S. No.
of
Sub- Sub-activities Hazard
activit
y/
Tanker driver reporting
1
in Gate-2 and checking Bad physical condiion of
by security and logistics the tanker / leakage
team
2
Weighing at weigh- Overloading of weigh-
bridge bridge
3
Tanker reaching at LPG Poor illumination
unloading bay
Overspeeding
Release of hydrocardon
due to damage of
equipment due to tanker
movement
4
Parking of tanker in the
unloading bay
4
Parking of tanker in the
unloading bay
Release of hydrocarbon
from sampling point
Surrounding checking
7 Hydrocarbon release
and hose connection
Overfilling and
corrsponding increase in
pressure
10
Monitor the tanker level
and the sphere level
11
Tanker disconnection LPG under pressure in the
from hose hose
11
Tanker disconnection LPG under pressure in the
from hose hose
Tilting of tanker
causing fire and a) Checking at the gate
explosion invoice quantiy, RTO paper
to check the capacity of the
tanker.
Collapse of weigh- b) Periodic maintenance of
bridge weigh-bridge
a) Rupture disc
Fire and explosion b) Testing certificate
Periodic checking and
replacement of defective
sampling chord (defined in
SOP)
a) PSV
Fire and Explosion b) LSHH interlock and ROV
will close.
a) Tanker rotagauge level
moitoring
Pump damage
b) SOP will be followed
religiously.
A) After unloading
Splashing of liquid completion, stop the pump.
LPG on the operator B) Depressurization of the
hose after completion of
unloading.
C) Isolation of tanker valve
and blinding of hose and
tanker side blind.
B) Depressurization of the
hose after completion of
unloading.
C) Isolation of tanker valve
and blinding of hose and
Fire and explosion tanker side blind.
Nil -
Nil -
Actual Risk
Responsibility
Factor Additional controls
recommended By By
R
Whom When