CHRONOGRAM OF ACTIVITIES

Activities Responsible Duration


st
Rent or Purchase of the land Coordinated by Agronomist Jean Berthony 1 week of June
Fence the land 2nd and 3rd week of June
Preparation of the water well
Preparation of the water storage

Registration of the planters 4th week of June


Purchase of the materials (water pump,
pickaxe, hoe, etc.
Preparation of the land for planting the Month of July
banana tree.
Purchase of the banana tree Beginning of august
Making the garden Middle of august

Budget
Description Unity Quantity Unity price Total cost USD Comm. Partic. Amount Total
USD requested USD USD

Rent of the land Tile of land 1 2352.94 2352.94 - 2352.94 2352.94


Fence of the land Unity 1 300 300 200 100 300
5 Planters1 Month 50 147.05 1470.58 - 1470.58 1470.58
Preparation for the water well
Dig the well Unity 1 2941.17 2941.17 - 2941.17 2941.17
Water pump Unity 1 1000 1000 - 1000 1000
Pipe Unity 1 600 600 - 600 600
Preparation of the water
storage

Purchase of the materials


Pickaxe Unity 5
hoe Unity 5
Plough Unity 5
Spade Unity 5
Recipient Dozen ½ dozen
Preparation of the land for
planting the banana tree.
Tractor Day 1
Fertilizer Sac 5 29.41 147.05 - 147.05 147.05
Purchase of the Unity 2000 0.29 588.23 - 588.23 588.23
banana tree
Transportation of the Truck
banana tree

1
This money that is in the budget for the planters is for paying the planters for the 10 first month of working. After that, the garden will generate enough
money to pay the planters.