Sun Power Engineering (Pvt) Ltd

No 74/12, Dikwella Road,Beliatta,Srilanka.


Tel:047-2251666, Hotline:071-8883344 Fax:047-2251666
Email:info@sunpowerengineering.lk
Web:www.sunpowerengineering.lk

PANEL TEST REPORT

Date
Job No.
Panel No.
Drawing No.

Page No. Attachment


01
02
03
04
05
06
07

1
1.0. VISUAL INSPECTION REPORT

No DESCRIPTION COMPATIBILITY REMARKS


ELECTRICAL

01 Panel Layout Comply to Specification


02 ACB/MCCB Settings as Specified
03 Thermal Overload Relay as Specified
04 Timer Setting as Specified
05 All Meters Tested Under Varying Load
06 Conductor Cross Section as IEC Specified
07 Fuse, Contractor, OC Devices Ratings as
Specified
08 Colors of Wires as Specified
09 Busbar Identification as Specified
10 Earth Connection to Metal Frame in all Sections
11 Number Marking as per Control Circuit Diagram
12 Earth Continuity Test
13 Insulation Resistance Test (1000V DC)
14 Dielectric Test (2.5kV DC for 1 Sec)
15 Full Functional Test as per SLD and Control
Circuit
16 Functionality Overload and Trip Circuit Tested
17 Busbar and Power Continuity Test
18 Electrical Interlock Check
19 Control Circuit as Specified
20 Terminal of Generator Start Signal Check
21 Phase Sequence in Motor Starter Check
22 Watt value and Rotating Direction Check in Watt
meter
23 ACB/MCCB Mechanical Interlock Checked
24 ACB/MCCB Full Functional while One CB is
Racked Out
25 Protection Relay Setting
26 ELR/EFR Testing Using Load Bank
27 ACB/MCCB Fixed Connection Check with Load
bank

2
2.0. FUNCTIONAL TEST REPORT

No DESCRIPTION COMPATIBILITY REMARKS


ELECTRICAL

01 Indicator Lamp
1.1 Phase Indicator
1.2 Control Indicator
1.3 Trip Indicator

02 Push Button Operation


03 Selector Switch Operation
04 Emergency Push Button Operation
05 Remote Operation of Generator (On) in ATS
06 Remote Operation of Generator (Off) in ATS
07 ELR/EFR Testing Using Load Bank
08 Over Current Relay Using Load Bank
09 ACB/MCCB Trip
Reset

10 MCB/ Isolators On/ Off


11 UVT Coil Operation
12 Shunt Coil Operation
13 Fuse Health (Continuity)
14 Timer Function
15 Phase Sequence w.r.t. Incoming Supply
14.1 BusBar
14.2 Outgoing MCCB/ MCB/ Isolator
14.3 Motor Starter (DOL/SD/VFD/SS)

16 Electrical Interlock Checked in ATS


17 Mechanical Interlock Checked in ATS
18 Volt Meter Function
19 Ammeter Function
20 Power Analyzer Function
21 Hour Counter Function
22 PFR Function Attached
23 Other Relay Function Attached

3
3.0. VISUAL INSPECTION REPORT- GENERAL

No DESCRIPTION COMPATIBILITY REMARKS


GENERAL

01 Panel Front Layout as per the drawing


02 Paint Color and Finish as Specified
03 Components in Doors are Mounted Straight
04 Paint Damage
05 Steel Damage
06 Front Door is Earth
07 Panel is Neat and Clean
08 Full Document in Drawing Pouch
09 SLD is Attached inside the Door
10 All Labels attached as Specified
11 Doors are aligned