Sei sulla pagina 1di 5

Executive Engagement: The Role of the Sponsor

Too often, the term “project  Providing feedback on recession and global
sponsor” conjures up the image status reports and making competition have forced
of a disconnected executive sure they reach the everyone to focus only on the
whose main responsibility is to necessary stakeholders top priorities,” says Mike Haran,
secure the project funds and  Championing the project at PMP, PgMP, program manager
then come in for the victory lap the executive level to at businesses services group
when it is all over. But an secure buy-in Experian, Chicago, Illinois,
engaged executive sponsor— USA. “Sponsors are under
with a vested business interest Despite the strategic continuous pressure to
in the project from kickoff to importance of the role, the deliver better results with
close—can mean the difference KPMG survey found that 68 fewer resources. This means
between success and failure. percent of companies do not that an executive’s
always have an effective commitment is even more
Indeed, one of the most sponsor. important now than before.”
common reasons why projects
fall short is a lack of executive In many cases, they are simply
sponsorship and management too busy. “Sponsors typically The Sponsor versus the
buy-in, according to the KPMG have a day job, too—often a Project Manager
New Zealand Project demanding one,” says David
Management Survey 2010.i In West, senior technical director Because the executive sponsor
addition, PMI‟s 2010 at engineering firm WSP, and the project manager will
Government Program London, England. “Not ideally be working closely from
Management Study found that devoting sufficient time to start to finish, both need a clear
81 percent of program the project is a common understanding of their roles.
managers at U.S. government failing.”
agencies said that strong “They must see themselves as
support from at least one But that could be a fatal error. compatible members of a
executive-level sponsor had a project team,” says Dr. Cooke-
high impact on project “The project sponsor has as Davies. “Each needs the other.
success.ii big an influence on the It cannot be the executive
outcome of the project as the sponsors seeing themselves
According to Diego Nei, project project manager,” says Terry as the project manager’s
portfolio manager at CEACRE, Cooke-Davies, PhD, group boss. That way lies ruin.”
a not-for-profit institution in chairman at consultancy
Salvador, Brazil, the sponsor‟s Human Systems International, Dr. Cooke-Davies suggests
key responsibilities include: London, England, and author of sponsors and project managers
Aspects of Complexity: put together an “emotional
 Providing clear direction for Managing Projects in a contract” that covers:
the project and how it links Complex World [PMI, 2011]. The time commitment
with the organization‟s each can expect from the
overall strategy In an increasingly competitive other
 Securing project resources marketplace marked by The frequency and
 Ensuring the project is on economic fluctuations, project nature of reports from the
time, on budget and on sponsors cannot afford to take project manager
scope a hands-off approach. “The
https://t.me/PrMaB
How often they will meet confusion for everyone and platform capacity, and adding
How the sponsor jeopardizes the project.” new escalators and elevators.
expects the project The next stage, which includes
manager to deal with The best sponsors make building the escalators and lifts
problems and when they themselves available to the at the Waverly Steps entrance,
will be escalated to the project manager and encourage is currently in progress and
sponsor communication, whether the scheduled for completion in
news is good or bad. 2012.
Once guidelines are in place, it
is up to the sponsor to walk the “The best rule of thumb is no Although the Scottish
fine line between being a surprises,” Dr. Cooke-Davies government is the primary
vested party and a says. “Talk openly about the investor, several key
micromanager. Dr. Cooke- project risks.” stakeholders could have helped
Davies says sponsors have to or hindered the project. For
be very clear that they are not a example, Mr. West explains,
project manager. “Sponsors The Project: the City of Edinburgh Council
have to let the project was keen to see major
managers manage the project The Organization: WSP, improvements that would
and create the environment London, England enhance the station‟s image as
to allow them to do that.” a “gateway to the city.” The
The Sector: Construction and council also has the power to
Instead of always turning to the Engineering grant planning permissions for
sponsor, project managers various aspects of the project.
should be encouraged to make The ROI: Strong sponsorship
many of the day-to-day calls on brought diverse stakeholders And Network Rail, which owns
their own. “Project managers together to create a project plan the station, was working on a
can‟t spend most of their lives that made business sense for major upgrade of the Edinburgh
providing information to the everyone. signaling center at the same
sponsor so they can make a time. The agency came in with
decision that the project When David West, senior its own plans for a much larger
manager should be making,” he technical director at engineering scheme but lacked the funding
says. firm WSP, came on as a to deliver it.
sponsor for the £132 million
Each person has his or her own project to revamp Edinburgh One of the biggest sticking
part to play. Waverly train station in points was a planned retail
Scotland‟s capital, a full array of deck over the entire station. It
“A sponsor and a project stakeholders was ready to take was an ambitious goal—and
manager have different roles: action. The only problem was completely unaffordable. That
The sponsor authorizes the that each of them had their own meant Mr. West had to find an
project, the project manager vision for how the project would acceptable middle ground. “My
executes the project,” says unfold. sponsorship challenge was
Dennis Creech, director of to develop an affordable
North American professional There was little doubt about the scheme which had sufficient
services and project need. The United Kingdom‟s benefits to be attractive to all
management at Cincom largest train station outside of the stakeholders and which
Systems Inc., Cincinnati, Ohio, London was operating at did not preclude further
USA. “A sponsor who gets maximum capacity during peak development in the future,”
involved in the details of the traveling hours, causing Mr. West says.
daily execution of the project congestion and wear-and-tear
has crossed that line and on facilities. Mr. West first set up a project
makes it difficult for the steering group with
project manager to fulfill their In 2004, the overhaul kicked off. representation from all major
role. More than one person The first part of the project stakeholders. “The steering
running a project causes called for developing longer group was the forum where all
platforms, remodeling stations key stakeholders met and
to take advantage of the new

https://t.me/PrMaB
debated the issues,” he says. a major motivational tool.
“This was where the competing “Teams get really energized if
aspirations were reviewed, The Sponsor As Translator their project is affecting the
analyzed and gradually whittled bottom line of the organization,”
down to the one option that all The role of the sponsor starts at Mr. Brown says. “Lay it on the
stakeholders wanted to see the very origin of the project. line for them, make it personal.
delivered.” Not only do sponsors lead the Tell them why the project is
project through the selection important for them and for you.”
He then created a table stake process until it is formally
setting out the joint objectives, authorized, they also play a At the same time, sponsors
to be signed by each crucial role in the development must act as liaisons to the
stakeholder representative. of the initial scope and charter. organizational stakeholders,
Ultimately, the retail deck was communicating how the project
scrapped, but a 28,000-panel “The first duty of the project will integrate into their
glass roof got the go-ahead. sponsor is to define the overarching strategy and goals,
project,” says WSP‟s Mr. West. Mr. West says. That means
As the owners of the project “The project sponsor identifies ensuring everyone who will
business case and guardians of what the project must achieve be potentially impacted by
the investor‟s interests, project and defines the project that will the project knows what to
sponsors must be the ones to deliver that. This requires a expect. “Since the nature of
secure buy-in from every good understanding of how the projects is to deliver change,
stakeholder. organization operates and of they often affect almost every
the corporate strategy.” department of the organization
“The executive sponsor has in one way or another, and the
to take diverse and often Once the project‟s departments have to be
competing stakeholder organizational goals are prepared if the benefits are to
interests and negotiate a defined, the sponsor must be fully recognized.”
common ground that all translate that vision into clearly
stakeholders can agree on understood deliverables for the As the project progresses,
and collaborate to deliver,” he project manager and team, Mr. sponsors must also relay any
says. “The executive sponsor‟s West says. information requirements,
job is to do this so as to deliver progress reports or warnings
maximum possible value to the But most project sponsors do from the project manager.
investor—and negotiate the not devote enough time
option with the best business explaining how the project The Project:
case.” aligns with the overall strategy,
says James Brown, PMI-SP, The Organization: New
Once the sponsor sorts out PMP, PgMP, senior manager, Balance, St. Louis, Missouri,
each stakeholder‟s desires and research program management USA
demands, he or she must then office at agronomy company
communicate to the project Pioneer Hi-Bred International, The Sector: Consumer Goods
manager what needs to be Des Moines, Iowa, USA.
delivered to meet those goals— The ROI: Strong team
and then let the project And that can create what Mr. alignment and motivation from
manager oversee the details. Haran calls “ambiguity the sponsor helped a team
poisoning”—what the project meet its rigid deadline.
In the end, the renovation manager suffers from when he
project was launched in a much or she cannot clearly At athletic shoe company New
shorter time period, and understand what the executive Balance, the commitment of
remains largely on schedule is asking for. one executive sponsor helped
and under budget. “It illustrates keep an IT project running on
the importance of stakeholder By making the effort to draw a track.
management and finding the clear connection from project to
common ground,” Mr. West strategy, sponsors provide Looking to improve its retail
says. team members with a sense of experience, New Balance
purpose. And that can serve as

https://t.me/PrMaB
launched a project to develop meetings to make sure the storytelling skills to put that
an application for in-store iPads team saw his commitment on a message across,” Dr. Cooke-
that would make product regular basis. Davies says. That may happen
information readily accessible. in a boardroom full of fellow
And because the app launch “It allowed for better executives or, informally, in the
needed to coincide with the communication and organization‟s hallways.
opening of a new retail store, expectations from the beginning
the deadline was unmovable. between myself as the project Another facet of the role is
manager and him as the supporting and motivating the
“It was imperative that the sponsor,” Ms. Janko Prior says. project team through the good
sponsor play a key role,” says “Any time the project times and the bad. Sponsors
Jessica Janko Prior, PMP, manager and the sponsor should not take all of the credit
senior project manager. “The can have enough when things go right and they
project had absolutely no room accessibility to each other, it should not allow the project
to miss these goals. With a tight allows for them to develop a manager and the team to take
timeline and the entire project better working relationship, all of the blame when things go
team being dispersed across one vision and continued wrong.
the country, aligning the team reporting, which leads to
was a challenge.” project success.” “I‟ve had CEOs red in the face
screaming at me and had my
At the kickoff meeting, the The sponsor also played the sponsor brave enough to say,
sponsor began by champion role well, using „Hey wait a minute Mr. CEO,
communicating a clear management discussions to here‟s the problem,‟” Mr. Brown
business case for the project, advocate for the project. “This says. “I tell sponsors to look in
backed by objectives, benefits was a key success factor for the mirror and ask, „How do you
and vision so everyone knew the project, as it showed his want to be viewed by your
their responsibilities. commitment and played a team, your peers, etc. If you
major part in keeping the team can treat the project manager
“As the project plan was excited about the project and its the way you‟d want to be
developed, the sponsor outcome,” she says. treated, you‟ll have teams
continued to play a very clamoring to work for you
involved role to make sure that And when the project came to a again.”
the plan was complete and successful close, the sponsor
detailed, including all of the publicly recognized the team for Sponsors should have
project scope,” Ms. Janko Prior a job well done. consistent interaction with team
says. “Throughout the members, including at project
project, the sponsor was “Overall, the project sponsor meetings. Not only will that help
continually looking at made the project easy for me to sponsors stay on top of the
expectations and making manage due to the fact that he project‟s progress, it will also
sure that they were all being was so involved with the morale demonstrate to the team that
met with the processes the and the accountability of the the organization is invested in
project team was following. If team,” Ms. Janko Prior says. the project.
he felt that key sponsors
needed more information, he Support does not always have
asked that more information be Chief Project Champion to be formal, either. Sometimes
provided. If he felt a team it may mean simply ordering in
member was not fully Perhaps the most important dinner when the team is
participating, he insisted that role for the sponsor is as working late or celebrating
the team adhere to processes project advocate. As such, small milestones along the way.
and provide full participation.” effective sponsors must know
how to convey the project vision “Sponsors want to do what the
The sponsor also made himself to anybody who can influence team needs them to do,” says
accessible to the team the outcome. “They see how Dr. Cooke-Davies. “Sponsors
throughout the project and much better the world will be encourage the project manager
attended all project-related when the project is complete to communicate their worries,
and have developed the

https://t.me/PrMaB
their fears, their successes and micromanagement. The environment and generate a
their hopes.” sponsor and project manager positive buzz for the project’s
also need to agree from the benefits each day,” says Mr.
Summary beginning on their roles to Haran. “They need to
ensure a harmonious and constantly let people know what
Being an effective project productive relationship. the project is and why it‟s
sponsor requires striking a important to the rest of the
delicate balance of involvement Along with supporting the organization.”
and trust in the project team. project manager and team, the
Project sponsors must sponsor must keep the It is an admittedly difficult role,
effectively communicate the organization apprised of the but one that can ultimately
organization’s vision, goals project‟s progress and benefits, ensure the success of a project.
and expectations to the team advocating for it at every turn.
throughout the life cycle “The sponsor should
without crossing the line into cultivate a positive

iKPMG New Zealand Project Management Survey 2010, KPMG. Results based on interviews
conducted in August 2010 with nearly 100 organizations in the country.

Program Management 2010: A study of program management in the U.S. Federal Government,
ii

PMI. Results based on a survey of forty “successful” programs across a variety of U.S.
government agencies, published in June 2010.

https://t.me/PrMaB

Potrebbero piacerti anche