Existing Capacity Peak New Transformer status Any constraints regarding new

Load transformer
Ram nagar 50x2= 100 MVA 25 MW One 50 MVA diverted to Project was to commission
Hatuha . three 50 MVA transformer but
only two 50 MVA transformer
commissioned .
Imamganj 20X2=40 MVA 22 MW One 50 MVA New Load constraint of 6 MW .
transformer present at GSS Erection and commissioning
Imamganj. work not started yet. M/s KPM
to start work within a week
Sheikhpura 1X50+2X20= 90 MVA 60 MW One 50 MVA New M/s KRR to start Foundation
transformer present at GSS work in 2-3 days after taking
Sheikhpura. shutdown request. Civil work to
be completed in 15-20 days.