METHOD STATEMENT
P0
FOR
KKS Code
Approved J. C. PARK WOODEN WORK
UMA
Reg. No.
Department Architecture DEPT.
780011
Revision History
INDEX
ARTICLE DESCRIPTION
1.0 PURPOSE
2.0 MATERIAL
5.0 MANPOWER
7.0 SAFETY
1.0 PURPOSE
To Define the Work Methodology to be adopted for Carrying out fixing of wooden
door frame at the Project.
2.0 MATERIAL
14. Remove temporary supports like thresh holds and corner parties’ final setting
of hold fast embedment and curing for 7 days.
15. Vertical members of the door frames shall be embedded in the floor for the full
thickness of the floor finish and shall be suitably strutted and wedged in order to
prevent warping during construction.
16. Architrave should be provided at the junction of plaster surface and wooden
frame.