Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Tender Document,
VOLUME I: PRE – QUALIFICATION BID AND TECHNICAL DATA-
SHEETS FOR CIVIL, MECHANICAL AND INSTRUMENTATION WORKS
NWRWS&KD
GOVERNMENT OF GUJARAT
NARMADA, WATER RESOURCES, WATER SUPPLY
& KALPSAR DEPARTMENT
Tender Cost
Name of the Work Time limit for the Work
(In Crores)
Sauni Yojna - Phase: II, Link - 2, Package - 4: 676.06 Time Limit 24 months for
Engineering, Procurement and Construction Construction and 10 years
(EPC) Contract for Supplying and laying MS for Operation &
Pipeline of 3000mm dia. (ID) for Length of Maintenance after
MS Twin Pipeline 27.711 Km (Total Length – commissioning
55.422 Km) from Bhimdad at Ch. 0.0 Km to
Kalubhar at Ch. 27.711 Km with all allied
works etc. complete including Operation and
Maintenance of the commissioned project for
10 years
Content
Chapter Title Page
1. Tender Notice 1
4. Project Introduction 12
4.1 Project Introduction _________________________________________________________________ 12
4.2 Description of Link 2 (Limdi Bhogavo II to Raidy) __________________________________________ 12
4.3 The details of 12 (twelve) initial packages which are under execution of SAUNI Yojana are given in
below table: _______________________________________________________________________ 13
4.4 Now, the following Packages are to be taken up. __________________________________________ 14
8. Data Sheet 81
1. Tender Notice
GOVERNMENT OF GUJARAT
NARMADA WATER RESOURCES, WATER SUPPLY AND KALPSAR
DEPARTMENT
Online tender (e-Tendering System) in three cover bid is invited by the Executive Engineer,
Bhavnagar Irrigation Project Division, T-11, Jilla Seva Sadan No. 2, Nilambaug Road, Near S. T.
stand, Bhavnagar-364001 (Gujarat State) for the following work from the prospective bidders
registered with Government of Gujarat / CPWD / Other State Governments.
All the relevant documents; as specified in this bid shall be submitted in prescribed manner.
The physical submission shall be made at the office of Superintending Engineer, Bhavnagar
Irrigation Project Circle, S-2, Jilla Seva Sadan No. 2, Nilambaug Road, Near S. T. stand,
Bhavnagar - 364001 Phone No-0278-2429044 up-to date shown in Table 1.1. Validity period of
E.M.D should not be less than 180 days. Penaltative action for not submitting original FDR
for E.M.D and DD for tender fee by bidder shall be initiated. E.M.D. Exemption certificate is not
allowed. Any documents in support of bid shall be submitted in electronic format only through
online (By Scanning etc.) & hard copy will not be accepted separately. For further details &
online submission of bid, please visit website www.nwr.nprocure.com.
A LAST DATE FOR DOWN LOADING BID Dt: 15/02/2017 up-to 17:00 Hrs.
DOCUMENT
B LAST DATE OF ON LINE SUBMISSION UP-TO Dt: 15/02/2017 up-to 18.00 Hrs.
C LAST DATE FOR PHYSICAL SUBMISSION From Dt: 16/02/2017 to 21/02/2017
OF DOCUMENT (In office hours)
D MODE OF PHYSICAL SUBMISSION RPAD / SPEED POST ONLY
E DATE & PLACE FOR SITE VISIT Site Visit: 20/01/2017 @ 09:00 Hrs.
from Kalubhar Dam
F DATE & PLACE FOR PRE-BID MEETING Pre-Bid: 24/01/2017 @ 12.00 Hrs.
At Committee Hall, Block No. 9,
4th floor, NWRWS & K Department,
Sachivalaya, Gandhinagar.
G DATE OF ONLINE OPENING (Pre- On Dt: 22/02/2017 at 12.00 Hrs. at the
Qualification Bid only) office of The Superintending Engineer,
Bhavnagar Irrigation Project Circle, S-2,
Jilla Seva Sadan No. 2, Nilambaug
Road, Near S. T. stand, Bhavnagar -
364001
Online bids for the above work are invited on EPC contract (turnkey) basis with
single point responsibility by the Executive Engineer, Bhavnagar Irrigation Project
Division, Bhavnagar, from the bidders registered in,
Class “AA” in Narmada, Water Resources, Water Supply and Kalpsar department
and / or Road and Building Department of Gujarat State
CPWD and other State Governments equivalent to class “AA” of Gujarat State Such
Bidder shall have to apply before the date of Submission of bid to get themselves
registered in “AA” class in Government of Gujarat and registered them before the date
of award of contract.
In case of JV, the provisions narrated in the forgoing paras shall be applicable.
a. Work
b. Schedule of E-Tendering
1. Downloading of Tender Documents up to Dt: 15/02/2017 up to 17.00 Hrs.
2. Online submission of PQ bid, Technical bid, Price bid and scanned copies of (1) EMD
(2) Tender fees (3) Other documents: 15/02/2017 up-to 18.00 Hrs.
3. Physical submission of EMD, Tender fees and other documents is From Dt:
16/02/2017 to 21/02/2017 (In office hours) at the office of the Superintending
Engineer, Bhavnagar Irrigation Project Circle, Bhavnagar by RPAD / Speed Post.
4. Opening of Pre-Qualification bids (online) on Dt: 22/02/2017at 12.00 Hrs. at the office
of The Superintending Engineer, Bhavnagar Irrigation Project Circle, S-2, Jilla Seva
Sadan No. 2, Nilambaug Road, Near S. T. stand, Bhavnagar - 364001.
Tender Documents are only available in Electronic Form. Interested Bidders can view
these tender documents online on nwr.nprocure.com. Bidders, who are interested in
bidding in this tender, can download tender documents. Bidder shall pay tender fee in
form of account payee demand draft payable to the Executive Engineer, Bhavnagar
Irrigation Project Division, Bhavnagar drawn on any Nationalized Bank.
The Demand Draft toward Tender Document fees can be submitted along with Earnest
Money Deposit before the due date as specified. This should be as per details given
online and it should be drawn before last date of the uploading of the Tender. The
intending bidders have to submit the following documents along with the EMD. The Bidder
should submit all the forms electronically only.
a) Latest Income Tax Return Certificate, PAN and Income Tax ward where assessed.
b) Current Calendar Year 2017 Solvency Certificate.( Min. Rs. 135.21 Crores)
c) Registration Certificate.
Further details of the work and plans can be available from the Office of the
Executive Engineer, Bhavnagar Irrigation Project Division, T-11, Jilla Seva Sadan
No. 2, Nilambaug Road, Near S. T. stand, Bhavnagar-364001 (Phone No. 0278-
2439803, 2427661).
The bid documents for the work are available only in Electronic format which can
be downloaded free of cost from the internet website www.nwr.nprocure.com
Site visit will be conducted on Date and Place as shown in Table 1.1. Bidders
Interested in participating in bid process are advised to attend site visit and
prepare with queries for Pre-bid meeting before submission of bid. Bidders may
contact for site visit at the Office of the Executive Engineer, Bhavnagar Irrigation
Project Division, T-11, Jilla Seva Sadan No. 2, Nilambaug Road, Near S. T. stand,
Bhavnagar-364001 (Phone No. 0278-2439803, 2427661). Pre bid querries may be
send by email also in soft and hard copy at the email address as below.
eebipdbvn@yahoo.co.in
mmipl_ww@mmipl.in
A Pre-bid meeting is proposed on Date as shown in Table 1.1.
Tenderer shall submit his offer in Electronic format on above mentioned website
up to Date as shown in Table 1.1 after Digitally Signing the same. Offer which is
not Digitally Signed will not be accepted. No offer in physical form will be accepted
and any such offer if received will be out-rightly rejected. Bidder will have to submit
separate account payee DD drawn in favour of Executive Engineer, Bhavnagar
Irrigation Project Division, Bhavnagar, for Tender document fee and EMD drawn in
favour of Executive Engineer, Bhavnagar Irrigation Project Division, Bhavnagar.
Physical submission should be by R.P.A.D. / Speed Post only in the office of the
Superintending Engineer, Bhavnagar Irrigation Project Circle, Bhavnagar.
The Pre-qualification bid will be opened on Date as shown in Table 1.1 on website
www.nwr.nprocure.com as mentioned in Section 2.3(b) above. Intending bidders
or their representatives who wish to participate in online tender opening can log on
to www.nwr.nprocure.com on the due date and time, mark their presence or
participate in online tender opening. Tenderer who wish to remain present at
Office of the Superintending Engineer, Bhavnagar Irrigation Project Circle, S-2,
Jilla Seva Sadan No. 2, Nilambaug Road, Near S. T. stand, Bhavnagar - 364001
Phone No-0278-2429044 at the time of tender opening can do so. Only one
representative of each firm will be allowed to remain present. The Technical bid
and price bid will be opened after Government’s decision on Pre-qualification bid
of tender.
m. Free vendor training camp will be organized every Saturday between 4.00 to 5.00
P.M. at (n) code solution –A Division of GNFC Ltd. Bidders are requested to take
benefit of the same.
n. EMD (FDR and Bank guarantee) and DD of Tender Fee and other documents
shall be submitted by R.P.A.D./Speed post only.
o. Other terms and conditions shall be applied as per terms and condition of the
tender documents within stipulated date and time.
p. The solvency certificate of minimum Rs. 135.21 Crores shall be submitted along
with the tender documents.
q. The documents, which are not uploaded online, but submitted physically (Hard
copy), will not be considered for Pre-qualification.
Executive Engineer
Bhavnagar Irrigation Project Division,
Bhavnagar,
DECLARATION
I / We also declare that the bid duly filled in online and digitally signed and the required Earnest
Money Deposit, Tender Fee and other required documents (scanned copy submitted on line) will
be submitted physically by RPAD / Speed Post only to office of the Superintending Engineer,
Bhavnagar Irrigation Project Circle, Bhavnagar as per the date mentioned in tender notice.
SCHEDULE OF E-TENDERING
Sauni Yojna - Phase: II, Link - 2, Package - 4: Engineering, Procurement and Construction (EPC)
Contract for Supplying and laying MS Pipeline of 3000mm dia. (ID) for Length of MS Twin
Pipeline 27.711 Km (Total Length – 55.422 Km) from Bhimdad at Ch. 0.0 Km to Kalubhar at Ch.
27.711 Km with all allied works etc. complete including Operation and Maintenance of the
commissioned project for 10 years.
Division: Executive Engineer, Bhavnagar Irrigation Project Division, T-11, Jilla Seva Sadan
No. 2, Nilambaug Road, Near S. T. stand, Bhavnagar-364001,
1.0 Name of Work Sauni Yojna - Phase: II, Link - 2, Package - 4: Engineering,
Procurement and Construction (EPC) Contract for Supplying
and laying MS Pipeline of 3000mm dia. (ID) for Length of MS
Twin Pipeline 27.711 Km (Total Length – 55.422 Km) from
Bhimdad at Ch. 0.0 Km to Kalubhar at Ch. 27.711 Km with all
allied works etc. complete including Operation and
Maintenance of the commissioned project for 10 years
2.0 Name of Employer Narmada Water Resources, Water Supply & Kalpsar
Department
3.0 Name of Concerned Chief Chief Engineer (Sau.) & Additional Secretary
Engineer
Address Narmada Water Resources, Water Supply and Kalpsar
Department, Block No. 9, 2nd floor, Sachivalaya, Gandhinagar.
Telephone No. 079 – 23251712
Fax No. 079 - 23251713
4.0 Name of Concerned Superintending Engineer, Bhavnagar Irrigation Project Circle
Superintending Engineer
Address Bhavnagar Irrigation Project Circle, S-2, Jilla Seva Sadan No.
2, Nilambaug Road, Near S. T. stand, Bhavnagar - 364001
Telephone No. 0278 - 2429044
Fax No. 0278 - 2429194
5.0 Name of Concerned Executive Engineer, Bhavnagar Irrigation Project Division
Executive Engineer
Address Bhavnagar Irrigation Project Division, T-11, Jilla Seva Sadan
No. 2, Nilambaug Road, Near S. T. stand, Bhavnagar – 364001
Telephone No. 0278 – 2439803
Fax No. 0278 – 2437661
6.0 Time allowed for completion 24 Months (excluding O & M period of 10 years).
of the work from the date of
written order to commence.
7.0 Amount of Earnest Money Rs. 676.06 Lakhs (Rs. 50,000/- in form of FDR / NSC +
Deposit (EMD) As specified remaining amount of Rs. 675.56 lakhs in form of Either FDR /
in bid. NSC or in form of Bank Guarantee from Nationalized
Bank/Scheduled Bank
8.0 Mode of submission of Bid
documents
Prequalification bid, Online submission on www.nwr.nprocure.com.
Technical Bid and Price Bid
along with scanned copy of
EMD, Tender Fee, Solvency
certificate, Registration
Certificate and Joint Venture
Agreement and Other
4. Project Introduction
Gujarat State is a water scarce state and has vast variation in rainfall in its own regions;
several parts of the State face floods during monsoon, at the same time several parts are
drought affected. The Saurashtra region is scarce in its water resources thereby affecting
its overall development.
The Gujarat Government has decided to augment various reservoirs of Saurashtra region
by construction of pipe line / feeder canals. The entire project is named as “Saurashtra
Narmada Avtran Irrigation Yojana (SAUNI Yojana)”. The entire works have been planned
to be executed in different links, in phased manner. The project is to be executed in the
four numbers of different links. These are named as:
In this Particular tender, part scope of Sauni Yojana Phase-II Link - 2, Package - 4 is
covered, which is defined briefly in below section.
The works to lift water from Limdi Bhogavo II reservoir and convey through twin pipelines
under the scope of work. The lifted water from Limdi Bhogavo II reservoir shall be
delivered the junction point at chainage 14 km. Such water received will be further
conveyed through system of pipeline and pumping station(s) to augment the reservoirs
listed in above table.
Now in this proposed package twin pipeline from Bhimdad reservoir to Kalubhar reservoir
is to be taken up. The length of the twin pipeline is 27.711 Km. The pipeline for Malpara
Branch is also included in this package.
4.3 The details of 12 (twelve) initial packages which are under execution of SAUNI
Yojana are given in below table:
Length in Approx.
Sr. No. Description of Packages
Km. Amount
1 Machhu II Dam to Ch. 15.3 km 15.00 435.24
Length in Approx.
Sr. No. Description of Packages
Km. Amount
Length in Approx.
Sr. No. Description of Packages
Km. Amount
Length in Approx.
Sr. No. Description of Packages
Km. Amount
Recently the tender for Link – 3, Machhu – I Chainage 66.295 km. to 97.295 km. (Aji-I
reservoir ) is awarded.
Length in Approx.
Package No. Description of Packages
Km. Amount
Length in Approx.
Sr. No. Description of Packages
Km. Amount
IV Bhimnad to Kalubhar Ch. 27.711 km (Twin Pipeline) 59.668 676.06
Kalubhar Ch. 27.711 km to MPS-1 Ch. 42.621 Km.
V 29.82 355.76
(Twin Pipeline)
MPS-1 Ch. 42.621 Km. to Setrunji Ch. 73.933 km.
VI 65.791 662.92
(Twin Pipeline)
Length in Approx.
Sr. No. Description of Packages
Km. Amount
Length in Approx.
Sr. No. Description of Packages
Km. Amount
MPS-1 (Ankadia) to MPS-2 Ch. 15.340 (Twin
IV 48.756 471.38
Pipeline)
V MPS-2 Ch. 15.340 to MPS-3 Ch. 59.98 km. 44.640 543.77
V-A MPS-2 to Bhadar Karmal Link Ch. 43.321 km. 44.911 369.74
5.3 Definitions
In this document the following words and expressions have the meaning hereby assigned
to them.
5.3.1 Bidder
Means individual, proprietary firm, firm in partnership, Limited Company, Corporation or
group of firms (not exceeding three) forming a joint venture, applying to become eligible to
tender.
5.3.3 E-Tender
Tender in which you can participate online by means of login on to the respective website
is E-Tender.
5.3.4 Online
Any activity that is done on website is referred as ‘Online’ activity for e.g., Submission of
Price Bid online would mean that the Price Bid has to be submitted on website.
5.3.5 Offline
Any activity that is done in conventional route is referred as ‘Offline’ activity for e.g.,
Submission of Earnest Money Deposit in Offline fashion would mean the Earnest Money
Deposit is to be Submitted in the Form of FDR/Bank Guarantee and is to be physically
sent to the Office of the Superintending Engineer concerned.
5.3.7 System
Means the computer which hosts the website (www.nwr.nprocure.com) where Bidder can
participate in the bidding.
5.3.8 Upload
The process of transferring electronic document from Bidder’s computer using internet
connection to the website is called uploading.
5.4 Invitation
Online Tenders on EPC basis with single point responsibility are invited
publically by the Executive Engineer, Bhavnagar Irrigation Project Division, T-11,
Jilla Seva Sadan No. 2, Nilambaug Road, Near S. T. stand, Bhavnagar, Gujarat State
from the bidders registered in “AA” in R&B Department or NWRWS&K Dept. and
equivalent class in CPWD / Railway / other State Government for the work of Sauni
Yojna - Phase: II, Link - 2, Package - 4: Engineering, Procurement and Construction
(EPC) Contract for Supplying and laying MS Pipeline of 3000mm dia. (ID) for Length of
MS Twin Pipeline 27.711 Km (Total Length – 55.422 Km) from Bhimdad at Ch. 0.0 Km to
Kalubhar at Ch. 27.711 Km with all allied works etc. complete including Operation and
Maintenance of the commissioned project for 10 years.
1. The concerned bidder shall submit the certificate of registration with the R & B
Department or NWRWS&K Department of Gujarat along with the bid, as specified.
2. The contractor registered outside Gujarat shall apply for getting registered himself in “AA”
class in the state of Government of Gujarat before the last date of online submission of
bid. The proof of the application for the registration shall have to be attached with the
tender & the tenderer shall get registered themselves on or before the date of award of
contract.
3. The contractor registered in CPWD / Railway and other State Govt. equivalent to class of
Gujarat mentioned in “AA”, they will be eligible to quote for the bid with the condition that
he / they shall apply for getting registered himself in “AA” class in the Gujarat state before
the last date of online submission of the bid. The proof of the application for the
registration shall have to be attached with the tender & the tenderer shall get registered
themselves on or before the date of award of contract.
4. Failure of taking action specified in above Paras, the concerned bidder shall be
disqualified and earnest money deposit shall be forfeited.
fixed by department or C.D.O. Gandhinagar and same shall be got approved from
department.
2. The major components of the project covered under this tender package comprises of
survey, investigations, design, procurement, erection/installation and construction of
RCC Sump, pump house with pumping machinery and electrical work, procure & laying of
pipeline with associated civil, mechanical, electrical and instrumentation works etc.
3. The work of this pipeline is to be executed on the land acquired under “Right of Use”
permission. The minimum width of ROU shall be considered as table shown below as per
site requirement.
The payment of standing crops, compensation of wells, bores, buildings, properties, any
of such requirements for work for the right of use permission to farmer / other affected
persons / owners, NOC and other miscellaneous charges shall be borne by the contractor
for the entire period of the contract. The contractor shall have to take enough precaution
to see that no adjacent/ surrounding land is damaged/ obstructed/ encroached by them
during the execution. Any such dispute / litigation if arise shall be the responsibility of the
contractor. However bidder/contractor shall note that ROU notification shall be issued by
the Department and land cost for getting ROU for laying pipeline shall be paid by the
department as per Government rules and regulations.
a. The contractor shall be responsible for acquiring necessary permission from the
competent authority for Road/ Railway / Highway / canal crossing / gas / oil / water
pipeline / crossings, forest clearance, any electrical cable line crossing,
Telecommunications etc. during laying of pipeline at his own cost and risk. However,
only the correspondence with concerned department shall be facilitated by the
department. All the statutory charges and other charges such as fees, insurance,
miscellaneous charges / expenditure etc., charges for occurrence of any damages,
NOC etc. for laying of pipeline below all the above mentioned crossings are to be paid
by the contractor. Also, the bidder shall refer the Clause 22 and Clause 80 of Vol II
Conditions of Contract. TPI inspection charges shall be borne by the government
during construction period.
b. However, the concerned department insists to pay such statutory charges through the
department / owner, such charges shall be paid by the department / owner and such
amounts shall be adjusted / recovered from the contractor’s bills. If any deposit which
is reimbursable only after the construction period and completion of Operation &
Maintenance of 10 years shall be paid by the department / owner.
c. All necessary persuasion is to be done by the contractor for getting/ obtaining
clearances/ permissions. On satisfactory completion of the work, required NOC is to
be obtained by the contractor from the concerned department. The contractor is
responsible for obtaining all necessary permissions / clearance / NOC / sanctions etc.
Required coordination for sanction from the concerned authority and NOC from the
concerned authority / field owner for satisfactory completion shall be provided by the
contractor.
d. Right of Way (ROW) and Facilities: The contractor shall bear all costs and charges for
special and / or temporary Rights-Of-Way (ROW), which he may require, including
those for access to the site. The contractor shall also obtain, at his risk and cost, any
additional facilities outside the site which he may require for the purposes of the
works.
e. Avoidance of Interference: The contractor shall not interfere unnecessarily or
improperly with:
i. The convenience of the public, or
ii. The access to and use and occupation of all roads and footpaths, irrespective of
whether they are public or in the possession of the employer or of others.
f. The contractor shall indemnify and hold the employer harmless against and from as
damages, losses and expenses (including legal fees and expenses) resulting from any
such unnecessary or improper interference.
i. Access Route: The contractor shall be deemed to have been satisfied as to the
suitability and availability of access routes to the site. The contractor shall use
reasonable efforts to prevent any road or bridge from being damage by the
contractor’s traffic or by the contractor’s personnel. These efforts shall include the
proper use of appropriate vehicles and routes. Except as otherwise stated in these
conditions:
ii. the contractor shall (as between the Parties) be responsible for any maintenance
which may be required for his use of access routes;
iii. The contractor shall provide all necessary signs or directions along access routes,
and shall obtain any permission which may be required from the relevant authorities
for his use of routes, signs and directions.
iv. the employer shall not be responsible for any claims which may arise from the use or
otherwise of any access route;
v. the employer does not guarantee the suitability or availability of particular access
routes, and Costs due to non-suitability or non-availability, for the site required by the
contractor, of access routes shall be borne by the contractor.
4. Subsequent to the commissioning of the project, the bidders will have to operate and
maintain the system for 10 years satisfactorily before handing over.
5.9 Deleted
5.10 Communication
5.10.1 Airports
Mumbai, Delhi, Ahmedabad, Rajkot & Bhavnagar are Airports nearby the site.
Bhavnagar is the airport in Gujarat, which is the nearest airport from the work site.
5.10.2 Railways
5.10.3 Roads
The above road gives access to the work site. If no direct access by public road is
available, contractor has to make his own arrangement for approaching the site.
At Bhavnagar, Private Hotels and Government Circuit house houses are available.
The Govt. Circuit houses are also available at Umarala.
5.11.2 Housing
The department has not envisaged providing for any housing colonies for bidders.
The bidder, therefore, has to make his own arrangements for housing of his
staff and labourers.
Marketing facilities for day to day needs are generally available at Umarala, Sihor
and Bhavnagar.
The contractor will have to make his own arrangement for water supply for
construction as well as for colonies or camps, which may be established by him.
Wells of farmers exist in nearby area. Suitability for domestic and constructional
use may have to be established in advance.
The bidder shall have to arrange from the Pashchim Gujarat Vij Company Ltd. for
his power requirements for construction purpose. All charges for the use of power
including its maintenance shall be borne by the contractor and paid directly to the
concerned authorities during construction stage. He shall comply with all the
requirements for purchase and use of electric power. During the Hydro-Testing,
commissioning and O & M of 10 years power charges for running of the system
will be paid by the Government / Department.
Telephone services are available for public use at Bhavnagar. Post offices are also
available at the above place. Almost every village is covered by postal services.
Petrol and Diesel pumps are installed by private agencies near Bhavnagar. The
bidder shall have to make his own arrangements for procuring the fuel required by
him.
5.12.1 Temperature
Gujarat State has tropical climate. The daily minimum temperature ranges from 5
Degree Celsius in December - January to 27 Degree Celsius in April-May. The
daily maximum temperature varies from 30 Degree Celsius in December - January
to 45 degree Celsius in April-May.
5.12.2 Rainfall
Average annual rainfall ranges from less than 500 mm in the North west region to
over 2000 mm in the South, with most part of the state receiving 500 to 800 mm of
rainfall. About 95% of rainfall occurs during the months June to September leaving
remaining period of the year almost dry.
Since rainfall is confined mainly to the period starting from middle of June to the
end of September, It may be necessary to close the work of concrete during the
monsoon. However, the work of earthwork and pipeline work can be continued in
dry spells during the monsoon.
specified additional period. The request and the bidder’s responses shall be made in
writing. A bidder may refuse the request without forfeiting his bid security. The Bid
Security amount of the bidders, who do not wish to extend the validity beyond the
previously specified period, shall be returned to the bidder within one month without
any interest. A bidder agreeing to the request shall not be required or permitted to
modify his bid, but shall be required to extend the validity of his Bid Security for the
period of the extension.
2. If the tender is uploaded by a proprietary firm, it shall be digitally signed by the proprietor.
3. If the tender is uploaded by a firm in partnership, it shall be digitally signed by all the
partners of the firms or alternatively by a partner holding power of attorney for the firm in
which case a certified copy of the power of attorney shall accompany the tender, a
certified copy of the partnership deed, full name, current address of the firm, current
addresses of all the partners of the firm shall also accompany the bid.
4. If the tender is uploaded by a limited company or a corporation, it shall be digitally signed
by a duly authorized person holding the power of attorney for signing the bid in which
case a certified copy of the power of attorney shall accompany the tender. Such limited
company or corporation may be required to furnish satisfactory evidence of its existence
before the contract is awarded. They should also furnish copy of Certificate of
Incorporation and Articles of Memorandum of Association.
5. Each bidder shall submit only one bid for the particular work. A bidder who submits more
than one bid in the particular work will be disqualified
6. The Joint Venture is allowed as per 6.4.3 of Section III; in case of Joint Venture, tender
shall be uploaded by the lead partner and it shall be digitally signed by the lead partner.
The Earnest Money deposit shall be drawn in favour of the Executive Engineer,
Bhavnagar Irrigation Project Division, Bhavnagar and shall be in the form of:
a. Total EMD must be Rs. 676.06 Lakhs. Of this total EMD, Rs.50,000/- fixed
deposit receipt or deposit at call receipt and the balance amount of Rs. 675.56
lakhs in form of Bank Guarantee of any Nationalized Bank or Scheduled Bank
with a validity period of not less than 6 months (180 days).
Or
b. Fixed deposit receipt / deposit at call receipt amounting to Rs. 676.06 Lakhs
from any Nationalized Bank or Scheduled Bank with a validity period of not less
than 6 months (180 days).
4. The Earnest Money Deposit shall be submitted along with bid fee and other required
documents mentioned in tender notice to the Superintending Engineer, Bhavnagar
Irrigation Project Circle, Bhavnagar only. It shall be valid for a period of not less than One
Hundred Eighty (180) days. However, if the last date of receipt of bid is extended, and if
the bidder has drawn out the FDR/BG for EMD, the bidder shall have to furnish the
FDR/BG duly renewed and extended for the period of 180 days counted as per latest
extension.(i.e. The validity of FDR for EMD shall be for 180 days from the date as per
latest extension). The same shall be extended by the bidder for a further period of ninety
days if required by department. Tender without submission of Earnest Money Deposit
shall be rejected as non-responsive.
5. If during Tender validity period, the tenderer withdraws his bid, the Earnest Money
Deposit shall be forfeited and the tenderer may be disqualified from bidding for further
works.
7. Within ten days from the date of issue of the letter accepting his price bid, the successful
tenderer shall furnish the required security for performance and plus additional security, if
required for unbalanced bids in accordance with the conditions of the contract and attend
the office of the Engineer-In-Charge for execution of the Contract document. If the
contractor does not turn up to pay security deposit and execute contract agreement within
specified (or extended) time after intimation to him about acceptance of his offer, the
earnest money paid for this work will be forfeited and tenderers tender shall be rejected
and then according to aforesaid provision of the tender, action to suspend registration of
contractor will be intimated without delay
a. A Bidder:
i. Withdraws his bid during bid- validity period specified.
b. A Successful bidder fails
i. To furnish security deposit in accordance with relevant clause in the bid.
ii. To Sign the contract within time limit specified in the bid.
9. In case of forfeiture of E.M.D., bidder shall be disqualified and shall not be allowed to bid
for further work under department for period of three years.
The bidder shall have to upload following legible documents duly digitally signed:
i. Scanned copy of the latest Income Tax return with permanent account number
(PAN) and Income Tax ward where assessed.
ii. Scanned Copies of notarised client certificates as regards previous experience,
if any (preferably in Form G)
iii. Declaration showing the details of all works completed in prescribed form
Annexure – IV (Duly Notarized).
iv. Declaration showing the details of works on hand with the contractor showing
the balance value of works that remain to be executed in each case in
prescribed form Annexure – V required for evaluation of the bidder (Duly
Notarized).
In case of forfeiture of E.M.D., bidder shall be disqualified and shall not be allowed
to bid for further work under department for period of three years
i. The designated officer of department will open the e-Tender Pre-Qualification Bid on
Date as shown in Table 1.1 on web site www.nwr.nprocure.com in the office of the
Superintending Engineer, Bhavnagar Irrigation Project Circle, Bhavnagar. The
intending bidder/s or his/their representative, if he/they wish, can participate in the
process of Online Bid Opening. Bidder can log on to www.nwr.nprocure.com on due
date and time and mark their presence or participate in online bid opening in the
department offices and view the results. To participate in Online Bid Opening Event, a
Multi Mantech International Pvt. Ltd.
28
SAUNI Yojana - Phase: II, Link - 2, Package - 4
Bidder will have to login with his User ID and password, and click on “mark my
attendance button” to view tender results.
ii. Bidder may depute one authorized person to remain present at the time of
opening of E-Tender. Based on the information furnished by the bidder in the E-
Tender Pre-Qualification bid, the physical and financial capabilities of the bidder shall
be evaluated with reference to the criteria fixed for the purpose of pre-qualification.
Earnest Money Deposit of unqualified bidder shall be released.
iii. Department reserves the right to accept or reject any of the application for
qualification without assigning any reason thereof.
iv. All the bidders who have paid EMD & tender fee, submitted registration
certificate, current calendar year 2017 solvency certificate, the pre-qualification bid of
such bidders only will be opened. After opening of the same, pre-qualification
evaluation of the same will be carried out & the technical bid of only pre-qualified
bidders will be opened after getting clearance from the competent authority of the
department.
v. The technical bid will be opened on suitable time by the competent tender opening
authority in the presence of bidders who wish may remain present. The technical bid
shall be evaluated and wanting details, if any, and clarification in respect of conditions
if any will be called from the tenderers. In such case, the bidder will be required to
submit clarifications/details (including with respect to conditions, if any) within the
stipulated time allowed for the purpose. If the bidder does not furnish the wanting
details/clarifications in times his tender would be liable for rejection.
The condition specified in technical bid should in-variably be accompanied by proper
financial evaluation with mode of calculation specifying assumptions, quantities, rate and
ceiling amounts for each condition and shall also accompany the information in the form
as per Volume III (F)
Ceiling amount shall be binding on the bidders and are liable to be added to the tender
amount.
The evaluation as given by the bidder as modified tender opening authority with the
ceiling limit will then be intimated to all the bidders. No further opportunity shall be given to
the bidders to modify/withdraw conditions at that stage. After completion of evaluation of
the technical bid in all respects the competent authority will decide about date of opening
of price bid and the same will be intimated to the qualified bidders. After opening of price
bid and their evaluation the tender inviting authority reserves the right to negotiate about
the tender (s) further with any or all the bidders
financial implication of technical bid, if any, shall be considered for evaluation & for final
acceptance of the bid as a lump sum price for the whole work.
It should be clearly understood that no foreign exchange sanctions will be made available
either for purpose of equipment, plants, machineries, materials of any kind or other things
required for execution of work.
v. Such Bidder, or any of its Joint Venture Member thereof has participated
as a consultant to the Authority in the preparation of any documents,
design or technical specifications of the Project.
A Bidder shall be liable for disqualification and forfeiture of BID Security, if any legal,
financial or technical adviser of the Authority in relation to the Project is engaged by the
Bidder or its Member or any Associate thereof, as the case may be, in any manner for
matters related to or incidental to such Project during the Bidding Process or subsequent
to the (i) issue of the Letter of Award or (ii) execution of the Agreement. In the event any
such adviser is engaged by the selected Bidder or Contractor, as the case may be, after
issue of the Letter of Award or execution of the Agreement for matters related or
incidental to the project, then notwithstanding anything to the contrary contained herein or
in the Letter of Award or the Agreement and without Prejudice to any other right or
remedy or the Authority, including the forfeiture and appropriation of the BID Security or
Performance Security, as the case may be, which the Authority may have there under or
otherwise, the Letter of Award or the Agreement, as the case may be, shall be liable to be
terminated without the Authority being liable in any manner whatsoever to the Selected
Bidder or Contractor for the same. For the avoidance or doubt, this disqualification shall
not apply where such adviser was engaged by the Bidder or its Member or Associate in
the past, but, its assignment expired (or) was terminated 6 (six) months prior to the date of
issue of this invitation nor will this disqualification apply where such adviser is engaged
after a period of 3 (three) years from the date of commercial operation of the Project
For the purposes of this Clause, the following terms shall have the meaning hereinafter
respectively assigned to them:
a. “corrupt practice” means (i) the offering, giving, receiving, or soliciting, directly or
indirectly, of anything of value to influence the actions of any person connected with
the Bidding Process (for avoidance of doubt, offering of employment to or employing
or engaging in any manner whatsoever, directly or indirectly, any official of the
Employer who is or has been associated in any manner, directly or indirectly, with the
Bidding Process or the Letter of Award or has dealt with matters concerning the
Agreement or arising there from, before or after the execution thereof, at any time
prior to the expiry of one year from the date such official resigns or retires from or
otherwise ceases to be in the service of the Employer, shall be deemed to constitute
influencing the actions of a person connected with the Bidding Process); or (ii) save
and except as permitted under this document, engaging in any manner whatsoever,
whether during the Bidding Process or after the issue of the Letter of Award or after
the execution of the Agreement, as the case may be, any person in respect of any
matter relating to the Project or the Letter of Award or the Contract Agreement, who
at any time has been or is a legal, financial or technical adviser of the Employer in
relation to any matter concerning the Project;
d. “undesirable practice” means (i) establishing contact with any person connected
with or employed or engaged by the Employer with the objective of canvassing,
lobbying or in any manner influencing or attempting to influence the Bidding Process;
or (ii) having a Conflict of Interest; and
6.1 General
The bidders should furnish all the information requested for in the downloaded forms duly
filling all the columns in the forms with relevant data in electronic formats. If information is
nil, the same should be mentioned as “Nil” or as “No”. If any particular query is not
applicable in case of the applicant, it should be stated as not applicable. However, the
bidders are cautioned that not giving complete information called for in the bid documents
in the form required or not giving it in clear terms or making any change in the
prescribed forms may result in the bidder being summarily disqualified.
1. The bidder’s name shall appear on each page of the prescribed Performa.
2. References, information and certificates from the respective clients certifying
suitability, technical know-how or capability of the bidder shall be signed by that
client, in full with his name in block letter and designation in that organization.
3. No further information will be entertained after submission of bid document unless it is
called for by the Government. Further clarification on only submitted details shall be
asked by the Govt. if required.
4. Any effort by a bidder to influence the Government in the process of examination,
clarification, evaluation of bid and in decision concerning qualification, may result in
disqualification of the bidder.
5. The qualification made for any other work of Government will not be considered valid
for the present work. The intending bidder shall have to apply afresh to get qualified
for this work.
6. The time for substantial completion of work is 24 Months (Twenty Four) (excluding
O & M period of 10 years)
the deployment of heavy construction equipment for the type of work described
earlier.
c. The tenderer must have adequate staff and equipment for carrying out work
in accordance with time schedule.
d. The bidder must have a Project Manager with not less than 15 (Fifteen) years’
experience in managing construction in the field of Civil Engineering works, of
similar nature along with engineering, technical and other key personal with
adequate experience in civil engineering work.
e. The tenderer must provide evidence of having adequate experience. The bidder
should upload the digitally signed scanned copies of supporting certificates, reports
relating to physical, financial, technical, machinery and other capability of the
applicants in their original language along with certified translation of all relevant
portion of the certificates / reports in English duly attached with their Digital
Signature. The applicant should upload the financial capabilities in Rupees only.
f. The tenderer are required to upload digitally signed scanned copies along with their
applications certificates obtained from the concerned authorities/ employers towards
proof.
To qualify, each bidder in the same name and style should have achieved the
following performances :
6.4.1.1 Turnover
Bidder must have achieved minimum annual financial turnover (at 2016-2017 Price
level) from contract receipt of works (in all classes of Civil Engineering construction
works only) of Rs 338.03 Crores in any one year of last SEVEN (7) financial years i.e.
from 2009-2010 to 2015-2016. Details shall be submitted in form - E.
The bidder must have completed similar nature of work in only single work in EPC
contract (of Government / Semi Government Works Only) for a Lift Irrigation or Water
Supply Project or Petroleum pipeline project with a minimum value of work Rs. 405.64
Crores for the conveyance of fluid with Pipeline works with supply, procurement &
construction within last SEVEN (7) financial years i.e. from 2009-2010 to 2015-16. It is
mandatory to furnish the details in Form - G and Statement - S2.
Turnover and cost of similar nature work of previous year shall be given additional
weightage of ten Percent per year to bring them to 2016-2017 price level to account for
price escalation as illustrated below:
Year Annual Turnover Effective Annual Turnover / Cost of work
/ Cost of Work at 2016-17 Price Level
2009-2010 A 1.95 x A
2010-2011 B 1.77 x B
2011-2012 C 1.61 x C
2012-2013 D 1.46 x D
2013-2014 E 1.33 x E
Note:
1) The amount of turnover / cost of work shall also include the cost of material
supplied, if any by the owner / Govt.
2) Financial year means period beginning from the 1st April to 31st March of the next
year.
3) The bidder who have applied for Corporate debt restricting (CDR) / facing
recovery proceedings from financial institutions / facing winding up proceedings /
those under BIFR in the last 7 financial years (2009-10 and 2015-16) shall be
considered for bid qualification, provided bidder has to submit bank authority letter
regarding restructuring process by bankers. In case of Joint Venture agreement,
this shall be applicable for both Lead partner and JV partner. Bidder shall have to
declare regarding tenders submitted in the prescribed format.
6.4.2.1 Pipeline
Procure and laying minimum 1800 mm Diameter (ID) of Mild Steel pipeline of minimum
length 22,570 Meter respectively in any one year of last SEVEN financial years (i.e. from
2009-2010 to 2015-16). It is mandatory to furnish the details in Statement S-1(a).
And
The bidder shall have successfully completed of operation & maintenance (minimum 2
years after commissioning) of work of Lift Irrigation Pipeline Project or water supply
pipeline with pumping station or petroleum pipeline project during last SEVEN (7)
financial years (i.e. from 2009-2010 to 2015-16) for a Single project having value of Rs.
202.82 Crores at 2016-17 price level. Additional weightage of 10 % will be given as per
Clause 6.4.1 above. It is mandatory to furnish the details in Statement S-1(b).
6.4.3 To fulfil the above criteria, the bidder shall note the following:
The bidder who satisfies all criteria mentioned above shall be considered qualified for
further evaluation.
Maintenance).
c. Experience of Operation and Maintenance prescribed in 6.4.2.2 shall be satisfied by
either Lead partner or Joint Venture partners.
Note : In case, if the bidder/JV partner has performed the similar nature of work or
pipeline as mentioned above in past, in joint venture with other Contractor(other than
present JV partner), the portion of the work (physically and financially) of the
contractor included in their original EPC contract work shall only be considered for
evaluation purpose.
The lead member and JV partner shall have “AA” class registration with Government
of Gujarat. In case of CPWD/ Railway and other State Governments registration
equivalent to class “AA” of Gujarat State having the above stated criteria, such bidder
shall have to apply on or before the last date of Submission of registration documents
to get himself registered in “AA” class in Government of Gujarat (R & B Department
and NWRWS&K Department) and obtain registration in AA class before the date of
finalization of regular tender procedure of particular work. The proof of application for
Registration in AA class shall have to be attached with the registration documents.
a. In case of the joint venture with foreign party, the experience of foreign party in India
only will be considered for qualification.
b. The individual members who join in JV shall have to give an undertaking that they will
maintain status-quo till the completion of work. This undertaking shall be submitted on
their letter head duly signed by authorized signatory.
c. The power of attorney shall be assigned to any authorized person of lead member and
authorization for assigning power of attorney shall be given jointly by the lead as well as
joint venture members.
d. The lead partner in charge shall be authorized to incur liabilities and receive instructions
for and on behalf of any partners of the joint venture and the entire execution of the
contract including payment.
e. All members of the joint venture shall be liable jointly and severally for the execution of
the contract in accordance with the contract terms and a relevant statement to this effect
shall be included in the authorization mentioned above as well as in the form of tender
and the form of agreement (in case of a successful bid).
f. An original notarized copy of the agreement as prescribed in Annexure-II entered into by
the joint venture partners shall be submitted with the bid. It should also distinctly show
the financial participation of each member of the joint venture and the responsibility of
each member as regards planning and execution of the work.
g. In case of conflict between the terms in contract agreement and the joint venture
documents, the terms in the contract agreement shall prevail.
h. All joint venture agreements should inter-alia include a provision to the effect that all
partners in the joint venture shall be jointly and severally liable to complete the work.
Project Manager should be graduate in Civil Engineering and should have at least fifteen
years of construction experience and ten years of similar nature work experience and
capacity to organize works of sizeable magnitudes, preferably of nature of construction
of large diameter Pipeline project including Pumping Station, Earthen dam, R.C.C. weir,
bridge, aqueduct, siphon training wall, Head regulator and spillway bridge and other
such hydraulic structure and building works. History of experience of the Engineer with
Multi Mantech International Pvt. Ltd.
38
SAUNI Yojana - Phase: II, Link - 2, Package - 4
regard to works he has handled for the firm or before with duration magnitude etc. be
briefly mentioned. Where the firm has several personnel and No. of works, the
particulars are mainly required for whoever is due to be in-charge of this work and
specific mention of this purpose be made. Mention of other is stated as additional
services available to credit of firm. Bio-data of all Site Engineers as per attached form
should be submitted.
Quality Control Engineer should be graduate in Civil Engineering and should have at
least ten years of quality control experience of similar nature work and capacity to
organize quality control of sizeable magnitudes, preferably of nature of construction of
large diameter Pipeline project including Pumping Station, Earthen dam, R.C.C. weir,
bridge, aqueduct, siphon training wall, Head regulator and spillway bridge and other
such hydraulic structure and building works. History of experience of the Engineer with
regard to works he has handled for the firm or before with duration magnitude etc. be
briefly mentioned. Where the firm has several personnel and No. of works, the
particulars are mainly required for whoever is due to be in-charge of this work and
specific mention of this purpose be made. Mention of other is stated as additional
services available to credit of firm. Bio-data of all Site Engineers as per attached form
should be submitted.
Site Engineer should be graduate in Civil Engineering and should have at least three
years of experience of similar nature work and capacity to organize works of sizeable
magnitudes, preferably of nature of construction of Earthen dam, R.C.C. weir, bridge,
aqueduct, siphon training wall, Head regulator and spillway bridge and other such
hydraulic structure and building works. History of experience of the Engineer with regard
to works he has handled for the firm or before with duration magnitude etc. be briefly
mentioned. Where the firm has several personnel and No. of works, the particulars are
mainly required for whoever is due to be in-charge of this work and specific mention of
this purpose be made. Mention of other is stated as additional services available to
credit of firm. Bio-data of all Site Engineers as per attached form should be submitted.
Site Engineer should be graduate in Mechanical Engineering and should have at least
three years’ experience of similar nature work and capacity to organize works of sizeable
magnitudes, preferably of nature of providing & erecting Pumping Machinery & laying of
MS Pipeline. History of experience of the Engineer with regard to works he has handled
for the firm or before with duration magnitude etc. be briefly mentioned. Where the firm
has several personnel and No. of works, the particulars are mainly required for whoever
is due to be in-charge of this work and specific mention of this purpose be made.
Mention of other is stated as additional services available to credit of firm. Bio-data of all
Site Engineers as per attached form should be submitted.
Site Engineer should be Graduate in Electrical Engineering and should have at least
three years’ experience of similar nature work and capacity to organize works of sizeable
magnitudes, preferably of nature of providing & installing Electrical works related to
Pumping Machinery installed for water/gas/crude pipeline projects. History of
experience of the Engineer with regard to works he has handled for the firm or before
with duration magnitude etc. be briefly mentioned. Where the firm has several personnel
Multi Mantech International Pvt. Ltd.
39
SAUNI Yojana - Phase: II, Link - 2, Package - 4
and No. of works, the particulars are mainly required for whoever is due to be in-charge
of this work and specific mention of this purpose be made. Mention of other is stated as
additional services available to credit of firm. Bio-data of all Site Engineers as per
attached form should be submitted.
10% of the above staff should be well conversant with one of the language such as
English, Hindi or Gujarati. Contractor must ensure their complete details of staff as
indicated above and incorporate the details with these documents, specifying part of
them to be stationed for the work. Availability of number of personnel with firm and
engaged on other works may also be mentioned which will be sort of additional to the
firms as services of such personnel will become available to the project in case of
urgency. The information of the staff should be given in registration documents along
with certificates of qualification and experience etc. with bio-data form as specified.
If sufficient Nos. of technical staff mentioned above is not available at the time of
tendering, contractor should give undertaking in writing to Govt. that the remaining
qualified technical staff as mentioned herein above should be engaged in work before
issue of work order. After submission of complete staff details work order will be issued.
Any change in staff during execution shall be intimated to Executive Engineer /
Engineer-in-charge and written approval of change should be taken form Executive
Engineer.
6.4.5 Machineries
The work of pipeline and Pumping Station will require sufficient numbers of equipment
like hauling equipment, allied equipment, plant for fabrication of pipe, carting of pipe to
site of work, welding machine, gas cutters and other such machinery tools and plants
required for the smooth execution of the work. Bidder should have sufficient machinery
which is required for execution of M.S. pipeline 55,422 meter as per the price bid
Volume - IV.
The list of machinery as available with bidder or intended to be acquired for this work by
the bidder should be furnished invariably by the bidder with the bid documents. Other
machinery specifically available but under use or to be used for other project could be
listed in addition.
The bidders who meet the minimum qualifying criteria stipulated in Section 6 . 4
above will be qualified only if their annual bid capacity is more than or equal to estimated
cost.
All the bidders shall give their list of on-going works with balance value of work to be
executed during time limit of this work (i.e. 24 months) for assessing their commitment as
on date of bid submission.
N = Number of years prescribed for completion of the works for which bids are invited (i.e.
24 months) Two Years.
The bidders must provide by uploading evidence of having adequate experience and
performance which include supporting certificate or report relating to physical, financial,
technical and other capability of the bidder from the respective clients in their original
language along with certified translation of all relevant portions of the information about
the financial capacity in Indian Rupees Only.
The bidder shall furnish his proposed approach and methodology for the design,
construction, erection and commissioning of the works and provide conceptual design of
the system with sizing of the components. The design should be supported with design
calculations and procedures for adoption for the EPC work.
Multi Mantech International Pvt. Ltd.
41
SAUNI Yojana - Phase: II, Link - 2, Package - 4
The bidder shall furnish his proposed approach and work plan, cash flow statement
ALONGWITH A DETAILED METHOD STATEMENT for the design, construction,
erection and commissioning of the works with appropriate construction / installation
equipment planning and development, duly supported with calculations and procedures
proposed to be adopted, justifying his capability of achieving the completion of works by
the latest commissioning date as fixed and as per the milestones specified within the
stipulated period of completion of construction contract.
The Bidder shall also submit his approach, work plan and method statement including
organizational chart, for the effective operation & maintenance of the works for the
stipulated period of O & M. The bidder shall furnish along with his bid CVs of the key
personnel associated for this project both for the construction and O & M of the works.
f. After approval of the qualification of the bidders, the technical bid will be opened on
suitable time by the competent tender opening authority in the presence of bidders
who wish may remain present. The technical bid shall be evaluated and wanting
details, if any, and clarification in respect of conditions if any will be called from the
tenderers. In such case, the bidder will be required to submit clarifications/details
(including with respect to conditions, if any) within the stipulated time allowed for the
purpose. If the bidder does not furnish the wanting details/clarifications in times his
tender would be liable for rejection.
The condition specified in technical bid should invariably be accompanied by proper
financial evaluation with mode of calculation specifying assumptions, quantities, rate
and ceiling amounts for each condition and shall also accompany the information in
the form as per Volume –III-F.
Ceiling amount shall be binding on the bidders and are liable to be added to the
tender amount.
g. The evaluation as given by the bidder as modified tender opening authority with the
ceiling limit will then be intimated to all the bidders. No further opportunity shall be
given to the bidders to modify/withdraw conditions at that stage. After completion of
evaluation of the technical bid in all respects the competent authority will decide
about date of opening of price bid and the same will be intimated to the qualified
bidders. After opening of price bid and their evaluation the tender inviting authority
reserves the right to negotiate about the tender (s) further with any or all the bidders
Executive Engineer
Bhavnagar Irrigation Project Division
Bhavnagar,
To,
The Executive Engineer,
Bhavnagar Irrigation Project Division,
Jilla Seva Sadan no: 2
Bhavnagar.
Gujarat State
Sub: SUBMISSION OF bid documents FOR THE WORK of Sauni Yojna - Phase: II, Link - 2,
Package - 4: Engineering, Procurement and Construction (EPC) Contract for Supplying and
laying MS Pipeline of 3000mm dia. (ID) for Length of MS Twin Pipeline 27.711 Km (Total
Length – 55.422 Km) from Bhimdad at Ch. 0.0 Km to Kalubhar at Ch. 27.711 Km with all
allied works etc. complete including Operation and Maintenance of the commissioned
project for 10 years
Sir,
1. Having examined the details given in the invitation to bidder for qualification and brief
note, the conditions of contract and quantities for the execution of above named work, we
the undersigned, offer to execute and complete such works and remedy any defects
therein in conformity with the conditions of contract, Specifications, Drawings, in
accordance with the said conditions.
2. We hereby certify that all the statements made and information supplied in the enclosed
Form A to I and accompanying statements and Annexures are true and correct.
3. We have furnished all information and details necessary for pre-qualification and have no
further pertinent information to supply.
4. We have submitted the required certified solvency certificate and authorize the
Government Of Gujarat to approach the Bank issuing the solvency certificate to verify the
correctness thereof. We also authorize, Government to approach individuals, employers,
firms and Corporation to verify our competency and general reputation.
5. We hereby apply for pre-qualification and bid for the work
6. We undertake, if our Bid is accepted, to commence the works immediately after the
receipt of the Engineer’s notice to commence, and to complete the whole of the works
comprised in the contract within the time stipulated in the Appendix to bid.
7. We agree to abide by this Bid Validity for the period of 120 days from the last date fixed
for submission of the same and it shall remain binding upon us and may be accepted at
any time before the expiration of that period.
8. We enclose here with fixed Deposit receipt / Deposit at call receipt / Bank Guarantee as
per the requirement of the bid Towards Earnest Money Deposit which is to be absolutely
forfeited by the Government, if we do not Deposit the amount against the security deposit
as decided by Government.
9. The Details are as given below:
Multi Mantech International Pvt. Ltd.
44
SAUNI Yojana - Phase: II, Link - 2, Package - 4
Signature.............. In the capacity of...................Duly authorised to sign bid for and on behalf
of.......................................................................... (IN BLOCK CAPITALS)
Address......................................... Witness....................................
Address.........................................
Occupation............................................................
Encl.:- Appendix
Seal of applicant
Form - A
DETAILS OF ORGANIZATION
(Details to be provided separately for each member, in case of a joint Venture)
1 Name of Bidder
2 Nationality of bidder
3 Office Address Telegraphic Address
Telephone Number Telex / Fax Number
4 Year of Establishment
5 Location of Establishment
6 Bid is submitted as
An Individual
A Proprietary Firm
A Firm in Partnership
A Limited Company or Corporation
7 Attach the Organization chart showing the structure of the
organization including the names of the Directors and Position
of Key Staff.
8 Number of year of experience
As a Prime Contractor (shouldering major responsibility)
In Own Country
In Other Countries (Specify Country)
In a Joint Venture
In Own Country
In Other Countries (Specify Country)
Form - B
DETAILS OF PERSONNEL
Provide details of key Technical and Administrative Personnel to be assigned for the work.
A) Details of the Board of Directors
Name of the Director
Address
Organisation of the Board of Director
Form - C
DETAILS OF EQUIPMENT
Bidder should give the details of Equipment/Machineries and other resources available with
them for the implementation of the project in Form C.
Form - D1
DETAILS OF EXPERIENCE OF COMPLETED WORKS
Provide details of the similar n a t u r e o f work completed during seven (7) Financial years ( i.e. from
2009-2010 to 2015-16) in the following Performa (separate Performa for each work
(Details to be provided separately for each member in case of a joint Venture)
1 Name of Work
2 Agreement No. & Date
3 Country and location
4 Client’s name and address
5 Total tendered cost of work (Rs. in Lakhs)
6 Cost of completed work
7 Brief description of works including principal features and quantity
of main items.
8 Annual achievement (duly supported by certificate from Engineer –
In – Charge)
Of key quantities, total physical output of last seven years.
(separately for each item) (For Pipeline, Electrical-Mechanical
work for pumping, Switch Yard etc. for Lift Irrigation or Water
Supply Project or Petroleum pipeline project.)
Financial Output in Rupees (Cost of Work) (Including cost of
materials supplied by the Department)
9 Period of completion
Originally Stipulated Time Limit
Date of Starting
Extended Time Limit, if any
Actual Date of Completion
Actual time taken to complete the work Reasons for non-
completion of work in stipulated time limit / extended time limit if so.
10 Name of applicant’s Engineer-in-charge of the work and his
educational qualification
11 Were there any penalties/ fines / stop notice / compensation /
liquidated damage imposed? (Yes or No, if yes, give case wise
details)
12 Give the details of annual financial capability and experience in
execution of Lift Irrigation or Water Supply Project or Petroleum
pipeline project in Statement S-2.
13 Details of litigation / arbitration cases, if any pertaining to work
completed.
14 Attach Client’s certificate in Form-G (Not below the rank of
Executive Engineer or equivalent)
SIGNATURE OF BIDDER
Form - D2
Provide details of works on-going during last seven (7) Financial Year i.e. from 2009-2010 to
2015-16. (In separate form for each work)
SIGNATURE OF BIDDER
Form - E
(vi) 2014-2015
(vii) 2015-2016
Gross income in the last seven years
Sr. Year Gross Income Reference page No. to balance
No. (Rs in Lakhs) sheet or other documents
(i) 2009-2010
(ii) 2010-2011
(iii) 2011-2012
(iv) 2012-2013
(v) 2013-2014
(vi) 2014-2015
(vii) 2015-2016
Total liabilities
Current ratio (ration of current assets/current
liabilities
Total liabilities to net worth
Maximum gross income from contract works
during last seven years
Note:
1. Certificate for the account audited by the Chartered Accountant should be given without
fail.
2. Certificate from the owners in support of successful completion of the works by the bidder
may be furnished.
3. C.A. certificate should be notarized.
SIGNATURE OF BIDDER
Form - F
ADDITIONAL INFORMATION
Please add any further information which the applicant considers relevant in regard to his
capabilities.
Please give a brief note indicating by applicant considers him-self eligible for qualification for
the work.
List of works for which tenderers have already submitted to the client but not awarded.
SIGNATURE OF BIDDER
Form – G
Name of Office:
Date:
i) Financial Rs.
(Including Lakhs
price
escalation)
ii) Physical
The agency has carried out the work timely / late and satisfactorily / unsatisfactorily.
SIGNATURE
Form- H
DECLARATION FORM
i. I/We hereby declare that I/We have visited the site and fully acquainted myself/ourselves
with local situations regarding materials, labour and other factors pertaining to the work
before the bid documents published on the website www.nwr.nprocure.com and
accordingly submitted our Bid for the work of Sauni Yojna - Phase: II, Link - 2, Package -
4: Engineering, Procurement and Construction (EPC) Contract for Supplying and laying
MS Pipeline of 3000mm dia. (ID) for Length of MS Twin Pipeline 27.711 Km (Total
Length – 55.422 Km) from Bhimdad at Ch. 0.0 Km to Kalubhar at Ch. 27.711 Km with all
allied works etc. complete including Operation and Maintenance of the commissioned
project for 10 years
ii. I/We hereby declare that I/We have carefully studied the conditions of contract,
specifications and other documents of this work and agree to execute the same
accordingly.
iii. I/We hereby declare that my /our near relatives are not working in this division or its sub
divisions as an Engineer of any category, Divisional Accountant, Store keeper, Manager
of Atithi / Vishram Gruha and in the Circle Office as a Superintending Engineer as on
today.
iv. I/We _____________________declare that I/We have read the tender documents
published on the website www.nwr.nprocure.com accordingly submitted our Technical
Bid for the work of ________________________________________.
Form - I
Telephone No
Statement S-1(a)
STATEMENT SHOWING THE DETAILS OF THE WORK OF MAGNITUDE CARRIED OUT FOR M.S. PIPE LINE OF INTERNAL DIA EQUAL OR
MORE THAN 1800 MM (ID) DURING LAST SEVEN (7) FINANCIAL YEARS (i.e. from 2009-2010 to 2015-16)
Sr. Name Place Cost of Date Date of Total Qty. Year-wise Length of completion (km) Reference
No of Work & The of Completion Of Pipeline of Client
. Country Start Certificate
Work Diameter Length 2009 - 2010- 2011- 2012- 2013- 2014- 2015-
in mm. in km. 2010 2011 2012 2013 2014 2015 2016
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Note:
1. Certificate from the client in support of successful completion of work by the bidder be furnished preferably in Form G attached herewith.
2. In case the work executed on EPC contract with joint venture, the portion of the bidder in the EPC contract shall be given and duly certified by
the client.
3. In column 7 & 8 the details of pipeline shall be given diameter wise, in each work.
4. All the certificate and supporting documents should be duly signed and notarized.
SIGNATURE OF BIDDER
Statement S-1(b)
STATEMENT SHOWING THE DETAILS OF EXPERIENCE IN OPERATION AND MAINTANCE OF LIFT IRRIGATION PIPELINE PROJECT/
WATER SUPPLY PROJECTS WITH PUMPING STATION / PETROLEUM PIPELINE PROJECTS AFTER COMMISIONING YEARS (i.e.2009 –
2010 Upto 2015-2016)
Note:
1. Certificate from the client regarding satisfactory completion of the O & M Shall be furnished.
2. Only experience in similar nature of work will be considered for evaluation.
3. All the certificate and supporting documents should be duly signed and notarized
SIGNATURE OF BIDDER
Statement S-2
STATEMENT SHOWING THE DETAILS OF EXPERIENCE IN EXECUTION OF IRRIGATION / LIFT IRRIGATION OR WATER SUPPLY PROJECT
OR PETROLEUM PIPELINE PROJECT PROJECTS DURING LAST SEVEN (7) FINANCIAL YEARS (i.e. from 2009-2010 to 2015-16)
Sr. Name of Locality Cost Date Whether If completed, Cost of Value of Construction work completed Reference
No. of of Completed or date of Work of Client’s
Work (Region) During the Year (Rs. In Lakhs)
in progress completion executed Certificate
Work Start
up to 2009 - 2010- 2011- 2012- 2013- 2014- 2015-
31/03/16 2010 2011 2012 2013 2014 2015 2016
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Note:
1. The work executed on EPC contract for pipeline works shall be given.
2. In case the work executed on EPC contract with joint venture, the portion of the bidder in the EPC contract shall be given and duly certified by
the client.
3. Certificate from the client in support for execution of work shall be attached preferably in form G attached herewith.
4. The bidder shall give work details in Form D1 and Form D2 in case of work completed and in progress respectively.
5. All the certificate and supporting documents should be duly signed and notarized.
SIGNATURE OF BIDDER
ANNXURE - I
We further agree that the guarantee herein contained shall remain in full force and effect during
the period that would be taken for the acceptance of tender.
However, unless a demand or claim under this guarantee is made only in writing on or before
the Dt: ……………………………… (Date specified shall not be less than 180 days) We shall be
discharged from all liabilities under the guarantee thereafter.
We undertake not to revoke the guarantee during its currency except with the previous
consent of Executive Engineer, Bhavnagar Irrigation Project Division, Bhavnagar in writing.
We lastly undertake not to revoke the guarantee for any change in constitution of the
Tenderer or the Bank.
Seal
ANNXURE - II
2. Definitions
In this deed the following words & expressions shall have the meaning set out b elow:
a. "The Employer" shall mean Narmada, W ater R esources, W ater Supply &
Kalpsar Department
b. "The Works" shall mean: Sauni Yojna - Phase: II, Link - 2, Package - 4: Engineering,
Procurement and Construction (EPC) Contract for Supplying and laying MS Pipeline of
3000mm dia. (ID) for Length of MS Twin Pipeline 27.711 Km (Total Length – 55.422
Km) from Bhimdad at Ch. 0.0 Km to Kalubhar at Ch. 27.711 Km with all allied works
etc. complete including Operation and Maintenance of the commissioned project for 10
years.
c. "The Tender" shall mean the Tender to be submitted by Joint Venture to the
Employer for the work /works for which tender will be floated by WR Dept.
d. "The Contract" shall mean the contract entered /to be entered into between the Joint
Venture and the Employer for the works.
3. Joint Venture (JV)
The Parties hereto declare that they have agreed to form a Joint Venture for the purpose
of submitting the tender. Application/ tender document initially and then tender and if
successful for the execution of the works as an integrated Joint Venture. The parties
are not under this agreement entering into any permanent partnership of Joint Venture
to tender or undertake any contract other than the subject works. Nothing herein contained
shall be considered to constitute the parties of partners to constitute either Party the agent
of the other.
4. Witness
a. The parties do not enter into an agreement of any permanent partnership of Joint
Venture to tender or undertake any Contract other than the specified above ;
b. That the operation of this Joint Venture firm concerns and is confined to the
work of _______________ of Narmada, W ater Resources, Water Supply &
Kalpsar Department.
c. The name of the Joint Venture firm for convenience and continuity shall be
_______________________________, alternatively the bid may be submitted
in the name of lead member along with Joint Venture agreement.
d. The Address of Joint Venture for communication shall be as under or the lead
member may also communicate with the department for submission of bid &
other correspondence related to the work.
e. The Joint Venture shall jointly submit tender application on the above name
according to all terms and conditions stated in the relevant instructions
contained in the bid documents alternatively the bid may be submitted in the
name of a lead member.
f. This Joint Venture shall regulate the relations between the parties thereto and
shall include without being limited to them the following conditions.
(1) _________________firm shall be the lead company in charge of
the Joint Venture for all intents and purpose.
(2) In case the said work is awarded to the lead member along with
collaboration with the Joint Venture, the partners of the Joint
Venture will nominate a person with duly notarised power of
Attorney on stamp paper, who will represent the lead member / the
Joint Venture with the authority to incur liabilities, receive
instructions and payments, sign and execute the contract for on
behalf of the Joint Venture,
(i) All the (Maximum Three) parties agree to make financial
participation and to place at disposal of Joint Venture the benefits
of its individual experience, technical knowledge, skill and shall in all
respect bear its share as regards planning and execution of the work
and responsibilitie s including the provision of information, advice
and other assistance required in the Joint Venture and participation shall
be as under:
Firm - B
Firm- C
All rights, interest, liabilities, obligation work experience and risks (and all net
profits or net losses) arising out of the contract shall be borne by the parties in
Multi Mantech International Pvt. Ltd
63
SAUNI Yojana - Phase: II, Link - 2, Package - 4
proportion to their shares. Each of the parties shall furnish its proportionate
share in any bonds, guarantees, sureties required for the works as well as it
proportionate share in connection with the works. The share and participation of
the two/three partners in working capital and other financial requirements shall
be in ratio as mentioned above.
5. Internal responsibilities and liabilities
a. The division of individual scope of work may be worked out mutually by the
parties but the party shall be jointly and severally liable to the employer fo r the whole
work.
b. The parties specifically undertake to carry out their separate works in full
compliance with the contract with the employer. Each party shall be responsible
jointly and severally for consequences if any arising out of defective or delayed
execution of works which f alls within the individual's party's area of
responsibility and/ or it has been caused due to acts and /or omission of the
concerned party.
c. The parties jointly and severally agree to replace modify or repair any defect in
their respective portions of works in accordance with the terms and condition of the
contract with the employer.
d. The parties jointly and severally shall indemnify and hold harmless to each other
against any claim made by the employer or any other third party for injury, damage,
loss or expenses is attributed to the breach /non-performance of his responsibilities
by the indemnifying party in accordance with the agreements and /or contract with the
employer.
e. None of parties have joined in any other Joint Venture for the said works.
6. Responsibilities and liabilities of Joint Venture towards the employer
a. Parties hereto shall be jointly and severally liable and responsible for the acts,
deeds and things done or omitted to be done in respect of the execution of the
contract and for any financial liability arising there from.
b. Par-ties hereto shall be jointly and severally responsible to the Employer for the
execution of the works in accordance with the contract conditions;
c. Parties hereto shall be jointly and severally indemnify to the Employer against
any claim made against the employer or any other third party if applicable for any
injury, damage or loss which may be attributed to the breach of the obligations under
the contract pursuant to the contract.
7. Site management
a. The execution of the work on the site will be managed by a lead member or a
Project Manager appointed by the Joint Venture and who will report to the
________ (J.V.) the project manager shall be authorized to represent the Joint
Venture on site in respect of matters arising under the contract.
b. The (Name of the J.V.) shall be jointly and severally
liable to the employer for the execution of the contract commitment in respect of
the works in accordance with contract conditions.
8. Termination of the Agreement
This agreement shall be terminated in the following circumstances.
a. The employer awards the contract for the work to the other Tenderer.
11. Negotiation
Any negotiation of agreement between the parties hereto and the employer subsequent to
the submission of the tender and prior to award, shall take place only with consent of
each of the parties who shall be represented at the such negotiation by one or more
representative(s) duly empowered to make such negotiation or agreement.
The Joint Venture through the parties individually shall take such insurance in
connection with the work in accordance with the tender condition as acceptable to the
employer.
The cost of the insurance premium paid by the Joint Venture shall be borne and paid
by the parties in proportion to the respective shares of work. Other insurance taken
individually by the parties shall be fully borne by the respective parties.
15. No change shall be made in this agreement without prior written consent of the
employer and other party. However if the employer directs the parties to make c hanges
in the agreement so as to full fill tender conditions the parties discuss with employer
and mutually agreed such changes required to be made in the agreement.
16. Default and withdrawals from the Joint Venture
In case that either party fails to observe the provision stipulated in this agreement
withdrawal from the Joint Venture, Loss and /or expenses incurred by other party due to such
default and /or withdrawals shall be fully compensated by the party who has defaulted. In
such case, the lead member shall be responsible for completion of the remaining works by
making necessary arrangements acceptable to the employer.
17. All matter relating to or arising due to this agreement shall be treated as confidential
and shall not be disclosed to any other party. In witness whereof the parties have
caused their duly authorized representatives to sign below.
Witness:
Date
Seal
Annexure – III
Deleted
Annexure – IV
Details of the work and magnitude carried out in the last 7 Financial years (i.e. from 2009-2010 to 2015-16)
Sr. Name of Place and Estimated Total Annual Turnover Period of Principal Max. Qty. if any E.W. /
No. Work Country cost of the Tendered Year Amount in Completion for Features Excavation / Concrete /
work Cost of the Rs. value entire work pipeline with details of year
Work
1 2 3 4 5 6 7 8 9 10
1
2
3
4
5
Note:
1. Certificate from the Income Tax Authority/Owner of Works/Chartered Accountant for annual turnover in the terms of year wise amount and
quantity shown in column No. 6 & 7 and 10 shall be furnished by the tenderer which clearly mentioned year wise amount of each work by
separately.
2. In column No. 10 quantity of excavation earth work concrete and pipe line work shall be given with supporting documents; which clearly
mentioned year wise quantity of 1) excavation/earthwork 2) concrete work 3) Pipeline of each work by separately
3. Details of works pertaining to Civil Engineer works only shall be mentioned in the above schedule.
4. All the certificate and supporting documents should be duly signed and notarized.
Annexure – V
Declaration regarding works on hand and works for which award is likely to be made to Tenderer (Tenderer is found L-1)
Sr. Name Place Work on Hand Works tendered for and tenderer is found L-1 Remarks
No. of & Tender Date Stipulated Cost of Cost of work Estimated Time Date Cost of work to
work country cost and of period of work remaining to Cost limit when be executed in
estimated Issue completion remaining be executed in of decision next 24 months
Cost of to be next 24 months work is (01/01/2017 to
work executed (01/01/2017 to expected 31/12/2018)
order as on 31/12/2018)
31/12/2016
1. 2 3 4 5 6 7 8 9 10 11 12 13
Notes:
1. The cost of work done and works on hand may be furnished in terms of Rupees.
2. Certificate of authentic document for details shown above shall be furnished
3. Certificate from the owner in support of successful completion of work by the contractor is to be furnished.
4. All the certificate and supporting documents should be duly signed and notarized
Annexure – VI
Annexure - VII
Bidder may submit their work plan, details methodology to be adopted for this work.
Annexure – VIII
Name of Applicant:
2. Please add any further information that you may consider to be relevant to the evaluation
of your application for qualification. If you wish to attach other documents, please list
below:
Annexure –IX
I/We
………………………………………………………………………………………………..Age…………
……………Business……………………………., Residence of
…………………………………………………………………. (With Full Address), hereby declare on
oath of God, that if our offer for the work of “Sauni Yojna - Phase: II, Link - 2, Package - 4:
Engineering, Procurement and Construction (EPC) Contract for Supplying and laying MS Pipeline
of 3000mm dia. (ID) for Length of MS Twin Pipeline 27.711 Km (Total Length – 55.422 Km) from
Bhimdad at Ch. 0.0 Km to Kalubhar at Ch. 27.711 Km with all allied works etc. complete including
Operation and Maintenance of the commissioned project for 10 years.” is accepted by the
competent authority & Awarded to us, I/We will engage & employ the technical staff on site of
work, required as per provision made in tender agreement. All technical staff will remain present
at the site of work during the work is continued.
Signature of Bidder
Place:-………………………
Date:-……………………...
Annexure –X
Signature of Contractor
Annexure –XI
Declaration of Contractors
I/We hereby declare that I/We have visited the site, condition of the ground realities and fully
acquainted myself/ ourselves also with local situation regarding material, labours, and other
factors pertaining to the work before submitting the tender.
1. I/We hereby declare that I/We have read the Tender documents published on the website
www.nwr.nprocure.com.
2. I/We hereby declare that I/We have carefully studied the conditions of contract and
specifications and other documents of this work and agree to execute the same
accordingly.
3. I/We hereby declare that my/our near relatives are not working in this Division or its Sub
Division as an Engineer of any category, Divisional Accountant, Store Keeper, Manager of
Atithi/ Vishram Gruh and in the Circle office as a Superintending Engineer as on today.
Signature of Contractor
Annexure –XII
Details of Technical and Supervisory Persons with Tender/ to be posted for this work only.
(Provide details separately for each member in case of a joint venture.)
Signature of Contractor
Annexure –XIII
Affidavit
Affidavit to be provided by the contractor to W.R. Department on Rs. 100 Stamp Paper (for
Joint Venture, all members of the JV shall provide the affidavit)
I / We _________________________________ the undersign under authority from
_____________________ having its office at _____________________ on oath solemnly
undertake.
1. That all the information / data have been provided by us in various formats / forms / along
with our tender submission in __________ in response to the notice inviting Tender No.
_________________ dated __________ relating to the work of
_______________________ are true and correct & represent the factual information
required for the pre-qualification of the contractor for the subject work.
2. That the certificates issued by the client for projects and attached with our tender
submissions as evidence of our technical capability, experience of similar project, work
done as well as the financial data for qualification are all valid as issued by the competent
authority.
3. That M/s. _______________ has not been blacklisted or banned for business with by the
Central / State Govt. / Public Sector undertaking / Municipal Corporation / Local bodies
etc. for whatsoever reasons. We are aware that any such blacklisting or banning of
business may result in to our disqualification for the tender (S) under process.
4. That M/s. ___________________ or any of the joint venture partners bidding for the
subject work have not abandoned any work awarded by the State Government during last
five years prior to the date of this affidavit.
5. That the information provided along with tender submission for the project relating to lifting
and arbitration is also true and correct.
6. That we have not suppressed any factual information that was asked for by the W.R.
Department or was directly or indirectly required for by the W.R. Department or was
directly or indirectly required for the purpose of our pre-qualification.
7. That we are aware that providing false information, data and documentation as well as
suppression of vital information will not only lead to our disqualification for award of
contract by W.R. Department but W.R. Department shall have all the right and privilege to
initiate criminal action against us.
(AUTHORIZED SIGNATORY)
(To be signed by company Secretary / full time director (s) / Managing Director / Proprietor /
Partners / of the firm or a partner holding power of attorney).
Schedule – I-A
The Bidder shall give below the list of special maintenance tools and tackles offered by him and
included in the prices quoted by him.
SIGNATURE: ______________________
NAME: ____________________________
DESIGNATION: ______________________
COMPANY: _________________________
DATE: ____________________________
COMPANY SEAL
In case any additional tools & tackles is required by the Contractor for O & M but not
included in the above will be supplied by the Contractor free of cost to the Employer.
The Contractor shall hand over all the maintenance tools & tackles in good condition to
the Employer at the time of handing over the works on expiry of O & M Contract.
Schedule – II-A
Make Owned
Capacity Year of Present
Description Qty. and or
or Output Manufacture Location
Model Leased
1. List of principal Plant
/ Equipment owned by
the Contractor
a) Cranes (Mobile)
b) Cranes (Tower)
c) Trucks / Dumpers
d) Excavators
e) Concrete Transit
Mixers
f) Concrete Batching
Plant
g) Dewatering Pumps
h) Site lab facilities
i) Slip form Shuttering
j) Electrical tooling kit
k) Other (Bidder to list)
SIGNATURE: ______________________
NAME: ____________________________
DESIGNATION: ______________________
COMPANY: _________________________
DATE: ____________________________
COMPANY SEAL
Note : The contractor shall have to submit proof of ownership of each equipment as
otherwise it will be considered that equipments are to be hired.
Schedule- III-A
Owned
Capacity Make
Year of or Present
Description Quantity or and
Manufacture Lease Location
Output Model
d
SIGNATURE: ________________________________
NAME: _____________________________________
DESIGNATION: ______________________________
COMPANY: _________________________________
DATE: ______________________________________
COMPANY SEAL
8. Data Sheet
Sr.
ITEM DESCRIPTION
No.
2 AIR VALVE
4 M. S. PIPE LINES
Sr.
Description Required Specs.
No.
1 General
(a) Size 200 mm, 150 mm
Sr.
Description Required Specs.
No.
(e) Isolation valve stem details (if Furnish during detail engineering
built-in)
7 DEVIATION Deviations (if any), from the above specifications,
clearly. If the deviation is for a betterment in
design / performance, then the it will be with
technical justification.
8 WEIGHT / DIMENTIONS
(a) Total Weight (kg) of the Furnish during detail engineering
Complete Assembly
(b) Over-all dimensions of the Furnish during detail engineering
complete assembly – L X B X
H (mm)
Sr.
Description Required Specs.
No.
3.1 General Double Flanged, for water application
(a) Size / Dia, mm 2400 mm, 600 mm
(b) Make Furnish during detail engineering
(it shall be of approved vendor list)
(c) Rating PN 1.6
(d) Standard to which IS 13095 (for valve,
manufactured IS 1538 (for Flange)
3.2 Mode of Operation: Hand / Gear operated
3.3 Materials of Construction
(a) Body Ductile Iron as per IS 1865 Gr. 500/7
(b) Shaft SS AISI 410
(c) Disc Ductile Iron as per IS 1865 Gr. 500/7
(d) Seat Ring SS AISI 304
(e) Bearing Bush Steel-backed PTFE
(f) Clamping Ring SS AISI 304
(g) Internal Hardware SS AISI 304
(h) External Hardware Carbon Steel IS 1367, CL 4.6 / 4
3.4 Mfg. Quality Assurance To get approved, prior to manufacturing
Plan (QAP)
3.5 Testing
(a) Seat Test Pressure (Hydro- As per Standard
test) – Kg/cm2
(b) Body Test Pressure (Hydro- As per Standard
test) – Kg/cm2
(c ) Disc Strength Test – Kg/cm2 As per IS 13095
3.6 Deviation Deviations (if any), from the above specifications,
clearly. If the deviation is for betterment in design /
performance, then it will be supported with technical
justification.
3.7 Weight / Dimension
(a) Total Weight (kg) of the Furnish during detail engineering
Complete Assembly
(b) Over-all dimensions of the Furnish during detail engineering
complete assembly –
L X B X H (mm)
3.8 By-pass Valve to Main Required
Valve
(4) M. S. PIPELINE
Sr.
Description Required Specs.
No.
1 Plates / HR coil / Pipe IS:2062, Gr.B Fe 410 /
Manufacturing
IS:10748 Gr.III Fe 410 /
IS: 3589
- of approved make
2 Welding & Electrodes ASME – SECT – IX, IS – 7310, IS – 7307, IS:
814, IS: 3613, IS: 6419, IS: 7280, IS – 9595
Approved Make Electrode
3 Food-grade Epoxy paint, for Shot blasting, followed by application of 406
Inside of pipeline micron Dry Film Thickness (DFT), solvent
free, high build, food-grade epoxy lining,
confirming to AWWA C-210-07/ BS 6920 -
suitable for potable water application as per
specification
4 Epoxy Paint Coating for out- Shot blasting, followed by supply and
side of pipeline For Pump application of primer & suitable epoxy paint,
making total DFT as 200 microns as per
House specifications
General Note:
a) Work allotted EPC agency shall furnish material test certificates of all the major
components during inspection of the equipment.
b) The datasheet given in this chapter of all the components shall be read in conjunction
with the respective Technical Specification of Civil, Mechanical, Electrical &
Instrumentation works (Vol-III-A, B, and C & D) & drawings.
c) Bidder have to confirm guaranteed particular and technical values shall be equal or better
then indicated in the datasheet. However all complete technical datasheet (to meet tender
requirement) shall be filled during detail engineering by work allotted EPC agency.
Bidder to confirm as “Type test certificates” of all the items shall be submitted
after award of work as part of engineering documents”.
1. Bidder shall submit all guaranteed & technical values mentioned in the particulars
at the time of Bidding, Other details shall be confirmed as to meet tender
requirement.
2. Mentioned all guaranteed performance & technical values are equal as per data
sheet or better than values mentioned in the Particulars
Sr.
Description Particulars
No.
1 General
a Make As per approved vendor list
c
Electro magnetic Flow meter Dia size 600 mm,800 mm
f 2 No.
(a)600 mm dia at Malpara
Quantity
(b)800 mm dia at Kalubhar
g Temperature 50°C
h Lining Neoprene / Hard rubber
i Flanges PN10DN carbon steel
j Output 4-20mA DC, smart HART protocol, Mod
bus RS-485
k Power supply for flow meter immediate
after header shall be 240 V AC, 50 Hz,
Zero and span adjustment, battery
backup for 2 hours.
Power Supply
Power supply for flow meter at remote
area shall be 230 v Ac or 24 VDC
through solar operated system or battery
operated for continuous operation
Sr.
Description Particulars
No.
Arrangement of solar panel, battery bank,
lockable enclosures and other required Provided
accessories at remote locations.
2 Flow sensor
a
Full bore type Electromagnetic with
Type
compatible to GSM/GPRS connectivity
g Material of construction
(a) Electrode SS 316
(b) Grounding ring SS 316
(c) Flanges Carbon steel
(d) Flow tube lining EPDM/Neoprene/PTEF
3 Flow Transmitter
a
Microprocessor based multi Channel
Type indicating type have back lit LCD/LED
display
b
Input From Electromagnetic flow element
Sr.
Description Particulars
No.
h
Min. 2 line back lit LCD for indication of
Display & Digit height actual flow rate, forward, reverse, sum
totalizes with 14mm or higher digit height
w
Manual reset facility for flow integrator Required ( shall be key operated)
x Required
Battery backup for integrator for 8 Hours