Document Reference

FREY-FIL CORPORATION FFC


Rev. No. Rev. Date
INFRA MANAGEMENT SYSTEM 00
Page Document No.
Construction of Detour Road @
1 of 10
Alignment B. M17-CIV-007-ABP-005

Construction of Abusag Bridge Location


San Jose, Baggao, Cagayan

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS


Contract ID: 18B00053
Contract Name: 001 - ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM
BRIDGE -REPLACEMENT OF PERMANENT WEAK BRIDGES ABUSAG
BRIDGE (B04258LZ) & APPROACHES Along Baybayog - Baggao - Dalin -
Sta. Margarita Road Baggao, Cagayan
Location of the Contract: Baggao - Dalin - Sta. Margarita Road Baggao, Cagayan
----------------------------------------------------------------------------------------------------------------------------------

Method Statement for


Alignment - B Detour Road Construction.

Revision and Approval Block


Re Prepared By Verified By Approved By Noted By
Issue
v Description Details Marcelo
Date PM
No Tenio Jr.
Sign
Date
Sign
Date
Sign
Date
Print Date: 05/Jun/2020
Document Reference
FREY-FIL CORPORATION FFC
Rev. No. Rev. Date
INFRA MANAGEMENT SYSTEM 00
Page Document No.
Construction of Detour Road @
2 of 10 M17-CIV-007-ABP-004
Alignment B.
Construction of Abusag Bridge Location
Baggao - Dalin - Sta. Margarita Road
Baggao, Cagayan

Contents

1. Purpose......................................................................................................................................2

2. Scope of Work...........................................................................................................................2

3. Responsibilities.........................................................................................................................3

4. Work Methodology....................................................................................................................3

5. Resources..................................................................................................................................4

5.1 Manpower................................................................................................................................4

5.2 Safety Equipment...................................................................................................................4

5.3 Equipment...............................................................................................................................4

6. Safety Precautions
--------------------------------------------------------------------------------------------------5

7. ENVIRONMENTAL PROTECTIONMEASURES----------------------------------------------------------5
8. Annexes................................................................................................................................5-10

1. Purpose
 To provide temporary access/diversion route to commuters affected in construction of the bridge.

2. Scope of Work
 Detour road Embankment covers handling, loading, transporting, placing and Grading of acceptable
materials excavated from roadway or from borrow sites for roadway construction at project up to the
approved design level.

Print Date: 05/Jun/2020


Document Reference
FREY-FIL CORPORATION FFC
Rev. No. Rev. Date
INFRA MANAGEMENT SYSTEM 00
Page Document No.
Construction of Detour Road @
3 of 10 M17-CIV-007-ABP-004
Alignment B.
Construction of Abusag Bridge Location
Baggao - Dalin - Sta. Margarita Road
Baggao, Cagayan

3. Responsibilities
Project Manager/Deputy Project Manager shall direct when and where to start the Road detour
works and established deadlines for activity to be finished with the time frame set forth on
the construction schedule.
Field Engineer/Site Engineer shall be responsible for the execution of roadway
embankment for detour road.
Quality Control Engineer shall be responsible in monitoring quality of works and materials
brought at site.
Surveyor shall be responsible for establishing boundaries, limits, elevations and extend of
roadway detour embankment.
Safety officer shall ensures that the safety of the workers ha taken into consideration at all
times. He makes sure that the stake, poles and barricades with warning tapes on it shall be
in placed whenever required as the roadway embankment progresses. Warning lights shall
likewise be introduced if found necessary.

4. Work Methodology

 Secure necessary permits prior to any construction activities.


 Layout and Staking for the proposed detour road.
 Removal and relocation of any affected utilities and facilities
 Clearing and grubbing.
- Removing and disposing of all unwanted and unsuitable materials such as trees,
grass, weeds and downed trees.
 Re-Established designed limits, center line with its elevations for preparation to received
borrow materials.
 Placing of Borrow Materials.
- Borrow materials is placed in uniformed level layers and properly moistened and
compacted with approved compacting equipment.
- Successive layers of the same depth of loose lift shall be placed and compacted until
reaching the intended design elevation of embankment.
- The loose depth of each lift is required to be such that the required compaction maybe
obtained, but in no case exceed 200mm.
 Grading of Borrow materials.
- Motor Grader shall be used for Grading, leveling and finishing of freshly backfill materials.
 Surveyor together with the Site Engineer/Field Engineer shall constantly monitor the work
operation to conform with the desired elevation and cross-section.
 Compaction of Borrow materials using Road roller and Water truck.
- Proper Compaction are required to be conducted on each lift, and the required compaction
obtained each lift before the next lift is placed.
 After completion of embankment works, laying of mixed gravel surface will commence with
thickness of 100mm and a width of 6 meter with compaction.
 Installation of road and safety signage.
 Provide rigger to control the sequencing in dumping of Borrow materials.
 Provide Flagman on both ends of work areas to control the traffic.
Note : Strict traffic management will be implemented.
Attached traffic scheme for implementation.

Print Date: 05/Jun/2020


Document Reference
FREY-FIL CORPORATION FFC
Rev. No. Rev. Date
INFRA MANAGEMENT SYSTEM 00
Page Document No.
Construction of Detour Road @
4 of 10 M17-CIV-007-ABP-004
Alignment B.
Construction of Abusag Bridge Location
Baggao - Dalin - Sta. Margarita Road
Baggao, Cagayan

5. Resources

5.1 Manpower

i. Project Manager
ii. Deputy Project Engineer
iii. Field Engineer
iv. Site Engineer
v. General Foreman
vi. Backhoe operator
vii. Dump truck operator.
viii. Loader Operator
ix. Water truck operator
x. Tower Light Operator
xi. Rigger
xii. Flagman
xiii. Safety Engineer.
xiv. Surveyor
xv. Survey Aide.
xvi. Mechanic
xvii. Lead man
xviii. Laborer

5.2 Materials and tools.


i. Wooden stake
ii. Warning tapes
iii. Spray paint and Markers
iv. Steel bar for staking (elevations).
v. Shovel
vi. Wheel borrow
vii. Concrete nails.
viii. Hammer

5.3 Equipment

i. Bulldozer
ii. Backhoe
iii. Dump tuck
iv. Grader
v. Loader
vi. Vibratory roller
vii. Water truck
viii. Tower light

Print Date: 05/Jun/2020


Document Reference
FREY-FIL CORPORATION FFC
Rev. No. Rev. Date
INFRA MANAGEMENT SYSTEM 00
Page Document No.
Construction of Detour Road @
5 of 10 M17-CIV-007-ABP-004
Alignment B.
Construction of Abusag Bridge Location
Baggao - Dalin - Sta. Margarita Road
Baggao, Cagayan

5. Safety Precautions.

As what has been the company’s standard operating procedure, safety of everyone including materials and
equipment is almost of our utmost concern..

Normal safety procedures being required at site are the following.

1) Safety tool box meeting shall be conducted everyday to remind workers about concerning the safety.
All workers shall be provided with PPE(PERSONAL PROTECTIVE EQUIPMENT) and shall be
Worn at all time on site. Safety Manager/Safety supervisor shall insure all the workers wear all the Safety
equipment provided.
2) All workers shall be advised to report any accident or injury to supervisor.
3) Proper and adequate provision of signage’s and barricades at diversions and temporary haul
road as Necessary.
4) Provision of rigger to guide the dump truck while unloading the borrow materials.
5) Provision of 2 Flagman to control traffic at both ends.
6) Prime importance shall be given for personnel safety and protection of utility lines/services. It
shall be insure that the personnel involved are aware about the company safety regulation and
confirmed that the machinery are regularly maintained. Further to above, the following key points
shall be considered important.

a) All moving vehicle/equipment shall have reverse horn.


b) Transporting of person per vehicle is restricted to the number of seats available.
c) Road safety sign /road diversion sign shall be installed wherever applicable for the safe Movement of
vehicles or equipment.

7. Environmental Protection Procedures.

All workers shall educate on good environment management practices and well discipline to environment. The
garbage bin shall be provided at the working area and supervisor shall insure its must be collected regularly and
disposed off at the approved dump site.

All workers shall insure that all tools and equipment machinery are in good condition to avoid any oil leakage that
could harm to environment.

Print Date: 05/Jun/2020


Document Reference
FREY-FIL CORPORATION FFC
Rev. No. Rev. Date
INFRA MANAGEMENT SYSTEM 00
Page Document No.
Construction of Detour Road @
6 of 10 M17-CIV-007-ABP-004
Alignment B.
Construction of Abusag Bridge Location
Baggao - Dalin - Sta. Margarita Road
Baggao, Cagayan

6. Annexes

Survey works.

Established elevation.

Print Date: 05/Jun/2020


Document Reference
FREY-FIL CORPORATION FFC
Rev. No. Rev. Date
INFRA MANAGEMENT SYSTEM 00
Page Document No.
Construction of Detour Road @
7 of 10 M17-CIV-007-ABP-004
Alignment B.
Construction of Abusag Bridge Location
Baggao - Dalin - Sta. Margarita Road
Baggao, Cagayan

Embankment laying using Dump truck.

Leveling/Grading of borrow materials.

Print Date: 05/Jun/2020


Document Reference
FREY-FIL CORPORATION FFC
Rev. No. Rev. Date
INFRA MANAGEMENT SYSTEM 00
Page Document No.
Construction of Detour Road @
8 of 10 M17-CIV-007-ABP-004
Alignment B.
Construction of Abusag Bridge Location
Baggao - Dalin - Sta. Margarita Road
Baggao, Cagayan

Compaction of Embankment materials.

Print Date: 05/Jun/2020


Document Reference
FREY-FIL CORPORATION FFC
Rev. No. Rev. Date
INFRA MANAGEMENT SYSTEM 00
Page Document No.
Construction of Detour Road @
9 of 10 M17-CIV-007-ABP-004
Alignment B.
Construction of Abusag Bridge Location
Baggao - Dalin - Sta. Margarita Road
Baggao, Cagayan

Print Date: 05/Jun/2020


Document Reference
FREY-FIL CORPORATION FFC
Rev. No. Rev. Date
INFRA MANAGEMENT SYSTEM 00
Page Document No.
Construction of Detour Road @
10 of 10 M17-CIV-007-ABP-004
Alignment B.
Construction of Abusag Bridge Location
Baggao - Dalin - Sta. Margarita Road
Baggao, Cagayan

Print Date: 05/Jun/2020