High Energy Drain Valves Body Temperature Mapping

UNIT-9, 3x660MW, KTPS


Sr.No Particulars of Drains Rechecking done on
30/12/19 @10.30 02/01/2020 @16.20 13/01/2020
Date & Time to 11.30 Hrs to17.10 Hrs @14.20 to16.10 Hrs
Load (MW) 365 503 656
Turbine Side
1 3.5 Mtrs MS (LHS) Main Isolating Drain v/v 43 27
2 3.5 Mtrs MS (LHS) ManualDrain v/v to AFT 27 39
3 3.5 Mtrs MS (LHS) Motorised Drain v/v to TFT 77 14 25
4 3.5 Mtrs MS (RHS) Main Isolating Drain v/v 63 46
5 3.5 Mtrs MS (RHS) ManualDrain v/v to AFT 34 48
6 3.5 Mtrs MS (RHS) Motorised Drain v/v to TFT 86 47 45
7 3.5 Mtrs Water Separator Drain Valve 70 45 39
8 3.5 Mtrs BFPT-A AUX/CRH STM inlet to TDBFB DRPL SOV 71 87 40
9 3.5 Mtrs STM supply to TDBFP-A DS MOV 68 52 43
10 3.5 Mtrs BFPT-B AUX/CRH STM inlet to TDBFB DRPL SOV 51 60
11 3.5 Mtrs STM supply to TDBFP-B DS MOV 24 30
12 9 Mtrs HPT Inner Casing Drain MOV 40 33
13 9 Mtrs HPT Outer Casing Drain MOV 62 47 30
14 9 Mtrs HPH-6 IP Extraction US of NRV DripLeg SOV 26 36
15 9 Mtrs HPH-8 HP Turb Extn NRV US DRN SOV 33 90
16 9 Mtrs HPH-6 IP Extraction DS of NRV DripLeg SOV 39 39
17 9 Mtrs HPH-8 HP Turb Extn NRV DS DRN SOV 55 134
18 9 Mtrs LPH-3 Extraction -3 NRV US DripLeg SOV 116 33 36
19 9 Mtrs LPH-4 Extraction -4 NRV US DripLeg SOV 133 42 50
20 9 Mtrs IP Extraction to Deareator NRV US DripLeg SOV 34 122
21 9 Mtrs LPH-3 Extraction -3 NRV DS DripLeg SOV 53 124
22 9 Mtrs LPH-4 Extraction -4 NRV DS DripLeg SOV 24 21
23 9 Mtrs IP Extraction to Deareator NRV DS DripLeg SOV 27 35
24 9 Mtrs CRH (LHS) Main Isolating Drain v/v 33 98
25 9 Mtrs CRH (LHS) ManualDrain v/v to AFT 26 51
26 9 Mtrs CRH (LHS) Motorised Drain v/v to TFT 27 42
27 9 Mtrs CRH (RHS) Main Isolating Drain v/v 37 71
28 9 Mtrs CRH (RHS) ManualDrain v/v to AFT 32 33
29 9 Mtrs CRH (RHS) Motorised Drain v/v to TFT 27 42
30 9 Mtrs HRH (LHS) Main Isolating Drain v/v 25 27
31 9 Mtrs HRH (LHS) ManualDrain v/v to AFT 31 27
32 9 Mtrs HRH (LHS) Motorised Drain v/v to TFT 38 28
33 9 Mtrs HRH (RHS) Main Isolating Drain v/v 86 29 32
34 9 Mtrs HRH (RHS) ManualDrain v/v to AFT 35 32
35 9 Mtrs HRH (RHS) Motorised Drain v/v to TFT 41 52
36 9 Mtrs MS Lead Pipe Drain Valve 47 44
37 9 Mtrs LPBP Valve Drain (L) to TFT 17 24
37A LPBP Valve Drain (L) to TFT - Bypass 18 24
38 9 Mtrs LPBP Valve Drain (R) to TFT 26 42
38A LPBP Valve Drain (R) to TFT- Bypass 52 80
39 9 Mtrs Gland Steam Header ( Near GSC ) 72 109 83
40 24 Mtrs HPH-7 CRH Extn NRV US DRN SOV to TFT 68 82 154
41 24 Mtrs HPH-7 CRH Extn NRV DS DRN SOV to TFT 70 66 45
42 24 Mtrs Drain From Aux Steam Header 59 44
42A Drain From Aux Steam Header - Bypass 45 61
43 MS Line Warm-Up DRN to TFT 58 90
44 CRH Line DRPL DRN to TFT 21 29
P.T.O
High Energy Drain Valves Body Temperature Mapping
UNIT-9, 3x660MW, KTPS
Sr. No Particulars of Drains
30/12/19 02/01/2020 13/01/2020
Date & Time @10.30 to @16.20 to17.10 @14.20 to16.10
11.30 Hrs Hrs Hrs
Load (MW) 365 503 656
Boiler Side
43 34 Mtrs Economizer Drains (Inlet) 68 38 85
44 44 Mtrs Furnace wall intermideate header drain iso. v/v (Left) 18 29
45 44 Mtrs Furnace wall intermideate header drain iso. v/v (Front) 19 28
46 44 Mtrs Furnace wall intermideate header drain iso. v/v (Right) 19 26
47 44 Mtrs Furnace wall intermideate header drain iso. v/v (Rear) 20 28
48 48 Mtrs Primary SH Inlet Drain (L) 21 48
49 48 Mtrs Primary SH Inlet Drain (R) 54 91
50 70 Mtrs RH Spray Drain (L) 30 80
51 RH Spray Drain (L)- Bypass 42 86
52 70 Mtrs RH Spray Drain (R) 28 60
53 RH Spray Drain (R) - Bypass 35 80
54 70 Mtrs Tertiary S/H outlet Header Drain (Left) 80 42 93
55 70 Mtrs Tertiary S/H outlet Header Drain (Right) 72 48 132
56 8 Mtrs Furnace Inlet Header Drain iso. (Left) 2nd valve 20 27
57 8 Mtrs Furnace Inlet Manifold Drain iso. (Rear) 2nd valve 20 25
58 8 Mtrs Furnace Inlet Header Drain iso. (Rear) 2nd valve 20 25
59 8 Mtrs Furnace Inlet Header Drain iso. (Front) 2nd valve 22 24
60 8 Mtrs Furnace Inlet Manifold Drain iso. (Front) 2nd valve 22 27
61 8 Mtrs Furnace Inlet Header Drain iso. (Right) 2nd valve 20 26
62 13 Mtrs BCP Discharge Line Outlet Drain Valve 20 27
63 13 Mtrs SAH Heating Steam CV Outlet Drain (Right) 43 53
64 13 Mtrs SAH Heating Steam CV Outlet Drain (Left) 49 42
65 34 Mtrs Pulveriser Inert System Drain 37 76
66 34 Mtrs Soot Blower Rear Wall Left Side Drain (HRSB) 32 57
67 34 Mtrs Soot Blower Side Wall Left Side Drain (HRSB) 22 42
68 34 Mtrs Soot Blower Rear Wall Right Side Drain (HRSB) 22 41
69 34 Mtrs Soot Blower Side Wall Right Side Drain (HRSB) 21 130
70 29 Mtrs Soot Blower Side Wall Left Side Drain (LRSB) 17 47
71 29 Mtrs Soot Blower Side Wall Left Side Drain (LRSB) 18 59
72 29 Mtrs Soot Blower Side Wall Left Side Drain (LRSB) 18 55
73 29 Mtrs Soot Blower Side Wall Left Side Drain (LRSB) 18 59
74 63 Mtrs Primary SH Blow Back Drain (Left) 19 28
75 63 Mtrs Primary SH Blow Back Drain (Right) 78 40 81
76 63 Mtrs Secondary SH Blow Back Drain (Left) 19 28
77 63 Mtrs Secondary SH Blow Back Drain (Right) 19 26
80 9 Mtrs AH Soot Blower Drain 51 94
81 72 Mtrs Secondary Inlet Manifold Inlet Drain 24 35
82 72 Mtrs Secondary Inlet Manifold Inlet Drain 24 36
83 29 Mtrs Soot Blower (Front Wall Warming ON-OFF Valve) 19 64
Boiler side Turbine side
(Suspected Bypass (Suspected Bypass
O
Temperature Ranges ( C) Valves) Valves)
>60-90 7 4
90-120 3 1
>120 2 4
Total 12 9

Note : 1. Valve body temp having more than 60oC are suspected passing/ partially open (highlighted values).
2. BM/TM/PCR sections are hereby requested to take necessary action to attend the defects and intimate the action taken.

Executive Engineer
POG,3x660MW
Copy 1. Dy.CE (Stg-III),
s.w.r.to: 2. SE ( Ops. / M )
Copy to: S/I - PCR (U# 9)
Copy to: Intranet website