Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
OF CONTENTS
This program helps project stakeholders to organize their teams and
activities
SPREADSHEETS DESCRIPTION
Data Filling out the Data sheet completes the header portion of all
1 remaining sheets in the project workb
Minicharter The Project Minicharter sheet can be used as a charter for small
2 projects or a summarization of a full char
Stoplight The Stoplight Report sheet contains a status report that can be 3used to keep sponsors, team members, an
Master Code Cost Code to organize your Cost Collection and Reporting 4
Budget The Budget sheet allows you to track original budget, expenditures
5 to date, and any cost variance.
CBA The Cost/Benefit Analysis sheet allows you to review the proposed
6 project and potential alternatives and m
Risks The Risk Management Matrix sheet allows you to identify, qualify,
7 quantify, and prioritize risks (events tha
PROJECT MANAGEMENT WORKBOOK - TABLE
OF CONTENTS
Issues The Issues Log sheet allows you to identify and monitor project8issues (unplanned events that have happe
Action The Action Items sheet allows you to track and monitor action items
9 assigned to team members. Action ite
Milestones The Deliverable Milestones sheet allows you to identify major deliverable
10 milestones and the due dates, o
WBS The Work Breakdown Structure sheet includes the activities that
11must be completed during a project, the e
Roster The Roster sheet provides contact information for all those involved
12 on the project.
R&R The Roles and Responsibilities sheet shows the primary role of13
team members, any deliverables in which
RAM The Resource Assignment Matrix sheet shows you what type of
14resource is responsible for, or somehow i
RCM The Resource Commitment Matrix sheet shows how many effort
15 hours each person on the project has be
A&C The Assumptions and Constraints sheet allows you to track project
16 assumptions and constraints.
Decision The Decision Log sheet allows you to track all major decisions 17
made during the course of the project.
PROJECT MANAGEMENT WORKBOOK - TABLE
Communitcat
OF CONTENTS
ions
The Communication Plan sheet allows you to detail your communication
18 plan: how you are going
Expectations The Expectations sheet allows you to identify and track the expectations
20 of various stakeholders.
Changes Log The Change Control Log sheet allows you to track all change requests
21 that are in process or finalized.
Deliverables The Deliverable Acceptance Log sheet allows you to track the 22
status of deliverable acceptances.
PERT The PERT Analysis sheet allows you to perform PERT analysis23on WBS tasks.
Delphi The Delphi Exercise sheet allows you to develop estimates for 24
WBS tasks through the Delphi technique.
TimeSum The Timesheet Totals sheet allows you to track effort hours of 25
your entire team by individual and by month
Timesheet The Timesheet can be used by each team member to submit effort
26 hours by activity, by month.
PROJECT MANAGEMENT WORKBOOK - TABLE
OF CONTENTS
Initial Project
Size The Initial Project Size Estimate sheet allows you to estimate, at
27high-levels (40,000 ft. view), the size of a
Estimate
Resource
Loading
The Resource Loading sheet allows you to identify the work
28 effort required, the duration, and the a
Quality
Metrics
The Project Quality Metrics sheet allows you to identify critical 29
success criteria, related quality metrics, and
Start up
Checklist
Project Start up Checklist. Guidelines to make sure stakehoders
35do not forget anything right at the start of
Document
Submittal
Document Submittal Form 38
Daily
Equipment Daily Equipment Report Form. Track your equipment usage with
39 this template.
Report
Project
Directory Project Directory Form. Essential tool to have stakeholder geographical
40 and IT located.
Request for
Information
Request for Information (RFI) Might be one of the most used
44 templates in every project due to the
Request for
Inspection
Request for Inspection (RFIn) Important form needed to guarantee
45 inspections when needed and avoid pr
Shop
Drawing
Submittal
Shop drawings Submittal Control Spreadsheet. Follow up shop46
drawings submittals to guarantee their com
Ctrl
PROJECT MANAGEMENT WORKBOOK - TABLE
Shop OF CONTENTS
Drawing Shop Drawings Submittal Form. Handy template to customize your
47 shop drawings submittals
Submittal
Procurement
Plan of Procurement Plan of Action Template. Follow up procurement 48
of project materials and equipment in a sys
Action
Meeting
Ground Meeting Ground Rules Template. Gides the stakeholders on meetings
49 behavior and expectations.
Rules
Design
Design Organization Chart Template. Allows you plan your50design team without having to start fro
Orgchart
CLAIMS
CAUSE &
EFFECT CLAIMS CAUSE & EFFECT MATRIX 52
MATRIX
PROJECT
RISKS PROJECT RISKS INVENTORY 53
INVENTORY
PROJECT MANAGEMENT WORKBOOK - TABLE
LABOR
OF CONTENTS
COMPETENC
Y Labor Competency Standards 54
STANDARD
PM
COMPETENC
Y
DEVELOPME Integrated Approach to PM Competency Improvement
55
NT
APPROACH
CRAWFORD
Crawford
ISHIKURA Ishikura Factor Table for Evaluating Roles
56
CIFTER
CRAWFORD
ISHIKURA
UNITS OF Crawford Ishikura Units of Competence 57
COMPETENC
E
CIFTER
SUMMARY
Crawford
OF UNITS, Ishikura Summary of Units, Elements and Performance
58 Criteria
ELEMENTS…
..
PROJECT MANAGEMENT WORKBOOK - TABLE
MANAGE OF CONTENTS
STAKEHOLD Manage Stakeholders Relationships 59
ERS
MANAGE
DEVELOPME
NT OF THE Manage Development of the Plan for the Project 60
PLAN
MANAGE
PROJECT Manage Project Progress 61
PROGRESS
MANAGE
PRODUCT
ACCEPTANC Manage Product Acceptance 62
E
MANAGE
PROJECT
TRANSITION Manage Project Transitions 63
S
EVALUATE &
IMPROVE
PROJECT Evaluate and Improve Project Performance 64
PERFORMA
NCE
PROCUREM
ENT Procurement Road Map 65
ROAD MAP
PROJECT MANAGEMENT WORKBOOK - TABLE
RESOURCE
OF CONTENTS
PLANNING Resource Planning Road Map 66
ROAD MAP
COST
ESTIMATING
& Cost Estimating and Budgeting Road Map 67
BUDGETING
ROAD MAP
COST
ACCOUNTIN
G ROAD Cost Accounting Road Map 68
MAP
RISK
MANAGEME
NT ROAD Risk Management Road Map 69
MAP
PROGRESS
MEASUREM
ENT Progress Measurement Road Map 70
ROAD MAP
COST
CONTROL Cost Control Road Map 71
ROAD MAP
PROJECT MANAGEMENT WORKBOOK - TABLE
OF CONTENTS
VA & VE
ROADValue Analysis & Value Engineering Road Map72
MAP
FORECASTI
NG Forecasting Road Map 73
ROAD MAP
FORENSIC
ANALYSIS Forensic Analysis Road Map 74
ROAD MAP
ET
SHE
EAD
SPR
THIS
TO
TO GO
GO
TO THISTO
SPREAD
SHEET
Data!A1
Mini Charter'!A1
Stoplight!A1
Master Code!A1
Budget!A1
CBA!A1
Risks!A1
ET
SHE
EAD
SPR
Issues!A1
THIS
TO
GO
Action!A1
TO
Milestones!A1
WBS!A1
Roster!A1
R&R'!A1
RAM!A1
RCM!A1
A&C'!Print_Area
Decision!A1
ET
SHE
EAD
SPR
Comm!A1
THIS
TO
GO
Stake!A1
TO
Expectations!A1
Chg Log'!A1
Deliver!A1
PERT!A1
Delphi!A1
TimeSum!A1
Timesheet!A1
ET
SHE
EAD
SPR
THIS
TO
Initial Project Size Estimate'!A1
GO
TO
Resource Loading'!A1
Quality Metrics'!A1
PM SCOPE'!A1
CO Log'!A1
Cost Breakdown'!A1
Estimate Checklist'!A1
PM Contract'!A1
Start up Checklist'!A1
Project Directory'!A1
Invoice!A1
Employee Report'!A1
Design Orgchart'!A1
CPMT '!A1
Project Project title here
Project # Project # here
Project manager Project manager name here
Sponsor Sponsor name here
Project artifacts Location of project documents here
Last updated Date of update here
Last Rev.
Design by:
No. Architectural Drawings
No. Civil Drawings
No. Mechanical Drawings
No. Electrical Drawings
No. Interior Design Drawings
Architectural Specifications
Civil Specifications
Mechanical Specifications
Electrical Specifications
Interior Design Specifications
Traffic Studies
Soil Investigation
Accoustic Studies
BOQ
WBS
Cost Estimate
Feasibility Study
Schedule of Finishings
TO GET BACK TO MAIN MENU:
Info!A1
Project Charter
Project Project title here Project #
Project manager Project manager name here Sponsor
Project artifacts Location of project documents here Updated
Background
Objectives
Success criteria 1-
2-
3-
4-
5-
Signatures
Sponsor
Signature
Printed name
Date
Project manager
Signature
Printed name
Date
Project Charter
Project # here TO GET BACK TO MAIN MENU:
Sponsor name here
Date of update here Info!A1
Out of Scope
Due Date
Risks
Risk Description
Project Charter
Stoplight Report
Project Project title here Project # Project # here
Project manager Project manager name here Sponsor Sponsor name here
Project artifacts Location of project documents here Updated Date of update here
Deliverables
1 2 3 4 5 6 7 8 9 10
Schedule
Scope
Cost
Risk
Issues
Planned completion
Est. completion
Management Alert
ID Situation Requiring Management Attention Action Plan Owner
Info!A1
MASTERCODE COST CODE SYST
GENERAL NOTES
1. L-M-S-R Labor - Material - Subcontract - Rental. (Category II)
2. Labor = Payroll Labor and Subcontract Labor (optional). (Category I)
3. Materials = Material only, including delivery and taxes. (Category I)
4. Subcontract = Labor & Material Subcontracts and Subcontract Labor (optional). (Category I)
5. Rental = Rental only, including delivery and taxes. (Category I)
6. None = Not Classified / Unclassified / No Class Assigned
7. N/A = Not Applicable
8. List Status = Account status in the Template File when 1st installed. (may be changed by user)
DIVISION 100 LAND & PROPERTY CLASS
Info!A1
. (Category I)
hanged by user)
LIST STATUS NOTES
Budget Status
Approved Budget Planned Expenditures to Date Actual Expenditures to Date Variance
$0.00 $0.00 $0.00 $0.00
Planned Remaining Budget Actual Remaining Budget Variance
$0.00 $0.00 $0.00
Additional $ needed
Budget Details
Internal Expenses
Salaries Hourly Rate # Hours Total Cost
Type of resource $0.00 0.00 $0.00
Type of resource $0.00 0.00 $0.00
Type of resource $0.00 0.00 $0.00
Type of resource $0.00 0.00 $0.00
Type of resource $0.00 0.00 $0.00
Type of resource $0.00 0.00 $0.00
Other Internal Expenses Total Cost
Type of expense $0.00
Type of expense $0.00
Type of expense $0.00
Total Internal Expenses $0.00
External Expenses
Consulting Costs Total Cost
Type of consulting $0.00
Type of consulting $0.00
Type of consulting $0.00
Capital Expenditures Total Cost
Type of expense $0.00
Type of expense $0.00
Type of expense $0.00
Total External Expenses $0.00
Budget
Total Budget $0.00
TO GET BACK TO MAIN MENU:
Info!A1
Cost/Benefit Analysis
Project Project title here Project # Project # here
Project manager Project manager name here Sponsor Sponsor name here
Project artifacts Location of project documents here Updated Date of update here
Benefits/Savings
Current Process FY01 FY02 FY03 FY04 FY05 Total
Total annual price
New Process
Total annual price
Annual savings $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Cumulative savings $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Cumulative costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Cumulative total net savings $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Future Value
Present Value Interest Rate # Periods Future Value
0 0.00 0 $0.00
Present Value
Future Value Interest Rate # Periods Present Value
$0.00 $0.00
Cost/Benefit Analysis
Info!A1
Risk Management Matrix (Risk Register)
Project Project title here Project # Project # here
Project manager Project manager name here Sponsor Sponsor name here
Project artifacts Location of project documents here Updated Date of update here
Detectability
Importance
Probability
Impact
Risk Response and Date Date to
ID Risk Description Category Trigger Event/Indicator Contingency Plan Owner Status
Description Entered Review
What act or event initiates How will you respond to If the risk becomes a
Who
either the risk occurrence or this risk and what actions reality, what will you do in
What is this risk? 0 monitors
precipitates the response will you take to match that response, as a backup, or
this risk?
strategy? response? alternative/ workaround?
1
2 0
3 0
4 0
5 0
6 0
7 0
8 0
9 0
10 0
11 0
12 0
13 0
Risk Management Matrix (Risk Register)
14 0
15 0
TO GET BACK TO MAIN MENU:
Info!A1
Issues Log
Project Project title here Project # Project # here
Project manager Project manager name here Sponsor Sponsor name here
Project artifacts Location of project documents here Updated Date of update here
Importance
Date Date to Date
ID Issue Description Project Impact Action Plan/Resolution Owner
Entered Review Resolved
How will this impact scope, How do you intend to deal with Who manages
1 What is the issue?
schedule & cost? this issue? this issue?
10
11
Issues Log
12
13
14
15
TO GET BACK TO MAIN MENU:
Info!A1
Action Items
Project Project title here Project # Project # here
Project manager Project manager name here Sponsor Sponsor name here
Project artifacts Location of project documents here Updated Date of update here
Who manages
1 What is the item to be completed?
this issue?
10
11
12
13
14
15
Action Items
oject # here TO GET BACK TO MAIN MENU:
ponsor name here
ate of update here Info!A1
Comments
Deliverable Milestones
Project Project title here Project # Project # here
Project manager Project manager name here Sponsor Sponsor name here
Project artifacts Location of project documents here Updated Date of update here
Planned Actual
ID Milestone Description Objectives Assumptions Constraints
Completion Completion
10
11
12
13
14
15
Deliverable Milestones
TO GET BACK TO MAIN MENU:
Info!A1
Work Breakdown Structure
Project Project title here Project # Project # here
Project manager Project manager name here Sponsor Sponsor name here
Project artifacts Location of project documents here Updated Date of update here
Dependencies
Effort Planned Estimate to
ID Task Status Cost Start Date Actual Completion Resource
Hours Completion Completion
1 ID # of task
10
11
12
13
14
15
Work Breakdown Structure
TO GET BACK TO MAIN MENU:
Info!A1
Roster
Project Project title here Project # Project # here
Project manager Project manager name here Sponsor Sponsor name here
Project artifacts Location of project documents here Updated Date of update here
Core/
Name Extended Title Dept. Phone Cell Phone E-Mail Project Role
Team
000.000.0000 000.000.0000
Core/
Name Extended Title Dept. Phone Cell Phone E-Mail Project Role
Team
TO GET BACK TO MAIN MENU:
Info!A1
Roles and Responsibilities
Project Project title here Project # Project # here
Project manager Project manager name here Sponsor Sponsor name here
Project artifacts Location of project documents here Updated Date of update here
% Assigned
Core/
Deliverables Other Project
Name Extended Deliverables Leading Project Role Responsibility
Participating On Assignments
Team
Roles and Responsibilities
TO GET BACK TO MAIN MENU:
Info!A1
Resource Assignment Matrix
Project Project title here Project # Project # here
Project manager Project manager name here Sponsor Sponsor name here
Project artifacts Location of project documents here Updated Date of update here
Appl'n Developer
Project Manager
Business Driver
Project Task
Data Steward
Data Modeler
IS Sponsor
Educator
DBA
Project Management and Requirements
Initiation
1 Develop preliminary project scope
2 Identify business need
3 Develop preliminary budget
4 Identify preliminary return on investment
5 Complete project charter
Planning
1 Establish project identity
2 Identify project team/resources
3 Conduct stakeholder analysis
4 Prepare draft project schedule
5 Conduct project kickoff meeting
6 Gather detailed user requirements
7 Define current business processes (as is)
8 Revise project schedule
9 Develop project communication plan
10 Develop project organizational structure
11 Identify training plan
12 Develop project quality plan
13 Develop scope management plan
14 Develop risk management plan
15 Develop change management plan
16 Develop cost management plan
17 Develop schedule management plan
18 Develop technical specifications
19 Develop technical architecture
20 Conduct project procurement
21 Finalize project budget
22 Finalize return on investment
23 Ongoing project management
Execution
1 Develop training materials
2 Execute communication plan
3 Develop software
4 Develop new business processes (to be)
5 Deploy new software
6 Conduct training
Closing
1 Get deliverable acceptance
2 Close out contracts
3 Finalize budget
4 Finalize return on investment
5 Conduct closure survey
6 Conduct/document lessons learned
7 Archive project
Legend
Creates the deliverable C1: primary creator; C2: contributor
Input required I
Reviews the deliverable R
Approves the deliverable A
Notified when the deliverable is complete N
Owns the deliverable upon completion O
TO GET BACK TO MAIN MENU:
Info!A1
QA Analyst
Resource Commitment Matrix
Project Project title here Project # Project # here
Project manager Project manager name here Sponsor Sponsor name here
Project artifacts Location of project documents here Updated Date of update here
Info!A1
Assumptions and Constraints
Project Project title here Project # Project # here
Project manager Project manager name here Sponsor Sponsor name here
Project artifacts Location of project documents here Updated Date of update here
10
11
12
13
14
15
Assumptions and Constraints
Decision Log
Project Project title here Project # Project # here
Project manager Project manager name here Sponsor Sponsor name here
Project artifacts Location of project documents here Updated Date of update here
10
11
12
13
14
15
Decision Log
TO GET BACK TO MAIN MENU:
Info!A1
Communication Plan
Project Project title here Project # Project # here
Project manager Project manager name here Sponsor Sponsor name here
Project artifacts Location of project documents here Updated Date of update here
Recipient/
ID Communication Description Frequency Format Owner
Attendees
10
11
12
13
14
15
16
Communication Plan
17
TO GET BACK TO MAIN MENU:
Info!A1
Stakeholder Analysis
Project Project title here Project # Project # here
Project Manager Project manager name here Sponsor Sponsor name here
Project Artifacts Location of project documents here Updated Date of update here
Risk
ID Stakeholder Role Impact Influence Needs
Tolerance
10
11
12
13
14
15
Stakeholder Analysis
TO GET BACK TO MAIN MENU:
Info!A1
Responsibility
Expectations
Project Project title here Project # Project # here
Project manager Project manager name here Sponsor Sponsor name here
Project artifacts Location of project documents here Updated Date of update here
ID Expectation Description Source Must Have Want to Have Nice to Have Date Identified
Expectations
TO GET BACK TO MAIN MENU:
Info!A1
Change Control Log
Project Project title here Project # Project # here
Project Manager Project manager name here Sponsor Sponsor name here
Project Artifacts Location of project documents here Updated Date of update here
Priority
Date Included in
ID Change Description Originator Date Entered Evaluator Status Date Paid
Assigned Rev. #
10
11
12
13
14
15
Change Control Log
TO GET BACK TO MAIN MENU:
Info!A1
Deliverable Acceptance Log
Project Project title here Project # Project # here
Project manager Project manager name here Sponsor Sponsor name here
Project artifacts Location of project documents here Updated Date of update here
Date of
ID Deliverable Description Comments Evaluator Status
Decision
10
11
12
13
14
15
Deliverable Acceptance Log
TO GET BACK TO MAIN MENU:
Info!A1
PERT Analysis
Project Project title here Project # Project # here
Project Manager Project manager name here Sponsor Sponsor name here
Project Artifacts Location of project documents here Updated Date of update here
5.00 3.00 8.00 5.17 0.83 0.83 -0.83 1.67 -1.67 2.50
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
PERT Analysis
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
PERT Analysis
0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
e TO GET BACK TO MAIN MENU:
me here
te here Info!A1
-3 Std
Dev
-2.50
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Delphi Exercise
Project Project title here Project # Project # here
Project manager Project manager name here Sponsor Sponsor name here
Project artifacts Location of project documents here Updated Date of update here
Info!A1
Timesheet Totals
Project Project title here Project # Project # here
Project manager Project manager name here Sponsor Sponsor name here
Project artifacts Location of project documents here Updated Date of update here
Info!A1
Timesheet
Project Project title here Project # Project # here
Project manager Project manager name here Sponsor Sponsor name here
Project artifacts Location of project documents here Updated Date of update here
Info!A1
Initial Project Size Estimate
Project Project title here Project # Project # here
Project manager Project manager name here Sponsor Sponsor name here
Project artifacts Location of project documents here Updated Date of update here
Scope Estimate
Technology Systems Impacted
1 to 2 3 to 5 6 or more
Cost Estimate
# of Resources Involved
Less than 10 11 to 50 51 or More
Cost Estimate
# of Resources Involved
Less than 10 11 to 50 51 or More
Low Avoid
Benefit
Medium
Info!A1
Resource Loading
Project Project title here Project # Project # here
Project manager Project manager name here Sponsor Sponsor name here
Project artifacts Location of project documents here Updated Date of update here
Estimate of Total
ID Names Activity Duration Commitment Level Total
Effort
0
Effort Hours Committed
Estimate of Total
ID Names Activity Duration Commitment Level Total
Effort
Total 0 0 0 0
TO GET BACK TO MAIN MENU:
Info!A1
Project Quality Metrics
Project Project title here Project # Project # here
Project Manager Project manager name here Sponsor Sponsor name here
Project Artifacts Location of project documents here Updated Date of update here
Critical Success
ID Potential Quality Metric Priority Metric Target Action Plan
Criteria
TO GET BACK TO MAIN MENU:
Info!A1
Action Plan
TO GET BACK TO MAIN MENU:
Info!A1
Change Order Log
Date:
Owner:
Contract amt:
Project name:
S = Submitted A = Approved
C.O.
number Description Amount
TO GET BACK TO MAIN MENU:
Info!A1
No:
S = Submitted A = Approved R = Rejected
Schedule Status
change S A R
Page of
Cost Breakdown
Date:
Sponsor:
Building ID:
Project name:
Location:
Processing Analyst
Info!A1
Trade description
Offsite Costs
(Not inc. in trade item breakdown)
Description Est. cost
TOTAL: $ _____________
Demolition
(Not inc. in trade item breakdown)
Description Est. cost
TOTAL: $ _____________
Date: ________________
Date: ________________
Date: ________________
Date: ________________
Date: ________________
Estimate Checklist
Site work
Backfill & grading
Basement excavation
Earth imported/export
Footings excavation
Off site improvements
Sewer lateral/waterline
Site preparation
Soil treatment
Other
Concrete
Flatwork
Footings
Foundation
Additives
Area wells
Bolts
Chamfer strips
Cold joint
Columns
Drayage
Expansion joint
Form oil & cleaner
Forms & whalers
Forms, stakes, braces
Poly/visqueen
Rebar-1/2" @ft.
Rebar-3/8" @ft.
Rebar-5/8" @ft.
Rebar-7/8" @ft.
Rental equipment
Straw/hay
Ties & tie wire
Waterproofing foundation
Window & door bucks
Wire mesh
Other
Rough lumber
Studs 2 x 4
Studs 2 x 6
Trusses
Fir 2 x 8 x 8
Fir 2 x 8 x10
Fir 2 x 8 x12
Fir 2 x 8 x14
Fir 2 x10 x10
Fir 2 x10 x12
Fir 2 x10 x14
Fir 2 x12 x10
Fir 2 x12 x12
Fir 2 x12 x14
Fir 2 x12 x _________
1 x 4 #2 Grade
1 x 6 #2 Grade
1 x 8 #2 Grade
1 x 10 #2 Grade
Post-4 x 4"
Post-6 x 6"
Glulam
Plywood 3/8"
Plywood 1/2"
Plywood 5/8"
Plywood 3/4"
Plywood T & G 5/8"
Plywood T & G 3/4"
Fascia
Soffit
Frieze
Caulking & sealants
Builders adhesive
Scaffolding
Equipment rental
Nails 16d box
Nails 16d nail gun
Nails 8d box
Nails 8d nail gun
Nails 16d duplex
Nails 8d duplex
Nails-finish (rough only)
Bolts, washers, nuts
Framing connectors
Saddles
Staples air gun
Other
Roofing
Built-up
Tile
Shake
Cedar
Drying-in
Felt-#15
Felt-#30
Ice & water shield
Flashing & counter F.
Drip edge
Valley tin
Roof jacks & vents
Galv. roof nails-3/4"
Galv. roof nails-1-1/2"
Simplex nails
Roofing cement
Other
Insulation
Walls
Ceiling
Miscellaneous insulation
Radiant barrier
Vapor barrier
Drywall
Corner bead
Drytite nails-@ lb.
Hot mud
J-Metal
Knife blades
Masking supplies
Perfa-tape
Quick-tape
Topping-boxes
Other
Finish carpentry
Base molding
Chair rail
Crown molding
Doors
Door casing
Front door
3/0 Exterior
2/8 Exterior
Fire rated/self-closing
3/0 Hollow C. interior
2/8 H. C. interior
2/6 H. C. interior
2/4 H. C. interior
2/0 H. C. interior
Bi-fold 7'
Bi-fold 6'
Bi-fold 5'
Bi-fold 4'
By-pass 7'
By-pass 6'
By-pass 5'
By-pass 4'
Pocket 3/0
Pocket 2/8
Pocket 2/6
Pocket 2/4
Specialty doors
Garage door
Shelving 1 x12
Shelving 1 x16
1 x 4" Pine
1 x 6" Pine
1 x12" Pine
3/4" Ply/pressed wood
Shims
Keyed locks
Deadbolts
Privacy locks
Passage locks
Other locks/latches
Pulls & catches
Door bumpers/stops
Towel bars/rings
Paper holders
Soap dishes
Closet rods
Robe hooks
Other bathroom hardw.
Door viewer
House numbers
Mail box
Garage door operator
Thresholds
Weatherstripping
Screen doors
Other
Wall coverings
Acoustical ceiling tile
Ceramic tile
Masking supplies
Paint rollers/brushes
Paint-alcohol sealer
Paint-latex
Paint-oil
Paint-PVA
Paneling (sheets)
Sandpaper, caulking, etc.
Stain & varnish
Textured paints
Wainscot
Wallpaper tools/glue
Wallpaper/border (rolls)
Other
Floor covering
Area rugs
Asphalt/rubber tile
Base (rubber)
Carpet glue
Carpet tool rental
Carpets
Ceramic tile
Concrete sealer
Cove
Hardwoods/parquet
Linoleum
Linoleum glue
Metal trim
Nails & glue
Other exterior carpets
Other floor paint
Padding
Quarry tile
Rock
Roller & blades
Seam filler
Seam tape
Staples
Synthetic turf
Tack strips
Other
Glazing
Windows
Patio sliding door
Stained glass
Sandblast/etched glass
Other glazing
Specialty glass
Mirrors
Medicine cabinets
Skylights
Other
Masonry
Fireplace
Fireplace face
Veneer
Masonry sidewalks/paths
Fence
Other
Plumbing
Rough
Finish
Jacuzzi - spa
Shower stall
Tub - enclosure
Extra water heaters
Fixture allowance
Water softener
Sprinkling system/rough
Other
HVAC
Furnace & distribution
Attic vents
Bathroom vents
Kitchen vent
Other vents
Evaporative cooler
Air conditioning
Special controls
Area heater
Wood-burning stove
Fireplace - gas log
Fireplace blower
BBQ grill
Humidifier
Electronic air purifier
Other
Electrical
Rough
Finish
Light fixture allowance
Landscape light(s)
Connect HVAC, etc.
Doorbell/chime
Security system
TV/stereo system/antenna
Intercom system
Computer system
Smoke/fire alarm system
Telephone installation
Other
Cabinets
Kitchen cabinets
Bath cabinets
Linen closets
Bookshelves
Pantry
Clothes chute
Garage - cabinets
Garage - workbench
Other
Hard surfaces/counters
Ceramic tile
Corian
Extra materials
Plastic laminate bid
Synthetic marble
Other
Appliances
Countertop unit
Dishwasher
Disposal
Freezer
Microwave oven
Range
Range hood
Refrigerator
Separate oven(s)
Trash compactor
Under cabinet units
Other
Decorating
Decorator fee
Model home furnishing
Other
Landscaping
Bark/gravel/rock
Boxes/borders/pots
Flowers
Fountain
Grading
Irrigating
Shrubs
Sod/lawn
Topsoil
Trees
Yard light
Other
Info!A1
Date:
Owner:
Project name:
Project number:
This agreement is made this ______ day of ________________, 19____ by and between
______________________________________, hereinafter called the Owners, whose address is
______________________________________, and __________________________, hereinafter
called the Project Manager, Contractor's License No. ___________, whose address is___________
___________________________________________________________________________________
The Project Manager agrees to manage and see to completion in an excellent and substantial
manner, the construction of a single family residence (herein called the "Project") for
_________________________ upon the real property located at __________________.
Pre-construction phase
1. Assist in finding a lender;
2. Obtain all necessary permits and handle all interface with the building department
(general, grading, electrical, mechanical, plumbing, etc.);
3. Provide a complete materials takeoff (bill of materials) for lumber and framing
hardware;
4. Coordinate the bidding process with at least three bids per each major craft;
5. Act as the clearing house for information to bidding subs;
6. Check up on the references of each subcontractor;
7. Assemble presentation to the lender;
8. Provide a detailed cost breakdown sheet for the lender;
9. Develop a critical path time line with completion of the living space targeted for
;
10 . Act as the contractor of record with the lender;
11 . Recommend to the Owners the most qualified and reasonably priced subcontractor
for each phase of construction based on the bids submitted;
12 . Finalize the contract documents with each sub, making sure everything is
"spelled out";
13 . Develop a list of contract addenda covering areas of payment disbursment, safety,
worker's compensation, cleanup, and craftmanship standards.
Construction phase
Goal: Make sure something progresses on the job site every working day in
order to get the _________________ into their new home by ____________.
The Project Manager will see to it that the Project is constructed and completed in strict
conformance with the plans and specifications and that all laws, ordinances, rules, and
regulations of the applicable governmental authorities are adhered to. Further, he agrees to:
1. Be the Owners' "eyes and ears in the field";
2. Meet with Owners on a regular basis to review progress;
3. Coordinate all utilities hookups;
4. Coordinate with the geologist and/or soils engineer;
5. Coordinate with the grader;
6. Supervise day-to-day construction, making sure the Project is built as intended by
the Owners and the Designer as per plans;
7. Make sure neighbors' property is respected;
8. Ensure subs maintain the highest degree of craftsmanship;
9. Schedule subs and suppliers;
10 . Review workers' comp. of each sub--have a Certificate of Workers' Comp. sent
to Project Manager by their carrier;
11 . Coordinate incidental day labor;
12 . Keep track of change orders;
13 . Verify lumber and materials deliveries to make sure we get what we ordered;
14 . Authorize payment of subs based upon ongoing review of their work;
15 . Obtain lien releases;
16 . Provide on-site problem-solving with subs;
17 . Coordinate with interior designer's installation;
18 . Call for and handle inspections and interface with Building Department;
19 . Make sure the job site is cleaned on a regular basis (Owners to provide manpower or
funds for labor);
20 . Insist that all workers maintain the highest safety standards;
21 . Pass along to the Owners any discounts the Project Manager is entitled to as a
General Contractor without charging any markups.
Fee schedule
In consideration for the above services rendered by the Project Manager, the Owners
agree to pay the Project Manager a Base Fee of 10% of the cost of construction, based
on the amount of the construction loan, plus, as an incentive to bring the Project in under
budget, a Final Draw of 50% of any unused loan funds that exist when the Notice of
Completion is filed by the Owners and all construction budgeted for in the construction
loan is completed.
The Base Fee is to be computed based on the total hard construction costs approved
in the construction loan, including permit costs, appliances and fixtures. Any soft costs
included in the construction loan, such as design, engineering, interior design as well as
furniture and drapery costs, are not to be considered in determining the Base Fee.
The final draw is to be paid within 15 days of filing the Notice of Completion, based
on the following:
* As a mutually-beneficial incentive to finish the construction in a timely manner and to
meet the completion goal stated above, the Project Manager shall receive the full
50% final draw as stipulated above if construction of the living space is completed
to warrant a Certificate of Occupancy from the City by ______________________
enabling the Owners to move in by ______________________________.
Info!A1
s, whose address is
_____, hereinafter
ress is___________
____________________
he building department
ly priced subcontractor
e everything is
nt disbursment, safety,
king day in
________.
completed in strict
ances, rules, and
Further, he agrees to:
is built as intended by
what we ordered;
heir work;
Department;
s to provide manpower or
r is entitled to as a
costs approved
es. Any soft costs
r design as well as
he Base Fee.
_______, to
1st of each
mpletion, based
________, 10%
15 calendar day
r's control, the time
______________ by
asonably rainy
ays in city approvals
__________).
allowance, made by
pgrades not called out
maining construction
____________.
Project Startup Checklist
Date:
Owner:
Contractor:
Project no:
Project name:
Info!A1
Supervisor Foreman
Supervisor Foreman
Cost Plus Fixed Fee Contract
Date:
Owner:
Address:
City, St, Zip:
Project name:
1 The contractor accepts the relationship of trust and confidence established between his company
and the owner by this agreement. He covenants with the owner to furnish his best skill and
judgement in furthering the interest of the owner. He agrees to furnish efficient business admin-
istration and supervision and to use his best efforts to furnish at all times an adequate supply of
workers and materials, and to perform the work in a most expeditious, economical and workman-
like manner.
2 The work to be performed under this contract shall start on the date .
The contractor shall use his best efforts to complete said work of improvement on or before
.
3 The owner agrees to reimburse the contractor for the direct "cost of the work" as defined in
paragraph 6 below. Such reimbursement shall be in addition to the contractor's fee stipulated in
paragraph 4.
4 In consideration of the performance of the contract, the owner agrees to pay the contractor as
compensation for his services a contractor's fee as follows:
All costs incurred over total project length paid as per paragraph 11, plus a fixed fee of
per .
5 The scope of the work shall consist of the "categories of work" described on the estimate attached
hereto. The estimate is attached solely for the purpose of describing the category of work. The
pricing on the estimate shall have no bearing on the cost of the work.
6 The term "cost of work" shall mean costs necessarily and reasonably incurred in the performance
of the work and actually paid by the Contractor, including all costs incurred due to changes and
extras not listed on the attached estimate.
7 The contractor shall procure the necessary permits for the work of improvement. Owner shall
pay the governmental fees and contractor's charges for said permits.
8 All portions of the work that contractor's employees cannot perform directly shall be performed
under subcontracts. Unless owner has agreed in advance all subcontracts shall be on a fixed price
basis. The contractor shall secure the owner's consent before entering into any subcontracts.
9 The contractor shall keep full and detailed accounts as may be necessary for proper financial
management under this agreement. The owner shall be afforded access to all the contractor's
records, books, correspondence, instructions, drawings, receipts, vouchers, memoranda and
similar data relating to this contract, and the contractor shall preserve all such records for a period
of three years after the final payment.
10 The owner agrees to pay a twenty-five percent deposit upon obtaining permits or start of job,
whichever occurs first.
11 The contractor shall, every two weeks during the course of work, deliver to the owner a state-
ment showing in complete detail all costs incurred by his company in the execution of this
contract for the preceding two week period. Accompanying said statement shall be a copy of all
back-up documentation including material procurement invoices, payrolls for all the labor and all
receipted bills for which payment is due. The owner shall review the statement and shall remit
such amount within three days of the owner's receipt of the statement. The final payment,
constituting the unpaid balance of the cost of the work and the final contractor's fee, shall be paid
by the owner to the contractor when the work has been completed and the contract fully per-
formed.
12 The contractor agrees to maintain workers' compensation and liability insurance in effect
throughout the course of the work.
13 The contractor hereby agrees to hold the owner harmless and to indemnify the owner against any
and all claims which may arise during the course of the work as a consequence of the negligent
acts or deliberate omissions of the contractor, its agents or employees.
This agreement is executed the day and year first written above.
Owner: Contractor:
License no:
Date: Date:
TO GET BACK TO MAIN MENU:
Info!A1
_______, 19_____
t on or before
as defined in
r's fee stipulated in
he contractor as
he estimate attached
ory of work. The
in the performance
ue to changes and
nt. Owner shall
hall be performed
l be on a fixed price
y subcontracts.
roper financial
the contractor's
emoranda and
records for a period
or start of job,
e owner a state-
ution of this
all be a copy of all
all the labor and all
nt and shall remit
nal payment,
's fee, shall be paid
tract fully per-
ce in effect
Date:
Owner:
Contract no:
Change order no:
Time Impact:
Cost Impact:
We agree to furnish labor & materials complete in accordance Above additional work to be performed under the same conditions
with the above specifications at above stated price. as specified in original contract unless otherwise stipulated.
Info!A1
Date
nal contract.
Document Submittal
From:
To: Subject:
Attention:
I certify that the item submitted here below is correct and in strict conformance with the contract.
Any deviation from contract requirements? Yes No
(if yes, fill out the technical specifications proposed changes form (TSPC))
Drawing reference:
Specification reference:
BOQ reference:
Description of Document:
Info!A1
and stamp)
actor receipt response:
and stamp)
Daily Equipment Report
Date:
Prepared by:
Contractor:
Project name:
Weather:
I = Idle
W =Working
Info!A1
Total Total
hours cost
Project Directory
Date revised:
Project name:
Public agencies
City or agency Contact Phone number
Architect/engineer
PMT/Contractors/suppliers
Company name Contact Phone number
TO GET BACK TO MAIN MENU:
Info!A1
Fax number
Fax number
Customer #.
0
0
Phone / Fax :
Sold To
Billed To Employee Information
Name
Employee
Number
Branch/Dept
1
2
3
4
5
6
7
8
9
10
11
12
Totals
Info!A1
Employee Information
0.00% 19-Apr-2004
nature
Your Company Name
Your company address
City, State and Zip code
Your phone number
Your web site address and / or e-mail
Employee Report
Report Begin Date
Report End Date
Info!A1
Total Time $
Total Hours
Billed
196.00 $8,472.80
88.00 $4,806.30
7.00 $0.00
7.00 $0.00
8.00 $319.60
8.00 $799.60
7.00 $419.65
8.00 $319.60
8.00 $319.60
7.00 $69.65
12.00 $1,199.40
12.00 $1,199.40
4.00 $159.80
108.00 $3,666.50
4.00 $0.00
4.00 $0.00
7.00 $0.00
23.00 $0.00
1.00 $79.95
8.00 $319.60
8.00 $319.60
7.00 $69.65
8.00 $239.60
8.00 $639.60
7.00 $559.65
8.00 $239.60
8.00 $639.60
7.00 $559.65
0.00 $0.00
Request for Clarification
From:
To: Subject:
Attention:
Discipline: Date:
This document is intended to address specific contractor's technical questions and queries related to the contract
documents and/or field conditions. This document together with the consultant's reply does not constitute changes
or variation to the contract nor can be considered as a change or variation order document to the contract.
Drawing reference:
Specification reference:
BOQ reference:
Clarification needed
Received by:
(signature and stamp)
Dare:
Date:
TO GET BACK TO MAIN MENU:
Info!A1
To: Subject:
Attention:
Discipline: Date:
This document is intended to address specific project owner need for information on a specified subject
This is not a bid request and there will be no commitment out of this information request.
Drawings reference:
Specification reference:
BOQ reference:
DATE:
TO GET BACK TO MAIN MENU:
Info!A1
on on a specified subject
Request for Inspection
From:
To: Subject:
Attention:
Date:
We request inspection and approval of the following site works and we confirm that work refere
been executed according to contract specifications and approved drawings.
Info!A1
and stamp)
actor receipt response:
and stamp)
SHOP DRAWINGSS SUBMITTAL AND APPROVAL C
To: Subject:
Attention:
Discipline: Date:
I certify that the item submitted here below is correct and in strict conformance with the contrac
Any deviation from contract requirements? Yes(if yes, fill out the technical specifications p
changes form (TSPC))
Shop Drawing
Contract Drawing Reference Description of Shop Drawing
No.
Info!A1
and stamp)
actor receipt response:
and stamp)
PROCUREMENT ACTION PLAN
1 2 3
Sec SECTION 5 CONCRETE
1 Concrete 22MPA
Concrete 35MPA
Concrete 50MPA
Concrete 55MPA
Concrete 75MPA
2 Water Stop
3 Curing Material
4 Joint Filler Strips
5 Epoxy Joint Filler
6 Bonding agent
7 Reinforcement Steel
8 welded wire fabric ASTM A497
9 Chairs & spacers
10 joint dowel Bars
11 Light Weight concrete
31 Vehicle detectors
Access Control Units & intercom to
32
Security room
Sec SECTION 8 SEWERAGE
33 Definition
MECHANICAL &
Sec SECTION 9 ELECTRICAL
WORKS
34 Garbage Chutes
EARTH WORK
Sec SECTION 12 RELATED TO
BUILDINGS
35 Earthwork
36 Termite Control
37c4 Sealant
39 Roofing
39a Light Weight concrete
39c Waterproofing
39p Fasteners
40 Composite Domes
THERMAL
Sec SECTION 15 INSULATION TO
BUILDINGS
41 Acoustic Insulation
42 Thermal Insulation
42a Mineral Fiber Insulation
42c Adhesive
42d Accessories
STRUCTURAL
Sec SECTION 16
STEEL WORKS
43 Structure Steel
Structural steel shapes Plates & Bars ASTM
43.1
A572 Grade 50
Corrosion resistanct Structural Steel ASTM
43.2
A588
Cold- Formed Steel Tubing: ASTM A 500
43.3
Grade B
43.4 Hot- Formed Steel Tubing: ASTM A 501
66.1 Furniture
67 Toilets Compartments
FINISHING TO
Sec SECTION 24
BUILDINGS
68 Skim Coat Plaster
68b Accessories
69a Lath
70 Polished Plaster
71 External Rendering
71a Glass Fiber Mesh
71b Accessories
72 Cement Board
73 gypsum Partition & Lining
74 Interior Stone Work
74a Grout
74b Stone Accessories
75 Stone Flooring
76 Agglomarate Tiles
77 ceramic Tiles
78 Cork tiles
80 Rubber Flooring
81 Vinyl Flooring
82 Wood Flooring
83 Terra Cotta Tiles
84 Traffic Coating
85 Epoxy Flooring
86 Gypsum Board Suspended Ceiling
88b Grout
89 Metal Ceiling
90 Wood Ceilings
91 Acoustical Panel Ceiling
92 Fabric Wall Covering
93 Joint Sealant
94 Access Panels
95 Exterior Stone Works
96 Fiber Glass Reinforced Plastic
97 Cement Board Ceiling
98 Brick Masonry
98a Anchors & accessories
98b Expansion Joint
98c Sealant
99 Metal Fabric
100 Chemical Stain
GLASS & GLAZING
Sec SECTION 25
101 Glazing
102 Aluminum Glazed Curtain Wall
103 Glass Blocks Skylight
104 Frameless Glass Doors
105 Mirrors
106 Metal Framed Sky Light
PAINTING &
Sec SECTION 26
DECORATION
107 Painting
108 Vinyl Wall Coverings
109 Intumescent Paint
EXTERNAL
Sec SECTION 27
WORKS
110 Colored Texture Concrete
Info!A1
QTY Specified or
ESTIMATE Alternative
Local Imported ORDER Deliver Date Used Submittal
4 5 6 7 8 9 10 11
ACTION ( DATE ) DELIVERED TO SITE
12 13 14 15 16 17 18
Remarks
19
Meeting Ground Rules Checklist
Here are some items you may want to consider when proposing ground rules for your meetings. Remember, this list
is not supposed to be all encompassing, but merely a guide or aide-memoir.
Attendance/Absence
How to deal with absence – Send a substitute? Send apologies? Send bagels?
Promptness
Acceptable reasons for tardiness, and consequences – e.g. "do not repeat for latecomers"
Meeting locations/set-up
Using a dedicated room for project work – is it permitted? Reservation rules/procedures?
Participation
Full engagement/participation from everyone – what does this mean in your group?
When & how to check engagement (and when/how to call breaks, and who has authority)
Treat each other with respect – No zingers, no personal slurs, no shouting down speaker, etc.
Do not say one thing in the meeting and something different outside
Open and honest dialogue – avoid hidden agendas and obfuscating information
Process checks – how and when to call one, who is permitted to call one
Task assignments
Who, how, when to assign tasks, and expectations for completing and reporting status
Interruptions
n No texting, emailing, or web surfing during a meeting – deal with other issues on breaks
Routine chores
Who does what and when – room and/or equipment reservation/prep, facilitation, etc.
No agenda = no meeting
TO GET BACK TO MAIN MENU:
Info!A1
- DESIGN TEAM Organization Chart
PROJEC
Project D
ADMINISTRATION
ADMINISTRATION
Architect Architect
Project Planner
Executive
Executive Architect
Secretary
CA
TO GET BACK TO MAIN MENU:
Info!A1
[PROJECT NAME]
PROJECT DIRECTOR
ARCHITECTURE INFRASTRUCTURE
INFRASTRUCTURE
Senior
Senior Electrical
Electrical Senior
Senior Mechanical
Mechanical
Engineer Engineer
INFRASTRUCTURE SUBCON
INFRASTRUCTURE SUBCON
INFRASTRUCTURE
INFRASTRUCTURE
HEADS OF DEPARTMENTS
Head of Head of
Mechanical Structural
Engineering Engineering
Department Department
Senior
Senior Mechanical
Mechanical Senior
Senior Civil
Civil
Engineer Engineer
FRASTRUCTURE SUBCONSULTANTS
FRASTRUCTURE SUBCONSULTANTS
- CONSTRUCTION PROJECT MANAGEMENT TEAM Org
[PROJ
PROJEC
Proje
ADMINISTRATION
HHRR/DOCUMENT CTRL.
Info!A1
[PROJECT NAME]
PROJECT DIRECTOR
Project Manager
HEADS OF DEPARTMEN
CONSTRUCTION
MANAGER
Sr. Architect Quantity Surveyor QA/QC Engineer
Engineering Mechanical
Department Engineering
Electrical Mechanical Department
Superintendent Superintendent
SUPERVISORY AND CAD SUPPORT
Senior
Senior Electrical
Electrical Senior
Senior
Engineer
Engineer Mechanical
Mechanical
Engineer
INFRASTRUCTURE SUBCO
TAIL ENGINEERING
HEADS OF DEPARTMENTS
Senior
Senior Senior
Senior Civil
Civil
Mechanical
Mechanical Engineer
Engineer
FRASTRUCTURE SUBCONSULTANTS
TYPICAL CAUSE & EFFECT MATRIX (2)
Results
in
Acceleration
Scope Changes
Results in
R
e
w
Results or
in k
Defective Work
ATRIX (2) TO GET BACK TO MAIN MENU:
Info!A1
PRODUCTIVITY LOSS
Allocation of Re
for Total Cost O
Results
in
PRODUCTIVITY LOSS
Results
In
in c
II r
Direct Manhour Growth
n e
Indirect Manhour Growth
c a
Increased Equipment and Materials quantities
r s
e e
a d
s h
e o
d m
Ultimate Effects fi e
e o
l ff
d ic
i e
n o
d v
ir e
e r
c h
t e
c a
OWNER o d
CONTRACTOR s c
t o
Allocation of Responsibility st
for Total Cost Overrun s
RETURN
Info!A1
POLITICAL PROGRAMME
Contingency Planning
Government Support Risk Assessment
War / Insurrection Logistic Schedule
Sabotage / Terrorism Quality Assurance
Civil Disorder Key Performance Indicators
Government Contract Breach Non-Optimal Capacity
Government Change Project Phasing
Revolution Progress Measure
Racial Conflict Flexibility
Electoral Reform Integration
Pressure Groups Facilities
Permissions Experts
Legislation Testing
Nan-Saudi Political Issues Surveys
Operability
ENVIRONMENTAL MARKET
Project Implementation / Operation Information Leak
Waste Disposal Transactional Misconduct
Discharge Negative Market Publicity
Chemical Pollution Partner Preference
Radiological Pollution Illegal Acts
Noise Pollution . Equipment Product Failure
Equipment Certification Quality Standard
Preservation Policies Business Recovery Procedure
Pressure Groups Crisis Communication
Emissions Marketing
Language
EXTERNAL ADVISOR LEGAL / REGULATORY
Intellectual {Property Loss Health & Safety Policies
Inexperienced Advisors Environmental Impact Assessment
Advisor Availability Emissions Control
Advisor Conflict Royal Commission Compliance
Unauthorized Communication Foreign Investment Regulation
Language Intellectual Property Infringement
Recommendation Acceptance Site Acquisition
External Affiliation
PROJECT RISK INVENTORY
CONTRACT COMMERCIAL
Confidential Information Supply Security
Evaluation Criteria Project Magnitude
Marketing Decisions Implementation Schedule
Material Pricing Supply disruption
Technology Availability Supplier Contingency Planning
Engineering Complexity Projected Reserves
Partnership Agreement Monopolization / Domination
Project Completion Timing Competition
Payment Cycle Project Feasibility
Project Costing Raw Material Supply
Partnership Sourcing Logistic Access
Contract Award Schedule Commodity Pricing
Reserve Categorization Site Selection
Debt Payment Funding Availability
Contractor Solvency Cost Overrun
Contractor Delay Theft
Permit / Licensing Fraud
Multiple Contracts Insurance
Payment Terms
Economic Stability
ECONOMIC SOCIAL
Non-Governmental Organizations Cultural Conflict
Seasonal Variation Skill emigration
Capital Costs Higher Education
Product Price Variation Unskilled Emigration
Currency Fluctuation Ageing Population
Tax Insurgency
Royalties Population Policies
Interest Rate Fluctuation Religious Growth
Credit Enhancement Religious Shift
Global Recession
Pension Requirements
Growth Rates
Monetary Policies
COMMUNICATION
Knowledge Sharing
Policies & Procedures
Documented Instructions
Reporting Structure
Regulatory Reporting
Inaccurate Content
Misinterpretation
Language
Categorization
Probability / Consequence
VENTORY
PHYSICAL RESOURCES
Resource Availability Succession Planning
Climate Change Staff training
country Training non-locals
Time Zone Global skills Demand
Weather Training Programme Timing
Altitude Staff Retention
Humidity Resource Security
Earthquake Local Labor Supply
Wind Resource Capabilities
Precipitation Staff Attraction
Force Majeure Language
Ecology Industrial Relations
Erosion Terms & Conditions
Subsidence Relocation
Biological Hazard Literacy
MANAGEMENT
TECHNOLOGICAL
INFORMATION
Point of Failure Decision-making
Plant Integration Document Management
Plant Processing Lines Project Management Planning
Operational Costs Project Implementation Planning
Infrastructure Change Management
Lifestyle Shift Delegation
Maintenance Risk Appetite
Technology Creep Increased Project Momentum
Performance Efficiency Fixed Assets
Shared Services/Infrastructure Management Competence
Design Capacity Quality of Information
Inappropriate Technology Quantity of Information
Operational Lifetime
TECHNICAL
Design Specification
Internal Control
Technical Knowledge
Research & Development cost
Licensing
Interfaces
Modifications
Inspection / Testing
Authorization
Working Conditions
Facilities
Utilities
Security
Access
Damage / Loss
Supervision
Change Control
Reliability
INFORMATION
TECHNOLOGY
System Failure
Inappropriate systems
Hardware / Software Contingencies
Human Error
Technological Lifetime
Technological Interaction
Documented Procedures
Inspection / Testing
Maintenance
Research & Development
Future Systems Requirements
UNIT TITLE: The productive function defined at that level in the functional map. A
general description of the set of elements.
PERFORMANCE
EVIDENCE REQUIRED FOR ASSESSMENT
CRITERIA
A result and an
assessment statement that
proves the worker’s
performance, and,
therefore, his competency. EVIDENCE OF PERFORMANCE
DIRECT PERFORMANCE
FIELDS OF
EVIDENCE OF KNOWLEDGE AND COMPREHENSION
APPLICATION
It includes the different It specifies the knowledge that allows workers to achieve a
circumstances –at the competent performance. It includes knowledge concerning
workplace, materials and the principles, methods or theories applied to fulfil the action
organisational described in the element.
environment– under which
the competency is
developed.
ASSESSMENT GUIDE
It establishes the assessment methods and the use of evidence to assess competency.
The ability to obtain quality results with the efficient and safe performance of an act
The ability to solve problems that may appear while exercising the productive functi
The ability to transfer knowledge, abilities and skills already possessed to other labo
hat level in the functional map. A
of elements.
TO GET BACK TO MAIN MENU:
OF PERFORMANCE
PRODUCT EVIDENCE
y describe:
GAP
INITIAL PROCESS REVIEW
SITUATION ANALYSIS
STUDY & USING CMM,
PEOPLE (Interviews) OPM3,
PREPARATION
PMBOK...
RESOURCES & TOOLS
EVALUATION
Improvement Plan
Areas & Improvement ac
Identified & Prioritized
Detailed actions & decisi
2. Process Improvement
Process
Current Definition Resource
Process Improvements enhancements
Analysis (PCMM, (tools,...)
PMBOK)
Competency
Competency Definition
Analysis Improvements
(People CMM) (PMCD
framework
Systematic
Change
Management
Improvement &
business
expectations
Re-evaluation
of desired
situation
Improvement Plan
Areas & Improvement actions
Identified & Prioritized
Detailed actions & decisions
Improved
Process and
Resources
Pilot
Improvements
M methodology Implementations
(Rollout, Training,
Competency
Development)
Competency
development
plans
definition &
updates
Executive
Management FINAL REVIEW
Involvement
TO GET BACK TO MAIN MENU:
Info!A1
UNITS OF COMPETENCE
PETENCE TO GET BACK TO MAIN MENU:
Info!A1
AIN MENU:
TO GET BACK TO MAIN MENU:
Info!A1
TO GET BACK TO MAIN MENU:
Info!A1
TO GET BACK TO MAIN MENU:
Info!A1
TO GET BACK TO MAIN MENU:
Info!A1
TO GET BACK TO MAIN MENU:
Info!A1
TO GET BACK TO MAIN MENU:
Info!A1
TO GET BACK TO MAIN MENU:
Info!A1
PROJECT EXECUTION BASIS FOR
PLANNING STRATEGY PROJECT
CONTROL
ID PROJECT CONTROL
PROCUREMENT REQUIREMENTS,
PLANNING CAPABILITIES &
PRIORITIES
CHANGE
INFORMATION
DEVELOP &
MANTAING
PROCUREMENT
PLANNING TOOLS
HISTORICAL CHART OF
INFORMATION ACCOUNTS
TO GET BACK TO MAIN MENU:
Info!A1
BASIS FOR
EXECUTION PROJECT
STRATEGY CONTROL
PROJECT
CHANGE
NFORMATION OBJECTIVES AND
ESTIMATE & REQUIREMENTS
INFORMATION
SCHEDULE
FOR ANALYSIS
INFORMATION
S FOR
JECT
TROL
ESTABLISH CONTRACT
REMENT REQUIREMENTS
EMENTS FOR PROJECT
CONTROL
PROJECT ORGANIZATION
EXECUTION
IMPLEMENTATION BREAKDOWN
STRATEGY
BASIS STRUCTURE
ID RESOURCE
ID KEY or DRIVING STUDY RESOURCE
LIMITS AND
OURCES & PRIORITIES AVAILABILITY
CONSTRAINTS
PROJECT
IMPLEMENTATION
BASIS
CHANGE
INFORMATION
BASIS FOR
RESOURCE RESOURCE PROJECT
REALLOCATE EXPENDITURE
QUANTITIES CONTROL
RESOURCES INFORMATION
& LIMITS PLANS
ID RESOURCE
OPTIMIZE REVIEW & DOCUMENT
LIMITS AND
RESOURCES RESOURCES PLAN
CONSTRAINTS
SOCIETAL
PROJECT VALUES & INFORMATION HISTORICAL
LEMENTATION PEOPLE FOR ANALYSIS INFORMATION
BASIS PERFORMANCE
ISSUES
S FOR
JECT BASIS FOR
TROL PROCUREMENT
ANS PLANNING
PROJECT
RICAL
ATION IMPLEMENTATION
BASIS
ASSET
CONTRACTUAL
ALTERNATIVE
DELIVERIES
SCOPE
INFORMATION
PROJECT FOR ANALYSIS
PLANNING
BASIS
WBS, WORK
PACKAGES &
EXECUTION
STRATEGY
CHART OF
ACCOUNTS
SCHEDULE
DURATIONS
COST SCOPE
RESOURCE
QUANTITIES
CONTINGENCY
FROM RISK
ANALYSIS
TO GET BACK TO MAIN MENU:
Info!A1
REQUIREMENTS CHART O
INFORMATION WBS ACCOUNT
AND
FOR ANALYSIS
OBJECTIVES
SIMULATE AND
ANALYZE
COST SCOPE OPTIMIZE THE
CASHFLOW
COSTS
HISTORICAL CHART OF
INFORMATION ACCOUNTS
SCHEDULE
CHART OF REVIEW
ACCOUNTS
HISTORICAL
COST INFO
REVIEW &
BUDGET COSTS DOCUMENT THE
BUDGET
BASELINE
ANALYZE DEVELOPMENT or
CASHFLOW BID
SCHEDULE
PROJECT
CONTROL
PROJECT PLAN & WORK
IMPLEMENTATION CONTROL CHANGES
PROGRESS
BASIS ACCOUNTS
PROGRESS
MEASUREMENT
PLANS
PROJECT
CHANGES TO CONTROL
CHANGES PROJECT PLAN & CORRECTION
ACCOUNTS CONTROL TO CHANGES
ACCOUNTS
COST
WORK INFORMATION FOR
PROGRESS FINANCING
COST
INFORMATION
CORRECTION
FOR CONTROL
TO CHANGES
COST
NFORMATION FOR WORK
FINANCING PROGRESS
CLOSE PROJECT
ACCOUNTS
RISK ASSESSMEN
ASSESS CHANGES
DEVELOP AND MAINTAIN AND TRENDS
METHODS AND TOOLS
RISK
PERFORMANCE
ASSESSMENT
TO GET BACK TO MAIN MENU:
Info!A1
ASSESS CHANGES
AND TRENDS ALTERNATIVES FOR
FURTHER ANALYSIS
CHANGE MANAGE
INFORMATION CONTINGENCY
PLANNING
BASIS
INFORMATION
RISK MITIGATION
RISK PROJECT
DEVELOP RISK IMPLEMENTATION
ACCEPTANCE MANAGEMENT PLAN
CRITERIA BASIS
RISK
HISTORICAL
MANAGEMENT
INFORMATION
PLAN
PROJECT
IMPLEMENTATION
BASIS
WORK, RESOURCE & PROCESS
PERFORMANCE
PROJECT
CONTROL
PLAN &
CONTROL
ACCOUNTS
PROJECT PROJECT
IMPLEMENTATION COST CHANGES
BASIS ACCOUNTING
PLANS
DEVELOP &
MANTAING
MEASUREMENT
TOOLS
HISTORICAL
PROJECT
INFORMATION
TO GET BACK TO MAIN MENU:
Info!A1
MEASURE PHYSICAL
PROGRESS PROJECT
ANGES CONTROL
PLAN &
CONTROL
ACCOUNTS
TRACK RESOURCES
TIATE
GRESS & REVIEW, CLASSIFY
ORMANCE AND ACCOUNT
UREMENT MEASURE
PERFORMANCE
STATUS SCHEDULE
STATUS FOR
CHANGES
HISTORICAL
PROJECT
INFORMATION
INFORMATION FOR
ENTERPRISE RESOURCE
PLANNING
PROJECT WBS, OBS,
IMPLEMENTATION WORK EXECUTION PLANNING
BASIS PACKAGES STRATEGY INFORMATION
DEVELOP &
MANTAING
IMPLEMENTATION CHANGES
TOOLS
HISTORICAL
INFORMATION CHANGES
TO GET BACK TO MAIN MENU:
Info!A1
PLANNING
INFORMATION
PROJECT VALIDATION
IMPLEMENTATION METRICS
BASIS
COMMUNICATE PLAN
& INITIATE PROJECT
CONTROL SYSTEMS
BASIS FOR
CONTROL
VALIDATION
METRICS
VALIDATE
OL PLAN
CATE PLAN
E PROJECT
SYSTEMS
S FOR
TROL
TO GET BACK TO MAIN ME
ASSET or
PROJECT
ASSET or PROJECT
TECHNICAL
SCOPE
INFO
STRATEGIC
ASSETS PLAN & INITIATE VA / VE STUDY SCOPE & DEFINE
REQUIREMENT STUDY DELIVERABLES
S
CUSTOMER HISTORICAL
REQUIREMENTS INFORMATION
TO GET BACK TO MAIN MENU:
Info!A1
COST
INFORMATION
PLANNING
INFORMATION
ALTERNATIVES FOR
FURTHER CREATIVITY
CANDIDATE
ALTERNATIVES
SCOPE PHYSICAL
DEFINITION PROGRESS
DEVELOP &
HISTORICAL
MANTAING PROJECT
FORECASTING INFORMATION
TOOLS
TO GET BACK TO MAIN MENU:
Info!A1
CORRECTIVE
TRENDS ACTION PERFORMANCE
ASSESSMENT ALTERNATIVE
ALTERNATIVES FORECAST
PLANNING CONTROL
INFORMATION BASIS
SELECTED
CORRECTIVE APPROVED
ALTERNATIVE
ACTION SCOPE
FORECAST
ESTABLISH &
E PLANS REPORT FORECAST
CURRENT FORECAST
MANAGEMENT
SCOPE
GOALS, REQUEST FOR
CLAIMS SPECIFIC
OBJECTIVES & ASSESSMENT
INFORMATION
POLICY
REQUIREMENTS
HISTORICAL
INFORMATION
ACK TO MAIN MENU:
ANALYZE CAUSATION,
RESPONSIBILITY AND
PERFORMANCE
SCOPE ANALYZE
BACKGROUND
SPECIFIC
INFORMATION
INFORMATION SCHEDULE
GATHER ANALYZE
INFORMATION COST
ANALYZE
PRODUCTIVITY
ANALYZE
ROOT CAUSES
LESSONS
REPORT LEARNED
REPORT
FINDINGS
INFO FOR
INFO FOR CHANGE
PROCUREMENT
MANAGEMENT