ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION - INSTALL EI-17-272-A322
PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION A: PLANNING INFORMATION
AIRCRAFT REGISTRATION (To be filled by Planning):

PART NUMBER AND SERIAL NUMBER (To be filled by Planning):

EFFECTIVE DATE:
25.Dec.2017

ATA-CHAPTER:
27(FLIGHT CONTROLS)

TYPE OF CHANGE:
EI/RI:APRD DATA,OEM,TC DATA

MAINTENANCE CLASSIFICATION:
HEAVY MAINTENANCE

COMPLIANCE:

MANDATORY

TYPE OF MODIFICATION/TASK:
Aircraft/Airframe

Component

MISCELLANEOUS:
Cabin Layout Change Yes No

Other Pax modification Yes No

Inspection Yes No

Document with hardtime limit

Document with repetitive interval

APPROVAL/SIGNATURE:
PREPARED BY: CHECKED BY: APPROVED BY:

NAME: Srihari Ayyavari NAME: Vivek R NAME: Meenakshisundaram.R

LC: LC: VVR LC:


SYY RJP
DATE: 26 Dec 2017 DATE: 26 Dec 2017 DATE: 26 Dec 2017

FORM NO. TSF1001R06 1 OF 5


produced byAMOS www.swiss-as.com
ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION - INSTALL EI-17-272-A322
PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION A: PLANNING INFORMATION
REVISION HISTORY:
REV DATE DESCRIPTION
A 25.Dec.2017 [ZDM][LUT][ANM] INITIAL ISSUE

EFFECTIVITY:
Title A/C-TYPE NEW P/N RANGE
SB CONF 004 A320 S/N
S/N RANGES: SERIAL NO FROM SERIAL NO TO INCL/EXCL
2162 4989 INCLUDED
2162 EXCLUDED
2183 EXCLUDED
2425 EXCLUDED
3582 EXCLUDED
TIME REQUIREMENT: DIM-TYPE BASE LINE DIMENSION AMOUNT/DATE Tolerance
Before Calendar Days 31.Dec.2021 +0D/-0D
SHOP PLANNING: SHOP/SKILL EST-MAN EST-MANHOUR TOTAL
ELECTRICAL WORK 1.0 20:00 = 20:00
REQUIRED PART NO DESCRIPTION UM QTY REQ REQ
271245A25R01 MOD KIT SB 27-1245 EA 1.0 100%
271245D10R02 MOD KIT SB 27-1245 EA 1.0 100%
D9100095215695 PLACARD SB 27-1245 EA 1.0 100%
27-1245 MODKIT1 MOD KIT SB 27-1245 EA 1.0 100%
27-1245 MODKIT2 MOD KIT SB 27-1245 EA 1.0 100%

Title A/C-TYPE NEW P/N RANGE


A320 S/N
S/N RANGES: SERIAL NO FROM SERIAL NO TO INCL/EXCL
INCLUDED ALL
TIME REQUIREMENT: DIM-TYPE BASE LINE DIMENSION AMOUNT/DATE Tolerance
Before Calendar Days 18.Dec.2021 +0D/-0D
SHOP PLANNING: SHOP/SKILL EST-MAN EST-MANHOUR TOTAL
ELECTRICAL WORK 1.0 20:00 = 20:00

Title A/C-TYPE NEW P/N RANGE


SB CONF 003 A320 S/N
S/N RANGES: SERIAL NO FROM SERIAL NO TO INCL/EXCL
2162 INCLUDED
2183 INCLUDED
2425 INCLUDED
TIME REQUIREMENT: DIM-TYPE BASE LINE DIMENSION AMOUNT/DATE Tolerance
Before Calendar Days 31.Dec.2021 +0D/-0D
SHOP PLANNING: SHOP/SKILL EST-MAN EST-MANHOUR TOTAL
ELECTRICAL WORK 1.0 20:00 = 20:00
REQUIRED PART NO DESCRIPTION UM QTY REQ REQ
271245A22R01 MOD KIT SB 27-1245 EA 1.0 100%
271245D10R02 MOD KIT SB 27-1245 EA 1.0 100%
D9100095215695 PLACARD SB 27-1245 EA 1.0 100%
27-1245 MODKIT1 MOD KIT SB 27-1245 EA 1.0 100%
27-1245 MODKIT2 MOD KIT SB 27-1245 EA 1.0 100%

FORM NO. TSF1001R06 2 OF 5


produced byAMOS www.swiss-as.com
ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION - INSTALL EI-17-272-A322
PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION A: PLANNING INFORMATION

Title A/C-TYPE NEW P/N RANGE


SB CONF 007 A320 S/N
S/N RANGES: SERIAL NO FROM SERIAL NO TO INCL/EXCL
3582 INCLUDED
TIME REQUIREMENT: DIM-TYPE BASE LINE DIMENSION AMOUNT/DATE Tolerance
Before Calendar Days 31.Dec.2021 +0D/-0D
SHOP PLANNING: SHOP/SKILL EST-MAN EST-MANHOUR TOTAL
ELECTRICAL WORK 1.0 20:00 = 20:00
REQUIRED PART NO DESCRIPTION UM QTY REQ REQ
271245A09R01 MOD KIT SB 27-1245 EA 1.0 100%
271245D10R02 MOD KIT SB 27-1245 EA 1.0 100%
D9100095215695 PLACARD SB 27-1245 EA 1.0 100%
27-1245 MODKIT1 MOD KIT SB 27-1245 EA 1.0 100%
27-1245 MODKIT2 MOD KIT SB 27-1245 EA 1.0 100%

REFERENCES:
DOC NO DOC-TYPE REVISION REV DATE ISSUED BY
06-20-00, 06-31-53, 06-41-52 AMM LATE --- AIRBUS S.A.S.
06-41-53, 11-00-00, 12-34-24 AMM LATE --- AIRBUS S.A.S.
20-16-00, 20-21-11, 20-21-15 AMM LATE --- AIRBUS S.A.S.
20-28-00, 21-26-00, 22-96-00 AMM LATE --- AIRBUS S.A.S.
20-32-20, 20-33-00, 20-33-11 ESPM LATE --- AIRBUS S.A.S.
20-33-44, 20-42-12, 20-42-13 ESPM LATE --- AIRBUS S.A.S.
20-43-10, 20-43-12, 20-44-51 ESPM LATE --- AIRBUS S.A.S.
20-51-12, 20-51-15, 20-51-21 ESPM LATE --- AIRBUS S.A.S.
20-51-22, 20-51-50, 20-52-10 ESPM LATE --- AIRBUS S.A.S.
20-52-21, 20-52-24, 20-54-50 ESPM LATE --- AIRBUS S.A.S.
20-54-55, 20-55-00, 20-56-51 ESPM LATE --- AIRBUS S.A.S.
22-97-00, 24-38-51, 24-41-00 AMM LATE --- AIRBUS S.A.S.
25-54-11, 25-54-12, 27-40-00 AMM LATE --- AIRBUS S.A.S.
27-41-00, 31-50-00, 31-60-00 AMM LATE --- AIRBUS S.A.S.
33-13-00, 33-14-00, 52-30-00 AMM LATE --- AIRBUS S.A.S.
51-24-00, 51-42-00, 51-43-00 SRM LATE --- AIRBUS S.A.S.
51-44-00, 51-44-11, 51-75-12 SRM LATE --- AIRBUS S.A.S.
53-42-14, 73-25-34 AMM LATE --- AIRBUS S.A.S.

DOCUMENT CLASSIFICATIONS:
APPROVAL BASIS: OEM SB
WORK CLASS: MODIFICATION
TECH FIELD: STRUCTURE
TECH FIELD: ELECTRICAL SYSTEMS
UPDATE: WEIGHT CHANGE

COST ESTIMATES:
LABOUR COST PER A/C MATERIAL COST PER A/C EST. TOTAL COST (ALL AFFECTED)
2'960.00 MYR 2'894.30 MYR 134'648.90 MYR

FORM NO. TSF1001R06 3 OF 5


produced byAMOS www.swiss-as.com
ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION - INSTALL EI-17-272-A322
PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION A: PLANNING INFORMATION
TEXT
REVISION DETAIL:
Initial issue.

THRESHOLD ACTION:
Perform task per Section B

INTERVAL ACTION:
Nil.

TERMINATING REQUIREMENT:
Nil.

NOTICE TO DEPARTMENT:
1. Planning to schedule EI. It is recommended to perform this EI
together with EI-17-273-A322 & EI-17-274-A322.
2. Material to ensure part availability.

DESCRIPTION:
1. Modify the Equipment and Wiring in the rear C/B Panel 121VU
2. Modify the Wiring between the Cockpit and the Avionics Compartment
3. Modify the Terminal Block 7105VT
4. Install the Additional Brackets Between Frame 72 and 73
5. Modify the Wiring of the Bundles 4214VB/4227VB

REASON:
To install the wiring provisions for ELSD installation.

CONCURRENT REQUIREMENT:
Nil.

IF ACCOMPLISHED PER PREVIOUS REVISION, MORE WORK NECESSARY:


N/A

SUMMARY OF DATA JUSTIFICATION:


This EI is in accordance with SB A320-27-1245

EFFECT ON ENVIRONMENTAL CONDITION:


Nil.

LIMITATION:
Nil.

CONTINUED AIRWORTHINESS:
Nil.

PUBLICATION CHANGE:
ASM, AWL, AWM, IPC

FORM NO. TSF1001R06 4 OF 5


produced byAMOS www.swiss-as.com
ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION - INSTALL EI-17-272-A322
PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION A: PLANNING INFORMATION

NUMBER OF PAGES IN SECTION B:


44

NOTE: The manpower estimates given in this Instruction (if any) are
based on the direct labour cost to do the work. These estimates
assume that the work will be done by experienced personnel, and may
need to be revised upwards to suit circumstances. The estimates do
not include the time to prepare, plan or inspect the work.
Manufacture and procurement of parts and tools, drying times for
paints, sealants, etc., and general administration work are also not
included.

REMARKS
1. MSN 2162, 2183, 2425 & 3582 will use a different placard P/N on
location FIN 33LM. Details are in Section B of this EI.

2. i) Mod Kit PN 27-1245 MODKIT1 is a combination of kit PN


271245A01R03 + 4 EA washer PN NAS1149F0316P.

ii) Mod Kit PN 27-1245 MODKIT1 is also equivalent to Mod Kit PN


271245A01R04.
Either one PN 27-1245 MODKIT1 or PN 271245A01R04 can be used to
perform this EI.

3. i) Mod Kit PN 27-1245 MODKIT2 is a combination of kit PN


271245D04R00 + 2 EA terminal PN EN3155-016M2018 + 1 EA terminal PN
EN3155-016M2222 + 1 EA Nut PN NSA5110-08-1.

ii) Mod Kit PN 27-1245 MODKIT2 is also equivalent to Mod Kit PN


271245D04R03.
Either one PN 27-1245 MODKIT2 or PN 271245D04R03 can be used to
perform this EI.

FORM NO. TSF1001R06 5 OF 5


produced byAMOS www.swiss-as.com
ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION –
EI-17-272-A322
INSTALL PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION B: ACCOMPLISHMENT INSTRUCTIONS

A. GENERAL INFORMATION

WARNING:​ MAKE SURE THAT YOU OBEY ALL THE WARNINGS AND ALL THE CAUTIONS INCLUDED IN THE
REFERENCED PROCEDURES.

CAUTION:​ ALWAYS OBEY THE PRECAUTIONS THAT FOLLOW TO KEEP ELECTRICAL WIRING IN A
SATISFACTORY CONDITION (ELECTRICALLY AND MECHANICALLY SERVICEABLE). WHEN YOU
DO MAINTENANCE WORK, REPAIRS OR MODIFICATIONS, ALWAYS KEEP ELECTRICAL WIRING,
COMPONENTS AND THE WORK AREA AS CLEAN AS POSSIBLE. TO DO THIS:

- PUT PROTECTION, SUCH AS PLASTIC SHEETING, CLOTHS, ETC. AS NECESSARY ON WIRING


AND COMPONENTS.

- REGULARLY REMOVE ALL SHAVINGS, UNWANTED MATERIAL AND OTHER CONTAMINATION.


THESE PRECAUTIONS WILL DECREASE THE RISK OF CONTAMINATION AND DAMAGE TO THE
ELECTRICAL WIRING INSTALLATION.

IF THERE IS CONTAMINATION, REFER TO ESPM 20-55-00.

B. WORK INSTRUCTION

I. GENERAL

(1) Standard Practices

(a) For circuit breaker safety practices, refer to AMM Task 20-16-00-912-001.

(b) For the Frame (FR) identification, refer to AMM 06-31-53, Page Block 001.

(c) For the identification of zones, refer to AMM 06-20-00, Page Block 001.

(d) For the identification of access panels, refer to AMM 06-41-52, Page Block 001 and AMM 06-41-53, Page
Block 001.

(e) For the wires and electrical bundle identification, refer to ESPM 20-32-20.

(f) For the general installation of electrical wire harnesses, refer to ESPM 20-33-00.

(g) For the installation of the wiring, refer to ESPM 20-33-11.

(h) For the installation of stow wire, refer to ESPM 20-42-13 and ESPM 20-54-55.

(i) For the general installation of splices, refer to ESPM 20-43-10.

(j) For the installation of parallel splices, refer to ESPM 20-43-12.

(k) Do a check of the electrical connectors before you connect them, refer to ESPM 20-52-10.

FORM NO. TSF1001R06 1 OF 44


ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION –
EI-17-272-A322
INSTALL PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION B: ACCOMPLISHMENT INSTRUCTIONS

(l) To install new wires, cut them to the necessary length, crimp the terminals and connect them.

(m) Route the new wire with the wires that are in the aircraft.

(n) Use existing spare conduits to route wires in locations with difficult access.

(o) For the cable tie application and tooling, refer to ESPM 20-33-44 and ESPM 20-56-51.

(p) For the protection of the connectors, contacts and terminals, refer to ESPM 20-54-50.

(q) Do a continuity test of the new and/or modified electrical wires, refer to ESPM 20-52-21.

(r) For the torque procedure of the electrical and mechanical connections, refer to ESPM 20-51-50.

(s) To torque tighten the electrical component fasteners, refer to AMM Task 20-21-15-912-001.

(t) For the replacement of the modules, refer to ESPM 20-44-51.

(u) For the locking procedure of the connectors, refer to ESPM 20-51-12.

(v) For the locking procedure of terminal blocks, refer to ESPM 20-51-15.

(w) For the installation of the shrink sleeves, refer to ESPM 20-42-12.

(x) For the electrical bonding procedure, refer to AMM Task 20-28-00-912-004 and ESPM 20-51-21.

(y) For the torque procedure of bonding lead screw, refer to ESPM 20-51-50.

(z) For the installation of bonding points, refer to ESPM 20-51-22.

(aa) For the table of maximum permitted resistance value, refer to AMM Task 20-28-00-869-002.

(ab) Put blanking caps on the disconnected electrical connectors.

(ac) Tag the parts that you must remove and retain to make the subsequent installation easier.

(ad) Put all the retained hardware in identified plastic bags and attach the bags to the related unit.

(ae) For the installation of placards, refer to AMM 11-00-00, Page Block 201.

(af) To torque tighten the standard threaded fasteners, refer to AMM Task 20-21-11-911-001.

(ag) Remove and install fasteners in accordance with SRM 51-42-00.

(ah) Obtain fastener hole diameters and drill data in accordance with SRM 51-44-00.

(ai) Obtain alternative and substitute fastener data in accordance with SRM 51-43-00.

(aj) If the length of any fastener specified in this Service Bulletin does not meet installation standards given in
SRM Chapter 51, then a fastener of the same specification, or an approved substitute, with a length which

FORM NO. TSF1001R06 2 OF 44


ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION –
EI-17-272-A322
INSTALL PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION B: ACCOMPLISHMENT INSTRUCTIONS

meets the installation standards given in SRM Chapter 51 may be used. In addition, washers may be
installed for fastener grip length in accordance with SRM Chapter 51.

(ak) Apply sealant in accordance with SRM 51-24-00.

(al) Renew the protective finish in accordance with SRM 51-75-12.

(am) For the specification of materials (Mat. No.) given in this Service Bulletin refer to Consumable Materials
List (CML).

II. PREPARATION

(1) Job Set-up

NOTE: The items given in this note shall be considered as the basic Aircraft configuration before you start a
maintenance task:

- Aircraft on the ground resting on landing gear (the ground safety locks and the wheel chocks are in
position on the landing gear)
- Engine shut down, thrust reversers closed and locked
- Aircraft in clean configuration
- Parking brake applied
- Aircraft electrical network de-energized
- Hydraulic systems depressurized
- Access to the cockpit and cabin is available
- All circuit breakers are in closed position
- All controls in NORM, AUTO or OFF position.

(a) Make sure that the aircraft is electrically grounded, refer to AMM Task 12-34-24-869-002.

(b) Put an access platform(s) in position below:

- The FWD cargo-compartment door 825


- The AFT cargo-compartment door 826
- The access door 312AR.

(c) Open the FWD cargo-compartment door 825, refer to AMM 06-41-52, Page Block 001 and AMM Task
52-30-00-860-001 or AMM Task 52-30-00-860-003 or AMM Task 52-30-00-860-005.

1​ To get access to the connector 1978VC on the RH between FR30 and FR34 or between FR35.6 and
FR35.7 remove the ceiling panel from the FWD cargo compartment, refer to AMM Task
25-54-12-000-002.

(d) Remove the FWD cargo-compartment partitions at Frame 24, refer to AMM 06-41-53, Page Block 001
and AMM Task 25-54-11-000-001.

(e) Open the AFT cargo-compartment door 826, refer to AMM 06-41-52, Page Block 001 and AMM Task
52-30-00-860-001 or AMM Task 52-30-00-860-003 or AMM Task 52-30-00-860-005.

FORM NO. TSF1001R06 3 OF 44


ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION –
EI-17-272-A322
INSTALL PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION B: ACCOMPLISHMENT INSTRUCTIONS

1​ To get access to the connector 7615VC on the RH at FR47 remove the floor panel from the AFT
cargo-compartment, refer to AMM Task 53-42-14-000-001.

(f) Open the access door 312AR.

(2) De-energize Electrical Network

(a) Make sure that the external connector(s) is (are) not connected to the aircraft receptacle(s) EXT PW.

(b) Put the warning notices in position on external power receptacle to tell persons not to connect an external
power source.

(c) Make sure that the EMER EXIT LT pushbutton switch on 25VU is on OFF position.

(d) In the cockpit, on the overhead panel 35VU release BAT pushbutton switches.

(e) Put a warning notices on panel 35VU to tell persons not to operate the batteries.

(f) Put a warning notices on refuel/defuel panel 800VU to tell persons not to operate the NORMAL
BATTERY switch.

(g) Put a warning notices in the cockpit to tell persons not to start the APU.

(h) Put a warning notices in the cockpit to tell persons not to start the ENG1,2.

(i) Battery disconnection:

1​ For job set-up, refer to the removal of the batteries, refer to AMM Task 24-38-51-000-001.
2​ Turn the knurled nut a quarter turn.
3​ Disconnect the connectors.
4​ Put blanking caps on the disconnected electrical connectors.

(j) Open, safety/lock and tag this (these) circuit breaker(s):

FORM NO. TSF1001R06 4 OF 44


ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION –
EI-17-272-A322
INSTALL PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION B: ACCOMPLISHMENT INSTRUCTIONS

(3) Remove the Equipment for access in the cockpit

(a) Remove and retain all the necessary panels to get access to the attaching points of the panel 702VU.

(b) Remove:

Refer to Fig. A-FBCAA Sheet 01


1 Panel Item (12) Retain
attached with:
2 Screw Item (9) Retain
1 Screw Item (10) Retain
1 Nut Item (11) Retain

(c) Remove the panel 702VU

Refer to Fig. A-FBCAA Sheet 01


FIN 702VU
1 Console Item (6) Retain
attached with:
4 Screw Item (8) Retain
4 Washer Item (7) Discard

FORM NO. TSF1001R06 5 OF 44


ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION –
EI-17-272-A322
INSTALL PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION B: ACCOMPLISHMENT INSTRUCTIONS

III. PROCEDURE

(1) Modify the Equipment and Wiring in the rear C/B Panel 121VU

OR

For MSN 2162, 2183 & 2425 only

For MSN 3582 only

FORM NO. TSF1001R06 6 OF 44


ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION –
EI-17-272-A322
INSTALL PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION B: ACCOMPLISHMENT INSTRUCTIONS

For MSN other than MSN 2162, 2183, 2425 & 3582

(a) Modify the equipment in the rear C/B panel 121VU.

Refer to Fig. A-FBBAA Sheet 01


Refer to AMM 11-00-00, Page Block 201
Refer to AMM Task 20-16-00-912-001
Refer to AMM Task 20-21-15-912-001
Refer to AMM Task 20-21-11-911-001

1​ Replace the placard 33LM (line P).

a​ Remove:

FIN 33LM
1 Placard D11311364A00 Item (2) Discard
NOTE​: For MSN other than MSN 2162, 2183, 2425 & 3582
or
1 Placard D11311357A00 Item (2) Discard
NOTE​: For MSN 2162, 2183 & 2425 only
or
1 Placard D11311725A00 Item (2) Discard
NOTE​: For MSN 3582 only

attached with:
5 Button Rivet Plastic ASNA2080G01 Item (3) Discard
or
5 Button Rivet Plastic ASNA2080G04 Item (4) Discard

b​ Install:

FIN 33LM
1 Placard D11312632A00 Item 2
NOTE​: For MSN other than MSN 2162, 2183, 2425 & 3582

or
1 Placard D11312819A00 Item 2
NOTE​: For MSN 2162, 2183 & 2425 only

or
1 Placard D11312630A00 Item 2
NOTE​: For MSN 3582 only

attached with:
FORM NO. TSF1001R06 7 OF 44
ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION –
EI-17-272-A322
INSTALL PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION B: ACCOMPLISHMENT INSTRUCTIONS

5 Button Rivet Plastic ASNA2080G01 Item 3


or
5 Button Rivet Plastic ASNA2080G04 Item 4
NOTE​: Install one of these PNs in relation with aircraft configuration.

2​ Open the rear C/B panel 121VU.

3​ At position P15, install:

FIN 95CE
1 Circuit Breaker EN2995-004A03AA Item 1

a​ Near the new Circuit Breaker, bond the placard identified 95CE, supplied in:
1 Placard Set D9100095215695

4​ Open, safety/lock and tag this circuit breaker:


1 Clip-Locking ABS0772A02A Item 13

(b) Modify the wiring in the rear C/B panel 121VU.

Refer to ESPM 20-33-00


Refer to ESPM 20-52-10
Refer to ESPM 20-54-50
Refer to ESPM 20-43-10
Refer to AMM 11-00-00, Page Block 201
Refer to AMM Task 20-16-00-912-001
Refer to AMM Task 20-21-15-912-001
Refer to AMM Task 20-21-11-911-001

1​ Modify the connection of the wire(s) as shown on this(these) wiring diagram(s) and the related hook-up
chart(s):
- Fig. A-FWAAA Sheet 01 and Fig. A-FHAAA Sheet 01 and if necessary use contact supplied in:

Bundle D9000095228695

2​ Install:
Refer to Fig. A-FWAAA Sheet 01
FIN 1034XP
1 Shunt NSA939526-02

3​ Near the shunt, bond the placard identified 1034XP, supplied in:
1 Placard Set D9100095215695

4​ Remove the wire(s) as shown on this(these) wiring diagram(s) and the related hook-up chart(s):
- Fig. A-FWBAA Sheet 01 and Fig. A-FHBAA Sheet 01.

5​ Install the wire(s) as shown on this(these) wiring diagram(s) and the related hook-up chart(s):

- Fig. A-FWAAA Sheet 01 and Fig. A-FHAAA Sheet 01


- Fig. A-FWBAA Sheet 01 and Fig. A-FHBAA Sheet 01, supplied in:

FORM NO. TSF1001R06 8 OF 44


ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION –
EI-17-272-A322
INSTALL PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION B: ACCOMPLISHMENT INSTRUCTIONS

Bundle D9000095228695
NOTE​: Wire 3154-2549 is not valid for this configuration.

6​ Install the splice 2429VS (PN E0360RK2424) between the wire No. 3154-1860R and the wire No.
3154-3019R, supplied in:

Bundle D9000095228695
NOTE​: If Service Bulletin No. A320-27-1248 (​EI-17-274-A322​) is accomplished simultaneously, it is not
necessary to perform this work step.

NOTE​: Identify the splice 2429VS with the identification sleeve, supplied in:

Bundle D9000095228695

7​ Do a continuity test of the new and/or modified electrical wires, refer to ESPM 20-52-21.

8​ Attach the wires with:


Refer to ESPM 20-33-44
Refer to ESPM 20-56-51

100 Tie-Cable NSA935401-03


100 Tie-Cable NSA935401-05
100 Tie-Cable NSA935401-08

(2) Modify the Wiring between the Cockpit and the Avionics Compartment

OR

(a) Modify the wiring between the cockpit and the avionics compartment:

Refer to ESPM 20-33-00


Refer to ESPM 20-52-10
Refer to ESPM 20-54-50

FORM NO. TSF1001R06 9 OF 44


ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION –
EI-17-272-A322
INSTALL PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION B: ACCOMPLISHMENT INSTRUCTIONS

1​ Modify the connection of the wire(s) as shown on this(these) wiring diagram(s) and the related hook-up
chart(s):
- Fig. A-FWCAA Sheet 01 and Fig. A-FHCAA Sheet 01 and if necessary use contacts supplied in:
Bundle D9000095228695

2​ Install the wire(s) as shown on this(these) wiring diagram(s) and the related hook-up chart(s):
- Fig. A-FWAAA Sheet 01 and Fig. A-FHAAA Sheet 01,
- Fig. A-FWCAA Sheet 01 and Fig. A-FHCAA Sheet 01, supplied in:

Bundle D9000095228695

3​ Do a continuity test of the new and/or modified electrical wires, refer to ESPM 20-52-21.

4​ Attach the wires with:


Refer to ESPM 20-33-44
Refer to ESPM 20-56-51

120 Tie-Cable NSA935401-03


120 Tie-Cable NSA935401-05
120 Tie-Cable NSA935401-08

(3) Modify the Terminal Block 7105VT

OR

FORM NO. TSF1001R06 10 OF 44


ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION –
EI-17-272-A322
INSTALL PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION B: ACCOMPLISHMENT INSTRUCTIONS

WARNING​: CUT, REMOVE AND DISCARD THE LOCKWIRE AS YOU DO THE TASK. LOOSE
LOCKWIRE CAN CUT OR BLIND YOU.

(a) At FR73 STGR6 RH, refer to Fig. A-GBAAB Sheet 02 and Fig. A-GBAAB Sheet 04, View H, remove:

1 Module Item (131) Retain


1 Module Item (132) Retain
2 Clamp-End Item (133) Retain
2 Washer Item (148) Discard
2 Bolt Item (149) Discard
1 Rail Item (158) Discard
1 Bracket Item (160) Discard
5 Rivet Item (201) Discard

(b) At FR73 STGR6 RH, refer to Fig. A-GBAAB Sheet 02 and Fig. A-GBAAB Sheet 04, View J, put the
bracket, Item 161 in position and transfer drill the holes.

(c) Clean and deburr the holes, use:

Textile - Lint Free Cotton 14SBA1 As required


made moist with:
Non Aqueous Cleaner – General 08BAA9 As required

(d) At FR73 STGR6 RH, refer to Fig. A-GBAAB Sheet 02 and Fig. A-GBAAB Sheet 04, View J and in
accordance with SRM 51-24-00, install:

1 Bracket D9249174523600 Item 161


5 Rivet EN6081AD4-14 Item 201
with
Polysulfide Sealant - General Purpose Interfay 06AAC1 As required

(e) Remove any excess sealant.

(f) Restore the internal surface protection on the fasteners, apply:

FORM NO. TSF1001R06 11 OF 44


ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION –
EI-17-272-A322
INSTALL PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION B: ACCOMPLISHMENT INSTRUCTIONS

Wash Primer – Structure 04CMA2 As required


Primer Polyurethane Paint – Corrosion Inhibiting 04EAC2 As required
Top Coat Polyurethane – Grey Internal Structure 04JME4 As required

(g) Get the rail, Item 179 and modules, Item 180 from:

1 Equipment D9299708101400 or D9299708105400

1​ At bracket, Item 161, refer to Fig. A-GBAAB Sheet 04, View J, install:

1 Module Item (131) Retained at removal


1 Module Item (132) Retained at removal
1 Rail NSA937901RB0090 Item 179
2 Module NSA937901M20-04 Item 180
1 Module NSA937901M22-03 Item 192
2 Screw NAS1801-08-8 Item 162
2 Washer NAS1149DN816K Item 163
2 Clipnut NSA5110-08-1 Item 164

2​ At bracket, Item 161, refer to Fig. A-GBAAB Sheet 02 and Fig. A-GBAAB Sheet 04, View J, install:

2 Clamp-End Item (133) Retained at removal

lock with:
Wire-Locking Dia: 0.6 mm Cres Nickel Alloy 14QEB1 As required

(h) Get the placards, Item 181, Item 182 and Item 194 from:

1 Equipment D9299708101400 or D9299708105400

1​ On the modules, Item 180, refer to Fig. A-GBAAB Sheet 04, View J, install:
1 Placard NSA937901E8 Item 181
1 Placard NSA937901E9 Item 182

2​ On the module, Item 192, refer to Fig. A-GBAAB Sheet 04, View J, install:

1 Placard NSA937901E10 Item 194

FORM NO. TSF1001R06 12 OF 44


ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION –
EI-17-272-A322
INSTALL PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION B: ACCOMPLISHMENT INSTRUCTIONS

(4) Install the Additional Brackets Between Frame 72 and 73

OR

FORM NO. TSF1001R06 13 OF 44


ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION –
EI-17-272-A322
INSTALL PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION B: ACCOMPLISHMENT INSTRUCTIONS

(a) At STGR4 RH, between FR72 and FR73, refer to Fig. A-GBAAB Sheet 02, View F and Fig. A-GBAAB
Sheet 03, View G, put the bracket, Item 150 in position and transfer drill the holes.

(b) Clean and deburr the holes, use:

Textile - Lint Free Cotton 14SBA1 As required


made moist with:
Non Aqueous Cleaner – General 08BAA9 As required

(c) At STGR4 RH, between FR72 and FR73, refer to Fig. A-GBAAB Sheet 02, View F and Fig. A-GBAAB
Sheet 03, View G, wet install:

1 Bracket ABS0785B05A Item 150


2 Rivet EN6081AD4-14 Item 201
with
Polysulfide Sealant - General Purpose Interfay 06AAC1 As required

(d) Remove any excess sealant.

(e) At bracket, Item 150, refer to Fig. A-GBAAB Sheet 05, View L, install:

1 Spacer NSA5527-03-02 Item 106


1 Screw NAS1801-08-20 Item 151
2 Bracket NSA935504-02 Item 156
1 Washer NAS1149DN816K Item 163
1 Clipnut NSA5110-08-1 Item 164

(f) Between FR72 and FR73 and STGR1 LH and STGR1 RH, refer to Fig. A-GBAAB Sheet 01, Fig.
A-GBAAB Sheet 08, View S and Fig. A-GBAAB Sheet 09, View T, clean the area with:

Textile - Lint Free Cotton 14SBA1 As required


made moist with
Non Aqueous Cleaner – General 08BAA9 As required

(g) Between FR72 and FR73 as shown in Fig. A-GBAAB Sheet 08, View S, drill the pilot holes in accordance
with SRM 51-44-11.

(h) Between FR72 and FR73 as shown in Fig. A-GBAAB Sheet 09, View T, put the Brackets, Item 170, 171,
172 and 173, in position and transfer drill the holes in accordance with SRM 51-44-11.

(i) Between FR72 and FR73 as shown in Fig. A-GBAAB Sheet 09, View T, in accordance with SRM
51-42-00, install:

1 Angle D9249174523400 Item 170


1 Bracket D9249174523200 Item 171
1 Angle D9249174523000 Item 172
1 Angle D9249174522800 Item 173
with
9 Rivet EN6081AD4-05 Item 165

FORM NO. TSF1001R06 14 OF 44


ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION –
EI-17-272-A322
INSTALL PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION B: ACCOMPLISHMENT INSTRUCTIONS

4 Rivet EN6081D5-06 Item 166


4 Rivet EN6081D5-05-5 Item 167

(j) Between FR72 and FR73 and STGR2 RH, refer to Fig. A-GBAAB Sheet 01, Views C and U, clean the
area shown with:

Textile - Lint Free Cotton 14SBA1 As required


made moist with
Non Aqueous Cleaner – General 08BAA9 As required

(k) Between FR72 and FR73 as shown in Fig. A-GBAAB Sheet 10, Views U and V, put the Bracket, Item
195, in position and transfer drill the hole diameters to between 4.06 mm (0.160 in.) and 4.17 mm (0.164
in.) in accordance with SRM 51-44-11.

(l) Between FR72 and FR73 as shown in Fig. A-GBAAB Sheet 10, Views U and V, in accordance with SRM
51-42-00, install:

1 Angle D9249174521800 Item 195


4 Rivet EN6081D5-06 Item 166

(m) Restore the internal surface protection on the fasteners, apply:

Wash Primer – Structure 04CMA2 As required


Primer Polyurethane Paint - Corrosion Inhibiting 04EAC2 As required
Top Coat Polyurethane – Grey Internal Structure 04JME4 As required

(5) Modify the Wiring of the Bundles 4214VB/4227VB

OR

FORM NO. TSF1001R06 15 OF 44


ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION –
EI-17-272-A322
INSTALL PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION B: ACCOMPLISHMENT INSTRUCTIONS

(a) At FR71 to FR73, between STGR22 RH and STGR5 RH, refer to Fig. A-GBAAB Sheet 02, View E and
Fig. A-GBAAB Sheet 05, View K, remove:

As required Cable Tie Item (159) Discard

(b) Get the placard, Item 169, and the sleeves, Item 193, from:

1 Equipment D9299708101400 or D9299708105400

(c) Between FR72 and FR73, reroute, install and connect the electrical wires, refer to Fig. A-GWAAC Sheet
01, Fig. A-GWAAC Sheet 02, Fig. A-GHAAC Sheet 01, END 2, Lines 1 thru 8 and 20 and 21, Fig.
A-GBAAB Sheet 01, View C, Fig. A-GBAAB Sheet 02, View E and Fig. A-GBAAB Sheet 05, Views L and
M, use:

20 Cable Tie NSA935401-06 Item 159


1 Placard E0248A2-4H9 Item 169
1 Stow Sleeve NSA936603CC0100 Item 193
1 Wire 2793-5994 Item 186
1 Wire 2793-5995 Item 187
1 Wire 2793-5899 Item 188

(d) At connector 9CE-H, refer to Fig. A-GBAAB Sheet 06, View N and Fig. A-GBAAB Sheet 07, Views P, Q
and R, remove:

As required Cable Tie Item (159) Discard


1 Bolt Item (113) Retain
1 Washer Item (103) Retain
1 Clamp Item (118) Retain
1 Spacer Item (111) Retain
1 Tubing Item (166) Discard
1 Tubing Item (167) Discard
2 Nut Item (122) Retain
2 Bolt Item (124) Retain
2 Washer Item (121) Retain
1 Bonding Lead Item (141) Retain
2 Washer Item (125) Retain
2 Clamp Item (123) Retain
1 Bonding Lead Item (142) Retain
1 Clamp Item (140) Retain
1 Lightning Protection Hose Item (128) Retain

FORM NO. TSF1001R06 16 OF 44


ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION –
EI-17-272-A322
INSTALL PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION B: ACCOMPLISHMENT INSTRUCTIONS

4 Socket Item (178) Discard

(e) Cut the tubing to length from:

0.26 (ME) Tubing E0126-04L


- for Item 166, 60 mm (2.362 in.)
- for Item 167, 200 mm (7.873 in.)

(f) At connector 9CE-H, refer to Fig. A-GBAAB Sheet 07, Views P and R, install:

1 Tubing E0126-04L Item 166


1 Tubing E0126-04L Item 167
1 Lightning Protection Hose Item (128) Retained at removal

(g) Get sockets, Item 178 from:

1 Equipment D9299708101400 or D9299708105400

(h) Install and connect the new electrical wires, refer to Fig. A-GWAAC Sheet 02, Fig. A-GHAAC Sheet 01,
END 1 and 2, Lines 9 thru 19 and Fig. A-GBAAB Sheet 07, View R, use:

1 Socket EN3155-019F2018 Item 178

(i) At connector 9CE-H, refer to Fig. A-GBAAB Sheet 07, Views P, Q and R, install:

1 Bolt Item (113) Retained at removal


1 Washer Item (103) Retained at removal
1 Clamp Item (118) Retained at removal
1 Spacer Item (111) Retained at removal
2 Nut Item (122) Retained at removal
2 Bolt Item (124) Retained at removal
2 Washer Item (121) Retained at removal
1 Bonding Lead Item (141) Retained at removal
2 Washer Item (125) Retained at removal
2 Clamp Item (123) Retained at removal
1 Bonding Lead Item (142) Retained at removal
1 Clamp Item (140) Retained at removal

(j) Lock the connector 9CE-H with:

Wire-Locking Dia: 0.6 mm Cres Nickel Alloy 14QEB1 As required

(k) Protect the bonding contact areas with:

Polysulfide Sealant - Fuel Tank Brushable 06ABA1 As required


Varnish – Electrical Bonding Structure 04TMB2 As required

(l) Install a placard on the bundle 4214VB/4227VB between Frame (FR)33 and FR35, FR46 and FR48 and
at FR66 and FR73, refer to Fig. A-GBAAB Sheet 01, View D, use:

FORM NO. TSF1001R06 17 OF 44


ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION –
EI-17-272-A322
INSTALL PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION B: ACCOMPLISHMENT INSTRUCTIONS

1 Placard-Set D9239206410000 Item 200

NOTE​: The Placard Set contains 4 placards.

IV. TEST

(1) Energize Electrical Network

(a) Job set-up:

1​ Battery re-connection:

a​ For job set-up, refer to the installation of the batteries, refer to AMM Task 24-38-51-400-001.
b​ Remove the blanking cap from the electrical connectors.
c​ Make sure that the electrical connectors are clean and in correct condition.
d​ Connect the connector on the battery.
e​ Turn the knurled nut a quarter turn.

2​ Remove all the warning notices.

3​ Make sure that this circuit breaker is open (safety clip):

4​ Energize the aircraft electrical circuits, refer to AMM Task 24-41-00-861-002.

5​ Voltage check:

a​ Do a voltage check at pin 1 of each following circuit breaker to make sure that there is 26VAC:
- 121VU: 95CE.

(2) Testing for the Modification of the Equipment and the Wiring in the rear C/B 121VU Panel and for the
Modification of the Wiring between the Cockpit and the Avionics Compartment

(a) Preliminary Tests:

NOTE​: If the aircraft is operated in CAT 3 conditions, you must also do the Land CAT 3 Capability Test,
refer to AMM Task 22-97-00-710-001.

1​ Do the operational test of the instrument and panel integral lighting, refer to AMM Task
33-13-00-710-001.

2​ Do the operational test of the light, refer to AMM Task 33-14-00-710-001.

FORM NO. TSF1001R06 18 OF 44


ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION –
EI-17-272-A322
INSTALL PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION B: ACCOMPLISHMENT INSTRUCTIONS

3​ Do the operational check of the avionics equipment ventilation-system via Multipurpose Control and
Display Unit (MCDU), refer to AMM Task 21-26-00-710-001.

4​ Do the operational test of the Automatic Flight System (AFS), refer to AMM Task 22-96-00-710-001.

5​ Do the operational test of the Electronic Instrument System (EIS), refer to AMM Task
31-60-00-710-001.

6​ Do the operational test of the Electronic Centralized Aircraft Monitoring (ECAM) control panel, refer to
AMM Task 31-50-00-710-004.

7​ Do the ground scanning of the central warning system, refer to AMM Task 31-50-00-710-001.

(b) Procedure:

1​ Test of the C/Bs (95CE, 15WN or 146RH and 2CN):

a​ Do the operational test of the Circuit Breaker Monitoring System (CBMS) for panel 121VU, refer to
AMM Task 31-50-00-710-005.

2​ Test of the connectors (84VC, 112VC, 120VC, 2216VC):

a​ Do an operational test of the Engine Interface Unit (EIU), refer to AMM Task 73-25-34-710-040 for
Aircraft equipped with CFM International (CFMI) engines or refer to AMM Task 73-25-34-710-043 for
Aircraft equipped with CFMB engines or refer to AMM Task 73-25-34-710-042) for Aircraft equipped
with International Aero Engines (IAE) engines or refer to AMM Task 73-25-34-710-801 for Aircraft
equipped with Pratt and Whitney (PW) engines.

(3) Testing

(a) Remove the safety clip(s) and/or tag(s) and close/unlock this (these) circuit breaker(s):

FORM NO. TSF1001R06 19 OF 44


ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION –
EI-17-272-A322
INSTALL PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION B: ACCOMPLISHMENT INSTRUCTIONS

(b) Do a continuity test, refer to ESPM 20-52-21.

(c) Do a insulation test, refer to ESPM 20-52-24.

(d) Check the synchronization between pitch trim hand wheel and stabilizer, refer to AMM Task
27-40-00-040-001.

(e) Do the system test of the THS actuator electrical control, refer to AMM Task 27-41-00-730-001.

(f) Check the Zero Adjustment of the THS, refer to AMM Task 27-41-00-220-003.

V. CLOSE-UP

(1) Install the Equipment removed for access in the cockpit

OR

(a) Install:

Refer to Fig. A-FBCAA Sheet 01


FORM NO. TSF1001R06 20 OF 44
ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION –
EI-17-272-A322
INSTALL PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION B: ACCOMPLISHMENT INSTRUCTIONS

FIN 702VU
1 Console Item (6) Retained at removal
attach with:
4 Washer NAS1149F0316P Item 7
4 Screw Item (8) Retained at removal
1 Panel Item (12) Retained at removal
attach with:
2 Screw Item (9) Retained at removal
1 Screw Item (10) Retained at removal
1 Nut Item (11) Retained at removal
NOTE​: Install the panels removed to get access to the attaching points of the panel 702VU.

(2) Close-up

(a) Make sure that the work areas are clean and clear of tools and other items of equipment.

(b) In the FWD cargo-compartment install the ceiling panel, refer to AMM Task 25-54-12-400-002.

(c) In the AFT cargo-compartment install the floor panel, refer to AMM Task 53-42-14-400-001.

(d) Install the FWD cargo-compartment partitions at Frame 24, refer to AMM 06-41-53, Page Block 001 and
AMM Task 25-54-11-400-001.

(e) Close the FWD cargo-compartment door 825 and AFT cargo-compartment door 826, refer to AMM
06-41-52, Page Block 001 and AMM Task 52-30-00-860-002 or AMM Task 52-30-00-860-004 or AMM
Task 52-30-00-860-009.

(f) Close the access door 312AR.

(g) Remove the access platform(s).

(h) Put the aircraft back to its initial configuration.

FORM NO. TSF1001R06 21 OF 44


ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION –
EI-17-272-A322
INSTALL PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION B: ACCOMPLISHMENT INSTRUCTIONS

FORM NO. TSF1001R06 22 OF 44


ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION –
EI-17-272-A322
INSTALL PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION B: ACCOMPLISHMENT INSTRUCTIONS

FORM NO. TSF1001R06 23 OF 44


ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION –
EI-17-272-A322
INSTALL PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION B: ACCOMPLISHMENT INSTRUCTIONS

FORM NO. TSF1001R06 24 OF 44


ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION –
EI-17-272-A322
INSTALL PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION B: ACCOMPLISHMENT INSTRUCTIONS

FORM NO. TSF1001R06 25 OF 44


ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION –
EI-17-272-A322
INSTALL PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION B: ACCOMPLISHMENT INSTRUCTIONS

FORM NO. TSF1001R06 26 OF 44


ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION –
EI-17-272-A322
INSTALL PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION B: ACCOMPLISHMENT INSTRUCTIONS

FORM NO. TSF1001R06 27 OF 44


ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION –
EI-17-272-A322
INSTALL PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION B: ACCOMPLISHMENT INSTRUCTIONS

FORM NO. TSF1001R06 28 OF 44


ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION –
EI-17-272-A322
INSTALL PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION B: ACCOMPLISHMENT INSTRUCTIONS

FORM NO. TSF1001R06 29 OF 44


ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION –
EI-17-272-A322
INSTALL PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION B: ACCOMPLISHMENT INSTRUCTIONS

FORM NO. TSF1001R06 30 OF 44


ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION –
EI-17-272-A322
INSTALL PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION B: ACCOMPLISHMENT INSTRUCTIONS

FORM NO. TSF1001R06 31 OF 44


ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION –
EI-17-272-A322
INSTALL PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION B: ACCOMPLISHMENT INSTRUCTIONS

FORM NO. TSF1001R06 32 OF 44


ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION –
EI-17-272-A322
INSTALL PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION B: ACCOMPLISHMENT INSTRUCTIONS

FORM NO. TSF1001R06 33 OF 44


ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION –
EI-17-272-A322
INSTALL PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION B: ACCOMPLISHMENT INSTRUCTIONS

FORM NO. TSF1001R06 34 OF 44


ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION –
EI-17-272-A322
INSTALL PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION B: ACCOMPLISHMENT INSTRUCTIONS

FORM NO. TSF1001R06 35 OF 44


ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION –
EI-17-272-A322
INSTALL PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION B: ACCOMPLISHMENT INSTRUCTIONS

FORM NO. TSF1001R06 36 OF 44


ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION –
EI-17-272-A322
INSTALL PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION B: ACCOMPLISHMENT INSTRUCTIONS

FORM NO. TSF1001R06 37 OF 44


ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION –
EI-17-272-A322
INSTALL PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION B: ACCOMPLISHMENT INSTRUCTIONS

FORM NO. TSF1001R06 38 OF 44


ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION –
EI-17-272-A322
INSTALL PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION B: ACCOMPLISHMENT INSTRUCTIONS

FORM NO. TSF1001R06 39 OF 44


ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION –
EI-17-272-A322
INSTALL PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION B: ACCOMPLISHMENT INSTRUCTIONS

FORM NO. TSF1001R06 40 OF 44


ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION –
EI-17-272-A322
INSTALL PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION B: ACCOMPLISHMENT INSTRUCTIONS

FORM NO. TSF1001R06 41 OF 44


ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION –
EI-17-272-A322
INSTALL PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION B: ACCOMPLISHMENT INSTRUCTIONS

FORM NO. TSF1001R06 42 OF 44


ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION –
EI-17-272-A322
INSTALL PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION B: ACCOMPLISHMENT INSTRUCTIONS

FORM NO. TSF1001R06 43 OF 44


ENGINEERING INSTRUCTION

SUBJECT: DOCUMENT NO:


FLIGHT CONTROLS - THS HYDRAULIC ACTUATION –
EI-17-272-A322
INSTALL PROVISIONS FOR ELSD INSTALLATION
REVISION DATE: REV:

25.Dec.2017 A
SECTION B: ACCOMPLISHMENT INSTRUCTIONS

FORM NO. TSF1001R06 44 OF 44


EI/RI CERTIFICATION SHEET
DOCUMENT NO: REV: A/C REGN: PART NUMBER: SERIAL NUMBER:
or
EI-17-272-A322 A
TYPE OF COMPLIANCE ACTION: PART/SECT. TO BE PERFORMED: TRADE: ZONE: STATION:
Once Off Repeat
First Accomplishment Terminating
NOTE: TECHNICAL LOG (e.g. MR1, etc):
NDT report is required for every NDT task.
Raise applicable form for Duplicate Inspection / Require Inspection Item / Critical
Task Inspection and state the control number of the form in action taken field.
RESULTS/FINDINGS: AME
Sign, Stamp & Date

ACTION TAKEN & CROSS REFERENCES: AME


Sign, Stamp & Date

CRS STATEMENT:
Certifies that the work specified except as otherwise specified was carried out in accordance with CAR-145 and in respect to that work the
VT
aircraft/aircraft component is considered ready for release to service
DATE COMPLETED: TAH/TSN: TAC/CSN: ACTUAL MANHOUR: ACTUAL MANPOWER: TOTAL ELAPSED TIME:

DESCRIPTION P/N ON S/N ON P/N OFF S/N OFF BATCH NO QTY

USE ADDITIONAL SHEET IF REQUIRED BY MAKING COPY OF THIS PAGE


NOTE: Technical Records to perform Status Reporting of the EI/RI in AMOS. EI/RI which is related to OEM SB, Technical Records to report the SB
status in the OEM web portal.