Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Issue 2
th
Publication date 4 September 2010
th
Compliance date 4 December 2010
SECTION 52 EARTHWORKS
Contents Page
52.001 Granular starter layers 2
52.002 Fill materials 2
52.003 Placing, compacting and in situ testing of fill material 4
52.004 Particular requirements for PFA embankments 6
52.005 Requirements for finished subgrade and capping 6
52.006 Protection against attack by sulphates 8
52.007 Filling to mobilise passive resistance to structures 8
52.008 Carrying of earthworks over and adjacent to bridges, culverts, 8
walls, etc.
52.009 Drainage 9
52.010 Permeable backing to earth retaining structures 10
52.011 Soil nails 10
52.012 Crib walling 18
52.013 Gabions and protective mattresses 18
52.014 Blanketing 19
52.015 Geotextiles 19
52.016 Geosynthetic soil reinforcement materials 19
52.017 Refacing of slopes 20
52.018 Topsoiling 20
52.019 Landscaping 21
52.020 Instrumentation and monitoring 22
52.021 Specialist surveys 30
52.022 Ground improvement 31
52.023 Swallow holes, naturally occurring cavities and disused mine 33
workings
52.024 Earthworks for reinforced soil and anchored earth structures 33
References 37
--``,,````,,,`````,,,``,,,`,`,`-`-`,,`,,`,`,,`---
British Standards 37
Network Rail standards 38
Model Clauses 38
Other publications 39
Page 1 of 39
SECTION 52 EARTHWORKS
Granular starter 52.001 Basal granular starter layers between embankment fill material
layers and the subgrade shall comply with Classes 6B, C or D as
appropriate to table 6/1 of the Highways Agency Specification
for Highway Works (SHW).
Granular starter layers shall be not less than 300 mm thick and
shall be formed in layers not exceeding 200 mm thick.
Fill materials 52.002 The Contractor shall be responsible for classifying and
determining the acceptability of earthworks materials in
accordance with table 6/1 of the SHW on the basis of tests
carried out at the point of excavation for on-site materials, and
at the point of deposition for imported materials. The source(s)
of imported material shall be agreed with the Employer’s
Representative before any materials are permitted to be
brought to site. If, in the opinion of the Employer’s
Representative, the material has become unacceptable for any
reason, the acceptability tests given in table 6/1 of the SHW
shall be repeated by the Contractor.
Page 2 of 39
The requirements in table 6/1 of the SHW for testing for the
effective angle of friction for granular fill may be relaxed if, in
the opinion of the Employer’s Representative, the nature of the
fill material demonstrates the effective angle of friction to be
greater than the minimum specified.
Materials proposed for general fill shall not include plant toxins
or have a pH greater than 9 or less than 5.
The grading and the name of the power station supplying the
PFA shall be submitted to the Employer’s Representative for
acceptance. A certificate of test results shall be provided to the
Employer’s Representative showing that the material complies
with the requirements of BS 3892-2.
Page 3 of 39
--``,,````,,,`````,,,``,,,`,`,`-`-`,,`,,`,`,,`---
Page 4 of 39
--``,,````,,,`````,,,``,,,`,`,`-`-`,,`,,`,`,,`---
Granular fill and For those Classes of fill subject to end-product compaction
PFA testing, sand replacement tests shall be carried out in
accordance with BS 1377-9. The results of these tests shall
confirm that a field dry density equal to or greater than the
percentage given in table 6/1 of the SHW of the maximum dry
density for the relevant Class of fill (previously made available
to the Employer’s Representative) has been achieved. Moisture
content tests in accordance with BS 1377-2 shall be carried out
immediately following compaction. The moisture content of fill
shall be within the range specified for that relevant Class of fill.
Chalk fill Chalk shall be placed according to the restrictions for Classes A
or B defined in figure 5/1 of the HA 44/91. Filling using chalk
and trafficking over chalk shall not be carried out during wet
weather. Wet weather shall be taken as during rain or snow,
within 2 hours of cessation of rain or snow, when snow is lying
on the ground surface or when the ground is frozen.
--``,,````,,,`````,,,``,,,`,`,`-`-`,,`,,`,`,,`---
Page 5 of 39
A copy of all test results for the placed and compacted fill
material shall be provided to the Employer’s Representative.
Page 6 of 39
--``,,````,,,`````,,,``,,,`,`,`-`-`,,`,,`,`,,`---
Page 7 of 39
--``,,````,,,`````,,,``,,,`,`,`-`-`,,`,,`,`,,`---
--``,,````,,,`````,,,``,,,`,`,`-`-`,,`,,`,`,,`---
Where rock with an undrained modulus of greater than 130
MN/m² occurs naturally at or near the subgrade level,
blanketing in accordance with Clause 52.014 shall be placed
and compacted to provide a formation with an undrained
modulus of less than 130 MN/m².
Protection 52.006 Fill with a water soluble sulphate content exceeding 1500 mg/l
against attack by (Design Sulfate Class DS-2 of BRE Special Digest No. 1, 2005)
sulphates shall not be placed within 500 mm of concrete/cementitious
structures unless these structures are designed for that Class
of sulphate concentration.
Filling to 52.007 Backfilling to the front of bases of retaining walls, gravity and
mobilise passive strutted abutments etc. shall be completed before the filling to
resistance to the back of the structure commences.
structures
Where required by Appendix 52/4, alternative fill materials may
be placed in front of foundations, retaining walls, etc. to
mobilise passive resistance to the structure.
Page 8 of 39
Drainage 52.009 The Contractor shall construct slope drains neatly and as
square as possible with the minimum of overbreak. The
excavated trenches shall be backfilled within 48 hours of
completion of excavation. Backfill shall be Type A drainage
material in accordance with SHW clause 505, placed in layers
not exceeding 225 mm thick with each layer being nominally
tamped.
Fin drains The materials used in fin drains shall have a minimum design
life of 60 years.
Page 9 of 39
Soil nails 52.011 The soil nailing locations, setting out and other details are
shown on the drawings.
Work Package The work shall be carried out in accordance with a Work
Plan Package Plan approved by the Employer’s Representative.
Approval shall be sought at least three weeks prior to installing
the first soil nails or carrying out associated earthworks.
Page 10 of 39
--``,,````,,,`````,,,``,,,`,`,`-`-`,,`,,`,`,,`---
(iii) the method of forming the facing and connecting the soil
nails to the facing,
(v) the minimum time between the completion of one soil nail
and the start of the next,
Once the Work Package Plan has been approved, details shall
not be amended without the prior approval of the Employer’s
Representative.
Page 11 of 39
--``,,````,,,`````,,,``,,,`,`,`-`-`,,`,,`,`,,`---
--``,,````,,,`````,,,``,,,`,`,`-`-`,,`,,`,`,,`---
Working Drawings shall include the location of soil nails,
connections and splices or couplers, drainage, test nails, facing
details, etc.
Fabrication Soil nails shall be fabricated and delivered to the Site ready for
installation in the Works. Soil nails shall be installed by suitably
trained personnel to the approved Work Package Plan and to
the pattern and dimensions shown on the Contract Drawings.
Soil nails formed from high yield deformed steel bars, and their
connections, shall comply with BS 4449 or an equivalent
European national standard. The fabricated nail and
connections to the facing shall have long-term corrosion
protection in the form of hot dip galvanising in accordance with
BS EN ISO 1461.
Page 12 of 39
Facing Details of the soil nail facing are shown on the Contract
Drawings and are detailed in Appendix 52/7.
Connections to Connections to the facing shall transfer the axial tensile forces
facing without forming a point of weakness: their strength shall be not
less than 90 per cent of the parent material. No bolt, screw,
dowel or rod shall be less than 12 mm nominal diameter.
Metallic components of the connections to the facing shall be
mild steel conforming to BS 4449, or other equivalent national
European standard, and shall be hot dip galvanised to BS EN
ISO 1461. Connections between the facing and the soil nails
shall be in accordance with the Contract Drawings and the
manufacturer’s recommendations.
Page 13 of 39
--``,,````,,,`````,,,``,,,`,`,`-`-`,,`,,`,`,,`---
The bearing plate shall be placed over the protruding soil nail
and tensioned to achieve a load of 5 kN.
Limitations on All vehicles and construction plant having a mass of more than
construction 1000 kg shall be kept at least 2 metres away from the facing or
plant external boundaries of the nailed slope. Where appropriate, fill
within 2 metres of the facing shall be compacted with plant
suitable for the Class of fill and having a mass of not more than
1000 kg.
Installation of Holes for soil nails shall be drilled by rotary auger drilling to the
drilled and depth, diameter, alignment and position shown on the Contract
grouted soil Drawings. Holes shall have a maximum deviation from the
nails position shown on the drawings of ±100 mm. The maximum
deviation of the drill holes from the specified alignment shall be
±5 degrees.
--``,,````,,,`````,,,``,,,`,`,`-`-`,,`,,`,`,,`---
The Contractor’s method of maintaining hole stability shall be
detailed in the Work Package Plan.
Page 14 of 39
Only when the grout has developed a strength of not less that
80 per cent of that specified for the 28 day strength, shall the
nail bearing plate be installed. The bearing plate shall be
bedded down and the nail tensioned by applying the specified
torque.
Soil nailing The Contractor shall keep daily records of the soil nails
records installed. Copies of these shall be submitted to the Employer’s
Representative within three days following the installation. The
records shall show the following:
Page 15 of 39
--``,,````,,,`````,,,``,,,`,`,`-`-`,,`,,`,`,,`---
Preliminary pullout tests shall be carried out in advance of the
main soil nailing operation at locations to be agreed with the
Employer’s Representative and as detailed in Appendix 52/8.
The soil nails to be tested shall not be loaded within three days
after grouting.
Page 16 of 39
Test acceptance The nail performance shall be deemed acceptable if the stress
criteria mobilised at failure per unit area of the nail perimeter, equals or
exceeds the design ultimate value. Unacceptable test results
shall result in modifications to the construction procedures.
Such modifications shall be approved by the Employer’s
Representative and the verification tests shall be repeated.
Page 17 of 39
--``,,````,,,`````,,,``,,,`,`,`-`-`,,`,,`,`,,`---
The form of the test results shall be agreed with the Employer’s
Representative and be included in the Work Package Plan.
Crib walling 52.012 The Contractor shall design the crib walling detailed in
Appendix 52/9 in accordance with the design specification and
procedures in Appendix 52/9 and BD 68/97.
Gabions and 52.013 Gabion cages shall comprise either of the following:
protective
mattresses (a) galvanised, hexagonal woven steel wire mesh in
accordance with BS 8002 with a minimum wire gauge of
2 mm and with minimum double twist weaved joints, or
Page 18 of 39
--``,,````,,,`````,,,``,,,`,`,`-`-`,,`,,`,`,,`---
Where ground water seepage may occur from the soil retained
behind the gabions, a geomembrane shall be placed and
secured to the rear of the gabion baskets and lapped 150 mm
under the bottom gabion. Positive drainage to the rear of the
gabion wall shall be provided where detailed on the Contract
Drawings. Typical drainage would comprise 150 mm diameter
perforated plastic pipe laid to a suitable fall (1 in 20) encased on
Grade C20 concrete with the top half of no-fines concrete.
Plastic carrier pipes of 150 mm diameter shall intercept the wall
drains at 5 metre intervals and carry the water to the track
drainage.
Blanketing 52.014 Where specified in Appendix 52/11, blanketing shall be laid and
compacted in accordance with Section 212 (Installation of new
and renewal of existing Permanent Way).
Geosynthetic 52.016 Geosynthetic materials used for soil reinforcement shall have
soil British Board of Agrément (BBA) accreditation. Where a
reinforcement current BBA Certificate is not available, samples of the material
materials shall be taken for control testing at a laboratory to the approval
of the Employer’s Representative.
Page 19 of 39
Refacing of 52.017 Material used to reface slopes shall be Acceptable granular fill
slopes in accordance with Clause 52.002.
Topsoiling 52.018 Except for topsoil classified as suitable material and stockpiled
for re-use in accordance with Section 50 (General requirements
for earthworks and excavations), topsoil shall be of the grade
specified in Appendix 52/14, in accordance with table 1 of BS
3882, and shall be free of all foreign matter and soil
contaminants.
Page 20 of 39
Topsoiling shall be carried out only when the subsoil and topsoil
are workable, not saturated, and free of frost or snow. Handling
and movement of topsoil shall be minimised, and care taken to
avoid its over compaction during and after spreading.
Page 21 of 39
Instrumentation 52.020 The Contractor shall provide, install, obtain readings and
and monitoring maintain for the duration of the Contract the instrumentation
shown on the Contract Drawings and detailed in Appendix
--``,,````,,,`````,,,``,,,`,`,`-`-`,,`,,`,`,,`---
52/16.
Page 22 of 39
Page 23 of 39
• Scheme name,
• Contractor’s name,
• Name of operator,
• Borehole/location No.
• Instrument type,
• Depth of instrument,
• Location of instrument,
• Instrument readings,
Instrumentation Borings for instrumentation shall be carried out using plant and
boreholes techniques to the approval of the Employer’s Representative.
Unless otherwise agreed, the minimum diameter of boring or
--``,,````,,,`````,,,``,,,`,`,`-`-`,,`,,`,`,,`---
Page 24 of 39
Installation and The Contractor shall prevent damage to the instruments and
protection associated cables at all times.
• Contractor’s name,
Page 25 of 39
• plant in use,
• groundwater records,
(a) Standpipe
Page 26 of 39
Page 27 of 39
--``,,````,,,`````,,,``,,,`,`,`-`-`,,`,,`,`,,`---
set in concrete and, where detailed on the Contract
Drawings, a protective fence shall be erected around the
cover.
Page 28 of 39
cover.
Page 29 of 39
--``,,````,,,`````,,,``,,,`,`,`-`-`,,`,,`,`,,`---
installation. Readings shall be taken whilst the probe is
travelling in both an upward and downward direction. Both
readings shall be recorded separately and reported to the
Employer’s Representative.
Items (c) and (e) shall also be presented graphically to show the
change in deviation and displacement depth.
Magnetic probe The access tubing for the magnetic probe extensometers shall
extensometers be either the access tubing used for inclinometers or dedicated
tubing. Where scheduled to be installed in boreholes, access
tubing, target and datum magnets shall be installed and grouted
in place in accordance with the manufacturer’s instructions and
as shown on the Contract Drawings.
Specialist 52.021 Topographic surveys of above and below ground features shall
surveys be carried out where specified in Appendix 52/19.
Page 30 of 39
• staffing levels,
Page 31 of 39
Provided by IHS Markit under license with Network Rail Licensee=Capita Symonds to Capita property & infrastructur/5965831001, User=Bong
No reproduction or networking permitted without license from IHS Not for Resale, 05/04/2018 05:48:50 MDT
Reference NR/L3/CIV/140/52C
Issue 2
th
Publication date 4 September 2010
th
Compliance date 4 December 2010
The total clay, silt and fine dust content shall not exceed 4 per
cent (by weight).
Vibrated stone The design, execution and performance of the Works shall be
columns - such that subsequent foundation settlements are limited to the
settlement criteria specified in Appendix 52/21.
behaviour of the
completed area
Vibrated stone Water jetting or flooding shall not be used as part of the
columns - vibroflotation Works if the bearing capacity of nearby structures
workmanship is likely to be reduced or nearby structures would be adversely
affected by settlement.
Vibrated stone The Contractor shall keep daily records of the vibroflotation
columns - site Works carried out and shall submit signed copies of these to
records the Employer’s Representative by noon of the next working day.
The records shall show the following for each column:
• date,
• type of backfill,
Page 32 of 39
Vibrated stone Testing of treated ground shall be undertaken both during and
columns - on completion of the ground treatment works. In advance of
testing the main ground improvement Works the Contractor shall carry
requirements out zone tests, as advised by the Employer’s Representative, to
confirm that the design meets the acceptability criteria.
The Contractor shall carry out control plate load testing at the
frequency detailed in Appendix 52/22.
Vibrated stone The Contractor shall design the required ground improvement
columns - depth and spacing to comply with the settlement criteria for
acceptability each structure as shown on the Contract Drawings and
criteria approved by the Employer’s Representative.
Swallow holes, 52.023 Infilled swallow holes and other naturally occurring cavities shall
naturally be excavated, filled and capped as detailed in Appendix 52/23.
occurring
cavities and Open swallow holes and other shallow cavities shall be flushed,
disused mine cleared of rubbish where to do so would not endanger
workings operatives, and filled and capped as detailed in Appendix 52/23.
--``,,````,,,`````,,,``,,,`,`,`-`-`,,`,,`,`,,`---
monitored, cleared, flushed, capped or have any other
treatment carried out as detailed in Appendix 52/23.
Page 33 of 39
Technical The system for reinforced soil and anchored earth structures
specification shall comprise the following:
Page 34 of 39
--``,,````,,,`````,,,``,,,`,`,`-`-`,,`,,`,`,,`---
Page 35 of 39
Page 36 of 39
--``,,````,,,`````,,,``,,,`,`,`-`-`,,`,,`,`,,`---
REFERENCES
This is a list of publications referred to within this Section of the Model Clauses.
Page 37 of 39
Page 38 of 39
--``,,````,,,`````,,,``,,,`,`,`-`-`,,`,,`,`,,`---
Page 39 of 39