Sei sulla pagina 1di 2

Remote operation of 220/132kV Salakati Substation – A glimpse

Somiran Das
Dy Manager-OS, RHQ-Shillong
Introduction
Successful implementation of remote operation scheme at
Salakati Substation to remotely control from 400kV
Bongaigaon Control Room on August`2007 introduce Scheme brief
North Eastern Region to the new field of technology. Under the scheme, following functions of Salakati Control
220/132kV Salakati Substation is the first unmanned Room were monitored and controlled from 400kV
Substation in NER. The scheme is based on the concept of Bongaigaon Control Room.
centralised RTU architecture, which is installed at Salakati Monitoring functions
and SCADA system at Bongaigaon. RTU is equipped with
digital and analogue inputs units and control outputs, • All power system parameters (such as Voltage,
communicate serially through twisted pair cable with Current, Frequency, MW, MVAR, Synchronization)
Control Centre at 400kV Bongaiagaon Control Room on as available in Control panels
IEC60870-5-101 protocol. At Bongaiagaon Control Centre • WTI and OLTC tap position of Transformers.
using SCADA PC, the operator can see the mimic of • All trip/non-trip alarms available in the
existing Control panels and issue control command. annunciation window facia.
• Open/close status of all Circuit Breakers, Isolators
Background & Earth switches
The 220/132kV Salakati Substation is located at Harigaon • Healthiness of auxiliary system i.e DC sytem,
in the District: Kokrajhar, BTC, Assam. The substation is ACDB, Room temperature
around 220 Km from Guwahati and 30 Km from New Control functions
Bongaigaon Railway Station. Salakati Substation provides • Open/Close of Circuit Breakers
the first inter-country connectivity with Bhutan through • Control of OLTC
132kV Salakati-Gelephu feeder. It also plays a vital role
• Synchrocheck before closing of Circuit Breakers
for NER Grid due to its connectivity with Eastern Region
through 220kV Birpara # I & II feeders and 400kV • Accept/Reset of alarms
Bongaigaon Sub-Station through 315 MVA, 400/220kV
ICT. The Substation was commissioned in the year 1987. The overall system architecture of Salakati Remote
It is in close proximity with 400kV Bongaigaon operation scheme is shown in Figure # 1. The purpose of
Substation. The road distance between the two Substations providing each equipments are explained herein.
is approx. 3.0 Kms.
Salakati substation comprises of 9 Nos - 220kV bays, 4 RTU
Nos - 132kV Bays, 2 Nos - 220/132kV, 50MVA RTU is a microprocessor controlled electronic device
Transformer. which intefaces the field devices/substation equipment to
The control room operation was manned by total 12 SCADA system. It performed the initial processing of the
personnel (one JE, two Technicians per shift) round the acquired data. New RTU installed at Salakati is equipped
clock. The power system parameters viz., MW, MVAR, with power supply module, CPU, digital & analogue
voltage, current etc were recorded mannually by shift inputs and control outputs module.
personnel in every hour. The CT & CVT secondaries of each feeders/Bus, WTI &
tap position of transformers are connected using electrical
Glossary of Terms transducers to RTU as analogue inputs.
RTU: Remote Terminal Unit All alarms and status information are connected to RTU as
SCADA: Supervisory Control And Data Acquisition digital inputs via contact multiplying relays .
GPS: Global Positioning System The control outputs of RTU are connected to Circuit
IEC: International Electrotechnical Commission Breakers via heavy duty auxiliary relay contacts.
ULDC: Unified Load Despatch Centre New RTU supplied under the scheme is integrated with
WTI: Winding Temperature Indication ULDC RTU to collect few analog datas.
OLTC: On Load Tap Changer RTU has four communication ports and support
interfaces viz., RS232, RS485, Ethernet.
Contd… next page
SCADA SYSTEM

NEW RTU ULDC RTU

Hardware inputs from


C&R panels/ fields
Figure # 1: Overall system architecture
SCADA System
SCADA system comprises of HMI (Human Machine
Interface i.e. PC with dual monitor), communication card, GPS » PC interface card with antenna, Make: Hopf
database and software, which is installed at Bongaigaon
Control Room. Data acquired by the RTU from substation Augmentation of C&R panels
equipments is transmitted to SCADA system. SCADA The existing hand reset trip relays have been replaced by
than complies and formats the data in such a way that a the self/ electrically reset trip relays.
control room operator using the HMI can make
supervisory decisions. It provides operator interface to Maintenance
monitor & control the substation equipment through Role of maintenance team in remotely control substation
displays & SLD. Mimic of existing control panels, SLD is very vital. For any exigencies, maintenance team has to
showing substation equipment & analog data’s has been report immediately. The routine maintenance/AMP of
provided to helps operator feel working in conventional substation shall be carried out by the maintenance team as
Control Room environment. done normally. Additionally, operation of Isolators,
SCADA also provides automatic logging and generation recording of relay indications/fault locators, PLCC
of hourly, monthly, yearly data’s as per user requirement. counter, DG set operation shall have to be done by
Communication medium maintenance team.
The data from RTU is transferred to SCADA system Execution
through twisted pair cable over IEC60870-5-101 protocol
The contract for execution of Salakati remote operation
in dual redundant mode using line drivers. Twisted pair
works was awarded to M/s AREVA T&D Systems India
communication cable is laid underground between
Limited, Noida at the total value of Rs. 37,35,317.00.
Salakati & Bongaigaon. Communication Port 1 & 2 of
RTU is used for data transfer at 9600 bps. Economic & Operational benefits
Line driver Economics play a major role in justifying remote operation
Line drivers are used for signal amplification as well as of existing substations. The saving from the 12 nos. shift
conversion from RS232 to RS485 & vice versa as the personnel’s engaged in the Control Room operation comes
length of cable is 1500 meters. Line driver is provided in out to Rs. 66,00000.00 (approx) in a year. So, the cost of
the two ends of the cable. implementing the remote operation scheme shall be
Time synchronization recovered within a year.
SCADA system is time synchronized by GPS based Conclusion
receiver (PC interface card) which in turn synchronizes
the time of RTU. There are ample advantages in implementing remote
operation system in existing substations. Apart from
Major equipment Type, Model & Make saving in operational cost, other advantages includes
RTU » Type: MiCOM C264 series, Make: AREVA
accurate & timely information of power system data`s,
SCADA PC » Model: Dell 380 Precesion, Make: Dell
sequence of events occurred with 1ms resolution,
SCADA software » E-terra, Ver.: 3.40, M/s AREVA
automatic report generation as per requirement etc.

Potrebbero piacerti anche