SPECIFICATION FOR SP PRIMARY & SECONDARY SUPPORTS

0 16.06.2020 First Issue NV US SVK


Rev. Date Revision Description Issued By Checked By Approved By

TABLE OF CONTENTS
2.0 UNIT RESPONSIBILITY...............................................................................................................................2
Page 2 of 3
Title: Specification for Spring Hanger and Support
2.1 SPRING HANGER SUPPLIER.......................................................................................................................2
4 2
6 ASSEMBLIES................................................................................................................................................3
6.1 DATA SHEETS AND DRAWINGS................................................................................................................3
6.2 INSPECTION AND TESTING.......................................................................................................................3
8 PROTECTIVE COATING................................................................................................................................3

ASME B31.8 Gas Transmission & Distribution Piping

API 6A Specification for Wellhead & Christmas Tree Equipment

MSS SP 58 Pipe Hangers & Supports: Materials, Design, Manufacture, Selection Application &
Installation

AWS D1.1 American Welding Society Structural Welding Code

2.0 UNIT RESPONSIBILITY

2.1 SPRING HANGER SUPPLIER


The responsibility of spring hanger supplier shall include design, materials, fabrication, factory setting,
protective coatings and shipping to the job site of the spring hanger assemblies detailed on data sheets
contained within the commodity specification.

be included in the design.

4
4.2 The cold setting and hot setting shall be identified by permanently attached white and red markers
respectively.

6 ASSEMBLIES
Page 3 of 3
Title: Specification for Spring Hanger and Support
The required hanger assemblies shall be detailed on data sheets included in commodity
specification.

6.1 DATA SHEETS AND DRAWINGS


6.1 The procurer shall provide the data sheets with the following; piping information, hot load, hydro test
load, travel, travel direction, overall dimensions and spring hanger assembly type.

6.2 The vendor is to provide the missing information on the hardware design such as hanger size, model
number, figure number etc. and return the data sheets with his quotations.

6.3 Weld sizes are to be shown on the assembly drawing by the vendor.

6.4 The vendor shall also provide outline drawings showing dimensioned mounting requirements for spring
hanger assemblies.

6.2 INSPECTION AND TESTING


Constant Support: Constant spring supports shall be selected to provide a total travel equal to the design
movement plus 20 % or one inch, whichever is greater.

8 PROTECTIVE COATING
All hardware and assembly shall be painted with min. 2 coats of synthetic enamel unless otherwise specified.
Spring coil shall

plate is clearly visible.

10.1 TRAVEL STOPS

10.1.1 Travel stops are to be removed and placed into their storage position after completion of the hydrostatic
testing, realignment of the piping connected to rotating machinery, and the installation of insulation.