Al Qouz Villa Project B2 Classic Schedule Layout 05-Jun-20 05:26

# Activity ID Activity Name Original PredecessorsStart Finish


Duration 2016 2017 2018 2019 2020 2021 2022 2023
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
1 364d 03-Apr-17 A 06-Dec-19 06-Dec-19, Al Qouz Villa Project B2
Al Qouz Villa Project B2
2 A1200 Drainage & Plumbing Works 352d 03-Apr-17 A 07-Aug-18 Drainage & Plumbing Works
3 A1210 Electrical Works 361d 03-Apr-17 A 20-Aug-18 Electrical Works
4 A1220 Selection of HVAC Contractor 0d 15-Aug-18 A 15-Aug-18 Selection of HVAC Contractor
5 A1230 HVAC Works 343d A1220 15-Aug-18 A 06-Dec-19 HVAC Works
6 A1240 Supply of tiles by client 1d A1220 01-Nov-17 01-Nov-17 Supply of tiles by client
7 A1250 Wall Tiles 44d A1240 01-Jan-18 01-Mar-18 Wall Tiles
8 A1260 Marble Flooring 64d A1240 01-Feb-18 01-May-18 Marble Flooring
9 A1270 EXTENSION OF UPPER ROOF SLAB + INCREASED HEIGHT93d
OF COMPOUND
A1250 02-Nov-18
WALL + REVISED
A 01-Apr-19
PARAPET
A WALL EXTENSION OF UPPER ROOF SLAB + INCREASED HEIGHT OF COMPOUND WALL + REVISED PAR
10 A1280 External Stone Cladding 50d A1250 01-Feb-19 A 11-Apr-19 External Stone Cladding
11 A1290 Roof Water Proofin g Works 67d A1250 26-Mar-18 26-Jun-18 Roof Water Proofin g Works
12 A1300 Aluminium & Glazing Works 66d A1250 02-Apr-18 02-Jul-18 Aluminium & Glazing Works
13 A1310 Wooden Doors 55d A1250 02-Apr-18 15-Jun-18 Wooden Doors
14 A1320 Kitchen Cabinets & Wardrobes 45d A1260 15-May-18 16-Jul-18 Kitchen Cabinets & Wardrobes
15 A1330 False Ceiling Works 15d A1320 16-Jul-18 03-Aug-18 False Ceiling Works
16 A1340 Dubai Municipality Inspection and Handover 7d A1330 15-Aug-18 23-Aug-18 Dubai Municipality Inspection and Handover

Primary Baseline Remaining Work Milestone Page 1 of 1 TASK filter: All Activities