclosing protection scheme upon fault
clearing. The three-pole reclosure shall be done through a synchro-
check relay.
(ii) A backup protection (21BU) shall be of the full scheme type distance
relay, consisting of first, second, and third zones of directional
distance elements for protection against phase and ground faults.
Two timing relays (2) shall be separately provided for time-delayed
trip of zone 2 and zone 3.
(iii) One (1) lot of high speed auxiliary tripping relays (94L-A, 94L-B, 94L-
C) for pilot single & three pole trip, as per Sub-Clause 3.2.20(h).
(iv) One (1) lot of high speed auxiliary tripping relays (94BU) for backup
trip as per Sub-Clause 3.2.20(h).
(v) One (1) lot of loss-of-potential alarm relay (27S), as per Sub-Clause
3.2.19(k).
(vi) One (1) reclosing relay of single shot (79-1), it shall be used in
conjunction with a synchro-check relay (25-27/59) in item (vii) and the
output contact of the interposing relay of the latched-in type, mounted
on Panel No. 5R, which represents the recloser cutoff switch (79CO)
in item (viii). The reclosing relay shall be capable of completing its
reclosing cycle in accordance with the requirements of Sub-Clause
3.2.20(f) for three-pole reclosing of the 230 kV line power circuit
breaker.
The reclosing relay (79-1) shall be used under the recloser operation
selection switch (79ROS) which is provided and mounted on the
panel 2R. The reclosing relay (79-1) can be selected as either
“Master” or “Follower” as required and based on the operation
selection switch (79ROS).
5-11
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
The line voltage and the bus voltage shall be wired to initiate the
synchro-check relay (25+27/59) for reclosing of the line breaker, via
the recloser cutoff switch (79CO) item (viii) in the “ON” position.
(viii) The recloser cutoff switch (79CO) shall be provided for use in “Local
Control Mode” under the control of control selector switch (43DCMS),
two-position, “Local Control Mode” – “Remote Control Mode” (DCMS
system control). The 43DCMS switch shall be mounted on the
control switchboard panel 2F drawing 71.2119.27.206.
The recloser cutoff switch (79CO) shall be used with the reclosing
relay (79-1) in item (vi) in the “ON” position for single-pole reclosing
as described in item (vi). For three-pole reclosing, the reclosing relay
(79-1) shall operate in conjunction with the synchro-check relay
(25+27/59) in item (vii) and the output contact of interposing relay of
the latched-in type mounted on panel No. 3R, which represents the
recloser cutoff switch (79CO) to perform reclosing of the 230 kV
circuit breaker.
(ix) One (1) line current differential cutoff switch (87L-CO) as per Sub-
Clause 3.2.16(k).
(x) One (1) communication channel cutoff switch (PTT-CO) as per Sub-
Clause 3.2.16(o) shall be furnished to disable channel signals when
pilot channels are out of service.
(xi) One (1) lot of loss-of-DC alarm relays (27XB, 27XR) rated 220 VDC
for control schematic circuits for all protective relaying system, 230
switchyard equipment, DC power supply for each 220 VDC motor that
operates each 230 kV disconnect switch, and DC supply for each 220
VDC mechanism device for each 230 kV single-pole breaker and 48
VDC control circuits of interposing relays. Loss-of-DC alarm relays
shall be in according to Sub-Clause 3.2.19(j).
(xii) One (1) set of direct transfer tripping scheme No. 1 (DTT1) for 230 kV
line No. 1 to Xe-Namnoy as per Sub-Clause 3.2.27, shall be provided
with 230 kV line No. 1 to Xe-Namnoy for tripping the remote end
power circuit breaker instantaneously by using the first transfer trip
transmitter. Each transmitter shall have two channels. This set of the
DTT1 scheme No. 1 shall have the same equipment as the second
set of the direct transfer tripping scheme No. 2 (DTT2) on Panel 2R,
Sub-Clause (xv). The Contractor shall furnish the first set of DTT1
scheme No. 1 equipment to be mounted and completely wired in
accordance with the requirements of the second set DTT2 scheme
No. 2 on Panel 2R, except that the two channels of the first
transmitter shall use the same OFC as the communication link but
with separate core between two channels and between the two
5-12
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
transmitters. The DTT1 scheme No. 1 shall be applied for the same
breaker failure protection and circuit breaker open protection as for
the DTT 2 No. 2 scheme on Panel 2R.
50
(2) One (1) non-direction ground overcurrent relay ( SG ) as per
51
Sub-Clause 3.2.19(g).
(3) One (1) auxiliary tripping and lockout relay 86S, as per Sub-
Clause 3.2.19(e).
(5) One (1) stub protection cutoff switch (51S-CO), as per Sub-
Clause 3.2.16(r).
(6) One (1) loss-of-DC alarm relay (27XR), for monitoring of 220 VDC
control circuit of stub protection relaying system, as per Sub-
Clause 3.2.19(j).
(3) One (1) auxiliary tripping and lockout relay (86BF), as per Sub-
Clause 3.2.25(c).
(4) One (1) breaker failure cutoff switch (50BF-CO), as per Sub-
Clause 3.2.16(i).
(5) One (1) loss-of-DC alarm relay (27XR), 220 VDC, as per Sub-
Clause 3.2.19(j).
5-13
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
(xv) Six (6) breaker trip supervision relays (95TCS-1, øA, 95TCS-1, øB,
95TCS-1, øC and 95TCS-2, øA, 95TCS-2, øB, 95TCS-2, øC) as per
Sub-Clause 3.2.26, for 230 kV circuit breaker (80112).
Each relaying system shall provide contact outputs for the following
functions:
- Recloser blocking
(xvii) One (1) lot of interwiring from primary pilot relaying system No. 1
(LP1) and backup protective relaying system equipment to associated
protective relay switchboard, Programmable Logic Controller (PLC) &
5-14
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
(xviii) One (1) lot of miniature circuit breaker (MCB) for VT potential
circuits for protective relay system, DC control circuit for each
relaying system DC control circuit of interposing relays, and etc., as
per Sub-Clause 3.2.6 shall be furnished mounted and wired.
The primary pilot relaying system No. 1 backup protective relaying system
equipment and direct transfer tripping scheme (DTT) shall also strictly meet
the requirements of this Specification and EGAT PPA, Schedule 15:
SCADA and Communication System and Schedule 16: Protective System.
(b) Panel No. 2R, Primary Pilot Relaying System No. 2 (LP2) shall comprise:
(ii) A full scheme type distance relay for backup protection (21-1, 21-2,
21-3) as per Sub-Clause 3.2.20(b)(i)(1) shall be furnished to achieve
the primary pilot relaying and the backup relaying for the protection of
the 230 kV transmission line.
(iv) Each relay line terminal shall be furnished with the following
functions:
5-15
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
(v) One (1) lot of high speed auxiliary tripping relays (94P-A, 94P-B, 94P-
C) for pilot single or three pole tripping as per Sub-Clause 3.2.20(h).
(vi) One (1) lot of high speed auxiliary tripping relays (94BU) for backup
three-pole trip, as per Sub-Clause 3.2.20(h).
(vii) One (1) lot of loss-of-potential alarm relay (27P) as per Sub-Clause
3.2.19(k).
(viii) One (1) lot of loss-of-DC alarm relay (27XR), 220 VDC as per Sub-
Clause 3.2.19(j).
(ix) One (1) lot of loss-of-DC alarm relays (27XB1-1, 27XB1-2, 27XB2),
220 VDC, for line breaker (8012) closing circuit, and tripping circuit
coil No. 1 and coil No. 2 as per Sub-Clause 3.2.19(j).
(x) One (1) reclosing relay of single shot (79-1) for center 230 kV circuit
breaker (80122) shall be furnished for use with a synchro-check relay
(25+27/59) in item (vii) on Panel No. 1R via a recloser operation
selection switch (79ROS) and the recloser cutoff switch (79CO) in items
(xi) and (xii) in this panel respectively. However, the output contacts of
interposing relays provided on Panel No. 5R shall be used to represent
the contacts of recloser cutoff switch (79CO) in the “ON” position.
(xi) One (1) recloser operation selection switch (79ROS), two position
“Master-Follower” for selection of either recloser (79-1) for circuit
breaker (80112) or recloser (79-1) for circuit breaker (80122) to be a
“Master” and the other will be a “Follower”. Necessary relays and
reclosing selection scheme shall be provided to accomplish the
recloser selection function, shall be furnished mounted and wired.
(xii) One (1) recloser cutoff switch (79CO) shall be furnished for use in “Local
Control Mode” under the control of control selector switch (43 DCMS)
which is mounted on the control switchboard panel 2F. The recloser
cutoff switch (79CO) shall have two-position “ON-Normal-OFF”
(xiii) The Contractor shall furnish wiring of all these protective relays and
devices to provide the pilot tripping and reclosing of the primary pilot
relaying system No. 2 (LP2) as defined under this Specification.
5-16
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
For backup protection, the Contractor shall also furnish wiring of the
high speed auxiliary tripping relays (94BU) for three-pole tripping of
the 230 kV line breaker to meet the requirement of the Specification.
Each relaying system shall provide contact outputs for the following
functions:
- Reclosing blocking
(xv) One (1) set of Direct Transfer Tripping scheme No. 2 (DTT2) for 230
kV line No. 1 to Xe-Namnoy as per Sub-Clause 3.2.27 shall be
provided with each line protection for tripping the remote end power
circuit breaker instantaneously by using the second transfer trip
transmitter. Each transmitter shall have two channels. The
associated communication link shall be optical fiber cable (OFC)
embedded in composite overhead galvanized shield wire (OPGW)
strung on the transmission line tower for the DTT1 scheme, channel
No. 1 and the channel No. 2 for the DTT2 scheme, shall also use the
same OFC but separate core as a communication link.
5-17
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
(1) One (1) lot of high speed auxiliary tripping relays for direct
transfer trip scheme (94DTT2) as per Sub-Clause 3.2.27(a).
(2) One (1) lot of timing relay (62DTT2) time delay open contact
(TDO), 0-200 ms, 220 VDC, as per Sub-Clause 3.3.27(b)(4).
(3) One (1) lot of timing relay (62DTT2), time delay close contact
(TDC), 0-2.5 sec., 220 VDC, as per Sub-Clause 3.2.27(a).
(4) One (1) lot of direct transfer auxiliary tripping and lockout relay
(86DTT2), 220 VDC, as per Sub-Clause 3.2.27(a).
(5) One (1) direct transfer trip cutoff switch (DTT2-CO), as per
Sub-Clause 3.2.16(o).
(6) One (1) lot of loss-of-DC alarm relay (27XR), 220 VDC, as per
Sub-Clause 3.2.19(j).
(xvi)Six (6) breaker trip supervision relays (95TCS-1, øA, øB, øC and
95TCS-2, øA, øB, øC) as per Sub-Clause 3.2.26 for 230 kV breaker
(80122).
(1) One (1) current detector relay shall contain three phase units
(50BF), as per Sub-Clause 3.2.25(a).
(3) One (1) auxiliary tripping and lockout relay (86BF), as per Sub-
Clause 3.2.19(c).
(4) One (1) breaker failure cutoff switch (50BF-CO), as per Sub-
Clause 3.2.16(i).
5-18
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
(5) One (1) loss-of-DC alarm relay (27XR) for use with DC control
circuit of breaker failure relaying, as per Sub-Clause 3.2.19(j).
(xviii) One (1) lot of interwiring from primary pilot relaying system No. 2
(LP2) and backup protective relaying system equipment to protective
relay switchboard panel No. 1R and other associated relay
switchboards, Programmable Logic Controller (PLC) board panel No.
5R, to marshalling cabinet for termination of primary pilot relays (LP2)
to teleprotection equipment, to the interposing relays which are
mounted on the same swing rack panel of PLC, panel No. 5R, and to
the relevant control switchboard panel and etc.
(xix)One (1) lot of miniature circuit breaker (MCB) for VT potential circuits
for protective relay system, DC supply control circuit for each relaying
system DC Control circuit of interposing relays, and etc., as per Sub-
Clause 3.2.6 shall be furnished mounted and wired.
(xx) One (1) lot of engraved nameplates for mounting each nameplate
behind or adjacent to each corresponding device shall be furnished
and installed and complete with inscription of each nameplate, as per
Sub-Clause 3.2.7 and 3.2.14.
The primary pilot relaying system No. 2 and backup protective relaying
5-19
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
(c) Panel No. 3R, Primary Pilot Relaying System No. 1 (LP1) using Line
Current Differential Relay for 230 kV Line No. 1 to EGAT 230 kV Ubon
Ratchathani 3 Substation
This panel shall have the same primary pilot relaying system No. 1 (LP1)
equipment, backup protective relaying equipment, stub protective relaying
equipment, breaker failure relaying system equipment and breaker trip
circuit supervision relays as Panel No. 1R, except that 230 kV line
breakers for 230 kV line No. 1 to EGAT 230 kV Ubon Ratchathani 3
substation shall be (80122) and (80132), the breaker failure protection
equipment and breaker trip circuit supervision relays shall be for 230 kV
line circuit breaker (80132) and stub protection shall be provided for the
section between the two line breakers (80122), (80132) and line
disconnect switch (80121).
(i) The direct transfer tripping scheme No. 1 equipment (DTT1) for 230
kV line No. 1 to EGAT Ubon Ratchathani 3 Substation as per Sub-
Clause 3.2.27, shall be provided with 230 kV line No. 1 to EGAT
Ubon Ratchathani 3 substation for tripping the remote end power
circuit breaker instantaneously by using the first transfer trip
transmitter. Each transmitter shall have two channels. This first set
of the DTT1 scheme No. 1 shall have the same equipment as the
second set of the DTT 2 scheme No. 2 on Panel 2R, Sub-Clause
(xv). The Contractor shall furnish the first set of DTT1 scheme No. 1
equipment to be mounted and completely wired in according to the
requirements of the second set DTT2 scheme No. 2 (Panel 2R)
except that the two channels of the first transmitter shall use the
same OFC as the communication link but with separate core between
two channels and between the two transmitters. The DTT1 scheme
No. 1 shall be applied for the same breaker failure protection and
circuit breaker open protection as for the DTT2 scheme No. 2 on
Panel 4R.
(ii) One (1) lot of interwiring from primary pilot relaying system No. 1
(LP1) and backup relaying system equipment to associated protective
relay switchboard, Programmable Logic Controller (PLC) and
Interposing relay board panel No. 5R, the relevant marshalling
cabinet for termination of primary pilot relaying system No. 1 (LP1)
and teleprotection equipment, to output contacts of interposing relays
for use with recloser cutoff switch (79CO) and the reclosing relay (79-
1) for either single-pole reclosing of the line breakers or three-pole
reclosing of the line breaker via a synchro-check relay (25+27/59),
and to the relevant control switchboard panel, shall be furnished.
5-20
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
The primary pilot relaying system No. 1 (LP1) and backup protective relay
system and direct transfer tripping scheme (DTT) shall also strictly meet the
requirements of the Specification and EGAT PPA, Schedule 15: SCADA
and Communication System and Schedule 16: Protective System.
(d) Panel No. 4R, Primary Pilot Relaying System No. 2 (LP2) using
Directional Distance Relay for 230 kV Line No. 1 to EGAT 230 kV Ubon
Ratchathani 3 Substation.
(i) This panel shall have the same primary pilot relaying system
equipment as of the Panel No. 2R except that they have not the
following equipment provided:
(ii) This panel shall be furnished with a reclosing relay of single shot
(79-1) and a recloser cutoff switch (79CO) as per Sub-Clause
3.2.20(f) and 3.2.16(f) respectively. The reclosing relay (79-1) shall
be used with the recloser cutoff switch (79CO) via the output contact
of interposing relay of the latched-in type mounted on the Panel No.
5R which represents the contact of the recloser cutoff switch (79CO)
in the “ON” position. The reclosing relay (79-1) shall operate in
conjunction with the synchro-check relay (25+27/59) through the
recloser cutoff switch (79CO) to reclose the main bus No. 2 230 kV
line circuit breaker (80132) of 230 kV line No. 1 to EGAT 230 kV
Ubon Ratchathani 3 substation.
(iii) The direct transfer tripping scheme No. 2 equipment (DTT2) for 230
kV line No. 1 to EGAT Ubon Ratchathani 3 Substation as per Sub-
Clause 3.2.27, shall be provided for this line for tripping remote end
power circuit breaker instantaneously by using the second transfer
trip transmitter. Each transmitter shall have two channels. This
second set of the DTT2 scheme No. 2 shall have the same
equipment as the second set of the DTT2 scheme No. 2 on Panel 2R,
Sub-Clause (xv). The Contractor shall furnish the first set of DTT2
scheme No. 2 equipment to be mounted and wired on Panel No. 4R
in accordance with the requirements of the second set of DTT2
scheme on Panel 2R, except that the two channels of the second
transmitter shall use the same OFC as the communication link but
with separate core between two channels and between two
transmitters. The DTT2 scheme No. 2 shall be applied for breaker
failure protection (80122) and (80132) as per Sub-Clause 3.2.27(b)(i)
and circuit breaker open protection as per Sub-Clause 3.2.27(b)(ii).
5-21
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
(iv) This panel shall interface with the Programmable Logic Controller
(PLC) with HMI including Input/Outputs (I/O) Module provided to
perform the control, monitoring, data acquisition, protection, alarms,
metering system and communication interface to the network system
bus of the DCMS system.
This panel shall also use the interposing relays with their output
contacts which represent the contact of the recloser cutoff switch
(79CO) for use with the reclosing relay (79-1) and the synchro-check
relay (25+27/59) for reclosing the 230 kV line No. 1 to EGAT 230 kV
Ubon Ratchathani 3 substation.
(v) This panel shall also interface with other relevant protective relay
switchboard in order to accomplish the necessary control and
protection system and shall meet the requirements of
EGAT PPA, Schedule 15: SCADA and Communication System and
Schedule 16: Protective System.
The two (2) primary pilot relaying system No. 1 and No. 2 together with
backup protective relaying system and direct transfer tripping scheme
(DTT) shall also strictly meet the requirements of this Specification and
EGAT PPA, Schedule 15: SCADA and Communication System and
Schedule 16: Protective System.
(e) Panel No. 5R, Programmable Logic Controller (PLC) and Interposing
Relays
(i) One (1) swing rack board shall be furnished by the Contractor of
Control and Protection System. The swing rack board shall be
constructed exactly the same as the swing rack type protective relay
switchboard construction as per Sub-Clause 3.2.2(b) and detailed
switchboard construction shall be in according to the drawing No.
71.2119.27.400.
The PLC and HMI are allowed, in local automatic mode, to perform
5-22
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
The Contractor shall provide minimum point list of the following digital
inputs:
The PLC shall also receive the analog inputs of electrical amp, volts,
watt, var and frequency from the transducer output 4-20 mA as per
Sub-Clause 3.2.18. The transducers shall be mounted and wired in
the transducer cabinet.
All data listed above which of 230 kV Pakse substation shall follow
the requirements of EGAT PPA, Schedule 15: Part B, Pakse SCADA
System and shall be collected by a Data Gateway and shall be
transmitted via OPGW as a communication link to EGAT national
Control Center (NCC), Backup National Control Center (NCC) and
Regional Control Center (RCC) for exchange of information and etc.
For three-phase fault, the reclosing relay (79-1) will operate the
synchro-check relay (25+27/59) via output contact which represents
the 79CO switch until the synchronism condition is met. The
incoming voltage and the running voltage shall be wired directly to the
synchro-check relay.
5-23
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
(f) Panel No. 6R, 230 kV Main Bus No. 1 Primary Protection Bus Differential
Relay (87B1P)
(i) One (1) set of 230 kV main bus No. 1 differential relay (87B1P) for
primary protection shall be of the low impedance, three-phase, high
speed, 50 Hz and the numerical type. Each set of differential relay
shall be furnished with three (3) units, detail of which shall be as per
Sub-Clause 3.2.19(c).
(ii) One (1) lot of auxiliary tripping and lockout relay (86B1P), as per Sub-
Clause 3.2.19(e).
(iii) One (1) bus differential cutoff switch (87B1P-CO), as per Sub-Clause
3.2.16(h).
(iv) One (1) loss-of-DC alarm relay (27XR), as per Sub-Clause 3.2.19(j),
220 VDC, for monitoring bus differential DC control schematic.
- Tripping of all 230 kV main bus circuit breakers with two (2) trip
coils per pole.
(vi) One (1) lot of miniature circuit breaker (MCB) for 220 VDC control
schematic circuits of bus differential relaying system, 230 kV circuit
breaker control system, 48 VDC control circuits of interposing relays
and etc., as listed in the Sub-Clause 3.2.6 shall be furnished,
mounted and wired.
5-24
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
(vii) One (1) lot engraved nameplates for mounting each nameplate
behind or adjacent to each corresponding device, and complete with
inscription on each nameplate shall be furnished and installed, as per
Sub-Clause 3.2.7 and 3.2.14.
The protective relaying system equipment shall also strictly meet the
requirements of this Specification and EGAT PPA, Schedule 15: SCADA
and Communication System and Schedule 16: Protective System.
(g) Panel No. 7R, 230 kV Main Bus No. 2 Primary Protection Bus Differential
Relay (87B2P)
This panel shall have the same primary bus differential protection and all
auxiliary equipment as listed in Panel No. 6R except that there shall be
two (2) units and the primary differential protection shall be for 230 kV
main bus No. 2.
The protective relaying system equipment shall also strictly meet the
requirements of this Specification and EGAT PPA, Schedule 15: SCADA
and Communication System and Schedule 16: Protective System.
(h) Panel No. 8R, 230 kV Main Bus No. 1 Secondary Protection Bus
Differential Relay (87B1S)
(i) One (1) set of 230 kV main bus No. 1 differential relay (87B1S) for
secondary differential protection shall be of the high impedance, high-
speed, single-phase, voltage operated type with overvoltage limit
device and shall be of the numerical type, as per Sub-Clause
3.2.19(c).
(ii) One (1) lot of auxiliary tripping and lockout relay (86B1S), as per Sub-
Clause 3.2.19(e).
(iii) One (1) bus differential cutoff switch (87B1S-CO), as per Sub-Clause
3.2.16(h).
(iv) One (1) loss-of-DC alarm relay (27XR), as per Sub-Clause 3.2.19(j),
for monitoring of 220 VDC bus differential relaying control schematic.
5-25
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
- Tripping of all 230 kV bus circuit breakers with two (2) trip coils per
pole.
(vi) One (1) lot of miniature circuit breaker (MCB) for 220 VDC control
schematic circuits of bus differential relaying system, 230 kV circuit
breaker control system, 48 VDC control schematic circuits of
interposing relays and etc., as listed in the Sub-Clause 3.2.6 shall be
furnished, mounted and wired.
(vii) One (1) lot engraved nameplates for mounting each nameplate
behind or adjacent to each corresponding device, and complete with
inscription on each nameplate shall be furnished and installed, as per
Sub-Clause 3.2.7 and 3.2.14.
The protective relaying system equipment shall also strictly meet the
requirements of this Specification and EGAT PPA, Schedule 15: ACADA
and Communication System and Schedule 16: Protective System.
(i) Panel No. 9R, 230 kV Main Bus No. 2, Secondary Protection Bus
Differential Relay (87B2S)
This panel shall have the same secondary bus differential protection and
all auxiliary equipment as listed in Panel No. 8R.
5-26
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
The protective relaying system equipment shall also strictly meet the
requirements of this Specification and EGAT PPA, Schedule 15: SCADA
and Communication System and Schedule 16: Protective System.
The swing rack type protective relay switchboard shall be furnished with
the following equipment. All equipment shall be furnished complete with
integral accessories, mounted and completely wired.
(2) One (1) auxiliary tripping and lockout relay (86K), as per Sub-
Clause 3.2.19(e).
50
(1) Three (3) single-phase non-directional overcurrent relays ( T)
51
of numerical type as per Sub-Clause 3.2.19(f).
(5) Alarm contacts for relay operation for initiating the Programmable
5-27
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
(iv) One (1) set of breaker failure protection for 230 kV bus breaker
(8212A), details of which shall be as follows:
(3) One (1) auxiliary tripping and lockout relay (86BF), as per Sub-
Clause 3.2.19(e).
(4) One (1) breaker failure cutoff switch (50BF-CO), as per Sub-
Clause 3.2.16(i).
(5) One (1) loss-of-DC alarm relay (27XR), 220 VDC, as per Sub-
Clause 3.2.19(j).
(v) Six (6) breaker trip supervision relays (95TCS-1, øA, øB, øC, and
95TCS-2, øA, øB, øC) for 230 kV breaker (80212A) as per Sub-
Clause 3.2.26 for supervising the electrical continuity in the tripping
circuit all time even though breaker closed or open. In the event that
the voltage supply drop below 40% of nominal voltage, this relay shall
also operate to provide contact outputs for alarm signaling.
5-28
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
(vi) All relay system outputs, auxiliary tripping and lockout relays, loss-of-
DC alarm relay, and etc shall furnish contacts to initiate the
Programmable Logic Controller (PLC) mounted on panel No. 5R for
sending these trouble alarms to the operator work station in the
power plant control room.
(vii) One (1) lot of miniature circuit breaker (MCB) for control circuits of
transformer differential protective relaying, transformer overcurrent
protection, DC control schematic of 230 kV breakers, DC control
circuit for interposing relays, and etc. as required and listed in the
Sub-Clause 3.2.6 “Power Supply Disconnects”, shall be furnished,
mounted and completely wired.
(viii) One (1) lot of engraved nameplates for mounting each nameplate
behind or adjacent to each corresponding device, and complete with
inscription on each nameplate shall be furnished and installed, as per
Sub-Clause 3.2.7 and 3.2.14.
(k) Panel No. 11R, 230 kV Primary Pilot Relaying System No. 1 (LP1) Line
Current Differential relay for 230 kV Line No. 2 to Ubon Ratchathani 3
Substation
This panel shall have the same primary pilot relaying system No. 1 (LP1)
equipment, backup protective relaying system equipment, stub protection,
breaker failure protection and breaker trip supervision relays as Panel No.
1R except that the 230 kV line breaker failure protection equipment and
breaker trip supervision relays on this panel shall be for 230 kV circuit
breaker (80212). The stub protection shall be provided for 230 kV line
No. 2 to Ubon Ratchathani 3 substation.
(i) One (1) set of direct transfer tripping scheme No. 1 (DTT1)
equipment for 230 kV line No. 2 to EGAT Ubon Ratchathani 3
substation, as per Sub-Clause 3.2.27, shall be provided for this line
for tripping the remote end powe circuit breaker instantaneously by
using the first transfer trip transmitter. Each transmitter shall have
two channels.
This set of the DTT1 scheme No. 1 shall have the same equipment
as the second set of the DTT2 scheme No. 2 on the Panel 2R, Sub-
Clause (xv).
The Contractor shall furnish the first set of DTT1 scheme No. 1
5-29
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
(ii) One (1) lot of interwiring from primary pilot relaying system No. 1
(LP1) and backup protective relaying system equipment to associated
protective relay switchboard, Programmable Logic Controller (PLC) &
interposing relay board panel 5R, marshalling cabinet for termination
of protective relaying system No. 1 and teleprotection equipment, to
output contacts of interposing for use with recloser cutoff switch
(79CO) and the reclosing relay (79-1) for reclosing of the line
breakers, and to the relevant control switchboard panel and etc. shall
be furnished.
The primary pilot relaying system No. 1 (LP1) and backup relaying system
equipment and direct transfer tripping scheme (DTT) shall also strictly meet
the requirements of this Specification and EGAT PPA, Schedule 15:
SCADA and Communication System and Schedule 16: Protective System.
(l) Panel No. 12R, 230 kV Primary Pilot Relaying System No. 2 (LP2) Using
Distance Protection for 230 kV Line No. 2 to Ubon Ratchathani Substation
This panel shall have to same primary pilot relaying system No. 2 (LP2)
equipment, backup protective relaying equipment, breaker failure relaying
equipment, and breaker trip circuit supervision relays as Panel 2R, except
that 230 kV line breakers for 230 kV line No. 2 to Ubon Ratchathani 3
Substation shall be (80212) and (80222), the breaker failure protection
equipment and breaker trip circuit supervision relays on this panel shall be
for 230 kV circuit breaker (80222) and the stub protection equipment shall
be provided for 230 kV line No. 2 to Ubon Ratchathani 3 Substation.
(i) One (1) set of the direct transfer tripping scheme No. 2 equipment
(DTT2) for 230 kV line No. 2 to EGAT Ubon Ratchathani 3 substation,
as per Sub-Clause 3.2.27, shall be provided for this line for tripping
the remote end power circuit breaker instantaneously by using the
second transfer trip transmitter. Each transmitter shall have to
channels.
This second set of DTT2 scheme No. 2 shall have the same
equipment as the second set of DTT2 scheme No. 2 on Panel 2R,
Sub-Clause (xv).
5-30
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
(ii) One (1) lot of interwiring from primary pilot relaying system No. 2
(LP2) and backup protective relaying system equipment to protective
relay switchboard Panel No. 11R, other associated protective relay
switchboard, Programmable Logic Controller (PLC) & interposing
relay board panel 5R, the relevant marshalling cabinet for termination
of primary pilot relaying system No. 2 (LP2) to the teleprotection
equipment, to output contacts of interposing relays which represent
contact of recloser cutoff switch (79CO) in the “ON” position and to
reclosing relay (79-1) for reclosing the line circuit breakers.
Interwiring between this panel and the relevant control switchboard
shall also be provided.
The primary pilot relaying system No. 2 (LP2) and backup relaying system
equipment and direct transfer tripping scheme (DTT) shall also strictly
meet the requirements of this Specification and EGAT PPA, Schedule 15:
SCADA and Communication System and Schedule 16: Protective
System.
(m) Panel No. 13R, 230 kV Primary Pilot Relaying System No. 1 (LP1) Using
Line Current Differential relay for 230 kV Line No. 2 to Xe-Namnoy
Switchyard
This panel shall have the same primary pilot relaying system No. 1 (LP1)
equipment, backup protective relaying equipment, stub protection relaying
equipment, breaker failure protection relaying equipment, and breaker trip
circuit supervision relays as Panel No. 3R (for 230 kV line No. 1 to Ubon
Ratchathani 3 Substation) except that the 230 kV line circuit breakers for
230 kV line No. 2 to Xe-Namnoy switchyard shall be (80222) and (80232),
the breaker failure relaying equipment and breaker trip circuit supervision
relays on this panel shall be for 230 kV circuit breaker (80232). The stub
protective relaying system shall be provided for 230 kV line No. 2 to Xe-
Namnoy switchyard.
(i) One (1) set of direct transfer tripping scheme No. 1 (DTT1)
equipment for 230 kV line No. 2 to Xe-Namnoy switchyard, as per
Sub-Clause 3.2.27, shall be provided for this line for tripping the
remote end power circuit breaker instantaneously by using the first
5-31
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
This set of the DTT1 scheme No. 1 shall have the same equipment
as the second set of the DTT2 scheme No. 2 on the Panel 2R, Sub-
Clause (xv).
The Contractor shall furnish the first set of DTT1 scheme No. 1
equipment to be mounted and completely wirely on this Panel No.
13R in accordance with the requirements of the second DTT 2
scheme No. 2 (Panel 2R), with separate core between two channels
and between the two transmitters. This DTT1 scheme No. 1 shall be
applied for breaker failure protection and circuit breaker open
protection similar to the DTT2 scheme No. 2 on Panel No. 14R.
(ii) One (1) lot of interwiring from primary pilot relaying system No. 1
(LP1) and backup protective relaying system equipment to associated
protective relay switchboard, Programmable Logic Controller (PLC)
and interposing relay board panel 5R, the relevant marshalling
cabinet for termination of protective relaying system No. 1 and
teleprotection equipment, to output contacts of interposing relays
which represent the contact of recloser cutoff switch (79CO) in the
“ON” position and to reclosing relay (79-1) for reclosing of the line
breakers, and to the relevant control switchboard panel and etc. shall
be furnished.
The primary pilot relaying system No. 1 (LP1) and backup relaying system
equipment shall also strictly meet the requirements of this Specification
and EGAT PPA, Schedule 15: SCADA and Communication System and
Schedule 16: Protective System.
(n) Panel No. 14R, 230 kV Primary Pilot Relaying System No. 2 (LP2) Using
Distance Protection for 230 kV Line No. 2 to Xe-Namnoy Switchyard
This panel shall have the same primary pilot relaying system No. 2 (LP2)
equipment, backup protective relaying equipment, Direct Transfer
Tripping Scheme equipment No. 2 (DTT2), and etc. as Panel 4R (230 kV
line No. 1 to Ubon Ratchathani 3 Substation), except that the 230 kV line
breakers for 230 kV line No. 2 (LP2) to Xe-Namnoy switchyard shall be
(80222) and (80232).
(i) One (1) set of the direct transfer tripping scheme No. 2 equipment
(DTT2) for 230 kV line No. 2 to Xe-Namnoy switchyard, as per Sub-
Clause 3.2.27, shall be provided for this line for tripping the remote end
power circuit breaker instantaneously by using the second transfer trip
transmitter. Each transmitter shall have to channels.
5-32
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
This second set of DTT2 scheme No. 2 shall have the same
equipment as the second set of DTT2 scheme No. 2 on Panel 2R,
Sub-Clause (xv).
(ii) One (1) lot of interwiring from primary pilot relaying system No. 2
(LP2) and backup protective relaying system equipment to associated
protective relay switchboard Panel No. 11R, 12R and other relevant
protective relay switchboard, to Programmable Logic Controller (PLC)
and Interposing relay board panel No. 5R, to relevant control
switchboard panel, to the marshalling cabinet for termination between
primary pilot relaying system No. 2 (LP2) and teleprotection
equipment, to output contacts of interposing relays which represent
contact of recloser cutoff switch (79CO) in the “ON” position and to
reclosing relay (79-1) for either single-pole reclosing or three-pole
reclosing of the line breaker via a synchro-check relay (25-27-59) and
etc., shall be furnished.
The primary pilot relaying system No. 2 (LP2) and backup relaying system
equipment shall also strictly meet the requirements of this Specification
and EGAT PPA, Schedule 15: SCADA and Communication System and
Schedule 16: Protective System.
There shall be two metering systems: one metering system (Panel No. IM)
shall be used for in ensuring and recording the active energy and reactive
energy of the two (2) 230 kV incoming transmission lines from Xe-Namnoy
switchyard and the other metering system (Panel No. OM) shall be used for
5-33
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
measuring and recording the active energy and reactive energy of the two (2)
230 kV outgoing transmission line to EGAT Ubon Ratchathani 3 substation.
Each 230 kV incoming transmission lines each 230 kV outgoing transmission
line, shall each be measured and recorded by one kWh/kVARh as “Backup
energy meter”. Metering system equipment shall meet the requirements of
this specification and EGAT PPA, Schedule 14: Metering System. Each Grid
TOU energy meter shall be furnished with accessories mounted on the
metering cabinet and all equipment shall be completely wired.
(i) Four (4) kWh/kVARh energy meters, 3ø, 4 wire, 50 Hz, 3-current
element, type, suitable for operation with instrument transformers
ratios and connections as shown on “Metering and Relaying
Diagram”, under both normal and short circuit conditions. Each 230
kV incoming line from Xe-Namnoy shall comprise one meter for “Main
energy meter” and the other one meter for “Backup energy meter”.
Details of each Grid TOU meter shall be in accordance with the
requirements as defined under this Specification, Sub-Clause 3.2.31.
(ii) Four (4) current and potential test switches, complete with four (4)
sets of multi-pole test plugs: one test switch for one “Main energy
meter” and other one for “Backup energy meter”, as per Sub-Clause
3.2.12.
(iii) One (1) lot of miniature circuit breakers (MCB) for VT potential
circuits for measuring system as required and listed in Sub-Clause
3.2.6 “Power supply Disconnects”. All MCB shall be provided with
three (3) electrically separate normally closed contacts: one contact
shall be wired to initiate Programmable Logic controller (PLC) and the
other two (2) contacts shall be wired to terminal block for future use.
(iv) One (1) lot engraved nameplates for mounting each nameplate
behind or adjacent to each corresponding equipment complete with
the inscription on each nameplate, shall be furnished as per Sub-
Clause 3.2.7 and 3.2.14.
Grid TOU energy meters for measuring and recording the active energy and
reactive energy for two (2) 230 kV outgoing transmission lines to EGAT Ubon
Ratchathani 3 substation indicated on the drawing No. 71.2119.27.007.
5-34
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
(i) Four (4) KWh/KVARh energy meter with each meter shall be 3ø, 4
wire, 50 Hz, 3-current element type, suitable for operation with
instrument transformers ratios and connections as shown on the
metering and relaying diagram under both normal and short circuit
conditions. Each 230 kV outgoing line shall comprise one meter for
“Main energy meter” and the other one meter for “Backup energy
meter”. Details of each meter shall meet the requirements as defined
in this Specification, Sub-Clause 3.2.31 and shall also follow strictly
EGAT PPA requirements of Schedule 14, Metering Systems.
(ii) Four (4) potential and current test switches, complete with four (4)
sets of multipole test plug, as per Sub-Clause 3.2.12.
(iii) One(1) lot of miniature circuit breakers (MCB) for VT potential control
circuits for measuring system, as required and listed in the Sub-
Clause 3.2.6 “Power Supply Disconnects”, shall be furnished,
mounted and wired. All MCB’s shall be provided with three (3)
electrically separate normally closed contacts: one for initiating the
Programmable Logic Controller (PLC) and the other two (2) contacts
shall be wired to terminal blocks for future use.
(iv) One (1) lot engraved nameplates for mounting each nameplate
behind or adjacent to each corresponding equipment complete with
the inscription on each nameplate, shall be furnished as per Sub-
Clause 3.2.7 and 3.2.14.
(i) Three (3) current transducers, single element type, rated output 4-20
mA unidirectional, external load resistance 0 to 10 k, suitable for
use with CT 2000:1A, CL 0.5, 50 VA as indicated on the drawing
above. Each output shall be wired with a twisted pair shield wire with
wire size 0.5 sq.mm to the Programmable Logic Controller (PLC)
board Panel 5R as indicated on the drawing No. 71.2119.27.207.
Each transducer shall be as per Sub-Clause 3.2.18(e).
5-35
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
(ii) One (1) watt/var transducer, each shall be of the three-phase, four
wire, unbalance load, three current element type, rated out put 4-20
mA, bidirectional, external load resistance 0 to 10k, suitable for use
230000 115
with CT 2000:1A, CL 0.5, 50 VA, and VT ratio 3 : , CL
3 3
0.5, 50 VA, as indicated on the drawing above. The output shall be
wired with twisted pairs shield wire with wire size 0.5 sq.mm to the
Programmable Logic Controller (PLC) board panel No. 5R as
indicated on drawing No. 71.2119.27.207. Each transducer shall be
as per Sub-Clause 3.2.18(b).
(iii) Three (3) voltage transducers, they shall be for measuring of the
three-phase line circuit, each transducer shall be single element
type, rated output to 4-20 mA, unidirectional, external load resistance
230000 115
0 to 10k, suitable for use with VT ratio 3 : , CL 0.5,
3 3
50 VA, as indicated on the above drawing. The output shall be wired
with twisted pairs shield wire with wire size 0.5 sq.mm to the
Programmable Logic Controller (PLC) board Panel No. 5R. Each
transducer shall be as per Sub-Clause 3.2.18(c).
(iv) One (1) potential and current test switch complete with one multi-pole
test plug as per Sub-Clause 3.2.12.
The transducers for this 230 kV line No. 1 shall have the same
transducers for current, watt/var, voltage, potential and current test switch
and wiring material in quantity and characteristic requirements as of
transducers for 230 kV line No. 1 to Xe-Namnoy in item (a).
(i) Three (3) current transducers, single element type, rated output 4-20
mA unidirectional, external load resistance 0 to 10 k, suitable for use
with CT 2000:1A, CL 0.5, 50 VA as indicated on the drawing above.
Each output shall be wired with a twisted pair shield wire with wire size
0.5 sq.mm to the Programmable Logic Controller (PLC) board Panel
5R as indicated on the drawing No. 71.2119.27.207. Each transducer
shall be as per Sub-Clause 3.2.18(e).
(ii) One (1) watt/var transducer, each shall be of the three-phase, four
wire, unbalance load, three current element type, rated out put 4-20
mA, bidirectional, external load resistance 0 to 10k, suitable for use
230000 115
with CT 2000:1A, CL 0.5, 50 VA, and VT ratio 3 : , CL
3 3
0.5, 50 VA, as indicated on the drawing above. The output shall be
wired with twisted pairs shield wire with wire size 0.5 sq.mm to the
Programmable Logic Controller (PLC) board panel No. 5R as
indicated on drawing No. 71.2119.27.207. Each transducer shall be
as per Sub-Clause 3.2.18(b).
(iii) Three (3) voltage transducers, they shall be for measuring of the
three-phase line circuit, each transducer shall be single element type,
5-36
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
(iv) One (1) potential and current test switch complete with one multi-pole
test plug as per Sub-Clause 3.2.12.
The transducers for this 230 kV line No. 2 shall have the same
transducers for current, watt/var, voltage, potential and current test switch
and wiring material in quantity and characteristic requirements as of
transducers for 230 kV line No. 2 to Xe-Namnoy in item (c).
(e) Three (3) voltage transducers, they shall be similar to item (a)(iii) above
except they shall be provided to measure 230 kV main bus No. 1, the
output shall be wire with twisted pairs shield wire with wire size 0.5 sq.mm
to the Programmable Logic Controller (PLC) mounted on Panel No. 5R.
(f) Three (3) voltage transducers, they shall be similar to item (a)(iii) above
except they shall be provided to measure 230 kV main bus No. 2, the
output shall be wire with twisted pairs shield wire with wire size 0.5 sq.mm
to the Programmable Logic Controller (PLC) mounted on Panel No. 5R.
(g) One (1) frequency transducer, single element type, frequency span
48-50-52 Hz, full scale output 4-20 mA, unidirectional, external load
resistance 0 to 10k. This transducer shall be for measuring frequency of
230 kV main bus No. 1. Each transducer shall be suitable for use with VT
23000 115
ratio : , CL 0.5, 50 VA, as indicated on the respective
3 3
drawing. Each transducer shall be as per Sub-Clause 3.2.12(f), the
output shall be wired with a twisted pair shield wire with 0.5 sq.mm wire
size to the Programmable Logic Controller (PLC) mounted on the Panel
No. 5R.
(h) One (1) frequency transducer, it shall be similar to item (g) except that it
shall be used for measuring 230 kV main bus No. 2 and shall be wired to
the Programmable Logic Controller (PLC) mounted on Panel No. 5R.
(i) One (1) potential test switch complete with one multi-pole test plug as per
Sub-Clause 3.2.12. This switch shall be used with voltage transducers in
item (e) and frequency transducer in item (g) for 230 kV bus No. 1 VT’s.
(j) One (1) potential test switch complete with one multi-pole test plug as per
Sub-Clause 3.2.12 for use with voltage transducers in item (f) and
frequency transducer in item (h) for 230 kV bus No. 2 VT’s.
(i) Three (3) current transducers, single element type, rated out 4-20 mA
unidirectional, external load resistance 0 to 10 k, suitable for use with
5-37
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
(ii) One (1) watt/var transducer, each shall be of the three-phase, four
wire, unbalance load, three current element type, rated out put 4-20
mA, bidirectional, external load resistance 0 to 10k, suitable for use
with CT 225:1A, CL 0.5, 50 VA, and three (3) auxiliary CT with ratio
22000 115
1:15A as indicated on item (i) and VT ratio 3 : , CL 0.5,
3 3
50 VA, as indicated on the respective drawing. The transducer
output shall be wired with twisted pairs shield wire with wire size 0.5
sq.mm to the Programmable Logic Controller (PLC) board panel 5R.
Each transducer shall be as per Sub-Clause 3.2.18(b).
(iii) Three (3) voltage transducers, they shall be for measuring of the three-
phase line circuit, each transducer shall be single element type, rated
output to 4-20 mA, unidirectional, external load resistance 0 to 10k,
22000 115
suitable for use with VT ratio 3 : , CL 0.5, 50 VA, as
3 3
indicated on the respective drawing. The output shall be wired with
twisted pairs shield wire with wire size 0.5 sq.mm to the Programmable
Logic Controller (PLC) board panel 5R. Each transducer shall be as
per Sub-Clause 3.2.18(c).
(iv) One (1) potential and current test switch complete with one multi-pole
test plug as per Sub-Clause 3.2.12.
(v) One (1) transformer tap position transducer for use with a multi-tap
resistor which is used as transformer LTC tap position with input resistor
range 0-10,000 ohm. Each transducer shall be rated output 4-20 mA
unidirectional external load resistance 0-10 k. The output shall be
wired with twisted pairs shield wire with wire size 0.5 sq.mm to the
Programmable Logic Controller (PLC) I/O module which is mounted on
Panel No. 5R. Each transducer shall be as per Sub-Clause 3.2.18(h).
(vi) One (1) potential and current test switch complete with one test plug
as per Sub-Clause 3.2.12.
(l) One (1) lot of miniature circuit breakers (MCB) shall be for use with VT
circuits supplied for transducers, and etc. as required per Sub-Clause
3.2.6 shall be furnished mounted and wired. All MCB’s shall be provided
three (3) electrically separate normally closed contacts: one contact shall
be wired to initiate the Programmable Logic Controller (PLC) and the
other two (2) contacts shall be wired to terminal blocks for future use.
(m) One (1) lot of engraved nameplates for mounting each nameplate behind
or adjacent to each corresponding device complete with the inscription for
each nameplate shall be furnished and installed as per Sub-Clause 3.2.7
5-38
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
and 3.2.14.
One (1) lot of Marshalling cabinets shall be furnished with terminal blocks
mounted in vertical rows on both sides of the center plate. The number of
rows and arrangement of these terminal blocks and the cabinet construction
shall be in accordance with the Drawing No. 71.2119.27.400.
Cables from the protective relay switchboard shall enter the cabinets from
bottom and be connected with terminal blocks on one side of vertical row while
the other side terminal blocks will be for connecting with the cables from the
teleprotection equipment. Switchboard wires for jumping between these two
vertical rows of terminal blocks shall be furnished and completely wired, as
required by the protection system.
Each fault recording system cabinet shall be furnished with fault recoding
system equipment with accessories mounted and complete wired as per
Specification, Sub-Clause 3.2.33. Each fault recording system (FRS) shall be
a modular design and shall be a micro processor-based instrument designed
for sensing, acquiring, storing and recording critical high-speed data during
power system faults and disturbance.
Each fault recording system shall be designed to operate by use dual channel
power supply: one power supply from 220 V ungrounded station battery and
the other AC supply from 700 VA, on-line, 50 Hz, Uninterruptible Power
Supply (UPS). The Contractor shall furnish this UPS together with the fault
recorder as specified in the Specification, as per sub-Clause 3.2.33(p)(ii).
Each fault recording system (FRS) shall be of the type/model that shall be in
according to the requirements of the Specification and shall meet the
requirements of EGAT PPA, Schedule 16: Protective System and EGAT
5-39
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
3.1 Standards
All equipment, materials, fabrication and testing under this Specification shall
conform to the latest applicable standard specifications and codes contained
in the following list, or to equivalent applicable standard specifications and
codes established and approved in the country of manufacturer of the
equipment. Where Standards are mentioned by name, equivalent applicable
standards may be used.
Any details not specifically covered by these standards shall be subject to the
approval of the Employer. In the event of contradictory requirements between
such standards and this Specification, the terms of the Specification shall
govern.
3.2.1 General
The control and protection equipment shall be designed to comply with the
climatic conditions as specified in General Technical Specification.
5-40
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
holes or fasteners shall be visible as viewed from the front of the panels.
Switchboards and cabinets shall be designed without any permanent bottom
braces and the bottoms shall be open. They shall be furnished with channel
bases. The front and rear panels of the switchboards and cabinets shall have
bent angle or flange edges with an outside radius not exceeding 10 mm.
Both sides of each control switchboard section shall be open except for
the two end sections; the left side of the left end section and the right side
of the right end section shall be enclosed.
The enclosed switchboard panel size shall be 660 mm deep. The height,
channel base, and panel width shall be as indicated on the drawings
entitled: “Control Switchboard Equipment Layout” for each substation.
The Contractor shall provide all wiring and wiring connections between
the individual sections.
Each basic panel assembly for switchboards and cabinets shall be a self-
contained unit with factory wiring complete to conveniently located
5-41
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
terminal blocks for the incoming cables. Each shall have vertical side
members, which include vertical raceways and raceway covers for factory
wiring, and shall be bolted to the right and left sides of the basic panel.
These side members shall provide separate raceways to house, protect,
and conceal the incoming cables and interpanel leads. Terminal blocks
shall be furnished and mounted in vertical rows on both sides of the basic
panel assembly.
Suitable wire slots with rubber bushings in vertical rows on both sides of
the basic panel assembly near terminal blocks shall be provided for
outgoing leads.
The cabinet door shall be hinged on the right hand side, front view.
The relay rack assembly shall be hinged on the left hand side, front view.
Each cabinet shall be designed for mounting standard 19-inch wide rack-
mounted relays.
Each relay rack assembly shall be arranged to swing through not less
than 120 degrees from closed position to allow easy access to the back of
the equipment mounted on the rack and to the interior of the cabinet.
5-42
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
the switchboard.
Panel opening of the swing rack assembly not utilized by equipment shall
be covered by cover plates.
The switchboard size shall be 800 mm wide and 610 mm deep. The
height of each switchboard shall be 2,300 mm plus a 40 mm channel
base.
Each marshalling cabinet shall be 900 mm wide 1,000 mm deep and the
height shall be 2,300 mm plus a 40 mm channel base.
Each cabinet shall have vertical side members, which include vertical
raceways and raceway covers for factory wiring, and shall be bolted to the
right and left sides of the cabinet. These side members shall provide
separate raceways to house, protect, and conceal the incoming cables
and interpanel leads.
Each cabinet shall be provided with cable entrance at the bottom of the
cabinet.
5-43
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
Each cabinet shall be 900 mm wide, 1,000 mm deep and the height shall
be 2,300 mm plus a 40 mm channel base.
Each cabinet shall have vertical side members, which include vertical
raceways and raceway covers for factory wiring, and shall be bolted to the
right and left sides of the cabinet. These side members shall provide
separate raceways to house, protect, and conceal the incoming cables
and interpanel leads.
Each cabinet shall be provided with cable entrance at the bottom of the
cabinet.
5-44
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
metering and for use with the Programmable Logic Controller (PLC). All
transducers shall be furnished, mounted and completely wired.
Each transducer cabinet shall be 900 mm wide, 1,000 mm deep and the
height shall be 2,300 mm plus a 40 mm channel base.
Each cabinet shall have vertical side members, which include vertical
raceways and raceway covers for factory wiring, and shall be bolted to the
right and left sides of the cabinet. These side members shall provide
separate raceways to house, protect, and conceal the incoming cables
and interpanel leads.
Terminal blocks shall be furnished and mounted in vertical rows and both
sides of the cabinet. The number of vertical rows and the arrangement of
terminal blocks shall be in accordance with Drawing No. 71.2119.27.400.
All wiring which connect to the external circuits shall terminate on these
terminal blocks.
Each cabinet shall be provided with cable entrance at the bottom of the
cabinet.
Each fault recording system cabinet shall be of the swing rack type,
consisting of a swing rack assembly, top sheet and rear enclosure
covering the back and ends of the entire structure. Each cabinet shall
have a front cover door equipped with a glass window for viewing all
targets and indications. The cabinet door shall be equipped with locking
handle, latched, fully concealed hinges, and complete with screened
louvers at the top and the bottom.
The cabinet door shall be hinged at the right hand side, front view. The
cabinet door shall be designed so as to provide a fixed, vertical narrow
section at the left hand side of the front panel for mounting the potential
and current test switches for connecting to the external circuits.
5-45
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
Each cabinet shall be designed for mounting standard 19-inch wide rack
mounted relays.
Each cabinet shall be provided with a vertical wiring duct complete with a
cover for factory wiring and a vertical raceway and a raceway cover to
house, protect, and conceal the incoming cables. The vertical wiring
ducts and vertical raceways shall be arranged as shown on the Drawing
No. 71.2119.27.400.
Panel opening of the swing rack assembly not utilized by equipment shall
be covered by cover plates.
The switchboard size shall be 915 mm wide and 800 mm deep. The
height of each switchboard shall be 2,300 mm plus a 40 mm channel
base.
Each hinged synchronizing panel shall be fabricated from not less than
2.5 mm leveled sheet steel and shall be approximately 360 mm wide, 550
mm high, and 200 mm deep. If specified, each hinged synchronizing
panel shall be furnished and shall constitute a part of each control board
assembly. Each shall be designed to swing back in line with the other
panels when not in use to present straight line appearance. Each shall be
readily removable and re-installed when future control board installation is
required. The rear sheet shall be readily removable for access to the
5-46
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
Each panel shall be furnished, mounted and completely wired with the
following equipment:
(i) One - Twin indicating voltmeter, 0-150 V scale, 150 V coil, 50 Hz,
144 mm square face, for incoming and running potential.
The Contractor shall submit for approval the following drawings and data,
sufficient to demonstrate fully that the equipment to be furnished will conform
to the requirements and intent of this Specification.
Each three line diagram shall show voltage and current connections to all
metering and relaying equipment.
Logic diagrams shall show details of the logic circuits for each individual
5-47
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
relay. These diagrams shall be required for the system as a whole as well
as for each individual relay and component.
The Contractor shall provide for approval the general assembly drawings
including dimensions, details of arrangement plan and section and floor
plan complete with anchor bolt setting plan.
The switchboards and cabinets proposed shall give the best optimum
result as called for in this Specification, and as basically required by
standard electrical engineering practice.
5-48
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
The Contractor, after having finished the design of the switchboards and
cabinets shall submit to the Engineer for approval all the design details
including individual equipment of the switchboards and cabinets and to all
associated equipment in the substation, and showing overall functions of
the schematic diagrams. The Engineer shall then review the schemes,
and should any proper functions required in this Specification or required
for sound engineering practice of the switchboards and cabinets entail
necessary modifications to the scheme or additional equipment other than
those originally proposed by the Bidder at the time of bidding, the
Engineer will return the scheme to the Contractor to carry out the
modification required without any extra charge to the Employer.
3.2.5 Wiring
All wiring used within the main control boards, protective relay switchboard,
interposing relay cabinets, marshalling cabinets fault recording system cabinet,
metering system cabinet and etc. shall conform to the NEC and NEMA
standards and shall be rated 600V, tinned, stranded copper switchboard wire,
cross-linked polyethylene insulated and in grey color. All wiring shall be No. 14
AWG (2.08 sq.mm) except for current transformer circuits which shall be No.
12 AWG (3.31 sq.mm). All hinged wiring shall be extra flexible. After
assembly, all control wiring shall be given a dielectric test of 1,500 V between
live parts and ground, and between opposite polarities. Internal wiring of each
basic panel assembly and each cabinet shall be neatly and carefully installed
in suitable wiring ducts with removable covers and complete to conveniently
located terminal blocks for connecting to incoming and outgoing leads.
Before connected to the terminal blocks, all wiring shall be terminated with
blade-type cable rugs. Multiple wires in one cable rug shall not be acceptable.
The cable rugs shall perfectly match the terminal blocks and shall be plugged
in without any modifications to the cable rugs.
The terminal arrangement shall group all leads for each particular function to
facilitate connections to the incoming and outgoing cables. The arrangement
shall be subject to the approval of the Engineer. Terminals for each CT circuit
shall be grouped together and separated from terminals for other CT circuits.
At least 25 per cent spare terminals shall be provided on each group of
terminal blocks for terminating spare conductors in control cables and for
future use, however a minimum of one spare terminal shall be provided on
each group of terminal blocks.
5-49
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
All incoming and outgoing cables shall enter the switchboards and the
cabinets through cable slots in the floor underneath the switchboards and the
cabinets.
Any control boards or cabinets that are split for shipment shall have terminal
blocks adjacent to the split and shall be provided with wiring required to
interconnect the split units.
Power supplies for panel mounted devices shall be provided with miniature
circuit breaker (MCB) connected to isolate the devices from power supplies in
the tripped or open condition. MCB shall be located within the panels.
Engraved nameplates shall be installed beside each set of MCB for
identification.
Power supply to each nature of control circuit and the potential transformer
secondary supply to each metering circuit shall be separated and required
separated MCB protection provided, including, but not be limited to the
following :
(i) Two (2) control circuits for each power circuit breaker; one control
circuit, including relay trip circuit for power circuit breaker trip coil
circuit #1, and one control circuit including relay trip circuit for power
circuit breaker trip coil circuit #2.
(ii) Two (2) control circuits for each line protection; one for primary pilot
relaying system No. 1 and one for primary pilot relaying system No. 2.
(vi) Each shunt reactor restricted earth fault relaying control circuit.
5-50
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
(iv) Line potential circuit for main transformer unit metering system.
Each MCB shall be furnished with three (3) electrically separate normally
closed contacts: one contact shall be wired to initiate the Programmable
Logic Controller (PLC) and the other two contacts shall be wired to
terminal block for future use.
Every point of terminal block and wire shall be assigned a designation, with
identical designation on each corresponding terminal block and wire. This
same designation shall also be indicated in the schematic and wiring
diagrams. As a rule, a designation will not change until the wire is terminated
or connected to other equipment. All wiring shall be designated at both ends
by printing on wire designation sleeves.
5-51
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
The name or NEMA standard device number of each device shall be marked
on the rear of the panels directly behind or adjacent to the corresponding
device.
System Frequency : 50 Hz
Secondary Ratings
Where auxiliary transformers are required for the correct operation of specific
metering, relaying, and control equipment furnished under this Specification,
the Contractor shall furnish such additional transformers as required without
additional cost to the Employer.
All indicating and pilot lamp assemblies shall be of the light emitting diode
(LED), suitable for use with 220VDC, switchboard type with color caps. The
color caps shall be red, green, white, blue or amber as required. All lamp bulbs
shall be interchangeable, and shall be replaceable from the front of the panels.
5-52
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
All lamp bulbs shall be interchangeable, and shall be replaceable from the
front of the panels.
Test switches and multipole test plugs shall be ABB, flexitest switches, type
FT-1.
The main control boards, interposing relay cabinets, transducer cabinets and
marshalling cabinets shall be supplied with terminal blocks for termination of
all wiring devices mounted in the switchboards and cabinets and all external
circuits. The terminal blocks shall be of nonflammable, self-extinguishing, non-
hygroscopic insulating material, rated for 600 V and shall conform to IEC 947-
7-1 and IEC 947-1 standards. The terminal blocks shall have adequate current
carrying capacity and shall be suitable for use in tropical climate. Terminals
shall maintain good electrical, mechanical, chemical, and other properties
even at operating temperature as high as 250°C and shall have excellent
mechanical strength and hardness; they shall be flexible but difficult to bend or
break even applied with thread and torque from the connected wires.
Insulating barrier between adjacent terminal shall be integral part of the
terminal block. All terminal blocks and terminations shall be grouped according
to circuit functions. Each terminal block shall have removable white marking
strip for marking circuit designation. One spare blank marking strip shall be
furnished with each terminal block. The terminal blocks shall be well arranged
in order that they permit safe wiring works on any terminal while all adjacent
terminals are live.
5-53
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
protection circuits and other circuits shall be of the spring loaded screw-on
type, screw-on type or screwless type. The screw-on type terminals shall be
designed in such a way that after the terminal block is unscrewed, the wire is
still engaged to the terminal block. The screwless type terminals shall be
designed to clamp the wire automatically after releasing or withdrawing the
screwdriver. The terminal blocks provided for marshalling cabinets shall be of
the knife disconnect type.
The terminal blocks shall be sized and rated in accordance with current
carrying capacity of wires. The terminals for power and CT circuits shall be
sized to accept 2x6 mm² conductors, and those for PT and control circuits
shall be sized for 2x4 mm² conductors. The terminals for alarm/status circuits,
and marshalling cabinet shall be sized for 2x2.5 mm² conductors.
The arrangement of all terminal blocks shall be such that incoming and
outgoing leads can be easily arranged for connections to terminals. Terminal
blocks shall be located so that the accessibility to them will not be lessened by
interference from structural members or panel instruments. Ample space shall
be provided to terminal blocks for termination of all external circuits.
3.2.14 Nameplates
5-54
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
The control and instrument switches shall be of the multistage, rotary type,
rated 600 V, 20 A, continuous duty, for both AC and DC services. Each
contact shall be of the readily renewable, self-cleaning type and shall be of the
wipe-type. A rectangular front-of-panel escutcheon plate shall be furnished
and engraved showing the switch position of control and instrument switches.
The switch identification shall be engraved on the escutcheon plate, or if
necessary, on a separate adjacent nameplate furnished by the Contractor.
The types of control switch handles and colors preferred shall be provided as
follows:
The total number of contacts and the total number of contact arrangements
shall be adequate for their required functions but minimum number of contacts
and contact arrangements shall be at least as shown on Drawing No.
71.2119.27.401.
If the schemes for control, protection and other equipment as proposed by the
Contractor and approved by the Engineer, required additional contacts than
those listed in this Specification and shown in the above drawing, the
contractor shall furnish these extra contacts and contact arrangements without
additional cost to the Employer.
5-55
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
Each trip transfer switch shall be of the maintained contact type, with
fixed, modern, oval black handle. The trip transfer switch function is to
permit the operation in order to transfer the tripping, reclosing, and
synchronizing functions to the bus tie breaker.
Each recloser cutoff switch shall be of the momentary contact type, three
position “on” “normal”, “off” with spring return to the normal position, with
fixed, modern, oval black handle. Each switch shall be complete with an
indicating red-light-emitting diode complete with integrally mounted resistor.
Each bus differential cutoff switch shall be of the maintained contract type,
two-position “on" "off", with fixed, modern, oval black handle. Each cutoff
switch shall be complete with an indicating red light-emitting diode
complete with an integrally mounted resistor.
Each breaker failure cutoff switch shall be of the maintained contact type,
two-position “on” “off”, with fixed, a modern, over black handle. Each
cutoff switch shall be complete with an indicating red light-emitting diode
complete with an integrally mounted resistor.
Each pushbutton switch shall be of the heavy duty type and constructed
for definite over-travel in both directions. Each shall be dust-proof, fully
shrouded to prevent accidental operation.
5-56
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
Each direct transfer trip cutoff switch shall be maintained contract type,
two-position, “on” “off” with fixed, modern, oval black handle. Each switch
shall be complete with an indicating red-light-emitting diode complete with
integrally mounted resistor.
Each differential cutoff switch shall be of the maintained contact type, with
fixed, modern, oval black handle and complete with separately mounted
red indicating lamp assembly.
Each cutoff switch shall be of the maintained contact type, with fixed,
modern, oval black handle and complete with separately mounted red-
light-emitting diode complete with integrally mounted resistor.
Each cutoff switch shall be of the maintained contact type, with fixed,
modern, oval black handle and complete with separately mounted red-
light-emitting diode complete with integrally mounted resistor.
Each stub protection cutoff switch shall be of the maintained contact type,
with fixed, modem, oval black handle, two-position: “ON-OFF”, and
complete with separately mounted red light-emitting diode with integrally
mounted resistor.
5-57
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
Scale plates shall have a permanent white finish with black graduations and
numerals. Varmeter scale plates shall be marked "_ _ IN(-)" at the left of the
scale, "-O-" at the center and "_ _(+) OUT" at the right. The scale range and
other details of each indicating instrument shall be as specified in the bills of
materials.
3.2.18 Transducers
(i) Burden
5-58
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
(vi) Adjustment
(vii) Environment
5-59
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
Each voltage transducer shall be of the single element type. Each shall be
designed for use with the Programmable Logic Controller (PLC) furnished
by other, and shall meet the following requirements:
Each current transducer shall be designed for use with the Programmable
Logic Controller (PLC) furnished by other, and shall meet the following
requirements
Each shall be suitable for use with the Programmable Logic Controller
(PLC) furnished by other, and shall meet the following requirements
5-60
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
External load : 0 to 10 k
5-61
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
3.2.19 Relays
All relays shall be designed for continuous operation at any voltage from 80
per cent to 120 per cent of rated DC voltage as specified and at a range of
ambient temperatures of 10°C to 55°C. Each protective relay shall be suitable
for operation with instrument transformer ratios and connections as shown on
the metering and relaying diagrams under both normal and short circuit
conditions.
Each relaying system shall be provided with test facilities for secondary
injection testing and for isolating the DC supply, current circuits, potential
circuits, tripping circuits, and all other output contacts which shall be free
contact by separated from test switch. All test switches shall be arranged so
that the current transformer secondary circuit cannot be open-circuited in any
position while the test plugs or cover plugs are being inserted or removed.
5-62
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
accidental short circuiting of the input or output DC supply. Each power supply
shall not generate any signal, noise, or impulse on the input DC supply leads
which is greater than 300 millivolts peak to peak.
Relays utilizing voltage divider type regulated power supplies shall not be
accepted.
All modules of static, digital or numerical type protective relays shall consist of
highly reliable logic circuits and circuit components. All modules shall be
mounted on plug-in circuit cards. Wiring boards shall be epoxy-fiberglass
construction. Printed circuit wiring shall be employed with soldered or welded
connections to circuit components. Wiring board shall be provided with heavy-
duty circuit connectors with gold-plated contacts.
Each digital or numerical relay shall have provisions fro monitoring any
hardware failures so they can be repaired before they effect relay operation.
These provisions shall also include output contacts for initiating the
Programmable Logic Controller (PLC). All output contacts shall be electrically
separate normally open contact type. Each PLC shall be Local Control Unit
(LCU) and operated in conjunction with one HMI which are mounted on the
swing rack type, programmable Logic Controller (PLC) and interposing relay
switchboard. Each PLC and HMI shall be part of the Distributed Control
System (DCS). The DCS system shall be used for control and monitoring of
the power plant, 230 kV switchyard and 115 kV switchyard as defined under
the title for “Control System” furnished by other Contractor.
Each digital or numerical relay shall be configured to comply with all the
Engineer’s needed functions before delivery. Configuration setting of the relay,
which is programmable, shall be supplied in CD-ROM.
The instruction manuals shall be prepared with the object of providing
sufficient detailed technical information of each type of protective relays to
enable the Employer to efficiently carry out commissioning and routine testing,
to provide guidance in the tracing of faults and to permit the ordering of
replacement parts. In this regard, each instruction manual shall give full details
of circuit operation, circuitry, components, and circuit diagrams. All technical
data, operating time curves, sample calculations and other characteristics
shall be based upon 50 hertz operation. The relay instruction books shall also
meet the requirements as listed in Drawings and Documents to be Furnished
by the Contractor under Special Conditions of Contract Documents.
The protective relays required shall be in according to ATTACHMENT NO.1
“EGAT ACCEPTED MAIN RELAY LIST NO. 1” page 1 of 3, page 2 of 3, page 3
of 3. The fault recording system required shall be in accordance with the
requirements of ATTACHMENT NO. 2, page 1 of 1, “EGAT ACCEPTED FAULT
RECORDING SYSTEM LIST. These ATTACHMENTS shall be included as parts
of this Specification.
(a) Synchro-Check Relays (25+27/59)
Each synchro-check relay shall be of the numerical type. Each relay shall
be used with automatic reclosing relay for line circuit breaker on loop
systems fed by power sources at two or more points. Each synchro-check
relay shall allow its reclosing relay to close the line breaker only on the
condition that the line voltage and bus voltage are in normal condition, of
the same frequency, equal and in-phase. Closing angle and operation
5-63
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
Each synchro-check relay shall incorporate a voltage check relay for the
options of reclosing on dead bus-live line and dead line-live bus.
Each voltage check relay shall have the operating time not more than 250
milliseconds.
Each relay shall include the instantaneous trip unit to ensure high speed
operation on heavy internal faults. Each relay shall incorporate current
taps or separate auxiliary current transformers to compensate for main
current transformer mismatch. A control switch (87K-CO) with a separate
red indicating lamp shall be provided with each set of relays, to segregate
the auxiliary tripping relay from the differential relays as necessary to
prevent false tripping due to the bypassing of the current transformers.
The red lamp shall light to indicate that the trip circuit from the differential
relays to the auxiliary tripping relay is closed. Each cut-off switch shall be
in accordance with the requirements of Sub-Clause 3.2.16(g).
Transformer differential relay shall include Ethernet rear port type RJ45
for the data communication between the relays at remote switchyards and
the PC at the central office.
5-64
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
Low impedance type bus differential relay shall include Ethernet rear port
type RJ45 for the data communication between the relays at remote
switchyards and the PC at the central office.
Low impedance type bus differential relay shall support IRIG-B signal
input and disturbance recorder function.
Each bus differential relay shall be furnished with three (3) electrically
separate normally open contacts in addition to those required by the bus
differential protection scheme. These contacts shall be : one contact shall
be wired to initiate the Programmable Logic Controller (PLC) and the
other two contacts shall be wired to terminal blocks for future use.
The shunt reactor differential relay shall operate correctly while the
switching of the transmission line is in operation.
Each shunt reactor differential relay shall be furnished with three (3)
electrically separate normally open contacts in addition to those required
by the shunt reactor differential protection scheme. These contacts shall
5-65
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
(e) Auxiliary Tripping and Lockout Relays (86KP, 86KS, 86B, 86R, 86RR,
86BF, 86S, 86DTT)
Auxiliary Tripping and Lockout Relays (86KP, 86KS, 86B, 86R, 86RG,
86BF, 86S). Auxiliary tripping and lockout relays shall be provided with
transformer protection, bus protection, direct transfer tripping, line shunt
reactor and breaker failure protection. Each relay shall be of the high
speed type, draw out, DC voltage operated, manual reset control switch
with cutoff contact provided to interrupt the operating coil. The minimum
number of contacts shall be sufficient and correct as specified in the
protective device function or bill of materials. All contacts shall be rated to
make and carry 30A, 600V for 3 seconds, 10A, 600V at continuous duty,
and be capable of interrupting of 2A of inductive current (L/R 40 ms) in a
220 V DC control circuit. They shall have an operating time including
bouncing time not exceeding 10 milliseconds at 250 Watt load.
Each overcurrent ground relay shall be furnished with three (3) electrically
separate normally open contacts in addition to those required by the
overcurrent ground protection scheme. These contacts shall be : one
contact shall be wired to initiate the Programmable Logic Controller
(PLC), and the other two contacts shall be wired to terminal blocks for
5-66
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
future use.
Each overcurrent ground relay shall be furnished with three (3) electrically
separate normally open contacts in addition to those required by the
overcurrent ground protection scheme. These contacts shall be: one
contact shall be wired to initiate the Programmable Logic Controller
(PLC), and the other two contacts shall be wired to terminal blocks for
future use.
Each overcurrent ground relay shall be furnished with three (3) electrically
separate normally open contacts in addition to those required by the
overcurrent ground protection scheme. These contacts shall be : one
contact shall be wired to initiate the Programmable Logic Controller
(PLC), and the other two contacts shall be wired to terminal blocks for
future use.
(j) Loss-of-DC Alarm Relays with Special Provision for Slow Dropout (27XB,
27XR)
Each shall have two (2) electrically separate normally closed contacts.
These shall be: one contact shall be wired to initiate the Programmable
Logic Controller (PLC) and two contacts shall be wired to terminal blocks
for future use. Each shall also have two (2) electrically separate normally
open contacts for future use.
5-67
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
Each 230 kV transmission line shall be protected by a two (2) primary pilot
relaying systems. Each system shall be included with a backup relaying
scheme. The first primary pilot relaying shall be a line current differential
protection and equipped with 64 kBit/sec ITU-TG703, 4 w interface with two
(2) channels of a multiplexing equipment for pilot trip via optical fiber cable as
a communication link. The first primary pilot relaying shall be equipped with a
full scheme type distance relay for back up protection. There shall be first,
second, and third zones of distance elements with two separate timing relays
to provide time-delayed trip for zone 2 and zone 3. All distance elements shall
be independently configured so that they shall perform the functions properly
during the loss of communication signal. The second primary pilot relaying
shall be a distance protection scheme using directional comparison, over
reaching transfer trip scheme via fiber optical cable embedded in the overhead
galvanized shield wire (OPGW) strung on the transmission line tower as a
communication link. The pilot channels for distance protection scheme shall
use frequency-shift keyed audio tone teleprotection equipment. The distance
protection scheme shall equip with first, second, and third zones of distance
elements complete with two separate timing relays to provide time-delayed trip
for zone 2 and zone 3 for use as a backup protection system.
Each primary pilot relaying system shall initiate single-pole and three-pole
tripping and reclosing operation scheme upon fault clearing. The three-pole
reclosure shall be done through a synchro-check relay.
The primary pilot relaying system No. 1 to be furnished shall consist of the
following components:
5-68
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
The current differential relay shall provide complete protection for all
combinations of phase faults and ground faults. Each current
differential relay shall be suitable for high speed pilot protection
applications and shall be of the numerical type. The current
differential protection scheme shall be based on phase segregation
measurements and equipped with 2 channels of 64 kBit/sec ITU-
TG.703, 4 wire interface with a multiplexing equipment of the
communication system for pilot trip via optical fiber cable embedded
in the OPGW shield wire strung on the transmission line tower, as a
communication link.
Current differential relay shall include Ethernet rear port type RJ45 for
the data communication between the relays at remote substations
and the PC at the central office.
The primary pilot relaying system No. 2 to be furnished shall consist of the
following components:
5-69
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
Each distance relay shall be of the integral type with all main and
auxiliary units mounted and wired in one enclosure. The measuring
element shall determine simultaneously the distance and direction of
the fault. It shall be insensitive to frequency changes, DC
components and harmonics in the fault circuit.
Each distance relay shall operate properly with high values of source
impedance. It shall be capable of measuring all faults with minimum
fault current of 0.2 time of rated current. The maximum continuous
operating current rating of the distance relay shall not be less than
2.0 time of rated current.
In any substation where there are more than one transmission line in
parallel, effective means for fault detection shall be provided for each
distance relay with either one or all the lines in operation.
Each distance relay shall be able to operate correctly for phase fault
arc resistance up to 5% of the impedance from the fault to the source.
5-70
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
Each distance relay shall operate correctly for all types of evolving
faults. This shall include phase-ground faults evolving to phase-
phase-ground faults, phase-phase faults evolving to phase-
phaseground faults, phase-phase faults evolving to three phase
faults, and external faults evolving to internal faults.
Each distance relay shall not misoperate for current reversals that
may occur during the clearing of external faults.
Distance relay shall include Ethernet rear port type RJ45 for the data
communication between the relays at remote switchyard and the PC
at the central office.
Each primary pilot relaying system No. 0 shall be furnished with the
following functions:
5-71
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
Each relay line terminal shall be equipped with a full scheme type
distance relay for backup protection for 230 kV line against all
combination of phase and ground faults, which consists of the
followings:
5-72
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
Each relaying system shall provide contact outputs for the following
functions:
(i) Single-pole and three-pole tripping of a circuit breaker with two trip
coils per pole.
(v) Contact outputs for keying the transfer trip transmitters as required.
(vii) Miscellaneous alarm contacts for relay operation for initiating the
annunciator.
(viii) Miscellaneous alarm contacts for relay operation for initiating the
Programmable Logic Controller (PLC).
5-73
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
Each single pole tripping relay shall be provided to select the faulted
phase for a single line to ground fault. They shall also prevent incorrect
operation of any zero sequence relays during single phasing period.
Each primary pilot relaying system shall be furnished with a cutoff switch
to disable channel signals when pilot channels are out of service.
Each reclosing relay shall be single shot, single pole and three-pole
reclosure. Each relay shall be provided for use with single pole and three-
pole tripping and reclosing scheme. Each relay shall be provided with one
high-speed, single-shot, and single-pole reclosure. For three-pole
reclosure, the reclosing relay shall be done through a synchro-check
relay. Each reclosing operation shall be initiated by contacts of the
primary protective relay. The times for single pole and three-pole
reclosure shall be separately adjustable.
Each shall be provided with two (2) electrically separate normally open
contacts; one for Programmable Logic Controller (PLC) of recloser
operation, and the other for Programmable Logic Controller (PLC) of
recloser lockout.
5-74
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
operation which may be single pole reclosure only, single pole and three-
pole reclosure, three-pole reclosure only, or no reclosure.
Each reclosing relay shall be blocked upon the three-pole tripping of the
circuit breakers that result from either a second phase being faulted
during the single phasing period or the circuit breaker is closed manually
on to a three-phase fault.
Each relaying system shall have provisions for monitoring any hardware
failures so they can be repaired before they affect relay operation. These
provisions shall also include output contacts for initiating the
Programmable Logic Controller (PLC). All output contacts shall be
electrically separate normally open contacts.
Each auxiliary tripping relay shall be high speed, self reset, DC voltage
operated type. Each relay shall contain at least seven (7) electrically
separate normally open contacts. The contacts shall be rated to carry
30A, for 3 seconds, 5A continuous, and be capable of interrupting 0.2A of
inductive current (L/R <40 ms.) in a 220 VDC control circuit. They shall
have an operating time not exceeding 10 milliseconds.
(l) Each primary pilot relaying system shall be provided with the audio tone
equipment and protective relay interfacing schemes.
5-75
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
Provisions shall also be made with each pilot relaying for selection of pilot
scheme modes of operation as specified above.
5-76
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
These relays shall operate the auxiliary tripping and lockout relay
(86KS) in Sub-Clause 3.2.19(e).
These relays shall operate the auxiliary tripping and lockout relay
(86KS) in Sub-Clause 3.2.19(e).
5-77
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
This relay shall operate the auxiliary tripping and lockout relay (86KS)
in Sub-Clause 3.2.19(e).
There shall be two (2) main bus differential protection schemes for each bus.
A separate auxiliary tripping and lockout relay shall be furnished with each set
of bus differential protection schemes. Each bus differential protection scheme
shall comprise the following components:
(b) Auxiliary Tripping and Lockout Relays (86B1P, 86B2P, 86B1S, 86B2S)
Each auxiliary tripping and lockout relay shall be in accordance with the
requirements of Sub-Clause 3.2.19(e).
5-78
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
Energizing the transmission lines from one end only could result in excessive
line end voltage and equipment damage. The transmission line shall not be
allowed to be energized from one end only for more than one minute with 1.2
p.u. voltage at the open end terminal. Each line terminal shall be furnished
with an overexcitation relay to protect the line over voltage and equipment
overexcitation at the open end terminal. Each overexcitation relay shall
operate in conjunction with the direct transfer trip scheme to provide tripping
the circuit breaker at the remote closed end terminal.
Each relay shall be furnished with three (3) electrically separate normally
open contacts in addition to those required by the line terminal
overvoltage protective relay function. These contacts shall be: one contact
shall be wired to initiate the Programmable Logic Controller (PLC), two
contacts shall be wired to terminal blocks for future use.
Each protective relaying shall provide contact outputs for the following
functions :
(i) Contact outputs for keying the transfer trip transmitters as required in
accordance with the direct transfer tripping system in Sub-Clause
3.2.28.
(iii) Contact output for initiating the Programmable Logic Controller (PLC).
(iv) Contact output for wiring to terminal block for future use.
5-79
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
These relays shall operate the auxiliary tripping and lockout relay
(86R) in Sub-Clause 3.2.19(e).
5-80
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
Each restricted earth fault protective relaying shall utilize the following
components :
Each restricted earth fault relay shall of the high speed, high
impedance, static, digital or numerical type. A cutoff switch (87RG-
CO) with a separate red indicating light shall be furnished with each
restricted earth fault protective relaying, to segregate the auxiliary
tripping and lockout relay in Sub-Clause 3.2.19(n) from the restricted
earth fault relay. The red lamp shall light to indicate that the trip circuit
from the restricted earth fault relay to the auxiliary tripping relay is
closed.
The restricted earth fault relay shall operate correctly while the
switching of the transmission line is in operation.
The necessary relay shall be provided so that upon failure of a 500 kV circuit
breaker to trip within its normal time, the trip circuit of all the appropriate circuit
breakers necessary to isolate the faulted line shall be energized to trip and
lockout. Lockout relays shall be provided to prevent reclose either manual or
5-81
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
automatic, until lockout relays are reset. Sensing for breaker failure shall be by
instantaneous overcurrent relays in conjunction with timing relays. Provision
shall also be made so that the remote end relays, of the line with the faulted
breaker, may trip the remote end breaker instantaneously.
Each timer shall be a time delay relay with timing range of 0.05 to 1.0
second and shall be continuously adjustable. Each timer shall be of the
digital or numerical type. An output contact with an indicating target shall
be provided with each timer.
A separate auxiliary tripping & lockout relay shall be furnished for each set
of breaker failure protection, and shall be in accordance with the
requirements described in Sub-Clause 3.2.19(e).
(e) Current detector relay and breaker failure timer shall be especially
designed for the breaker failure function and it is unnecessary to create
any logic to form the breaker failure function.
5-82
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
Each circuit breaker trip circuit shall be equipped with a trip circuit supervision
relay. Each circuit breaker shall have six trip circuits. Each trip circuit
supervision relay shall be designed to supervise the electrical continuity in the
tripping circuit all time even though breaker closed or open. In the event that
the voltage supply drops below 40% of nominal voltage, this relay shall also
operate to provide contact outputs for alarm signaling.
Each breaker trip circuit supervision shall be separated from other relays.
Each relay shall be provided with three (3) electrically separate normally
closed contacts. These contacts shall be : one contact shall be wired to initiate
the Programmable Logic Controller (PLC), one contact shall be wired to initiate
the annunciator and the other for future use.
Each relay shall also be provided with one (1) electrically separate normally
open contact for future use.
Operation of the circuit breaker shall not cause these relays to misoperate.
Any additional equipment required for complete functions of breaker trip circuit
supervision shall also be included with each trip circuit supervision relaying.
Direct transfer tripping system shall be provided with each protection for
tripping the remote end power circuit breakers instantaneously by using two
(2) transfer trip transmitters. Each transmitter shall have two channels.
The channel No. 1 shall be used in conjunction with the optical fiber cable
(OFC) embedded in the overhead shield wire (OPGW) strung on the
transmission line tower, as a communication link and the other one shall be
use the same optical fiber cable but separate core of the OFC as a
communication link.
In order to accomplish the functions of direct transfer tripping scheme for each
5-83
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
230 kV transmission line protection, the following relays shall be furnished and
operated in conjunction with the direct transfer tripping scheme as follows:
(a) A timer to be furnished shall be time delay relay (62DTT) with timing
range of 0-200 milliseconds and shall be continuously adjustable. The
timer shall be of digital or numerical type. An output contact shall be of
the time delay open contact characteristic. This timer shall be used under
the supervision of the circuit breaker auxiliary contact (52b) at the open
end terminal of the line to prolong the sending signal to the remote closed
end terminal until the received trip signal will then trip the remote end
circuit breaker according to the requirements of the DTT system.
(b) A timer to be furnished shall be a timing delay relay (62TT) with timing
range of 0-2.5 seconds and shall be continuously adjustable. The timer
shall be of the digital or numerical type. An output contact shall be of the
time delay close contact characteristic. The timer will be connected in
parallel with a high speed auxiliary tripping relay (94TT) which is a part of
the direct transfer tripping scheme.
Both relays will be energized by receiving trip command from the remote
open end terminal of the line, the auxiliary tripping relay (94TT) will trip the
local end breaker instantaneously and then the breaker will reclose by
automatic reclosure. If the reclosing is successful operation i.e. it is a
temporary fault and if not, the circuit breaker will trip again due to a
permanent fault. In the condition of a permanent fault, the timer (62TT1)
will give the output close contact to initiate the auxiliary tripping and
lockout relay (86DTT1) to block autoreclosure, block manual closing
circuit of the breaker, to initiate the Programmable Logic Controller (PLC),
as required by the DTT scheme.
A high speed auxiliary tripping relay (94TT) and auxiliary tripping and
lockout relay (86DTT1) shall also be furnished with the direct transfer
tripping scheme.
For breaker failure protection, the direct transfer trip system shall
provide means as described above to operate the remote end relays,
of the line with the faulted breaker, to trip instantaneously by using
carrier-aided direct transfer trip scheme as described above.
5-84
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
One direct transfer trip system shall be furnished with one cutoff
switch. This cutoff switch shall be for the direct transfer trip that will
utilize an optic cable (OFC) as a communication link.
The Contractor shall provide direct transfer trip schematic diagram for
transmission line and equipment protection for the switchyard under
this specification and the direct transfer trip shall match and meet with
EGAT direct transfer trip system requirements.
Stub protection shall be applied for the breaker and a half bus arrangement
and shall be provided only to protect the section between the two line breakers
and the associated line disconnect switch in the open position and in case of
the transmission line is taken out of service for maintenance. The two line
breakers are also required to close for connecting the two main buses for
reliability of the substation.
50
(a) Three (3) non-directional phase overcurrent relays ( ( S ) , single-
51
phase, as per Sub-Clause 3.2.19(f).
50
(b) One (1) non-directional ground overcurrent relays ( ( SG ) , single-
51
phase, as per Sub-Clause 3.2.19(g).
(c) Auxiliary tripping and lockout relay (86S), as per Sub-Clause 3.2.19(e).
50
(d) Stub protection cutoff switch ( S CO ) , as per Sub-Clause 3.2.16(q).
51
Any additional equipment and accessories, although not itemized herein, but
necessary to complete the sound functions of the stub protection scheme,
shall be furnished, mounted and wired by the Contractor without extra charge
to the Employer as specified in this Specification, Sub-Clause 3.2.3(k).
Additional auxiliary and control relays shall be used to complete the function of
power circuit breaker tripping and reclosing, trouble alarm, or any indication
5-85
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
Auxiliary and control relays shall be of the semi-flush mounted type if feasible,
otherwise of the surface mounted, switchboard type, with a removable cover
and transparent window, where applicable, and shall be finished dull black.
The coils of standard-speed relays shall be suitable for continuous duty at their
normal operating voltage. All contacts shall be of the renewable type with
ample current-carrying and interrupting capacity for the application, and shall
withstand at least 30 A, 600 V at 3 seconds and 5A, 600V at continuous duty.
Auxiliary tripping relays of the mechanically latched-in type shall have manual
reset devices operable from the front of the panel by means of a red oval
handle and shall have an operating time including bouncing time not
exceeding 10 milliseconds at 250 Watt load. Auxiliary relays of the self-reset,
standard-speed type shall have an operating time not exceeding 40
milliseconds. Auxiliary relays of the self-reset, medium speed type shall have
an operating time not exceeding 30 milliseconds. Auxiliary relays of the self-
reset, high speed type shall have an operating time including bouncing time
not exceeding 10 milliseconds at 250 Watt load.
Auxiliary relay of the self-reset, high speed type shall have an operating time
including bouncing time not exceeding 10 milliseconds at 250 Watt load.
All auxiliary and control relays, except as otherwise specified, shall operate on
DC voltage as specified in the attached Bill of Materials and elsewhere in this
Specification and shall have sufficient number of electrically separate contacts
for the tripping, lockout, the fault recording system and indicating circuits
specified.
Interposing relays shall be furnished, mounted and wired within each control
switchboard panel to provide, output contacts to represent contacts of the
breaker discrepancy control switches (CS), discrepancy control switches of
motor operated disconnect switch control switch (DCS), synchronizing selector
switches (SS) and for switching the incoming line voltage and running bus
voltage of CVT or VT to initiate the synchro-check relay (25+27/59) for closing
the power circuit breaker in the “Local Control Mode”. Interposing relay output
contacts shall also provided for the Remote inputs/outputs (I/O) modules
which are mounted within the control switchboard to operate the switchyard
equipment by receiving the command from the Programmable Logic Controller
(PLC) and HMI in “Remote Control Mode”. The Programmable Logic
Controller (PLC) and HMI shall a separately mounted part of the Distributed
Control System (DCS). The DCS system wil be located in the power plant
control room for control and monitoring of the overall plant equipment and all
switchyard equipment via the Programmable Logic Controller (PLC).
Interposing relays shall also be furnished, mounted and wired on the swing
rack type board together with the programmable Logic Controller (PLC). This
panel will be located among the protective relay switchboard. Interposing
relay output contracts shall be provided to represent the contract of the
5-86
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
recloser cutoff switch (79CO) in the “ON” position for use with a reclosing relay
operation.
The coils shall be suitable for continuous duty at their normal operating voltage
of 48 VDC. All contacts shall be of the renewable type with ample current-
carrying and interrupting capacity for the application, and shall withstand at
least 10 A at 1 second, 5 A at continuous duty, and be capable of interrupting
0.3 A of inductive current (L/R 40 ms) in a 220 VDC control circuit.
3.2.31 Grid TOU Energy Meters for 230 kV Revenue Metering System
The metering type shall be Grid TOU Energy Meter. Each energy meter shall
be three-phase, unbalance system, three current element, 50 Hz, high
precision, solid state type, accuracy class 0.2S for kWh meter and 0.5 for
kVARh meter. Both kWh and kVARh shall be integrally mounted in the same
enclosure. Each grid TOU energy meter shall be inspected in according to
IEC standard or equality international standard with aging reliability, safety and
accuracy. Each meter shall be of 19 inch rack mounted, back connected, with
essailec connectors, dustproof, fully tropicalized, switchboard type, and
complete with accessories for mounting. Each meter shall be suitable for
operation with instrument transformer ratios and connections as shown on the
metering and relaying diagram under both normal and short circuit conditions.
Each 230 kV line shall be furnished witch two (2) sets of kWh/kVARh for
measuring and recording active energy (kWh) and reactive energy (kVARh).
One set shall be defined as “Main Energy Meter” and the other set shall be
defined as “Backup Energy Meter”. The 230 kV line metering system shall
meet this Specification and shall also meet the requirements of EGAT PPA,
Schedule 14: Metering System.
Both kWh and kVARh shall be provided with registration number on the front
face of not less than seven (7) digits.
Programming facilities shall be provided with each meter for any parameter
setting. The meter shall have a case, which can be sealed in such a way that
the internal parts of meter are accessible only after breaking the seal.
Each energy meter shall have the following characteristics and requirements:
(a) General
5-87
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
(b) Accuracy
The meter shall have accuracy class 0.2S according to IEC 62052-1 and
62053-22 for active energy (kilowatt-hours) and 0.5 for reactive energy
(kilovar-hours).
The meter shall measure and display at lest the following electric values:
(xi) Frequency
(xiv)Billing Values
The billing values are the energy of each billing period and/or the
accumulative energy, comprise of the total energy and the energy of each
tariff rate. Those billing values shall be recorded in the meter and can be
set to display on the front panel. The displaying values, billing values, the
summated energy of each tariff rate shall be equal to the total energy
during the same billing period.
(d) Calibration
The meter shall be calibrated and/or tested using the pulse stream from
LEDs or infrared on the front panel that has rate proportional to the
measured power. EGAT on behalf of the Employer shall be able to adjust
5-88
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
the percentage error manually or via software program. If the meter has
never used in EGAT before, the calibration software shall be provided.
(v) Frequency : 50 + 5 Hz
(iii) Frequency : 50 + 5 Hz
(i) The meter shall support at least 4 tariff rates or each of 4 quadrants
of active and reactive energy measurement in each billing period.
(ii) The meter shall support maximum demand (block interval demand)
calculation for each above tariff rates corresponding to the selectable
of 15 or 30 minutes interval. Those maximum demand and the time
of maximum demand shall be recorded in the meter, and can be set
to display on front panel or read by the service software.
(iii) The billing reset for ending of billing period shall be automatic reset
by calendar time programming.
The load profile shall be either average demand (kW, kVAR, kVA) profile
or energy profile (kWh, kVARh, kVAh) recording in selectable time interval
of 1, 5, 10, 15, 30 or 60 minutes.
5-89
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
(iii) The meter shall normally draw power from VT circuits that can be any
voltage level in the full measuring range of 57.5-130 VAC (phase to
neutral). Even if one or two measuring voltage inputs are missing,
the meter shall still operate correctly without losing any accuracy of
the measurement (voltage from 1-phase input is sufficient to power
the meter). If all voltage inputs are missing, the meter shall
changeover to draw power from an auxiliary power supply
automatically without any effect to the accuracy of the meter.
(m) Communication
(i) Optical port 1 port (flag or opticom port according to IEC 62056-21
(IEC1107 or ANSI standard)
The meter shall be local accessed by using the optical port, flag or
opticom port according to IEC 62056-21 (IEC 1107) or ANSI
standards.
5-90
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
The calendar clock of the meter also can be synchronized by local GPS
standard time receiver too, and each meter shall be equipped with the
port (other than the communication port specified in Sub-Clause (m) that
could be connected to the above GPS receiver.
The bidder has to show the list of the GPS receiver(s) (manufacturer,
model, type) which supported time synchronization of meter.
(p) Software(s)
The bidder shall supply the meter parameter setting software for the
applied meters in case of these meter(s) could not be programmed by
EGAT existing software
5-91
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
(1) The bidder shall supply the meter calibration software (the
percentage error adjustment of the meter) to calibrate all applied
meters in case of the applied meters could not be calibrated by
the EGAT existing software.
(1) The purpose of the AMR software shall be used for metering data
collection and time synchronization automatically via the selected
communication.
(2) In case of the meter has not specified in the EGAT Accepted
TOU Energy Meter List (document no. 1009), the bidder shall
apply for approval, and the AMR software will be one of the
important feature to be included for the consideration.
(3) The bidder shall either providing the right for EGAT to use
existing AMR software to read and sync time the applied meter or
providing the new AMR software for EGAT approval.
(i) All of above software shall be delivered to EGAT with complete set of
instruction manuals both in English and Thai language.
(iv) The instruction manuals shall be both in hard copy and electronic files
in CD-ROM. Important remark for software(s).
(vi) The bidder shall supply the communication protocol and necessary
information of the meter to EGAT (or the third part appointed by the
Employer), to develop the interface (meter accessing) software.
(r) Certification
(i) The type test of the meter shall be certified according to class 0.2S
(kWh) of IEC 60687 or IEC 62052-11 and IEC 62053-22 standard, by
the third party who have been authorized by ISO/IEC 17025 standard
or equivalent. The bidder shall supply the type test report to EGAT
during bid evaluation period. The meter shall not be acceptable if
those type test is not available.
5-92
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
(ii) The factory test report of active and reactive energy of every energy
meter shall be supplied with the meter at the time deliver to EGAT.
3.2.32 Grid TOU Energy Meters for Generating Unit Metering System
The metering type shall be unit TOU Energy Meter. Each energy meter shall
be three-phase, unbalance system, three current element, 50 Hz, high
precision, solid state type, accuracy class 0.2S for kWh meter and 0.5 for
kVARh meter. Both kWh and kVARh shall be integrally mounted in the same
enclosure. Each unit TOU energy meter shall be inspected in according to
IEC standard or equality international standard with aging reliability, safety and
accuracy. Each meter shall be of 19 inch rack mounted, back connected, with
essailec connectors, dustproof, fully tropicalized, switchboard type, and
complete with accessories for mounting. Each meter shall be suitable for
operation with instrument transformer ratios and connections as shown on the
metering and relaying diagram under both normal and short circuit conditions.
Both kWh and kVARh shall be provided with registration number on the front
face of not less than seven (7) digits.
Each generating unit shall be furnished with two (2) sets of kWh/kVARh for
measuring and recording, on the high side of each main transformer unit the
active energy (kWh) and reactive energy (kVARh) as called for in EGAT PPA
requirements, Schedule 14: Metering System. One set of Grid TOU energy
meter shall be defined as “Main Energy Meter” and the other shall be defined
as “Backup Energy Meter”. Each Grid TOU energy meter shall also meet the
requirements of this Specification.
Programming facilities shall be provided with each meter for any parameter
setting. The meter shall have a case, which can be sealed in such a way that
the internal parts of meter are accessible only after breaking the seal.
Each energy meter shall have the following characteristics and requirements:
(a) General
(b) Accuracy
The meter shall have accuracy class 0.2S according to IEC 62052-1 and
62053-22 for active energy (kilowatt-hours) and 0.5 for reactive energy
(kilovar-hours).
5-93
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
The meter shall measure and display at lest the following electric values:
(xi) Frequency
(xiv)Billing Values
The billing values are the energy of each billing period and/or the
accumulative energy, comprise of the total energy and the energy of each
tariff rate. Those billing values shall be recorded in the meter and can be
set to display on the front panel. The displaying values, billing values, the
summated energy of each tariff rate shall be equal to the total energy
during the same billing period.
(d) Calibration
The meter shall be calibrated and/or tested using the pulse stream from
LEDs or infrared on the front panel that has rate proportional to the
measured power. EGAT on behalf of the Employer shall be able to adjust
the percentage error manually or via software program. If the meter has
never used in EGAT before, the calibration software shall be provided.
(iv) Frequency : 50 + 5 Hz
5-94
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
20 x In short-circuited
(iii) Frequency : 50 + 5 Hz
(i) The meter shall support at least 4 tariff rates or each of 4 quadrants
of active and reactive energy measurement in each billing period.
(ii) The meter shall support maximum demand (block interval demand)
calculation for each above tariff rates corresponding to the selectable
of 1 or 15 or 30 minutes interval. Those maximum demand and the
time of maximum demand shall be recorded in the meter, and can be
set to display on front panel or read by the service software.
(iii) The billing reset for ending of billing period shall be automatic reset
by calendar time programming.
The load profile shall be either average demand (kW, kVAR, kVA) profile
or energy profile (kWh, kVARh, kVAh) recording in selectable time interval
of 1, 5, 10, 15, 30 or 60 minutes.
5-95
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
(iii) The meter shall normally draw power from VT circuits that can be any
voltage level in the full measuring range of 57.5-130 VAC (phase to
neutral). Even if one or two measuring voltage inputs are missing,
the meter shall still operate correctly without losing any accuracy of
the measurement (voltage from 1-phase input is sufficient to power
the meter). If all voltage inputs are missing, the meter shall
changeover to draw power from an auxiliary power supply
automatically without any effect to the accuracy of the meter.
(m) Communication
(i) Optical port 1 port (flag or opticom port according to IEC 62056-21
(IEC1107 or ANSI standard)
The meter shall be local accessed by using the optical port, flag or
opticom port according to IEC 62056-21 (IEC 1107) or ANSI
standards.
(iii) The RS-485 port shall be provide for meter accessing via dial up
(PSTN or GSM) network and should be supported for multi-drop
connection.
(iv) The Ethernet port shall be provided for remote access the meters via
IP based (TCP/IP) network.
5-96
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
The calendar clock of the meter also can be synchronized by local GPS
standard time receiver too, and each meter shall be equipped with the
port (other than the communication port specified in Sub-Clause (m) that
could be connected to the above GPS receiver.
The bidder has to show the list of the GPS receiver(s) (manufacturer,
model, type) which supported time synchronization of meter.
(p) Software(s)
The bidder shall supply the meter parameter setting software for the
applied meters in case of these meter(s) could not be programmed by
EGAT existing software
(1) The bidder shall supply the meter calibration software (the
percentage error adjustment of the meter) to calibrate all applied
meters in case of the applied meters could not be calibrated by
the EGAT existing software.
5-97
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
(1) The purpose of the AMR software shall be used for metering
data collection and time synchronization automatically via the
selected communication.
(2) In case of the meter has not specified in the EGAT Accepted
TOU Energy Meter List, the bidder shall apply for approval, and
the AMR software will be one of the important feature to be
included for the consideration.
(3) The bidder shall either providing the right for EGAT and
Employer to use existing AMR software to read and sync time
the applied meter or providing the new AMR software for EGAT
approval.
(i) All of above software shall be delivered to EGAT with complete set of
instruction manuals both in English and Thai language.
(iii) The instruction manuals shall be both in hard copy and electronic files
in CD-ROM. Important remark for software(s).
(v) The bidder shall supply the communication protocol and necessary
information of the meter to EGAT (or the third part appointed by the
Employer), to develop the interface (meter accessing) software.
(r) Certification
(i) The type test of the meter shall be certified according to class 0.2S
(kWh) of IEC 60687 or IEC 62052-11 and IEC 62053-22 standard, by
the third party who have been authorized by ISO/IEC 17025 standard
or equivalent. The bidder shall supply the type test report to
Employer and EGAT during bid evaluation period. The meter shall
not be acceptable if those type test is not available.
(ii) The factory test report of active and reactive energy of every energy
meter shall be supplied with the meter at the time deliver to EGAT.
(a) General
5-98
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
All Plug-In circuit boards and modules shall be equipped with card guides
to prevent damage resulting from misalignment of connectors and sockets
during insertion and removal of circuit boards and modules. Circuit cards
and modules shall be easily replaceable without requiring the removal of
the entire fault recorder, or other circuit cards or modules of the fault
recorder from the rack. Modular units of the fault recorder shall be self-
supporting and require no external supports of bracing.
Optical fiber optic cables shall be provided to link fault recorder cubicles
together in order to operate as one system and to eliminate any possible
time skew. The linked configuration shall include complete time
synchronization and initiation of all recorders from any starting sensor by
means of cross triggering. The signal for cross triggering function shall not
be the event channel. For the protection of optical fiber cables, plastic-
pipe shall be used for the ones inside the building and iron-pipe shall be
used for the ones outside the building.
(b) Relays
Each event input shall be dry contact. The maximum time resolution
of the event input shall be at least one millisecond. Each individual
event channel shall be selectable for either electrically separate
normally open or normally closed contact input. The event channels
shall be synchronized with the analog channels.
5-99
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
(d) Sampling
(e) Triggering
The inputs to the sensors of each fault recorder shall be selectable from
any combination of recorded channels for that recorder. Each sensor shall
be provided with a LED target to indicate which sensor has operated and
an operation limiter with an adjust time range from 0.1 to 60 seconds. The
operation limiter shall be automatically reset when the sensor input
returns to normal. Limited operation on one sensor shall not affect the
operation of any other sensor in the system. The following type of starting
sensor shall be supplied.
One (1) single phase frequency starting sensor shall be provided for
sensing abnormal frequency conditions. The sensor shall be
adjustable from 0 to 2 Hz. over or under the normal frequency with a
step of 0.1 Hz and 0.01 Hz accuracy. The sensor shall monitor the
system frequency for at least 40 ms before starting the recorder. The
frequency sensor shall include a transducer output that can be
recorded on one of the analog channels to provide accurate cycle-by-
cycle plots of frequency versus time during the disturbance. This
sensor shall trigger the fault recorder to operate at low scan rate (less
than 1,000 samples per second).
5-100
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
One (1) zero sequence voltage starting sensor shall be provided for
sensing ground earth-fault conditions. The sensor shall be adjustable
from 1 to 20 Vrms. The sensor shall be supplied with 3 percent full
scale accuracy and the maximum response time of 10 ms.
The fault recorder shall automatically trigger, record data and print out the
data locally, and shall also automatically dial and transmit data to the
master station.
(iii) FailIncluding printer Off-line, paper out, printer fail, system manual
mode, CPU fail, power fail, and modern fail.
The alarm output shall have both normally open and normally close
contact output.
(g) Communications
For modem communication, only one telephone number per each system
5-101
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
via one local modem shall be used. Modem splitter method, LAN Modem
or phone switch (PABX) shall not be accepted.
(v) Internal speaker Volume control & switch On-Off, at least 8 status LED
(i.e. CD, CS, MEM, MSG, OH, RD, SD and TR)
The fault recording system shall be provide Ethernet 2(two) port of 10/100
Mbps. for communicate to EGAT relay protection center.
(j) Clock
The fault recording shall be supplied with built-in calendar and clock to
provide accurate date and time including month, day, year (or day, month,
year) hour, minute, second and millisecond for each operation of the
recorder. The linked fault recorder shall be time coordinated to within one
millisecond of each other.
(k) Synchronizing
The fault recording system shall be provided with the following time
synchronizing features.
(i) Synchronizing the fault recording system clock from an external clock
(using the external clock from GPS System) So, GPS clock receiver
and accessories shall be provided and completely installed in the
cabinet per system. Power Supply for GPS clock receiver shall be
125 Vdc.
(ii) Any clock utilizing the AC power supply as a time base shall upon the
loss of AC power, transfer to crystal oscillator control upon return of
AC power, the clock shall transfer back to the AC power supply as a
base.
5-102
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
(iv) The synchronizing input and output for any external clock shall be
approved by the Employer to ensure proper interfacing.
(vi) All Analog, Event Channel Waveform, Sensor Operation, Time Mark
(x) Summary of computed data, for instance, fault duration, relay time,
breaker time, percent of voltage dip, fault current, distance to fault,
etc.
Automatic range factors shall be printed on print out of local printer at the
start of each analog axis. Autoranging function or equivalent feature shall
be required to reduce peak-to-peak deflection of each analog channel.
A horizontal dotted line cross each channel of the fault record shall be
printed to mark the end of pre-fault data and the beginning of the fault
data. The local printer shall print the maximum number of 16 channels per
page.
(m) Storage
The fault recorder shall be equipped with at least 200 GB of internal hard
disk for data storage. The internal hard disk shall be SATA, EIDE or SCSI
interfaces. PCMCIA-hard disk (PC card), compact flash or compact- disk
shall not be accepted. The total storage used for fault records shall not be
less than 32 MB per Data Acquisition Unit (DAU).
(n) Security
For access security to the Fault Recording System, there shall be 3 levels
of password access for user. Each access level shall automatically
determine the access rights of the lower levels.
The fault recording system shall provide local man machine interface to
set up the system and permit easily field modification, either through built-
in patch panel or a monitor, and key board or keypad. The local man
5-103
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
- CPU failure
- Operation
- Printer failure
- Loss of Power
- Others
The fault recording system shall be furnished with the local man machine
interface. Otherwise, the industrial personal computer with a monitor shall
be provided.
(i) The 220 Vdc ungrounded station battery. The recorder shall be
furnished with a DC-to DC converter to provide transient surge
isolation between the station battery and the fault recorder. The
recorder shall be designed for continuous operation over the voltage
range of 100 to 145 Vdc without malfunction to allow for the
discharged and fully charged condition of the battery, ambient
temperature 10°C to 55°C, and humidity of 0 to 95 percent. The
recorder shall be immune to damage from accidental short circuiting
of the input or output DC supply. The recorder shall not produce any
signal, noise, or impulse which is greater than 300 millivolts peak-to-
peak on the input DC supply leads.
5-104
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
Local controller unit complete with carrying bags and all identical software
as the master station shall be supplied for each fault recording system.
The manufacturer shall be well-known of the world computer-technology.
The local controller unit shall be high performance, high reliability and
pass International standard such as ISO, IEC. The local controller unit
shall be separately quoted and shall meet the following specification.
5-105
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
version.
Recommended manufacturer for the local controller unit that have been
used in the Employer with satisfactory are Compaq, Dell, Fujitsu, IBM and
Toshiba.
Each fault recorder shall be furnished with test switches mounted and
completely wired for current and potential channels as specified in the
Metering and Relaying diagram. Test switches complete with test plugs
shall be flexitest switch, type FT-1 as specified in Sub-Clause 3.2.12
(t) Software
(vi) Automatically poll or receive calls from the remote sites for any
change of status including diagnosed problems or data.
(vii) Communication link shall be able to read, down-load, and up-load all
operating parameters of any of the remote fault recorder sites. During
up-load and down load parameters if communication error occurred,
5-106
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
the master station and remote fault recorder system shall roll back to
use the old parameters thus preventing improper operation.
(viii) A remote fault record shall be saved into a single file or single folder
in the hard disk of the master station. Large number of remote fault
records shall not reduce operating speed or cause malfunction of the
master station.
(1) It shall has at least two levels of sorting record data, i.e. by
record name and by record date, and shall be able to open or
display many records at the same time. (multi-records)
(3) For the same bus voltage, it shall be able to display each phase
voltage waveform with the same scale factor.
(4) For the same line current, it shall be able to display each phase
current waveform with the same scale factor.
(5) All waveforms which shown in the screen and on the print
preview shall be exactly the same.
(7) It shall be able to calculate RMS value and time interval of the
waveform in each cycle or in the specified range of time.
(9) For remote data at master station, the polling period shall be
continuous selectable over 1 minute to 48 hours. (at least)
5-107
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
(12) Graphic display for all analog and event channels shall include
channel identification, engineering unit, scaling, date and time
with resolution of one millisecond.
(15) The calculated channels function that has been already created
and saved shall be available whenever a record is displayed.
(xii) For the start up, all application software and all setting parameters,
the Manufacturer shall supply a copy of this software in diskette (FDD
3.5 Inches 1.4MB) or CD.
(xiii) The manufacturer shall provide both software & hardware (for example:
hard lock, etc.) for extension in the future that can use with other fault
recording systems (of same manufacturer) not less than 100 systems in
both the master station at head office and local controller unit that the
Employer use to connect with these fault recording systems.
5-108
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
(v) Documentation
(iii) One certified copy of factory test report shall be supplied for fault
recording system.
(w) Warranty
A1 594 x841
A2 420 x594
A3 297 x420
After the switchboard and cabinet structures have been fabricated and all
components assembled, the complete gear including instruments, relays and
devices shall be given standard factory tests and all others in accordance with
the latest applicable standards of NEMA and ANSI. These tests shall include,
5-109
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
Finishing and Painting. Finished panel surfaces shall be free from waves,
bellies, or other imperfections. Exterior and interior surfaces shall be cleaned by
sanding and steam cleaning, ground smooth, filled, primed, sanded and shall be
finish-painted inside and outside with RAL7036 or ANSI 61 medium gray.
One quart of matching paint shall be furnished under each item of equipment
for touching up damaged places.
A list of spare parts, tools and accessories shall be furnished with the type
number, style number, and catalog number of each spare parts as required for
each type of relays, instruments, control switches, meters, and auxiliary devices
based upon 50 hertz operation and the voltages as applied to the circuit.
The Contractor shall furnished the spare parts, tools and accessories as
specified for Control and Protection equipment with same type/models, maker,
as specified in the control and protection relay switchboards offered in this
Package, as listed in Part D: Transmission System, Section 9: Spare Parts
and Tools.
A : for approval
I : for information
5-110
Xe Pian Xe Namnoy HPP - Lao PDR Part D Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
(p) CT Calculation A
5-111
Xe Pian Xe Namnoy HPP - Lao PDR Part D - Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
Attachment No. 1
5-112
Xe Pian Xe Namnoy HPP - Lao PDR Part D - Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
Attachment No. 1 (Cont’)
5-113
Xe Pian Xe Namnoy HPP - Lao PDR Part D - Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
5-114
Xe Pian Xe Namnoy HPP - Lao PDR Part D - Transmission System
Annex 3 Particular Technical Specifications Section 5: 230 kV Control and Protection System for
Pakse Substation
Attachment No. 2
Accepted
Manufacturer
Type/Model
IDM Hathaway/USA
TR2000 Rochester (RIS)/USA
BEN5000 Hathaway/BELGIUM
SIEMEAS R SIEMENS/GERMANY
TESLA 3000 ERL Phase/CANADA
Note
5-115