Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Engineering Structures
journal homepage: www.elsevier.com/locate/engstruct
Short communication
A R T I C L E I N F O A B S T R A C T
Keywords: This paper describes an investigation into the collapse mode of a single-span, segmental post-tensioned concrete
Post-tensioned concrete beam bridge caused both by the effect of chloride induced corrosion in Prestressed Post Tensioned Bridge and by some
Collapse mechanism initial faults during tendons design. Collapse was determined by the breakage of the tendons and the wires inside
Corrosion the tendons appear completely rusted.
Manufacturing lacks
A numerical investigation was also carried out in order to determine the local mechanisms that led to the
collapse of a segment of the Petrulla Viaduct in the south of Italy (Sicily) after a widespread beam damage was
found. The main damage is the consequence of both an inadequate grout cementitious mortar filling, capable of
introducing chemicals by which corrosion travelled along the tendons, and an inadequate distance among the
ducts employed. The latter produces rotation of the wings around a point in the transversal section.
1. Introduction or notches that are under stress. The dissolved hydrogen then assists in
the fracture of the metal.
Many of the bridges built in Italy are Prestressed or Post Tensioned Documented cases of prestressed tension members failure as a result
(PT) concrete girders where the tendons are the main load-carrying of corrosion make this a most pressing problem. Since prestressed
elements. The advantages of PT bridges compared to bridges con- concrete members rely on the tensile strength of the prestressing steels
structed using conventional reinforcement include greater span length, to resist loads, loss of even few wires or strands per member [3] could
structural efficiency, reduced materials, and a more streamlined ap- result catastrophic.
pearance. Although prestressed concrete members were generally Damage during service, frequently appearing after several years or
manufactured with concrete of relatively higher strength, time has decades of exploitation, is usually most consequential. The lacking or
shown that they are subject to the same adverse effects of reinforcement insufficiently alkaline protection already from the beginning or its loss
corrosion as reinforced concrete members are. Corrosion can take many due to carbonation and/or depassivation after chloride attack are the
forms beyond that which occurs with a great loss of material; for ex- major causes of later damage or even of a failure. Responsible for that
ample corrosion may occur by the interaction of corrosion and me- are usually the failures caused by shortcomings in planning and/or
chanical stress to produce a failure by cracking. This type of failure is execution as well as inaccurate or inefficient structural measures.
known as stress corrosion cracking, often abbreviated to SCC [1,2]. SCC Execution faults and construction errors concern e.g. the injection of the
is an insidious form of corrosion; it produces a marked loss of me- ducts with mortar in case of post tensioned concrete (a mortar-free
chanical strength with little metal loss; the damage is not obvious to section of tendons is exposed to the risk of corrosion, when penetration
casual inspection and the stress corrosion cracks can trigger mechanical of moisture is possible and oxygen can enter the duct space), the con-
fast fracture and catastrophic failure of components and structures. crete technology (too small concrete cover and too low concrete
Besides, when cracking is clearly a result of hydrogen embrittle- quality, under certain conditions not protect. The prestressing tendons,
ment, is called as hydrogen attack. In fact, hydrogen dissolves in all the procedure (technology) of the production of the structural elements,
metals to a moderate extent. It is a very small atom that fits in between as well as waterproof sealing (not present or damaged) and drainage
the metal atoms in the crystals of the metal [4]. Consequently it can (damaged), can strongly affect the durability of PT elements.
diffuse much more rapidly than larger atoms. The use of poor quality materials and poor construction practices
Hydrogen tends to be attracted to regions of high triaxial tensile accelerate and aggravate the problem of corrosion, so that actually, the
stress where the metal structure is dilated as the regions ahead of cracks annual cost of corrosion was estimated to be very high [5–8].
⁎
Corresponding author.
E-mail addresses: lanania@dica.unict.it (L. Anania), abadala@dica.unict.it (A. Badalà), gdagata@dica.unict.it (G. D'Agata).
https://doi.org/10.1016/j.engstruct.2018.02.039
Received 22 November 2016; Received in revised form 4 January 2018; Accepted 12 February 2018
0141-0296/ © 2018 Elsevier Ltd. All rights reserved.
L. Anania et al. Engineering Structures 162 (2018) 226–244
So, a brittle collapse of the bridge deck may be caused by a number failure of the prestressing tendons as a consequence of their dete-
of design deficiencies (individually or combined), namely: (i) in- rioration through corrosion (Figs. 5 and 6). In the mid span of the
adequate duct venting, (ii) incomplete duct filling, (iii) strands pressing collapsed span, the complete dissolution of some strands in tendons
against the duct interior surface, (iv) strand congestion, (v) subsidence, numbered as No. (number) 4 and 5 can be observed. But the collapse
or (vi) poor consistency with segregation [13,14]. was due also to some design lacks in the PT beam (i.e.: no gap presence
In Italy, research on steel corrosion [9] is more focused on re- among the ducts and inappropriate grout for prestressed concrete ten-
inforced concrete (RC) structures than on Post tensioned concrete dons). As reported in Fig. 5 the tendon numbered as 4 and 5 and ori-
structures. PT structures adequately designed and constructed have ginally composed by 12 strands, now present only 7 strands. The
been generally considered highly durable because the prestressing breakage of the tendons produced the expulsion of the ducts anchorages
tendons would be protected from corrosion by the duct filling. But, at the head beam due to the release of elastic energy (Figs. 7 and 8).
some deterioration problems due to corrosion have been discovered in
some existing bridges, raising serious concerns about the long-term 4. Analysis of Petrulla viaduct executive project
durability [10] of PT bridges. In this kind of concrete structures, the
high stress level in the tendons strongly modifies the steel corrosion According to the original project, the single longitudinal beam was
process [11,12]. pre-stressed by means of five tendons realized by twelve strands of
Macrocell corrosion with a local anode and a large cathode fre- 0.6 in. each. So according to Standard Production Italian Specifications
quently occurs in chloride induced corrosion of rebars in concrete and is Law Act 1086-1971 and Following Revisions for the 7 wire strands, the
responsible for very high local corrosion attacks and reduction in cross- strand nominal diameter and the nominal area will be 15.20 mm and
section. In PT beam with inadequate grout and protection of the ten- 140 mm2 respectively. Then, each tendon exhibits a cross section (or
donds, the process is equal to the mild reinforcement corrosion: in fact, equivalent diameter) of 1680 mm2. The tendons layout is derived from
the mild reinforcing in concrete is normally protected from corrosion by the original executive project and represented in Fig. 9 in which the
the passive film formed at the steel/concrete interface inside the alka- position of each tendon (in figure called ‘cavo’ according to the Italian
line cementitious matrix. But, if the passivity is compromised, than language) and the corresponding anchor-head regions are represented.
active corrosion may occur at an unacceptable rate. For instance, this It’s worth to note that for the “cavo 4” and “cavo 5” (called tendon No.4
passivation can be eliminated either by a decrease in the pH value and tendon No. 5 in the following) the anchor-head region is on the
(pH < 9) due to carbonation, or by the presence of chloride salts, extrados of the deck beam. Fig. 10, shows the strand disposition in the
which initiate an expansive corrosion of the reinforcing steel and mid span. The pretension of the tendons was applied in progressive
eventually damage the surrounding concrete. steps i.e. No. 1–3, tendons were fully tensioned at the beginning, before
The importance of chloride ion in the corrosion of steel in concrete the bridge erection, while No. 5–6 tendons were tensioned up to 35% of
has been developed into the concept of chloride threshold level. the specified tensile strength after the transversal beams construction.
Chloride threshold level is defined as the chloride content at steel depth The other 65% of the specified pretension was applied after the casting
which is necessary to sustain local passive film breakdown and to in- and hardening of the deck slab.
itiate corrosion process [15–17]. So, chloride threshold level can re- During the construction, tendons no. 4 and no. 5 of Fig. 10 were
present a key element in predicting the life service of structures exposed tensioned at the end, to achieve 100% of the specified pre-stress to be
to environmental conditions [18]. applied in the tendons. To this aim some slots at the extrados of the
Concrete structures such as bridges, buildings and other reinforced deck slab had to be filled by grout after tensioning (Fig. 11). Thus, a
concrete structures might suffer severe damages due to macrocell cor- volume of potential accumulation of water for saturation of the con-
rosion [19–21]. crete, is created and this allows the entrance of aggressive ions.
This is partly due to the shrinkage during the curing of the concrete
2. The case studied: Petrulla bridge collapse used to fill the holes, which results in the formation of cold joints at the
interface between the old and new concrete. This is necessary to com-
The case studied is a forensic analysis for the collapse of the Petrulla plete the existing slab, from which bleed water infiltrates and perco-
viaduct. The viaduct is constituted by n. 13 simple supported deck with lates, accumulating in the tank arranged in the prefabricated beam in
span variable from 35 to 50 m long. It is located in south of Italy, in in a the cap, up to the saturation of the mortar injection of the cables.
city, Licata, of Sicily island at both ‘Salso river’ and sea proximity. The From the original project, in the cross section at the mid span of the
name of the river derived by the Italian word ‘salsedine’ that means PT beam, the tendons, placed in a duct of 70 mm in diameter, converge
saltiness. The environmental condition can be considered as aggressive. into a narrow space (Fig. 10), which does not meet the minimum gap
The viaduct was built in the early ‘80s. The original as-built project required by the international codes (ACI 318 – R 18.16, Grout for
were approved in 1985. It was designed according to the Italian Code in bonding prestressed tendons) [24]. Therefore, a right constipation of
force at the time of the executive project (D.M. 1980) [28]. The viaduct the concrete during the cast is not ensured. This is unable to develop
was mainly devoted to vehicular traffic concerning to the transport of and disseminate the tangential stresses due to the adherence [22,23].
raw materials for agriculture as fertilizers and similar. In fact, it is in According to Eurocode 2 [25], in fact, for ducts of 70 mm, the required
countryside, far away from urban center. The Fig. 1 shows the global gap among the tendons must not be less than the duct diameter. In the
aerial view of the bridge and its location to the river proximity. case studied, no gap was found among the tendons and this caused the
So this viaduct is constituted by multiple bridge span. Each single formation of voids as shown in Figs. 12 and 13. As will be explained and
span is made up of four longitudinal post tensioned double tee beams. shown in detail in the section devoted to the FEM analysis, these gaps
The superstructure of the viaduct is supported by ten piers. The sche- caused the implosion of the cross section of the deck, with inward ro-
matization of the typical deck span is represented in Fig. 2. Concrete tation of the lower flanges, resulting in expulsion for tensile of the mild
slab completes the bridge deck. reinforcement placed along the section web. A uniform rust distribution
In August 2014, a span of the viaduct suddenly collapsed. The col- can be noted along both the tendons and the duct.
lapse mode consisted in forming a plastic hinge in the mid-span of a The internal tendons located inside the structural concrete section,
bridge beam as shown in Figs. 3 and 4. are housed in corrugated metal ducts, and bonded to the structural
concrete by means of cementitious grout. In the past, there have been
3. On site inspection of Petrulla viaduct no problems due to using grout, capable of filling the interstitial spaces
between tendons and ducts for the bonding of prestressing tendons,
The inspection, after collapsing, revealed fractured strands and with portland cement as the cementing material capable of preventing
227
L. Anania et al. Engineering Structures 162 (2018) 226–244
Salso River
Collapsed Span
Petrulla Viaduct
Mediterranean sea
Fig. 1. Global aerial view of the bridge.
any introduction of chemicals listed as harmful to tendons. bridge, which induced variations in tensile forces among the tendon
Nowadays, International Standards list the basic requirements for and neutral axis depth with a conseguent failure of one or more strands
the grout for prestressed concrete structures [26,27]. In fact, while the and a re-distribution of the applied load.
first line of corrosion protection of grouted PT tendon relies on ade- An important warning sign of the imminent collapse could have
quate sealing of ducts from external sources of corrodants (i.e., water, been noticed by a severe and characteristic crack pattern, present in all
air, Cl–, and carbon dioxide), the second line of corrosion protection the other adjacent bridge spans [26]. Figs. 16 and 17 show the cracking
relies on direct contact of strands with a cementitious grout for which a induced by the implosion of the section, premonitory of collapse, due to
high pH (> 13) is maintained. In situ inspection, on the collapsed span the combined effect of both the corrosion and internal voids because of
shows the presence of an inadequate grout, consisting of a clear mortar no gap among the ducts.
(Fig. 15) and not of portland cement (dark grey color) as required by
international standards. As we can observe in the collapsed bridge beam 5. Hardened concrete characterization
span, the mortar was completely crumbled or absent in many points
(Fig. 14), because it lacked consistency. This would have been im- The main physical-mechanical characteristics of the materials em-
possible for a cement mortar of suitable resistance (not less than ployed were investigated by means of an accurate campaign of tests.
30 Mpa). This kind of material favored the collection of chloride and The object of this investigation was both the collapsed span (No. 10) as
moisture inside the tendons, especially in the presence of air due to the well as the nearby span identified in the project with the number 9. A
voids as well as to the aggressive environment. Corrosion induced a set of concrete cores for the estimation of the actual compressive
variation of the cross-sectionional of the individual tendons in PT strength have been tested. To this aim, some concrete cores with
Fig. 2. Typical deck span of the bridge (geometrical characteristics are in cm).
228
L. Anania et al. Engineering Structures 162 (2018) 226–244
229
L. Anania et al. Engineering Structures 162 (2018) 226–244
Fig. 7 and 8 . (7) Expulsion of the ducts head anchorages. (8) Global view of the expulsion at the head of the girder beam.
Fig. 9. Prescribed pattern of the tendons along the PT beam in the original project (cavo = Tendons).
Cold joints
Fig. 11. Detail of the head anchorage holes for the tendons numbered as 4 and 5.
Fig. 10. Mid span cross section of the PT beam derived from the original project
(cavo = Tendon).
230
L. Anania et al. Engineering Structures 162 (2018) 226–244
Fig. 15. View of the non-Portland cement grout for the bonding of tendons and advanced
corrosion of both duct and strands.
Fig. 17. Detailed view of vertical mild reinforcement expelled by the rotation of the lower
Fig. 14. View of the tendons in collapsed span.
flange.
231
L. Anania et al. Engineering Structures 162 (2018) 226–244
Fig. 18. Sample extraction of the collapsed span (a) slab, (b) I beam.
1
2
3 4
11
5 6 7 8 9 10
Table 1 Similar considerations can be made also for spans that have not yet
Localization of in site drilled core for the compressive strength estimation-collapsed span. collapsed, where resistance values not lower than 48.9 MPa were ob-
tained, with an average value of 68.75 MPa corresponding to theore-
Collapsed span 10
tical cubic design strength of 71.0 MPa.
Sample for compressive strength assessment
n.3 concrete drills (D = h=100 mm) on n. 3 beams; C1-C2-C3
n.3 concrete drills (D = h=100 mm) on the slab; S1-S2-S3 5.2. Young modulus assessment
Samples for Elastic Modulus determination (UNI 6556)
n.3 concrete drills (D = 60; h = 150 mm) on n.3 beam; E1-E2-E3 The determination of the E secant modulus of elasticity, is carried
n.3 drills (D = 60; h = 150 mm) on the slab Es1-Es2-Es3 out in accordance with UNI 6556/76 [29], by the measurement of the
deflection increments corresponding to the application of loading and
unloading cycles (at least three) up to a maximum test strength equal to
The concrete used was of excellent quality, and would correspond to about one third of the compressive strength of the concrete. To de-
a class of resistance far superior to that provided for the project (Rck termine secant elastic modulus we starts from a base stress σ0, equal to
40 MPa), equivalent to approximately Rck 72 MPa. A low dispersion in 1/10 of the maximum stress of σn test. The experimental data is sum-
the results is visible in the sample of the collapsed span. This is prob- marized in Tables 6 and 7, where abbreviation D, H and A have the
ably due to a not continuous control of the concrete batching at the same meaning given above and σi are the intermediate stress values
time of the construction. recorded during the tests.
232
L. Anania et al. Engineering Structures 162 (2018) 226–244
Table 2
Localization of in site drilled core for the compressive strength estimation- collapsed span.
Span no 9:
Table 3
Carbonation depth on drilled cores.
C1 320 30 30 S1 360 0 25 apparent that the tensile strength of concrete is almost equal to 1/16 of
C2 180 25 25 S2 330 7 10
the compression one. Figs. 24 and 25 show, respectively, a specimen in
C3 200 30 25 S3 370 8 30
C4 160 38 – S4 360 6 –
testing machine and a typical broken sample after the test.
C5 180 35 – S5 330 6 –
C6 240 35 35 S6 370 6 –
6. Chloride content in the grout in the ducts
The grout inside the ducts might also act as a secondary protection
to the PT tendon. To this aim, a necessary condition for strand pro-
tection is that Cl is maintained below a critical concentration–, either as
a background grout contaminant or from an external source.
The European Standards UNI EN 206 at sect. 5.2.6 list a range be-
A B tween 0.1 and 0.2 wt (wt) percent cement as the acid soluble Cl− limit
for PT grout or prestressed concrete. American Standard [31,32] lists
this upper limit as 0.08 wt% cement. This threshold was also found in
the literature [33,34]. In sufficient concentration, Cl– facilitates corro-
sion of PT strand by transitioning steel from a passive state, for which
corrosion rate is negligible, to an active one where corrosion rate may
be unacceptably high and reducing grout electrical resistivity. The aim
of this section is to highlight possible deficiencies of the grout employed
during the bridge construction. From the standpoint of strand corro-
sion, a worst case scenario arises in situations where the grout is sub-
jected to repetitive wetting (presumably from periodic water infiltra-
Fig. 22. Example of Phenolphthalein on the drilled core.
tion from a source external to the duct) and drying. In the case studied,
during the rains periodic water infiltrations occur from the cold joint at
The value of the modulus of elasticity becomes useful in the cal- the anchor-head region of tendons No. 4 and 5. Asphalt drainage waters
culation process. transport hydrocarbon deposits and various chemicals which percolates
along the tendons.
5.3. Tensile strength estimation on drilled core According to UNI 9944 [35] and UNI 196-2 [36] the sulfates and
chlorides content can be assessed. All samples were dried in an oven at
The determination of the value of the tensile strength of the con- 105° ± 5°, and then cooled and treated with an acid solution. In the
crete drilled cores were carried out according to the UNI EN 12390-6 specific case the sample showed a concentration of chlorides of 0.24%
[30] Tensile splitting strength of test specimens. Tables 8 and 9 summar- weight cement, higher than both the European and American standard
ized the data obtained for the collapsed span and No. 9, respectively limits. Samples also show a concentration of sulfates equal to 1.77
where F is the load applied and fct is the tensile strength measured. It is lower that UNI EN 197-1:2006 threshold.
233
L. Anania et al. Engineering Structures 162 (2018) 226–244
Table 4
Ultimate strength for drilled concrete cores- collapsed span.
7. Mild reinforcement and strands mechanical characterization topography on samples, while the latter are most valuable for illus-
trating contrasts in composition in multiphase samples. X-ray genera-
Samples of both mild reinforcement bars and tendons were taken tion is produced by inelastic collisions of the incident electrons with
from the viaduct in order to carry out a series of tests aimed to the electrons in discrete orbital (shells) of atoms in the sample.
assessment of the tensile strength, the nominal diameter as well as for Characteristic X-rays are produced for each element in a mineral that is
chemical investigations. “excited” by the electron beam.
The report of data obtained for the sample extracted from the col-
7.1. Tensile strength determination lapsed span, is in Figs. 28 and 29. The presence of steel oxide confirms
that an active corrosion occurred on the tendons; this was accelerated
For the mild reinforcement a yielding strength fy higher than by the complete dissolution of the ducts, so many strands get particu-
600 MPa was measured. This value is in good accordance with modern larly severe conditions due to the air-water interface caused by the
steel reinforcement belonging to B450C class according to Italian voids among the tendons. Therefore, poor intergranular or transgra-
Codes. nular cracks are visible in the microstructure of the fractured surface,
Three samples of the prestressing steel 1000 mm long, were taken such as that stress corrosion cracking phenomena can be considered as
from three parts of the collapsed span, to measure the nominal diameter not responsible of the collapse of the bridge [37]. In fact, Stress Cor-
(Aeq), ultimate tensile strength (fpt), 0.2% proof strength, (fp(0.2), 1% rosion Cracking (SCC) determines a minimal overall loss of the mate-
proof strength (fp(1)), the modulus of Elasticity (E) as well as elongation rial. On the contrary, in the case study, a great loss of the overall ma-
(Agt). The latter mechanical characteristics, were assessed by an ex- terial was found.
tensometer gauge 600 mm long. The data obtained are summarized in
Table 10 where the symbol Tn=1,2,3 indicates to the sample tested.
Sample T3 was taken from most damaged strand of the broken tendons 8. FEM Analysis
at the mid span of the beam. The least damaged part of the broken
strand was selected to this aim, samples T1 and T2 were taken from the The study and the comprehension of the collapse mechanism of the
head of the girder collapsed beam (Fig. 26). span, as well as the mechanisms of spread damage due to the implosion
A drastic cross section area reduction is evident in the T3 sample as of the PT beam, was carried out by means of a non-linear FEM analysis,
shown in Fig. 27. Moving away from the damaged zone there was a using the SAP 2000 software [38].
reduction up to 26.42% of the original area of the some strands found in The numerical investigation was carried out by referring to two
situ and of the cross section area (equivalent diameter) of the tendon. main models where many different cases were considered for each
model.
7.2. SEM analysis on the strands The mechanical properties implemented in the numerical model
were derived directly from the tests carried out on the concrete cores,
In the specific case the SEM analysis carried out on the extracted the mild reinforcement and the strands.
samples was finalized to demonstrate the presence of sodium chloride The first model considers the whole 3-dimensional structure of the
as consequence of a misuse, at the construction time, of not appropriate PT beam. Firstly, in order to validate the original project results, the
water in the grout mixture. The SEM analysis, in fact, aims to perform a bridge was firstly analyzed by accounting for the design values of the
chemical analysis of the sample and it is performed by means of a employed materials, then by considering the average material strength
scanning electron microscope. A beam of electrons accelerated by an under the effect of the corrosion as obtained from laboratory tests.
electric field, and focused by an electromagnetic lens system, strikes the The second model studied only the transversal section of the studied
sample and explores a specific surface by means of a scanning device. beam was developed with the average material strength and accounting
These signals include secondary electrons and backscattered electrons; for the corrosion effect and the mistakes noted after the collapse
the former are commonly most valuable for showing morphology and
Table 5
Ultimate strength for drilled concrete cores-span No. 9.
3 2
Mv [kg/m ] Dmax [mm] W [g] D [mm] H [mm] A [mm ] C [N] Rc [N/mm2]
234
L. Anania et al. Engineering Structures 162 (2018) 226–244
Table 6
Elastic modulus for drilled concrete cores-collapsed span.
D [mm] H [mm] A [mm2] 6.6 [MPa] 11.1 [MPa] 15.7 [MPa] 20.2 [MPa] Modulus [MPa]
Table 7
Elastic modulus for drilled concrete cores- span No. 9.
m Geometrical features σ1 σ2 σ3 E
2
D [mm] H [mm] A [mm ] 6.6 [MPa] 11.1 [MPa] 15.7 [MPa] Modulus [MPa]
235
L. Anania et al. Engineering Structures 162 (2018) 226–244
Table 10
Parameter of the strands in situ.
Sample Deff Aeff [mm2] fp(0.2) fp(1) fpt [MPa] Agt [%] E [MPa]
[mm] [MPa] [MPa]
236
L. Anania et al. Engineering Structures 162 (2018) 226–244
237
L. Anania et al. Engineering Structures 162 (2018) 226–244
stiffness of the links with a step of 2 m along the tendons can be eval- The value applied in the SAP model was equal to −5.75E−3 m/m
uated from literature relationship kGA/s, where k is a constant equal to in terms of strain load, corresponding to a stress of 1150 MPa.
5/6, and A is the area of the grout inside the duct, defined by the dif- The Limit States of sect. 3.13 of the D.M. 2 Agosto 1980 are require
ference between the duct area and the tendon area. A final adherence to combine the individual loads with specific load factors to achieve
value equal to 166 kN/mm can be assumed by referring to a stiffness of design objectives.
the link inputted with a one meter step.
238
L. Anania et al. Engineering Structures 162 (2018) 226–244
Fig. 32. Load case stage 3–live load applied on single lane of the bridge deck.
indicated in Fig. 35 where corrosion is concentrated as the evidence of represents the closest mechanism to the real collapse mode
the in situ inspection. In the case cited above, the longitudinal stress contour reported in
After this stage, if the numerical analysis converges, a new stage is Fig. 36 is obtained at a step load very close to the collapse. The cyan
considered by reducing gradually, the cross section of the tendons from zone shows where the tensile stresses overcome the characteristic ten-
90% up to 39%. Sap code automatically calculate their relaxation. At sile strength of the concrete employed. In Fig. 37 a longitudinal shear
each stage the analysis continues from the state at end of previous non gradient is visible with a change of the sign of the shear strength. That
linear stage as schematized in Fig. 34. occurs in the same zone where a great damage was observed in the real
More than fifty models were studied by varying the number of the structure.
corroded tendons (only the No. 1–2–3- or all the tendons). Fig. 35 in-
dicated the portion of tendons where the corrosion was changed during 8.5. Local damage model
the numerical analysis. The percentage of the cross section area in re-
spect to the non-damaged one, and the stiffness of the links due to the The model used for the non linear FEM analysis (Fig. 38) represents
deterioration of the mortar grout were modified with a consequent half of the lower portion of the cross section of the PT concrete beam,
reduction of the adherence between strands and concrete. symmetrical with respect to the vertical axis. That is, a portion of a
No convergence is found when the cross section of the tendon be- thickness of 20 cm correspondent to the step of the vertical mild re-
comes equal to 39% of the original one, never under only dead load. inforcement in the span, provided in the as-built project drawings and
The reduction of 61%, equal to 660 mm2 corresponding to an equiva- detected in situ. The model was implemented by Sap2000 [38] Code
lent tendon diameter of Φ 29 mm and an estimated adherence value of using Shell Layered elements for the section and frame element for the
16.5 ton/mm per meter, agrees with the tendon residual diameter di- mild reinforcement. They are connected by Links gap reacting only in
rectly evident during on site inspection. So, it can be said that it compression. In order to highlight the post-expulsion of the vertical
Fig. 33. Live load applied on single lane of the bridge deck.
239
L. Anania et al. Engineering Structures 162 (2018) 226–244
Fig. 34. Example of load case where the tendons cross sections was changed.
LICATA
bars as well as the complex phenomena of damage observed in situ, the value for the concrete reported in Table 8, was reached.
concrete cover was not considered because it was carbonated, fragile So cracks occured along the bridge beam as documented by Figs. 40
and very thin. and 41.
The constraints (in green) restore the symmetry conditions. In the The cracking pattern of Figs. 40 and 41 is also proved by the de-
local model, loads have been applied in order to simulate the real formed scheme of Fig. 42, where the expulsion of the stirrup bars is
conditions of stresses, induced in the analyzed beam part, both by the evident in yellow color. A detailed view of the expulsed stirrups along
reactive load of the post tensioned tendons (pushing from the bottom the bridge span is represented in Fig. 42.
upwards) and by the shear stresses due to shear and torsion. The former The numerical investigation confirms the nature of the severe da-
is equivalent to a nodal vertical load of 5.8 kN each. The latter equal to mage pattern found in all the spans of the Petrulla viaduct. Moreover,
0.3 MPa were applied as surface loads acting in the face of the cross the gradual corrosion of both ducts and strands (Figs. 43 and 44), to-
section. They were assessed by the difference of the maximum shear gether with the deterioration of the inadequate mortar grouted in the
pattern, highlighted in Fig. 36 with the cyan1 color, between section duct, produced the following effects: (i) an increase of the voids for the
20 cm distant. The horizontal shear stresses were neglected. strands corrosion and reduction of the tendon cross section up to 39%
The constitutive laws of the materials employed in the local model of the as built bridge tendons; (ii) a reduction in the upward thrust
are exactly the same as the global model of the bridge. provided by the tendons, due to the great loss of the pre-stress force
Fig. 39 gives back principal tensile stresses in the concrete. A associated with re-distribution of tension; (iii) increasing of the shear
maximum value of 4.916 Mpa, higher than the experimental average stress in the beam section, due to the same stress re-distribution and to
the decreasing of the vertical load component offered by pre-stressed
tendons.
1
For interpretation of color in Fig. 36, the reader is referred to the web version of this
article.
240
L. Anania et al. Engineering Structures 162 (2018) 226–244
Breaking zones.
Tensile cracks due
to the overcoming of
the tensile resistance
of the concrete.
LICATA
Fig. 37. Longitudinal shear stress gradient on the global model of the collapsed bridge.
241
L. Anania et al. Engineering Structures 162 (2018) 226–244
Fig. 40. Cracking on the bridge span due to tensile tress and to the expulsion of the stirrups.
242
L. Anania et al. Engineering Structures 162 (2018) 226–244
Stirrup
9. Conclusions
243
L. Anania et al. Engineering Structures 162 (2018) 226–244
244