THERMAX LIMITED

BOILER & HEATER GROUP

Document No.: QH0581-7830-210


Rev: 0
Date: 12/06/2019
Pages :09

DOCUMENT TITLE: Execution philosophy

EIL JOB NO. : A545


PACKAGE /UNIT NO.: 681-LZ-102-A/B/C/D/E/F/G & H
PR CODE : A545-680-LM-PR-7830
DORC Reference No.:
THERMAX JOB NO. : QH0581/582/583/584/585/586/587/588

SUPPLY: HEAT RECOVERY STEAM GENERATOR PACKAGE

OWNER :- DANGOTE OIL REFINING COMPANY

Project Name:

0 12.06.2019 First Issue VD VD VD


Rev. Date Purpose Prepared By Checked By Approved By
05-JUL-2019
KUMAR PRAMOD(B891)

Page 1 of 19
Thermax Limited PROJECT EXECUTION PHILOSOPHY FOR HRSG
Boiler & Heater Group CUSTOMER – DANGOTE OIL REFINING COMPANY

Boiler Brief Specifications:

Site Location Lekki FTZ, Lagos, Nigeria

Natural Circulation, Single drum, Supplementary Fired


Type/Model
HRSG

Steam Generation – 110 TPH


Parameters & Fuel Steam Pressure – 107 Kg/cm2(g)
Steam Temperature – 520 Deg C
Fuel - Natural Gas/Flue Gas/LCO/IFO
No. of units 8

EDC 6th April’17--- Project no : QH581-8

FOB Mundra Port - Material below 30T


FAS Mundra Port - Material above 30T

14 Months from EDC for Unit 1 & 2


CDC 15 Months from EDC for Unit 3 & 4
16 Months from EDC for Unit 5 & 6
17 Months from EDC for Unit 7 & 8

List of Annexures
For Signed off Scope List, Refer Annexure 1
For AVL Refer Annexure 2
Latest GA of HRSG Refer Annexure 3
Read Annexure 4, WBS specific philosophy (table) in conjunction with this
document. Shop allocation is part of this annexure 4.
For Process Improvements – Valve Release refer annexure 5

A] GENERAL

1. Dangote’s PO received on Thermax ,Mundra (SEZ) and therefore all project


material will be shipped from Mundra port only. All our PRPs will be Ti PRPs except for
Third country shipment. As of now no Third country shipment is envisaged in this job.
2. Boiler design code is as per ASME SEC-1-UN STAMPED.
3. All 8 HRSGs will be assembled in water front inside Mundra Port.
4. Please take a note of all the new WBS added for mandatory spares of individual
bought out items & for mundra assembly WBS. Engg, Materials to take necessary
accesses to PLM etc in advance to prevent hurdles during execution.
5. Mandatory spares & Commissioning spares are per unit.

Page Document No. Rev. No. Date Prepared by Approved by


05-JUL-2019
1 of 8 QH581/2017/001 1 21/4/2017 ARV NDN
KUMAR PRAMOD(B891)

Page 2 of 19
Thermax Limited PROJECT EXECUTION PHILOSOPHY FOR HRSG
Boiler & Heater Group CUSTOMER – DANGOTE OIL REFINING COMPANY

6. Since Budget & time frame are very tight, proactive care need to be taken during
execution stage by respective departments to have sufficient savings/floats while
negotiating with vendors.
7. Regarding structural material section deviation, additional vendor approval
discussions is being carried out with EIL.

B] GENERAL POINTS FOR ENGINEERING

1. When there is additional requirements w.r.t the either Contract (eg in form of
customer comments in TL or vendor documents) or Qty/weight overrun w.r.t
budget, Details of these Qty/Weight additions/overruns should be e mailed by Lead
Engg to PPM, & PPM concurrence to be taken before Baan Entries. Detailed back
up documents will be attached during Weight Overrun/Cost Overrun clearance.

2. Whichever engineering department is releasing a document through DDR they will


be the Owner of this document & they will directly get the interface inputs, other
inputs if any from other internal engg departments as per project requirement. In
case of any issue they need to escalate to engineering planner, PM, concerned
HODs as applicable. This applies to specification release & corresponding vendor
document approval also.

3. Any clarity with respect to tender should be highlighted by engineering upfront so


that we can get the clarity from EIL/Dangote during KOM. During execution phase
vendor documents should be approved after TL review process. EIL document
approval should not be linked to TL’s vendor document approval. Any additional

4. Any vendor deviations, if genuinely required needs to be taken up with EIL & settled
before issuing PO to vendor. Due to time constraints, if we need to go ahead with
ordering, PM will give the final decision regarding the same.

C] GENERAL POINTS FOR PROCUREMENT

1. Approved vendor list (AVL) is applicable & Refer annexure 1 for the same. This
vendor list also applicable for our vendor, sub vendors etc.
2. For Items not available in AVL, TL will submit vendor PTRs to EIL for approval.
3. Chinese/ East European vendors are acceptable provided they are in AVL or
comply with the EIL specification and meet PTR requirement.
4. All shelf life material manufacturing to be done only after taking written confirmation
from PM.
5. The purpose of creating new WBS for individual item spares is having a single
owner for a WBS, special focus and also to ensure separate PO & packing for
these spares which will be opened only in Dangote Site.
6. The Purpose of creating new WBS for Mundra Assembly items is to identify &
ensure special focus for Module items & ensure separate packing for the same.

Page Document No. Rev. No. Date Prepared by Approved by


05-JUL-2019
2 of 8 QH581/2017/001 1 21/4/2017 ARV NDN
KUMAR PRAMOD(B891)

Page 3 of 19
Thermax Limited PROJECT EXECUTION PHILOSOPHY FOR HRSG
Boiler & Heater Group CUSTOMER – DANGOTE OIL REFINING COMPANY

7. Attached excel file of the WBS wise execution philosophy may indicate the sourcing
plan/country of origin as per our budget basis & final decision of best vendor needs
to be taken during execution.
8. First advance for this job is awaited hence sub vendor PO will only be placed on
clearance from SBU/BU Head till the time we receive First Advance.
9. Fabrication Vendor loading & blasting/painting loading needs to be planned
meticulously to avoid any helpless situations after loading.

D] SPECIFIC POINTS
Sr
.
Details Plan of Action By Whom By When
N
o.
A Mech Engg
1. AMR revalidation for Mech 22/04/17
Superheater tubes, pipes Eng
and attemperator pipes
2. Budget, schedule basis of
B & H, TECC of all the Mech Info
structures within the Eng
module is bolted & the
same will be followed for
execution. EIL has given
clearance for IS 2062 E
250 BR structural steel in
place of S275 JR
3. IS2062 shall also be used
for plate fabricated items
Mech Info
like Casing, Ducting, Base Eng
Frame, shipping frame
etc.
4. Module to Module
connections which are to Mech Info
be done at site will be Engg
bolted.
5. Design of Structures as Mech Info
per AISC Codes may be Engg
acceptable.
6. Thermally spray aluminum
paint not applicable for Mech
this package. Engg Info

7. All Fuel Line piping,


Page Document No. Rev. No. Date Prepared by Approved by
05-JUL-2019
3 of 8 QH581/2017/001 1 21/4/2017 ARV NDN
KUMAR PRAMOD(B891)

Page 4 of 19
Thermax Limited PROJECT EXECUTION PHILOSOPHY FOR HRSG
Boiler & Heater Group CUSTOMER – DANGOTE OIL REFINING COMPANY

Sr
.
Details Plan of Action By Whom By When
N
o.
Valves shall be of SS Projects/
material after Filter upto Engg Info
Burner Inlet.
8. Fire proofing is not
applicable. Engg Info
9. NACE is not applicable for
HRSG package.

1. There will be Total 3 fuel skids-1 Process Info


B Process for Natural gas & FG, 1 for IFO/
Engg
LCO & 1 for propane
2. Steam drum holdup time 2min
Process Info
between NWL to LLT
3. The Piping B/L isolation valve
sizes shall be as per EIL P&ID Process Info
4. Corrosion allowance shall be
1mm AS tubes, 1.5mm CS tubes, Process Info
3mm for drum, casing &
duct:3mm
5. Burner shall be capable of Process Info
COMBINATION FIRING for any
ONE liquid and any ONE
gaseous fuel at the same time.
6. Minimum liner material is SS409. Process Info
However for bottom it is min SS
304 with 2 mm thk

Page Document No. Rev. No. Date Prepared by Approved by


05-JUL-2019
4 of 8 QH581/2017/001 1 21/4/2017 ARV NDN
KUMAR PRAMOD(B891)

Page 5 of 19
Thermax Limited PROJECT EXECUTION PHILOSOPHY FOR HRSG
Boiler & Heater Group CUSTOMER – DANGOTE OIL REFINING COMPANY

Sr
.
Details Plan of Action By Whom By When
N
o.

C E&I 1. All Fuel Line piping, Valves shall E & I Info


be of SS material after Filter up
to Burner Inlet including LPG
lines.
2. BMS PLC shall be SIL-3
TMR/QMR 1 per HRSG.
3. BOP PLC shall be SIL-3
TMR/QMR 1 per HRSG
4. SB PLC shall be Non SIL DMR 1
per HRSG.
5. Steam Tracing shall be provided
for all Fuel Lines.
6. All Instrumentation shall be
suitable for Zone IIA/IIB , T3 area
classification.
7. SWAS & CEMS shall be located
in Shelter with HVAC. We have
considered common Shelter
SWAS and CEMS.
8. DCS is excluded from our scope
of supply.
9. Foundation field bus Instruments
shall be considered for Closed
Loop and Open Loop other than
those used in interlocks for BMS
and BOP.
10. Intrinsically Safe Instruments to
be used for Hazardous area
protection.
11. Prefabricated Hook Ups are not
required for this Project.
12. Vortex flowmeter to be used for
Page Document No. Rev. No. Date Prepared by Approved by
05-JUL-2019
5 of 8 QH581/2017/001 1 21/4/2017 ARV NDN
KUMAR PRAMOD(B891)

Page 6 of 19
Thermax Limited PROJECT EXECUTION PHILOSOPHY FOR HRSG
Boiler & Heater Group CUSTOMER – DANGOTE OIL REFINING COMPANY

Sr
.
Details Plan of Action By Whom By When
N
o.
all applications for Line sizes 6
inch and below.
E&I Info
13. SS Junction Box shall be
provided for all FF signals.
14. 2 nos Handheld configurator is
specified for each HRSG. We
can optimize this during
execution by reducing the
quantity suitably.
15. Ultrasonic Flow meter shall be
provided only for Flare.
16. Flowmeter for Instrument Air &
Plant Air shall be vortex type.
17. Flowmeter for Cooling water shall
be electromagnetic type.
18. Temperature Transmitter shall be
provided for all Temperature
elements.
19. Field Mounted PC based HMI
with Annunciator shall be
provided for each HRSG. The
details requirement for the same
shall be discussed during detail
Engg for optimization.
20. For all fuel lines On/OFF Valve
shall be Ball Type only.
21. GWR to be used for Level
measurements below 2400mm
tapping distance. However for
Steam drum there are additional
special requirements (2 GWR + 1
EDLI for BMS, DPT for control).
22. AMC is applicable for PLC and
Analyzer. We have provided
separate quotation for AMC.
23. Instrument Cabling scope is upto
Field Junction Box. However FO
Cabling for CEMS, SWAS shall
be supplied upto Control Room.
24. Supply of cabling between BMS,
BOP, DCS, MCC is in our scope.
25. Distance between equipments
are mentioned in Tender
Page Document No. Rev. No. Date Prepared by Approved by
05-JUL-2019
6 of 8 QH581/2017/001 1 21/4/2017 ARV NDN
KUMAR PRAMOD(B891)

Page 7 of 19
Thermax Limited PROJECT EXECUTION PHILOSOPHY FOR HRSG
Boiler & Heater Group CUSTOMER – DANGOTE OIL REFINING COMPANY

Sr
.
Details Plan of Action By Whom By When
N
o.
specification.
26. LT MCC per Boiler for Motor
rating below 55KW is only our
scope. E&I Info
27. LTMCC, EMCC shall be located
in Substation 11.
28. All LT, HT Cabling from Field to
SS-11 for equipments supplied
by us is in our scope.
29. Complete Lighting (LED) within
HRSG package is in our scope.
30. PDB for MOV and Sootblower
shall be supplied by us.
31. Sootblower PDB shall be
flameproof type.
32. Microprocessor based Electrical
Control System & RTU panel
shall be supplied by us. The
exact configuration shall be
discussed with EIL during Detail
Engg stage.
33. Overground Earthing is in our
scope.
34. Hazardous area classification for
Electrical items shall be as per
IS5572.
35. Fireproofing is not applicable.
36. During the pre-kick off meeting
EIL insisted for Schneider make
PLCs since for entire Dangote
complex they are going to
procure Schneider make PLCs.
Thermax to revert on this issue.

Page Document No. Rev. No. Date Prepared by Approved by


05-JUL-2019
7 of 8 QH581/2017/001 1 21/4/2017 ARV NDN
KUMAR PRAMOD(B891)

Page 8 of 19
Thermax Limited PROJECT EXECUTION PHILOSOPHY FOR HRSG
Boiler & Heater Group CUSTOMER – DANGOTE OIL REFINING COMPANY

Sr
.
Details Plan of Action By Whom By When
N
o.
Procurement Refer WBS wise Excel format for Mat Info
D procurement & dispatch condition
portion

E QC – Material QC needs to take special care QC Info


Inspection during inspections to ensure material
with respect to TL drawings,
specifications. Any errors is supply
may lead to huge back charges
since erection is not in TL scope

For Items which are getting packed QC Info


QC – Packing in Wooden boxes - Only After
Inspection physical packing in boxes, Packing
slip to be prepared. After this
inspection, boxes needs to be
closed by vendors which needs to
be witnessed QC.
Packing slip needs to be signed off
between vendor & QC prior to
dispatch. It should contain Name &
contact no of QC personnel who
ever have cleared the consignment.
Pressure will not be put on QC for
urgency during packing inspection.
Even after this, if any shortage is
observed within the individual boxes
with respect to packing slip it will be
processed by QC & they will be the
single point contact for arranging the
material from vendor through
functional departments as per site
requirement. This philosophy will
apply to all the items & not restricted
to Hardware.

Page Document No. Rev. No. Date Prepared by Approved by


05-JUL-2019
8 of 8 QH581/2017/001 1 21/4/2017 ARV NDN
KUMAR PRAMOD(B891)

Page 9 of 19
Refer comment sheet attached

05-JUL-2019
KUMAR PRAMOD(B891)

Page 10 of 19
THERMAX LIMITED
BOILER & HEATER GROUP
- This document is retained for information. It is vendor's
responsibility to comply with all the MR/PR requirement. If
Document No.: QH0581-7830-210 anything found missing at later stage then vendor to comply the
Rev: 0 same without any cost and time implication.
Date: 12/06/2019
Pages :09

DOCUMENT TITLE: Execution philosophy


Code: R (With Comments)
Checked by: PK
Date: 05/07/2019
EIL JOB NO. : A545
PACKAGE /UNIT NO.: 681-LZ-102-A/B/C/D/E/F/G & H
PR CODE : A545-680-LM-PR-7830
DORC Reference No.:
THERMAX JOB NO. : QH0581/582/583/584/585/586/587/588

SUPPLY: HEAT RECOVERY STEAM GENERATOR PACKAGE

OWNER :- DANGOTE OIL REFINING COMPANY

Project Name:

0 12.06.2019 First Issue VD VD VD


Rev. Date Purpose Prepared By Checked By Approved By
05-JUL-2019
KUMAR PRAMOD(B891)

Page 11 of 19
Thermax Limited PROJECT EXECUTION PHILOSOPHY FOR HRSG
Boiler & Heater Group CUSTOMER – DANGOTE OIL REFINING COMPANY

Boiler Brief Specifications:

Site Location Lekki FTZ, Lagos, Nigeria

Natural Circulation, Single drum, Supplementary Fired


Type/Model
HRSG

Steam Generation – 110 TPH


Parameters & Fuel Steam Pressure – 107 Kg/cm2(g)
Steam Temperature – 520 Deg C
Fuel - Natural Gas/Flue Gas/LCO/IFO
No. of units 8
Fuel gas
th
EDC 6 April’17--- Project no : QH581-8

FOB Mundra Port - Material below 30T


Vendor to check FAS Mundra Port - Material above 30T
and attach these
annexures 14 Months from EDC for Unit 1 & 2
CDC 15 Months from EDC for Unit 3 & 4
16 Months from EDC for Unit 5 & 6
17 Months from EDC for Unit 7 & 8

List of Annexures
For Signed off Scope List, Refer Annexure 1
For AVL Refer Annexure 2
Latest GA of HRSG Refer Annexure 3
Read Annexure 4, WBS specific philosophy (table) in conjunction with this
document. Shop allocation is part of this annexure 4.
For Process Improvements – Valve Release refer annexure 5

A] GENERAL

1. Dangote’s PO received on Thermax ,Mundra (SEZ) and therefore all project


material will be shipped from Mundra port only. All our PRPs will be Ti PRPs except for
Third country shipment. As of now no Third country shipment is envisaged in this job.
2. Boiler design code is as per ASME SEC-1-UN STAMPED.
3. All 8 HRSGs will be assembled in water front inside Mundra Port.
4. Please take a note of all the new WBS added for mandatory spares of individual
bought out items & for mundra assembly WBS. Engg, Materials to take necessary
accesses to PLM etc in advance to prevent hurdles during execution.
5. Mandatory spares & Commissioning spares are per unit.

Page Document No. Rev. No. Date Prepared by Approved by


05-JUL-2019
1 of 8 QH581/2017/001 1 21/4/2017 ARV NDN
KUMAR PRAMOD(B891)

Page 12 of 19
Thermax Limited PROJECT EXECUTION PHILOSOPHY FOR HRSG
Boiler & Heater Group CUSTOMER – DANGOTE OIL REFINING COMPANY

6. Since Budget & time frame are very tight, proactive care need to be taken during
execution stage by respective departments to have sufficient savings/floats while
negotiating with vendors.
7. Regarding structural material section deviation, additional vendor approval
discussions is being carried out with EIL.

B] GENERAL POINTS FOR ENGINEERING

1. When there is additional requirements w.r.t the either Contract (eg in form of
customer comments in TL or vendor documents) or Qty/weight overrun w.r.t
budget, Details of these Qty/Weight additions/overruns should be e mailed by Lead
Engg to PPM, & PPM concurrence to be taken before Baan Entries. Detailed back
up documents will be attached during Weight Overrun/Cost Overrun clearance.

2. Whichever engineering department is releasing a document through DDR they will


be the Owner of this document & they will directly get the interface inputs, other
inputs if any from other internal engg departments as per project requirement. In
case of any issue they need to escalate to engineering planner, PM, concerned
HODs as applicable. This applies to specification release & corresponding vendor
document approval also.

3. Any clarity with respect to tender should be highlighted by engineering upfront so


that we can get the clarity from EIL/Dangote during KOM. During execution phase
vendor documents should be approved after TL review process. EIL document
approval should not be linked to TL’s vendor document approval. Any additional

4. Any vendor deviations, if genuinely required needs to be taken up with EIL & settled
before issuing PO to vendor. Due to time constraints, if we need to go ahead with
ordering, PM will give the final decision regarding the same.

C] GENERAL POINTS FOR PROCUREMENT

1. Approved vendor list (AVL) is applicable & Refer annexure 1 for the same. This
vendor list also applicable for our vendor, sub vendors etc.
2. For Items not available in AVL, TL will submit vendor PTRs to EIL for approval.
3. Chinese/ East European vendors are acceptable provided they are in AVL or
comply with the EIL specification and meet PTR requirement.
4. All shelf life material manufacturing to be done only after taking written confirmation
from PM.
5. The purpose of creating new WBS for individual item spares is having a single
owner for a WBS, special focus and also to ensure separate PO & packing for
these spares which will be opened only in Dangote Site.
6. The Purpose of creating new WBS for Mundra Assembly items is to identify &
ensure special focus for Module items & ensure separate packing for the same.

Page Document No. Rev. No. Date Prepared by Approved by


05-JUL-2019
2 of 8 QH581/2017/001 1 21/4/2017 ARV NDN
KUMAR PRAMOD(B891)

Page 13 of 19
Thermax Limited PROJECT EXECUTION PHILOSOPHY FOR HRSG
Boiler & Heater Group CUSTOMER – DANGOTE OIL REFINING COMPANY

7. Attached excel file of the WBS wise execution philosophy may indicate the sourcing
plan/country of origin as per our budget basis & final decision of best vendor needs
to be taken during execution.
8. First advance for this job is awaited hence sub vendor PO will only be placed on
clearance from SBU/BU Head till the time we receive First Advance.
9. Fabrication Vendor loading & blasting/painting loading needs to be planned
meticulously to avoid any helpless situations after loading.

D] SPECIFIC POINTS
Sr
.
Details Plan of Action By Whom By When
N
o.
A Mech Engg
1. AMR revalidation for Mech 22/04/17
Superheater tubes, pipes Eng
and attemperator pipes
2. Budget, schedule basis of
B & H, TECC of all the Mech Info
structures within the Eng
module is bolted & the
same will be followed for
execution. EIL has given
clearance for IS 2062 E
250 BR structural steel in
place of S275 JR
3. IS2062 shall also be used
for plate fabricated items
Mech Info
like Casing, Ducting, Base Eng
Frame, shipping frame
etc.
4. Module to Module
connections which are to Mech Info
be done at site will be Engg
bolted.
5. Design of Structures as Mech Info
per AISC Codes may be Engg
acceptable.
6. Thermally spray aluminum
paint not applicable for Mech
this package. Engg Info

7. All Fuel Line piping,


Page Document No. Rev. No. Date Prepared by Approved by
05-JUL-2019
3 of 8 QH581/2017/001 1 21/4/2017 ARV NDN
KUMAR PRAMOD(B891)

Page 14 of 19
Thermax Limited PROJECT EXECUTION PHILOSOPHY FOR HRSG
Boiler & Heater Group CUSTOMER – DANGOTE OIL REFINING COMPANY

Sr
.
Details Plan of Action By Whom By When
N
o.
Valves shall be of SS Projects/
material after Filter upto Engg Info
Burner Inlet.
8. Fire proofing is not
applicable. Engg Info
9. NACE is not applicable for
HRSG package.

1. There will be Total 3 fuel skids-1 Process Info


B Process for Natural gas & FG, 1 for IFO/
Engg
LCO & 1 for propane
2. Steam drum holdup time 2min
Process Info
between NWL to LLT
3. The Piping B/L isolation valve
sizes shall be as per EIL P&ID Process Info
4. Corrosion allowance shall be
1mm AS tubes, 1.5mm CS tubes, Process Info
3mm for drum, casing &
duct:3mm
Corrosion 5. Burner shall be capable of Process Info
allowance for drum COMBINATION FIRING for any
internals shall be ONE liquid and any ONE
1.5 mm shall also gaseous fuel at the same time.
be mentioned 6. Minimum liner material is SS409. Process Info
However for bottom it is min SS
304 with 2 mm thk

Page Document No. Rev. No. Date Prepared by Approved by


05-JUL-2019
4 of 8 QH581/2017/001 1 21/4/2017 ARV NDN
KUMAR PRAMOD(B891)

Page 15 of 19
Thermax Limited PROJECT EXECUTION PHILOSOPHY FOR HRSG
Boiler & Heater Group CUSTOMER – DANGOTE OIL REFINING COMPANY

Sr
.
Details Plan of Action By Whom By When
N
o.

C E&I 1. All Fuel Line piping, Valves shall E & I Info


be of SS material after Filter up
to Burner Inlet including LPG
lines.
2. BMS PLC shall be SIL-3
TMR/QMR 1 per HRSG.
3. BOP PLC shall be SIL-3
TMR/QMR 1 per HRSG
4. SB PLC shall be Non SIL DMR 1
per HRSG.
5. Steam Tracing shall be provided
for all Fuel Lines.
6. All Instrumentation shall be
suitable for Zone IIA/IIB , T3 area
classification.
7. SWAS & CEMS shall be located
in Shelter with HVAC. We have
considered common Shelter
SWAS and CEMS.
8. DCS is excluded from our scope
of supply.
9. Foundation field bus Instruments
shall be considered for Closed
Loop and Open Loop other than
those used in interlocks for BMS
and BOP.
10. Intrinsically Safe Instruments to
be used for Hazardous area
protection.
11. Prefabricated Hook Ups are not
required for this Project.
12. Vortex flowmeter to be used for
Page Document No. Rev. No. Date Prepared by Approved by
05-JUL-2019
5 of 8 QH581/2017/001 1 21/4/2017 ARV NDN
KUMAR PRAMOD(B891)

Page 16 of 19
Thermax Limited PROJECT EXECUTION PHILOSOPHY FOR HRSG
Boiler & Heater Group CUSTOMER – DANGOTE OIL REFINING COMPANY

Sr
.
Details Plan of Action By Whom By When
N
o.
all applications for Line sizes 6
inch and below.
E&I Info
13. SS Junction Box shall be
provided for all FF signals.
14. 2 nos Handheld configurator is
specified for each HRSG. We
can optimize this during
execution by reducing the
quantity suitably.
15. Ultrasonic Flow meter shall be
provided only for Flare.
16. Flowmeter for Instrument Air &
Plant Air shall be vortex type.
17. Flowmeter for Cooling water shall
be electromagnetic type.
18. Temperature Transmitter shall be
provided for all Temperature
elements.
19. Field Mounted PC based HMI
with Annunciator shall be
provided for each HRSG. The
details requirement for the same
shall be discussed during detail
Engg for optimization.
20. For all fuel lines On/OFF Valve
shall be Ball Type only.
21. GWR to be used for Level
measurements below 2400mm
tapping distance. However for
Steam drum there are additional
special requirements (2 GWR + 1
EDLI for BMS, DPT for control).
22. AMC is applicable for PLC and
Analyzer. We have provided
separate quotation for AMC.
23. Instrument Cabling scope is upto
Field Junction Box. However FO
Cabling for CEMS, SWAS shall
be supplied upto Control Room.
24. Supply of cabling between BMS,
BOP, DCS, MCC is in our scope.
25. Distance between equipments
are mentioned in Tender
Page Document No. Rev. No. Date Prepared by Approved by
05-JUL-2019
6 of 8 QH581/2017/001 1 21/4/2017 ARV NDN
KUMAR PRAMOD(B891)

Page 17 of 19
Thermax Limited PROJECT EXECUTION PHILOSOPHY FOR HRSG
Boiler & Heater Group CUSTOMER – DANGOTE OIL REFINING COMPANY

Sr
.
Details Plan of Action By Whom By When
N
o.
specification.
26. LT MCC per Boiler for Motor
rating below 55KW is only our
scope. E&I Info
27. LTMCC, EMCC shall be located
in Substation 11.
28. All LT, HT Cabling from Field to
SS-11 for equipments supplied
by us is in our scope.
29. Complete Lighting (LED) within
HRSG package is in our scope.
30. PDB for MOV and Sootblower
shall be supplied by us.
31. Sootblower PDB shall be
flameproof type.
32. Microprocessor based Electrical
Control System & RTU panel
shall be supplied by us. The
exact configuration shall be
discussed with EIL during Detail
Engg stage.
33. Overground Earthing is in our
scope.
34. Hazardous area classification for
Electrical items shall be as per
IS5572.
35. Fireproofing is not applicable.
36. During the pre-kick off meeting
EIL insisted for Schneider make
PLCs since for entire Dangote
complex they are going to
procure Schneider make PLCs.
Thermax to revert on this issue.

Page Document No. Rev. No. Date Prepared by Approved by


05-JUL-2019
7 of 8 QH581/2017/001 1 21/4/2017 ARV NDN
KUMAR PRAMOD(B891)

Page 18 of 19
Thermax Limited PROJECT EXECUTION PHILOSOPHY FOR HRSG
Boiler & Heater Group CUSTOMER – DANGOTE OIL REFINING COMPANY

Sr
.
Details Plan of Action By Whom By When
N
o.
Procurement Refer WBS wise Excel format for Mat Info
D procurement & dispatch condition
portion

E QC – Material QC needs to take special care QC Info


Inspection during inspections to ensure material
with respect to TL drawings,
specifications. Any errors is supply
may lead to huge back charges
since erection is not in TL scope

For Items which are getting packed QC Info


QC – Packing in Wooden boxes - Only After
Inspection physical packing in boxes, Packing
slip to be prepared. After this
inspection, boxes needs to be
closed by vendors which needs to
be witnessed QC.
Packing slip needs to be signed off
between vendor & QC prior to
dispatch. It should contain Name &
contact no of QC personnel who
ever have cleared the consignment.
Pressure will not be put on QC for
urgency during packing inspection.
Even after this, if any shortage is
observed within the individual boxes
with respect to packing slip it will be
processed by QC & they will be the
single point contact for arranging the
material from vendor through
functional departments as per site
requirement. This philosophy will
apply to all the items & not restricted
to Hardware.

Page Document No. Rev. No. Date Prepared by Approved by


05-JUL-2019
8 of 8 QH581/2017/001 1 21/4/2017 ARV NDN
KUMAR PRAMOD(B891)

Page 19 of 19

Potrebbero piacerti anche