Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
CAIRN-TSG-L-SP-0015
REVISION RECORD
Revision Philosophy
All revisions for review will be issued at A1, with subsequent A2, A3, etc as required.
All revisions approved for issue or implementation will be issued at B1, with subsequent B2, B3, etc as required.
All revisions approved for issue or design and construction will be issued at C1, with subsequent C2, C3, etc as
required.
Narrative sections revised from previous pprove issues are to be noted in the table below and/or highlighted using
the appropriate revision status thus: | A2
Previous revision highlighting to be removed at subsequent issues.
Drawings/diagrams revised from previous approved issues are highlighted by 'clouding' the affected areas and by
the use of a triangle containing the revision status.
Revision History
TABLE OF CONTENTS
1.0 SCOPE 4
3.0 FABRICATION 4
4.0 WELDING 5
6.0 INSTALLATION 8
9.0 INSULATION 9
1.0 SCOPE
This specification covers the requirements governing the fabrication, installation, inspection & testing of
piping assemblies in shop or field. This specification is to be used with the individual specification and/or
drawings, if furnished. In case of conflict, the individual specification and /or drawings shall govern.
3.0 FABRICATION
3.1 Carbon steel pipes shall be cut by mechanical or thermal cutting depending upon thickness and size however
thermal cutting shall not be employed for galvanized and stainless steel materials.
3.2 Bevel end preparation shall be done by bevel cutting machines and suitably grinded.
3.3 For pipes up to 2 Inch NB, the internal burrs shall be removed by suitable grinding.
3.4 Dimensional tolerances: In addition to the tolerances contained within specified codes and standards,
dimensional tolerances for finished fabricated piping shall conform to those shown in Figure-1 attached
herewith.
3.5 Care shall be taken during cutting & welding such that the final dimensions of spools are within the applicable
tolerances.
3.6 Threaded, Socket Weld & Brazed Piping
3.6.1 Threads shall be clean cut with no burrs or stripping and shall be according to ASME B1.20.1,
tapered. Dies shall be new, sharp and properly designed for the piping material. Ends shall be
reamed to remove burrs.
3.6.2 Immediately before erecting the piping all threads of pipe and fittings shall be thoroughly cleaned of
cuttings, dirt, oil or other foreign matter. The male threads shall be coated with thread sealant
and the piping made up sufficiently for the threads to seize. Sealant shall be Teflon tape.
3.6.3 Threaded connections shall be gauge checked or chased after welding or heat treatment.
3.6.4 When socket weld/brazed fittings or valves are used, pipe shall be spaced approximately 1/16-inch
to avoid “bottoming” which could result in excessive weld stresses.
3.6.5 The inside of the brazed fitting and outside of the tube shall be cleaned with sand paper. Flux paste
to be evenly applied to the joint.
3.6.6 Brazing temperature shall be achieved as quickly as possible using a suitably sized torch.
3.6.7 Seal welding of threaded connections when specified shall include the first block valve, cover all
threads and be done with electrodes not to exceed 1/8 inch in diameter. The joint shall be cleaned
of all cutting oil & other foreign material and made up of dry to full thread engagement. Thermo wells
shall not be seal welded.
3.7 Branch connections
3.7.1 All branch connections shall be joined to the header with full penetration welds.
3.7.2 Reinforcing pads shall be added only after external and internal visual inspection of the attachment.
Reinforcing pads shall be provided with ¼” tapped weep hole. Weep holes shall be plugged after
completion of welding.
3.8 Exposed machined and threaded surfaces shall be protected from oxidation during heat treatment.
3.9 Flange bolt holes shall straddle the established horizontal and vertical centerlines of the pipe except where
connection to equipment dictates otherwise.
3.10 Cleaning of the piping after fabrication and heat treatment shall be performed externally and internally to
remove all loose scale, weld spatter, sand and other foreign materials.
3.11 All piping supports shall be fabricated and installed as per approved drawings/standards.
4.0 WELDING
4.1 Welders and welding procedure shall be qualified per ASME B 31.3, latest edition.
4.2 For 90-10 Cu-Ni piping, welders and welding procedures shall be qualified as per ASME Code Section IX.
4.3 Welding shall be performed as per approved WPS and PQR.
4.4 No chill rings or backup rings are to be used.
4.5 The joints to be field welded shall be beveled as per ASME B 16.25
4.6 The deposited filler metal shall match the chemistry and minimum physical properties when similar metals
are welded.
4.7 Stress relieving shall be as per ASME B 31.3.
5.7 Acceptance criteria based on visual, radiography and other types of examination shall be as per ASME
B 31.3 with the following modifications.
5.7.1 The internal weld protrusion on ‘pigged lines’ shall not exceed 1.6 mm (1/16 inch).
5.7.2 Orifice flange butt welds shall be internally ground smooth and flush.
5.7.3 For 90-10 Cu-Ni piping, radiographic examination of welds shall be as per ASME Section VIII, UW
51.
5.8 Hydrostatic testing is not required for shop-fabricated piping where the pipe is to be field-tested.
Hydrostatic testing is required on skid-mounted assemblies. Pressure test shall be performed as per
ASME B 31.3 and the appropriate specification class chart.
5.9 All instruments shall be excluded during hydro test.
5.10 All piping shall be flushed prior to hydro testing.
5.11 Those field weld joints, which cannot be leak tested due to unavoidable reasons, shall always be 100%
radiographed.
Requirements as given above in clause 5.1 to 5.11 are general however in case of any conflict with welding
and weld inspection specification, the welding specification shall govern.
5.12 TESTING
Pressure test shall be performed as per ASME B31.3, latest edition.
5.12.1 The following items coming in line with piping shall not be subjected to field pressure testing:
a) Strainers and Filter elements.
b) Pressure relieving devices such as rupture discs and pressure relief valves.
c) Locally mounted pressure gauges.
d) Control valves, shutdown valves etc.
e) Vessel and equipment like pumps, compressors etc. vessel may be tested along with a
piping system, provided the vessel test pressure is not less than the piping system test
pressure.
f) Any other equipment designated by the Company.
5.12.1.1 All the elements which are not to be tested along with the piping shall either be
blanked off during testing or spool pieces inserted during testing.
5.12.1.2 Any temporary corrosion protection coating given on piping at manufacture’s shop /
fabrication yard is to be removed at all inspection points, before final testing.
5.12.1.3 Prior to hydrotesting, vessels & piping are to be flushed by high pressure, high
Volume fresh water or inhibited sea water. However for using Inhibited sea
water company approval shall be required.
5.12.1.4 All piping shall be supported as per approved drawing before pressure testing, spring
and other variable type supports shall be locked to prevent movement.
highest point of the piping system & will be caliberated and checked for accuracy.
5.12.5.3 Care shall be exercised to avoid increase in pressure due to temperature variation
during the test.
5.12.5.4 After completion of hydrostatic test, the pressure shall be released gradually in
steps. All the vents and drains shall be kept open till the lines are fully drained.
The contractor shall then dry the system by blowing compressed dry air and reinstall
items removed during hydrotesting.
5.12.5.5 All testing and calibration of gauges, instrument etc. will be carried out in presence of
company or its authorised representative. Record shall be made of each piping
system during the testing. These records shall be prepared in tabulated
forms and shall include
a) Date of Test
b) Identification of piping and equipment tested with medium.
c) Test medium.
d) Test Pressure.
e) Test Duration.
f) Acceptance of Test result by Company.
5.12.5.6 Testing shall be deemed as complete only after defects noticed during testing have
been rectified and retesting of the system/line has been done to the satisfaction of
the company’s representative.
5.12.5.7 Temporary supports shall be provided wherever required during testing.
6.0 INSTALLATION
6.1 Piping shall be installed in accordance with the approved piping drawings.
6.2 Piping installation shall include the supply and installation of supports shown in the drawing.
6.3 All lines shall be installed true and plumb except where specifically noted on the drawing.
6.4 Installation of piping shall be scheduled so that no undue strain shall be inflicted on equipment due to lack of
support, dead weight or misalignment.
6.5 Piping shall be removed after installation at all rotating equipment connecting points to check the alignment
with and without piping to ensure that the piping does not affect the alignment of the equipment. After
checking the alignment, piping shall be re-installed.
6.6 Flange bolts shall be tightened evenly and sequentially to avoid distortion or overstressing of
equipments.
6.7 During installation/fabrication, care shall be taken at all times to protect the entry of foreign materials by
providing protector caps and covers or other suitable means.
6.8 Before installing prefabricated piping, the inside of the pipe shall be inspected by the contractor to ensure that
all foreign mater is removed.
6.9 Stainless steel materials shall be lifted with nylon or other approved slings, which are free from dirt or ferritic
particles. Under no circumstances, chain or wire ropes shall be used.
6.10 To prevent damage to valve seal and seat surfaces, valves when installed shall be left in following open/close
positions: