A- SCOPE OF WORK
s/n Description of works total Price
1 mobilization
Supply and installation of false ceiling with channels and panels instead of the
2 damaged ceiling including all the necessary accessories to return it as per pre-fire
condition
Supply and Application of Internal Paint instead for the damaged area and this
3
works includes sanding and stucco emulsion paint
Sanitary and Plumping ;
Pipe 4"
Pipe 3"
Pipe 2"
4 Pipe Clumps
PPR Pipe
Sanitary work
Flue Trip 190000
WC
5 Electrical work ( DB Dressing, Cladding and fire affected wires to be changed )
Supply and replacement of wooden door handle with one door frame replacement
6
B- PRICE
Total price/190,000 one hundred ninety thousand U.A.E Dirhams only
Excluding VAT
C- TERMS OF PAYMENTS :
1- 60 % advance payment
2- 30% progress payment
3- 10% after handing over
D- EXCLUSIONS :
1 Additional repairs that is not affected by fire
2 Electrical and water source by client
E- TIME INTERVAL :
45 Days from site handover