Sei sulla pagina 1di 12

Project : F/Y:2075/076 Page-1 of 12/Column Rebar/IPC-01

Donar :
Name of the School :
Location : Rasuwa, Nepal.
Contract Package No:-

Bar Schedule of Columns


Nos Nos. Total Unit
of Unit Total Total
S.N Description Dia Colu of Length Length m weight weight Kg Remarks
Bar Kg
mn mm

foundation

c1 12 6 16 2.4 230.40 0.888 204.60

cf1 12 6 32 2.2 422.40 0.888 375.09

cf1 12 6 16 4.8 460.80 0.888 409.19

A Columns at Grid 1-1


1 Column C1

Submitted by: Checked and Verified by: Approved by:


Bar Schedule of Columns Page-2 of 12/Column Rebar/IPC-01

Nos Nos. Total Unit


of Unit Total Total
S.N Description Dia of weight Remarks
Colu Bar Length Length m Kg weight Kg
mn mm

8-20ɸ 20 6 8 4.4 208.80 2.467 515.11

Lap 20 6 8 1.2 57.60 2.467 142.10

Stirrups 8 12 32 2 675.84 0.395 266.96

4-16ɸ 16 3 8 4.4 105.60 1.578 166.64

4-20ɸ 20 3 8 4.4 105.60 2.467 260.52

Lap 20 3 8 1.2 28.80 2.467 71.05

Submitted by: Checked and Verified by: Approved by:


Bar Schedule of Columns Page-3 of 12/Column Rebar/IPC-01

Nos Nos. Total Unit


of Unit Total Total
S.N Description Dia of weight Remarks
Colu Bar Length Length m Kg weight Kg
mn mm

Stirrups 8 6 32 2 299.52 0.395 118.31

tie Beam

12 1 6 46.4 278.10 0.888 246.95

Lap 12 12 6 0.7 51.84 0.888 46.03

Stirrups 8 1 368 1 463.68 0.395 183.15

beam

Submitted by: Checked and Verified by: Approved by:


Bar Schedule of Columns Page-4 of 12/Column Rebar/IPC-01

Nos Nos. Total Unit


of Unit Total Total
S.N Description Dia of weight Remarks
Colu Bar Length Length m Kg weight Kg
mn mm

16 1 6 46.4 278.40 1.578 439.32

Lap 16 12 6 1.0 69.12 1.578 109.07

Stirrups 8 1 368 2 574.08 0.395 226.76

Total quantity for this bill 3,780.84

Submitted by: Checked and Verified by: Approved by:


Government of Nepal
National Reconstruction Authority (NRA)
Central Level Project Implementation Unit - Education
Rasuwa

Length Breadth Height Weight


S.N. Description of Work No. Quantity Unit Remarks
(m) (m) (m) Kg/unit
CIVIL WORKS for BLOCK 2- 4 Classrooms
EARTH WORKS
SITE CLEARANCE & MOBILIZATION :
Site clearance 1 13.00 6.20 80.60
Sub Total 80.60 sq.m
EARTHWORK IN EXCAVATION :
Foundation
Footing (F1) 3 2.60 2.60 1.58 31.94
Footing (CF) 3 4.80 2.30 1.73 57.13
Foundation beam
Grid A,B,C : 2-3 3 1.350 0.500 0.900 1.82 cu.m
Grid 1,2- : A-B,B-C 4 2.500 0.500 0.900 4.50 cu.m
Ramp 1 8.075 0.100 0.300 0.24 Cu.m
Sub Total 95.64 cu.m
EARTH BACK FILLING :
Room 1,2 2 4.50 3.70 0.300 9.99
Corridor 2 4.50 1.55 0.300 4.19
total cutting 1 95.64 95.64
Deducion
Boulder soling -1 14.74 -14.74
PCC -1 3.63 -3.63
RCC
Footing and Beam -1 31.52 -31.52
Column -1 1.64 -1.64
Brick work -1 10.66 -10.66
Sub Total 47.63 cu.m

BOULDER SOLING :
1.5 mm thick Boulder soling for
rooms
Foundation
Footing 1(F1) 3 2.30 2.30 0.15 2.38
Combined Footing (CF1) 3 4.50 2.00 0.15 4.05
Foundation Beam
Grid A,B,C : 2-3 3 1.350 0.500 0.150 0.30
Grid 1,2- : A-B,B-C 4 2.500 0.500 0.150 0.75
Grid 3- : A-B,B-C 1 2.200 0.500 0.150 0.17
Room 1,2 2 4.50 3.70 0.150 5.00
Corridor 2 4.50 1.55 0.150 2.09
Sub Total 14.74 cu.m
CONCRETE WORKS
P.C.C (1:3:6) Works
Foundation
Footing 1(F1) 3 2.30 2.30 0.08 1.19

Contractor Consultant DLPIU CLPIU


Length Breadth Height Weight
S.N. Description of Work No. Quantity Unit Remarks
(m) (m) (m) Kg/unit
Combined Footing (CF1) 3 4.50 2.00 0.08 2.03
Foundation Beam
Grid A,B,C : 2-3 3 1.350 0.300 0.08 0.09
Grid 1,2- : A-B,B-C 4 2.500 0.300 0.08 0.23
Grid 3- : A-B,B-C 2 2.200 0.300 0.08 0.10
Sub Total 3.63 cu.m
P.C.C (1:2:4) Works
Room 1,2 2 4.50 3.70 0.08 2.50
Corridor 2 4.50 1.55 0.08 1.05 cu.m
Sub Total 3.54 cu.m
P.C.C FOR R.C.C. Works(1:1.5:3)
Foundations
Foundation
Footing 1(F1) 3 2.30 2.30 0.45 7.14
Combined Footing (CF1) 3 4.50 2.00 0.60 16.20
Foundation Beam and tie beam
Grid A,B,C : 2-3 3 3.550 0.300 0.35 1.12
Grid 2,3- : A-B,B-C 4 4.350 0.300 0.35 1.83
Grid 1- : A-B,B-C 2 4.400 0.300 0.35 0.92
Grid A,B,C 3 4.950 0.300 0.35 1.56
Grid 2,3 2 8.700 0.300 0.35 1.83
Grid 1 1 8.800 0.300 0.35 0.92
Sub total (a) 31.52
Columns
C1 6 0.450 0.450 7.500 9.11
C2 3 0.400 0.400 7.500 3.60
Slab beam
Grid A,B,C 3 4.950 0.300 0.35 1.56
Grid 2,3 2 8.700 0.300 0.35 1.83
Grid 1 1 8.800 0.300 0.35 0.92
Slab
1 10.650 6.875 0.125 9.15
1 11.250 7.475 0.125 10.51
Sub Total 68.21 cu.m
STEEL REINFORCEMENT
foundation 1 988.877 988.88
Column 2 1,540.678 3,081.36
tie beam 2 476.140 952.28
for slab 2 1,000.000 2,000.00
beam 2 775.148 1,550.30

8,572.81 kgs
FORM WORKS
Foundation Footing
Foundation
Footing 1(F1) 3 9.20 0.45 12.42
Combined Footing (CF1) 3 13.00 0.60 23.40
Foundation Beam and tie beam
Grid A,B,C : 2-3 3 3.550 0.70 7.46

Contractor Consultant DLPIU CLPIU


Length Breadth Height Weight
S.N. Description of Work No. Quantity Unit Remarks
(m) (m) (m) Kg/unit
Grid 2,3- : A-B,B-C 4 4.350 0.70 12.18
Grid 1- : A-B,B-C 2 4.400 0.70 6.16
Grid A,B,C 3 4.950 0.70 10.40
Grid 2,3 2 8.700 0.70 12.18
Grid 1 1 8.800 0.70 6.16
Sub total (a) 90.35
Columns
C1 6 1.800 7.500 81.00
C2 3 1.600 7.500 36.00
Slab beam sides
Grid A,B,C 3 4.950 1.00 14.85
Grid 2,3 2 8.700 1.00 17.40
Grid 1 1 8.800 1.00 8.80
Slab with beam base
1 10.650 6.875 73.22
sides formworks 1 35.050 0.125 4.38
1 11.250 7.475 84.09
sides formworks 1 37.450 0.125 4.68
sill 6 3.550 0.075 1.60
8 4.350 0.075 2.61
8 3.250 0.075 1.95
Sub Total 420.93 sq.m
BRICK MASONRY WORKS
Full Brick (250 mm) Works (1:4c/s)
total
height
+below
Grid A,B,C/2-3 3 3.550 0.230 5.650 13.84 beam
Grid 2,3/A-B,B-C 4 4.350 0.230 5.650 22.61
Cooridor wall at first floor 2 4.350 0.230 1.100 2.20
Deduction
door -4 1.100 0.230 2.100 -2.13
window -12 1.500 0.230 1.200 -4.97
sill -6 3.550 0.230 0.075 -0.37
-8 4.350 0.230 0.075 -0.60
-8 3.250 0.230 0.075 -0.45
Sub Total 30.14 cu.m

Contractor Consultant DLPIU CLPIU


Nos./Pi Height/
S.N Description of works length Breath Quantity Unit
eces Thickness
1 EARTH WORKS
1.1 Site Clearance
Site clearance 1 6.00 5.00 30.00 Sq.m

1.2 Earth Work Excavation


Foundation
Footing 8.00 0.90 0.90 0.90 5.83 cu.m

1.3 Earth Back Filling


Footing 1.75 cu.m

1.4 Boulder Soling


Footing 8.00 0.75 0.75 0.15 0.68 cu.m
2 CONCRETE WORKS
2.1 P.C.C.(1:3:6) Works
Footing 8.00 0.75 0.75 0.075 0.34 cu.m
2.2 P.C.C (1:1.5:3) For R.C.C. Works M20
Footing first step 8.00 0.75 0.75 0.30 1.35
Footing second step 8.00 0.30 0.30 0.90 0.65
Total 2.00 cu.m
2.3 Steel Reinforcement Works

Providing high strength deformed bars (HYSD)


of grade Fe:450 approved reinforcement for
R.C.C work and approved bar bending
schedule including straightening, cutting,
bending, placing and binding in position by
binding wires all complete as per drawing,
specification and instruction by the Engineer.
Reinforcement for footing 2.00 299.70 kg
Nos./Pi Height/ Units Wt. Total Wt. in
S.N. Description of works length Breath Quantity Unit
eces Thickness (Kg) kg
3 Steel Structure
Vertical Steel Post 100x100x4 8 5.50 44.00 m 11.73 516.12
Landing Beam ISMC 100 8 4.00 32.00 m 9.56 305.92
Stair Beam ISMC 100 4 3.13 12.52 m 9.56 119.69
Railing Top Rail ISNB 40 L 4 26.00 104.00 m 3.23 335.92
Railing vertical ISB 25x25x2.6 174 0.90 156.60 m 1.69 264.65
Railing intermediate Rail ISB 25x25x2.6 1 26.00 26.00 m 1.69 43.94
Landing angle ISA 40x40x5 3 19.50 58.50 m 3.00 175.50
Landing checker plate 5mm 3 4.00 1.5 5 18.00 39.25 706.50
Roof Truss ISMC 100 2 4.00 8.00 m 9.56 76.48
Roof Truss purlin pipe ISNB 65L 5 4.00 20.00 m 5.71 114.20
Steps angle ISA 40x40x5 18 4.60 82.80 m 3.00 248.40
Step vertical flat 25X5 18 6.60 118.80 m 0.98 116.54
Step checker plate 5mm 18 2.00 0.45 5 16.20 39.25 635.85
Step suport vertical angle ISA 40x40x5 36 0.15 5.40 m 3.00 16.20
Joint plate for post 8
Base plate of Steel post at top of RCC 8.0 0.30 0.30 12 0.72 m2 94.20 67.82
footing
M16 dia Bolts & Nuts 32 0.40 12.80 m 1.58 20.22
Gusset Plate 96 0.10 0.05 6 0.480 m 2 47.10 22.61
Joint plate for connection of Steel post at 16 0.30 0.30 12 1.44 94.20 135.65
middle m2
Nuts and Bolts Lump-sum kg 3.00
Total of Steel works 3,925.22
4 CGI Sheet Roofing 6.50 4.50 m2 29.25
Abstract of Cost

Government of Nepal
National Reconstruction Authority(NRA)
Central Level Project Implementation Unit(Education)
Gyaneshwor, Kathmandu
Name of the School :
Location :
Type of Building : 2 storey 4 classrooms
Abstract of Cost
Rate Amount
Item No. Description of Works Unit Quantity
(NPR) (NPR)
1 EARTH WORKS
1.1 SITE CLEARANCE & MOBILIZATION :
Clearing and grubbing the site for construction by removing
150mm thick top soil including bushes, small trees, leveling of
undulated ground, shorting and stacking/storing selected top soil
for reuse in landscaping works, disposing unsuitable materials sq.m 30.00
from site, etc., all complete as per drawings, specifications and
instructions of the Engineer.

1.2 EARTHWORK IN EXCAVATION :


Excavation in foundations in all type of soils for foundation,
trenches, footing, pits etc. to the required depth including
dewatering by manual or mechanical means etc. as per
specifications with all contractor’s own machinery and
equipment's, providing crossing of track, shoring, strutting,
timbering and buttressing with appropriate materials and all such
measures necessary to retain in position the sides of the cu.m 5.83
foundation pit and including refilling the excavated material with
watering, ramming, leveling the site and disposing off the
surplus/unusable earth to outside the construction premises, etc.
all complete as per drawings, specifications and instructions of
the Engineer.

1.3 EARTH BACK FILLING :


Back filling in foundation and sides of foundation with approved
soil obtained from the excavation at site and stacked at site or
brought from outside in layer not exceeding 15 cm thick
(compacted thickness) including transportation of soil, spreading
in required line and level, sprinkling water, ramming, compacting cu.m 1.75
with mechanical rammers, testing, etc., all complete as per
drawing, specification and instructions of the Engineer.

1.4 BOULDER SOLING


Providing and laying uncoursed hand packed Dry Rubble Stone
soling in foundation, under floor plinth with out any special
dressing of stone including filling interstices with suitable quarry
waste or stone chips or quarry sand, watering, compacting using
appropriate mechanical compaction means with all contractors cu.m 0.68
materials, handling, placing etc. all complete as per drawings,
specifications and instruction of the Engineer. The complete item
including all lead & lift.
Abstract of Cost

Rate Amount
Item No. Description of Works Unit Quantity
(NPR) (NPR)
2 CONCRETE WORKS
2.1 P.C.C (1:3:6) Works
Providing and laying machine mixed Plain Cement Concrete of
nominal mix 1:3:6 (1 cement : 3 sand : 6 coarse aggregate ) for
leveling course in foundations and under floor of building, etc. in
all level with broken stone aggregate of size not more than 25
mm of approved quality including formwork wherever necessary,
dewatering, batching, mixing, transporting, placing, compacting, cu.m 0.34
curing, including all lead and lift, etc. all complete as per
drawings, specifications and the instructions of the Engineer.

2.2 P.C.C. FOR R.C.C. WORKS


Providing and laying in position machine mixed and machine
vibrated cement concrete of mix 1:1.5:3 (1 cement:1.5 sand: 3
coarse aggreagate) M20 grade for reinforced cement concrete
work using approved cement with 20 mm graded machine
crushed stone aggregate of approved quality in various locations
and heights including transportation of concrete to site of placing,
compaction, finished to required line and level, protection and
curing, etc. all complete as per drawings, specifications and the cu.m 2.00
instructions of the Engineer, but excluding the cost of centering,
shuttering, and reinforcement, but including the cost of 2.5%
SILICA Admixture by Weight of Cement all complete as per
drawings, specifications and instructions of the Engineer.

2.3 STEEL REINFORCEMENT


Providing and fixing in position Fe 500 steel reinforcement of
various diameter confirming to relevant IS code in R.C.C. works
including straightening, cutting, bending, binding with 20 SWG
annealed wire for tying the reinforcement bars at each junctions
(binding wire shall not be measured separately) including all
waste and cut pieces, provision for adequate numbers of spacers,
chairs, providing and placing cement mortar (1:1) cover blocks to kg 299.70
keep the bars in intended position at all levels all complete as per
drawings, specifications and instructions of the Engineer.
(Authorized lap length and for the bar length exceeding 10 meter
in length shall be measured for the payment).

2.4 METAL WORKS(TRUSS)


Abstract of Cost

Rate Amount
Item No. Description of Works Unit Quantity
(NPR) (NPR)
2.4.1 Providing and fixing Steel Staircase with post, channel
Beam,purlin,rafters, base plate, Gausate plate,checker plate,
brackets etc., made with required grade mild steel tubes and mild
steel sections of required sizes, including hoisting, fixing in
position with MS bed plates, shoe angles, anchor bolts etc., and
concrete grouting, concreting nut bolts, fabrication, fixing and
treated with two coats of anticorrosive paints all complete as per
drawings, specifications and instructions of the Engineer. Rate
shall include preparing shop drawings, obtaining Engineer's or
Client's approval, supplying, fabricating, delivering at site, k.g 3,925.22
hoisting and fixing in position, temporary staging, preparation of
surface, applying Zinc chromate/Phosphate primer of one coat
before and one coat after erection including two coats of synthetic
enamel paint of approved make and color etc. all complete as per
drawing, specification and instruction of the Engineer.

3 CGI SHEET ROOFING


3.1 Providing & fixing precoated galvanized iron profile Terracota
sheets (size, shape and pitch of corrugation as approved by
Engineer) 0.50 mm +/- 5% total coated thickness (TCT), Zinc
coating 120gsm as per IS: 277 , 5-7 microns epoxy primer on
both side of the sheet and polyester top coat 15-18 microns. Sheet
should have protective guard film of 25 microns minimum to
avoid scratches while transportation and should be supplied in
single length up to 6 meter or as desired by Engineer. The sheet cu.m 29.25
shall be fixed using self drilling /self tapping screws of size (5.5x
55mm) with EPDM seal etc., all complete up to any pitch in
horizontal/ vertical or curved surfaces excluding the cost of
purlins, rafters and trusses and including cutting to size and shape
wherever required.

Total of Civil Works:- -