Major Upstream Projects in Nigeria

November 10, 2005

Investor Relations - www.total.com


Nigeria : well-diversified portfolio of Total-operated projects

OML 58 (40%, op.)


Upgrade start-up : 2008(e)

Expanding from onshore to


offshore and deep-offshore
NLNG (15%)

Amenam (30.4%, op.) Operations concentrated in


Oil phase start-up : 2003 eastern area
Gas phase start-up : 2007(e)

Rapid build up of gas and LNG


Ofon Ph. II (40%, op.)
activities
Start-up : 2009(e)

New phases on existing projects


Usan (20%, op.)
Akpo (24%, op.)
Start-up : 2010(e)
Start-up : 2008(e)

Total-operated
Participation

1 Investor Relations – 3C974


Growing with deep-offshore operated projects

Port Harcourt

NLNG
Akpo and Usan : two giant field
Bonny
OML 99
developments operated by Total
25m OFON
50m
Amenam OML 100
ODUDU
NKARIKA
OML 102 Resulting from successful
OPL 221 OPL 222 OPL 223 exploration between 2000 and 2005
500m
USAN ƒ Successful appraisal on Usan in 2005
1000m

AKPO
Very concentrated area of operations
1500m
50km
OPL 246 / OML 130

High level of local content

Akpo FPSO (24%, op.) Usan FPSO (20%, op.)


Start-up : 2008(e) Start-up : 2010(e)
Peak production : 225 kboe/d Peak production : > 150 kboe/d

2 Investor Relations – 3C974


Akpo development launched in 2005

Total operator, 24%

5 exploration/appraisal wells on Akpo field (100 km2)

Approx. 600 Mb of condensate + 1 Tcf of gas*


to supply NLNG
Western Central Eastern
Accumulation Accumulation Accumulation

E
44 producing wells on 5 reservoirs (lobes and channels)
3000 m

B+C T op
E C L (*
OUT
Production capacities :
W LOBE )

W ODT
E+F ƒ 175 kb/d of condensates
D

G
2,000 m 4500 m
ƒ 300 Mcfd gas export
ƒ 200 Mcfd re-injected
ƒ 2 Mb storage capacity, offloading every 5 days

Main milestones :
ƒ Discovery in 2000
ƒ Project sanctioning : 2005
ƒ Drilling spud : 2006(e)
ƒ First condensates : end-2008(e)
ƒ First gas : 2009(e)

* proved and probable reserves


3 Investor Relations – 3C974
Akpo : managing a worldwide-based project

Location

SPS

Akpo ƒ Nigeria Asset management, fabrication and


Project HQ installation of Umbilical
Flowlines and Riser (UFR),
FPSO
UFR Subsea Production Systems (SPS)
SPS and installation of FPSO
Drilling and Operations
FPSO
ƒ France Engineering & Management
ƒ Korea FPSO
UFR ƒ UK Wellheads
ƒ USA Subsea manifolds
Drilling ƒ Germany Control systems
FPSO

Capex : approx. 5 B$ Drilling rigs secured


EPC contracts signed in May 2005 Nigerian content
ƒ Approx. 30%
ƒ 7.5 million manhours

4 Investor Relations – 3C974


OML 130 : new potential poles of development for the next decade

PREOWEI-1
PREOWEI-2

AKPO-4 AKPO-3
AKPO-1
AKPO-5
OPL246 AKPO-2
Akpo Pole
EGINA-2
KURO OML 130
EGINA-1

EGINA SOUTH –1

Egina Pole

11 wells drilled end-2005 Additional recoverable oil > 500 Mb


ƒ Gas reserves under evaluation

OML130 conversion (50% of OPL 246) Further exploration & appraisal underway
in 2005 ƒ 3 wells planned for 2006

5 discoveries : Akpo, Egina, Preowei, Main challenges :


Egina South, Kuro ƒ Reservoir complexity
ƒ Spread of oil fields

5 Investor Relations – 3C974


Usan : Total operator of the “triangular bulge”

OPL 221 OPL 222 OPL 223


Usan Efere
FPSO Okpok

3
2 Usan-1
5
8
6 4 Ukot-1

7 Ukot-2

NLNG Amenam

Total operator, 20%

OPL 221, 222, 223 : 5,000 km2 of


prospective acreage

Usan FPSO as a central hub

Several satellites: Usan West, Ukot


Akpo Other possible development poles

6 Investor Relations – 3C974


Usan : development studies underway

Spread moored FPSO SPS


ƒ 2 Mbbls hull ƒ 7 manifolds Discovery in 2002
ƒ >150 kboe/d ƒ 35 vertical trees
Basic engineering underway

FID : 2006(e)

Deep-offshore development
ƒ Water depth of 730-850 m
ƒ FPSO: process capacity 150-200 kboe/d
- Storage capacity 2 Mb
ƒ 26 km of production lines
ƒ 24 km of injection lines
ƒ Offloading buoy
URF : 67 km 35 wells
ƒ 2 x 10”production loops ƒ 20 producers, 15 injectors First oil target 2010(e)
ƒ 3 x 8” injection lines ƒ 20 intelligent completions
ƒ Flexible or riser towers

7 Investor Relations – 3C974


Consolidating conventional offshore positions for both oil
and gas projects
Ofon 1997 Ofon II 2009(e)
Amenam-East
post-2010(e)

Ime 1995
Ikike BONNY
post-2010(e) NLNG

Amenam gas
2007(e)

Afia 1993

Amenam (oil) 2003 LQ LQ


OML 99
(EPNL)
e
pip

OML 102
gas

FSO Unity 2003


(EPNL)
Nkarika
po

OML 100
post-2010(e)
Ak

(EPNL)
LQ

Edikan 1994 Odudu 1993

Producing Approved Project

8 Investor Relations – 3C974


Amenam : phased development of a giant field
Amenam-East
post-2010(e) Amenam Phase I (oil) : 125 kb/d*

BONNY
Total operator, 30.4%
NLNG
Start-up : July 2003

FSO

Short development schedule

Low technical costs

Amenam Phase II (gas) : additional 50 kboe/d*


LQ
OML 99
(EPNL) Start-up : 2007(e)
e
pip

Supplying NLNG
gas

300 Mcfd delivery


po

OML 100
Ak

(EPNL)
24” export export pipeline to NLNG plant,
60 km long, capacity of 750 Mcfd
Amenam oil 2003 Amenam gas
2007(e) 9,500 tons process and treatment platform
for water injection and gas export
Producing Approved Project
12 slots drilling platform for 6 water
injection wells

* production capacity
9 Investor Relations – 3C974
Ofon Phase II : +70 kboe/d to peak production by end-2009(e)

Ofon Phase II Ofon production (100%)


Future field layout
kboe/d*
150
OFD2 OFD-3
15 slots 12 slots
9 OP 3 OP
6 WI 5 WI

No routine Gas
5.1 km electrical cable flaring
OFQ 10” Oilll 100
W II
124 beds Future GL

OFP1+OFP2 OFP1
Oil 105 kbopd
W.I. 250 kbwpd
WP 100 kbwpd
GL: 800 000 m3/d
EC: 2x3 + 2x30 MWiso
Oil Phase II
Gas export: 3 MSm3/d
OFP2
50
OFD-4
15 slots
Gas to AMENAM OFD1 6 OP
18 slots 5 WI
70 km - 12" 12 OP
6 WI
3 WP
OFD-5
Oil Phase I
Oil to Odudu ODP1 - ( existing )
18 slots
12” x 41 km - 7 OP
7 WI
Links: Oil +WI + GL + EC
2004 2010(e)

FID : 2006(e) Total operator, 40%

Project start-up : 2009(e) Gas monetization through NLNG

High level of local content Flaring ends end-2009(e)

* in a 25 $/b Brent environment


10 Investor Relations – 3C974
OML 58 upgrade

Existing plants on OML 58

Obite - Obagi
12’’ HP gas
6’’ condensate
Obagi Total operator, 40%
Electrical cable
Flow station
Fiber optic cable
Large gas reserves

Obite Capacity increased from 218 to 335 Mcfd


Treatment center end-2005(e) (debottlenecking)

Field upgrade project, up to 510 Mcfd

Pipeline project, to increase transportation


Obite - Ibewa capacity to NLNG
12’’ HP gas
Electrical cable Basic engineering underway
Fiber optic cable
FID : 2006(e)

Start-up : 2008(e)
12’’ Obagi - Rumuekpe Ibewa
Production cluster
7 gas wells
1 spare slot

11 Investor Relations – 3C974


Obite power plant

90 km line to Onitsha Future double line


330 kV single line for second phase
extension to 960 MW

Power generation priority

OML 57 100 km 40% EPNL, 60% NNPC

Okpai
Consolidated in JV Oil & Gas activities
Warri Owerri
Obite

Ahoada OML 58 Aba/Alaoji


Afam Gas supply from OML 58 : 70 Mcfd
Yenegoa

Port Harcourt
440 MW Power Plant (combined cycle)
Bonny

Basic engineering launched

FID : 2006(e)
40 km line Future double line
330 kV single line saturation
expected

12 Investor Relations – 3C974


Total : strong growth of gas supply to NLNG

Gas supply scheme to NLNG Total-operated gas supply for Trains 1-6

Mcfd
OML 58
OBITE 800

Port Harcourt
600
Deep-offshore
OPL 246
50 km NLNG IK + AE
400
OFON
AMENAM / Offshore
KPONO ODUDU
200

USAN
OML 58
0
OPL 246
OPL 222 2004 2010(e) 2015(e)

AKPO

Supply portfolio Train 7 supply to be covered by


ƒ Onshore (OML 58, Obagi / Obite) existing acreage
ƒ Offshore (Amenam Gas, Ofon)
ƒ Deep-offshore (Akpo)

NLNG, Total 15%


13 Investor Relations – 3C974
NLNG : four new trains by 2010(e)

22 Mt/y in 2007(e)
Train 4
4 Mt/y
Start-up : 4Q 2005(e)

LNG
Jetty 3/4 Condensate Train 5
Storages
4 Mt/y
GTS1/2/3/4/5 LNG
storage Start-up : 2006(e)
Slug
Flares Catchers
LNG
Storages LNG Water feed line Flare
Storages Condensate
LNG/Cond. Flares Storages
Jetty 1

Utilities
Cooling water areaCond.stab..
L Train 6
Power gen.
T1 T2 & common T3 P T4 T5 T6 T7
G
Materials facilities
T3 4 Mt/y
LNG/LPG
Offloading Jetty Start-up : 2007(e)
Jetty 2

Technical &
administrative
LPG buildings
Train 7
Storages 8 Mt/y
FID : 2006(e)
Start-up : 2010(e)

11 customers with 16 Sale & Purchase Agreements


23 dedicated vessels
NLNG, Total 15%
14 Investor Relations – 3C974
Wide range of non-operated projects

Forcados Yokri Gbaran (Ubie)


First gas : Q2 2006(e) First gas : 2008(e)
Peak production (oil) : 190 kb/d Peak production (oil) : 120 kb/d
Design (gas) : 230 Mcfd Design (gas) : 1.05 Bcfd

Afam & Alscon Gas Supply


Bonga First gas : 2008(e)
First gas : Q4 2005(e) Peak production (oil) : 30 kb/d
Peak production (oil) : 225 kb/d Design (gas) : 240 Mcfd
Design (gas) : 170 Mcfd

EGGS Phase 2
Soku Debottlenecking Gas pipeline
First gas : Q4 2007(e)
First gas : Q4 2006(e)
Length : 56 km
Design (gas) : 1.05 Bcfd
Design (gas) : 1.4 Bcfd
Bonny Terminal Upgrade EGGS Phase 1
Revamping Gas pipeline
Completion : LT First gas : Q3 2006(e)
Total operator Plateau (oil) : 1.2 Mb/d Length : 84 km
Participation Design (gas) : 1.4 Bcfd

SPDC (10%) and SNEPCO (Bonga, 12.5%)


15 Investor Relations – 3C974