Construction of four lane divided bidirectional flyover

along outer ring road at Kittur Rani


Chennammacircle,Bangalore
`
Kittur Rani Chennamma Circle Flyover
LOCATION PLAN 1

FFLLY
YOOV
VEERR
`
Kittur Rani Chennamma Circle Flyover

SALIENT PROJECT DETAILS 2

NAME OF THE PROJECT : Construction of four lane divided bidirectional


flyover along outer ring road at Kittur Rani
Chennammacircle,Bangalore.

CLIENT : Bruhath Bengaluru MahanagaraPalike.

CONTRACTOR : M/s M.VenkataRao Infra projects pvt ltd

PROOF CONSULTANT : M/s Shrikhande Consultant Pvt. Ltd.

PROJECT MANAGEMENT CONSULTANT : M/s Shrikhande Consultant Pvt. Ltd.

CONTRACT VALUE : Rs. 35.80 Crore

FINANCIAL PROGRESS : Rs 10.19 Crore (28.46%)

PHYSICAL PROGRESS : 36.12%

DATE OF ISSUE OF LETTER OF INTENT : 15.10.2013.

DATE OF ISSUE OF WORK ORDER : 20.12.2013.

DATE OF HANDING OVER OF SITE BY BBMP : 23.12.2013.

DATE OF SIGNING THE AGREEMENT : 20.12.2013.


BETWEEN BBMP AND MVRIPPL.

CONTRACT PERIOD : 18 Months (Including monsoon period)

CONTRACT COMPLETION DATE : 30.04.2016 (EOT Approved on 10.07.2015)

PERIOD OF MAINTENANCE : 24 Months

LIQUIDATED DAMAGES : 0.1% of the value of balance work per day


Limited to 10% of the total value of the
Work.
`
Kittur Rani Chennamma Circle Flyover
3

SALIENT FEATURES OF FLYOVER/STORM WATER DRAIN AT KITTUR RANI CHENNAMMA CIRCLE,


BANGALORE.

PORTION
SL.NO DESCRIPTION
MYSORE ROAD OBLIGATORY KANAKAPURA ROAD
END SPAN END
I FLYOVER
Length of solid Ramp(RE
1 Wall) portion 82.84M NIL 87.56M

2 length of viaduct portion 66.90M NIL 89.20M

3 Gradient 1IN20(5%) NIL 1IN20(5%)

4 Total Deck width 17M 17M 17M

5 Clear carriageway Width 7.5M 7.5M 7.5M

6 Crash barrier width 0.5M 0.5M 0.5M

7 Median width 1.0M 1.0M 1.0M

8 Total no of Pier foundation 2 2 3

9 Span arrangement 22.3M 35M 22.3M

10 Type of super structures RC I GIRDER PSC GIRDER RC I GIRDER

11 Type of Bearing POT –PTFE POT -PTFE POT -PTFE

12 Type of Pier foundation OPEN/PILE PILE PILE

13 Type of AbutmentFoundn OPEN NIL PILE

14 Type of Abutment SOLID RCC NIL SOLID RCC

II STORM WATER DRAIN

1 Length of the Drain 135M 25M 90M

2 Width of the Drain(CLEAR) 8M 8M 8M

3 Height of the Drain(CLEAR) 4M 4M 4M

4 Type RCC RCC RCC


`
Kittur Rani Chennamma Circle Flyover

(TOTAL CONTRACT VALUE – 35.80Crore)5


`
Kittur Rani Chennamma Circle Flyover

PHOTOGRAGH SHOWING DIFFERENT STAGES OF WORK31

Reinforcement for Pile P-3/E

Pile concreting in progress for P-3/B


`
Kittur Rani Chennamma Circle Flyover

Pile cap marking for P-2

SE visit to site
`
Kittur Rani Chennamma Circle Flyover

Subgrade testing for service road

Service road works in progress


`
Kittur Rani Chennamma Circle Flyover
`
Kittur Rani Chennamma Circle Flyover

Concreting forSWD deck slab near AP-1

Concreting for SWDdeck slab near Junction on Mysore


side