Appendix “C”

(COMPENSATION)

Page 1 of 12
ITT-20-QAI-PRJ-0017

APPENDIX “C”

COMPENSATION

1. COMPANY shall compensate CONTRACTOR for the WORK performed under the CONTRACT, as the total Lump Sum Price of USD
………………………….. amount in figures (………………... amount if words) in accordance with the following Cost Breakdown:

1.1 CONSTRUCTION WORK (PRODUCT PIPING)

UNIT PRICE
SR# ITEM DESCRIPTION UNIT QTY. TOTAL (USD) REMARKS
(USD)
1.0 PIPING WORKS
Works include shifting from store and placing of pipes &
fittings at required location for welding or threading as
indicated in project drawings or as per site requirement.
Making weld joints / thread as per ANSI B 31.3 in joining pipe
lengths and welded pipe fittings such as flanges, bends,
10% of Radiography
1.1 reducers, tees etc. The work also includes gas cutting/cold
also included .
cutting as per requirement, grinding, beveling etc. the
welding of both the faces of slip-on Flanges will be
considered as one welding joint where used, complete in all
respect as per project specifications, drawings, relevant
international/codes and tender documents.

The estimated number of joints for different pipe sizes are as


follows:

i Dia. 16" Std. Wt. Nos. 45


ii Dia. 12" Std. Wt. Nos. 190
iii Dia. 8" Std. Wt. Nos. 70
iv Dia. 6" Std. Wt. Nos. 375
v Dia. 4" Std. Wt. Nos. 275
vi Dia. 3" Std. Wt. Nos. 40

Page 2 of 12
ITT-20-QAI-PRJ-0017

vii Dia. 2" Std. Wt. Nos. 30


viii Dia. 1" Sch. 80 Nos. 165
ix Dia. 3/4" Sch. 80 Nos. 650
2.0 SURFACE PREPARATION WITH PAINTING SYSTEM:
Works include supply of all material, application of painting Painting specs and
system, surface preparation to S.A. 2.5 and apply of painting procedures shall be
2.1
system as per relevant specification, complete in all respect approved by
as per COMPANY requirement. COMPANY
i Dia. 16" m2 101
ii Dia. 12" m2 202
iii Dia. 8" m2 32
iv Dia. 6" m2 181
v Dia. 4" m2 28
vi Dia. 3" m2 4
vii Dia. 2" m2 1
vii Dia. 1" m2 1
viii Dia. 3/4" m2 1
3.0 INSTALLATION OF VALVES/STRAINERS
Installation of valves/strainers includes the placing of
It includes installation of
valves/strainers between flanges and bolting up with gasket.
3.1 Gate, Ball, Check,
Work also includes Lifting and Transportation from store and
Globe and Strainers.
unloading at work site.
i Dia. 12" Nos. 12
ii Dia. 8" Nos. 8
iii Dia. 6" Nos. 24
iv Dia. 4" Nos. 34
v Dia. 3" Nos. 4
vi Dia. 2" Nos. 4

Installation / bolting of Blind Flanges & Spectacle Blinds any


3.2 Nos. 20
diameter as per drawings.

Page 3 of 12
ITT-20-QAI-PRJ-0017

4.0 HYDROSTATIC TESTING:

CONTRACTOR shall
provide all material and
Hydrostatic testing of piping as per ASME B-31.3 for Product equipment required for
4.1 Piping of the following sizes as per project specification and hydrostatic testing,
COMPANY requirements. including supply of
potable water and
electricity for test.

i Dia. 16" m 83
ii Dia. 12" m 207
iii Dia. 8" m 48
iv Dia. 6" m 359
v Dia. 4" m 83
vi Dia. 3" m 14
vii Dia. 2" m 7
vii Dia. 1" m 14
viii Dia. 3/4" m 7
5.0 INSTALLATION OF TRV
Installation of TRV includes the placing of TRV between
5.1 flanges and bolting up with gasket. Work also includes Lifting Jobs 12
and Transportation from store and unloading at work site.
Installation of PUMS:
Installation of product pumps with all accessories on
proposed foundation. Installation of instruments tubing and
valves, testing, inspection, start-up & commissioning,
complete in all respect, as per COMPANY requirements,
scope of works, drawings, tender documents, etc. and
6.0 Jobs 4
manufacturer recommendation. Works include loading,
transportation, unloading at proposed location, placing on
foundation, leveling, supply and placing of cementitious
grouting and shims if required, hot and cold alignment,
bolting up with piping, complete in all respect as per Engineer
instruction and manufacturer recommendation.

Page 4 of 12
ITT-20-QAI-PRJ-0017

INSTALLATION OF PSV Installation of PSVs includes the


placing of PSV between flanges and bolting up with gasket.
7.0
Work also includes Lifting and Transportation from store and
unloading at work site.
i Dia. 4" x 3" Nos. 4
8.0 INSTALLATION OF METERING SKID
It includes installation of Metering Skid with all accessories
on proposed location, complete in all respect, as per
COMPANY's requirements, scope of works, drawings, tender
documents, etc. and manufacturer recommendation. Works
include loading, transportation, unloading at proposed
8.1 Jobs 6
location, placing on proposed location, leveling, supply and
placing of cementitious grouting and shims if required, hot
and cold alignment, bolting up with piping, complete in all
respect as per Engineer instruction and manufacturer
recommendation.
9.0 INSTALLATION OF TOP LOADING ARMS
Installation of Top Loading Arms at Gantry Loading Platform.
It includes the placing of loading arm at respective flange and
9.1 bolting up with gasket. Work also includes Lifting and Jobs 6
Transportation from store and unloading at work site.
10.0 INSTALLATION OF FUEL PUMPS
Installation of Fuel pumps with all accessories on proposed
foundation. Installation of instruments tubing and valves,
testing, inspection, start-up & commissioning, complete in all
respect, as per COMPANY requirements, scope of works,
drawings, tender documents, etc. and manufacturer
10.1 recommendation. Works include loading, transportation, Jobs 2
unloading at proposed location, placing on foundation,
leveling, supply and placing of cementitious grouting and
shims if required, hot and cold alignment, bolting up with
piping, complete in all respect as per Engineer instruction
and manufacturer recommendation.
12.0 INSTALLATION OF SLOP TANK

Page 5 of 12
ITT-20-QAI-PRJ-0017

Installation of horizontal Slop Tank, Dia. 1.9m x length 4.5 m


(T/T) complete with manholes and appurtenances in Slop Pit
as per project drawing and site requirements. It includes the
12.1 placing of Slop tank at respective foundation and tie-ins with Job 1
piping. Work also includes Lifting and Transportation from
store and unloading at work site. Approximate weight is 3160
Kg.

13.0 INSTALLATION OF AIR VESSEL


Installation of vertical Instrument Air Vessel Dia. 1.0 m x
height 1.3 m (T/T) complete with manholes and
appurtenances as per project drawing and site requirements.
13.1 It includes the placing of Vessel at respective foundation and Job 1
tie-ins with piping. Work also includes Lifting and
Transportation from store and unloading at work site.
Approximate weight is 672 Kg.

TOTAL (Inclusive of 7% withholding Tax)


S.NO NOTE:
The Quantities taken in this BOQ are estimated, only for bidding purpose. CONTRACTOR is responsible to estimate the
1 quantities as per site requirements, drawings & tender documents.
CONTRACTOR is responsible to add any missing / required item as per scope of works, drawings, specifications & tender
2 documents.
CONTRACTOR is responsible to estimate the quantities before going to purchase the supply items except ITEMs provided by
3 COMPANY. Any Leftover / balance items may not be taken by COMPANY.
CONTRACTOR is responsible to estimate the quantities before going to execute the job. Payments shall be made on actual
4 work done.

1.2 CONSTRUCTION WORK for (FIRE, FOAM & UTILITIES PIPING)

UNIT
SR# ITEM DESCRIPTION UNIT QTY. TOTAL REMARKS
RATE
1.0 PIPING WORKS

Page 6 of 12
ITT-20-QAI-PRJ-0017

Works include shifting from store and placing of pipes & fittings at
required location for welding or threading as indicated in project 10% of
drawings or as per site requirement. Making weld joints / thread as Radiography also
per ANSI B 31.3 in joining pipe lengths and welded pipe fittings included for new
1.1 such as flanges, bends, reducers, tees etc. The work also work and shall be
includes gas cutting/cold cutting as per requirement, grinding, as per ASME 31.3
beveling etc. the welding of both the faces of slip-on Flanges will and project
be considered as one welding joint where used, complete in all specifications
respect as per project specifications, drawings, relevant
international/codes and tender documents.

The estimated number of joints for different pipe sizes are as


follows:

i Dia. 12" Std. Wt. Nos. 6


ii Dia. 10" Std. Wt. Nos. 16
iii Dia. 6" Std. Wt. Nos. 286
iv Dia. 4" Std. Wt. Nos. 149
v Dia. 3" Std. Wt. Nos. 37
vi Dia. 2-1/2" Std. Wt. Nos. 60
vii Dia. 2" Std. Wt. Nos. 149
viii Dia. 1-1/2" Std. Wt. Nos. 4
ix Dia. 3/4" Sch. 80 Nos. 231
x Dia. 1/2" Sch. 80 Nos. 55

2.0 SURFACE PREPARATION WITH PAINTING SYSTEM:


Works include supply of all material, application of painting Only approved
system, surface preparation to S.A. 2.5 and apply of painting Paint by
2.1
system as per relevant specification, complete in all respect as COMPANY is
per COMPANY requirement. recommended.

i Dia. 12" m2 1
ii Dia. 6" m2 348

Page 7 of 12
ITT-20-QAI-PRJ-0017

iii Dia. 4" m2 80


iv Dia. 3" m2 6 Painting shall be
v Dia. 2-1/2" m2 30 done as per project
vi Dia. 2" m2 32 specifications.
vii Dia. 3/4" m2 3

3.0 SURFACE PREPARATION WITH COATING:


Works include supply of all material, application of primer followed
by POLYKEN coating system, surface preparation to S.A. 2.5 etc
3.1
all as per relevant specification, complete in all respect as per
COMPANY requirement.

i Dia. 10" m2 91 Coating shall be


ii Dia. 4" m2 7 done as per project
iii Dia. 2" m2 20 specifications.

3.0 INSTALLATION OF VALVES/STRAINERS


Installation of valves / strainers includes the placing of It includes
valves/strainers between flanges and bolting up with gasket. Work installation of Gate,
3.1
also includes Lifting and Transportation from store and unloading Ball, Check Valves
at work site. and Strainers.

i Dia. 6" Nos. 15


ii Dia. 4" Nos. 7
iii Dia. 3" Nos. 4
iv Dia. 2" Nos. 10

Installation / bolting of Blind Flanges & Spectacle Blinds any


3.2 Nos. 7
diameter as per drawings.

4.0 HYDROSTATIC TESTING:

Page 8 of 12
ITT-20-QAI-PRJ-0017

CONTRACTOR
shall provide all
material and
Hydrostatic testing of piping as per ASME B-31.3 for Product equipment required
4.1 Piping of the following sizes as per project specification and for hydrostatic
COMPANY requirements. testing, including
supply of potable
water and
electricity for test.

i Dia. 6" m 690


ii Dia. 4" m 322
iii Dia. 3" m 18
iv Dia. 2-1/2" m 138
v Dia. 2" m 306
vi Dia. 3/4" m 38

5.0 INSTALLATION OF FIRE WATER PUMP SKID


Installation of Fire pumps skid with all accessories on proposed
foundation, testing, inspection, start-up & commissioning,
complete in all respect, as per COMPANY requirements, scope of
works, drawings, tender documents, etc and manufacturer
recommendation. Works include loading, transportation, unloading
5.1 at proposed location, placing on foundation, leveling, supply and Job 1
placing of cementitious grouting and shims if required, hot and
cold alignment, bolting up with piping, complete in all respect as
per Engineer instruction and manufacturer recommendation.

6.0 INSTALLATION OF FOAM SKID


Installation of Foam skid includes loading, transportation from
store, unloading at site, placing on foundation, leveling, bolting up
6.1 with piping, complete in all respect as per Engineer instruction and Job 1
manufacturer recommendation.

Page 9 of 12
ITT-20-QAI-PRJ-0017

7.0 INSTALLATION OF FIRE WATER MONITORS


It includes loading, transportation, lifting, unloading, installation of
Firewater monitors at respective locations as shown in project
7.1 drawings. Installation of monitors includes placing of monitors, Nos. 2
tightening of stud bolts along with gaskets as per manufacturer
recommendation.

8.0 INSTALLATION OF FIRE HYDRANT


It includes loading, transportation, lifting, unloading, installation of
Fire Hydrant & Pumper Connection at respective location shown
8.1 in drawings. Work also includes provision of supporting structure Nos. 9
and placing of Hydrants as per manufacturer recommendation and
Engineer requirements.

9.0 INSTALLATION OF FUEL PUMPS


Installation of fuel pumps with all accessories on proposed
foundation. Installation of instruments tubing and valves, testing,
inspection, start-up & commissioning, complete in all respect, as
per COMPANY requirements, scope of works, drawings, tender
documents, etc and manufacturer recommendation. Works
9.1 include loading, transportation, unloading at proposed location, Nos. 2
placing on foundation, leveling, supply and placing of cementitious
grouting and shims if required, hot and cold alignment, bolting up
with piping, complete in all respect as per Engineer instruction and
manufacturer recommendation.

INSTALLATION OF INSTRUMENT AIR COMPRESSOR


10.0
PACKAGE
Installation of Instrument Air Compressor Package complete with
accessories as per project drawing and manufacturer
recommendations. It includes the placing of Instrument air
10.1 Compressor Package at respective foundation and tie-ins with Nos. 2
piping. Work also includes Lifting and Transportation from store
and unloading at work site.

Page 10 of 12
ITT-20-QAI-PRJ-0017

11.0 INSTALLATION OF SLOP PUMP


Installation of product pumps with all accessories on proposed
foundation. Installation of instruments tubing and valves, testing,
inspection, start-up & commissioning, complete in all respect, as
per COMPANY requirements, scope of works, drawings, tender
documents, etc and manufacturer recommendation. Works
11.1 include loading, transportation, unloading at proposed location, Job 1
placing on foundation, leveling, supply and placing of cementitious
grouting and shims if required, hot and cold alignment, bolting up
with piping, complete in all respect as per Engineer instruction and
manufacturer recommendation.

SUB TOTAL
TOTAL
S.NO NOTE:
The Quantities taken in this BOQ are estimated, only for bidding purpose. CONTRACTOR is responsible to estimate the
1
quantities as per site requirements, drawings & tender documents.
CONTRACTOR is responsible to add any missing / required item as per scope of works, drawings, specifications & tender
2
documents.
CONTRACTOR is responsible to estimate the quantities before going to purchase the supply items except ITEMs provided by
3
COMPANY. Any Leftover / balance items may not be taken by COMPANY.
CONTRACTOR is responsible to estimate the quantities before going to execute the job. Payments shall be made on actual work
4
done.

2. COMPANY shall compensate CONTRACTOR for the WORK performed under the CONTRACT, as follow:

Milestone Description of Milestones Milestone Amount % (*)


#
Successful acceptance of the WORK and issue of
1 90%
PROVISIONAL ACCEPTANCE CERTIFICATE (Note 1)

Page 11 of 12
ITT-20-QAI-PRJ-0017

2 Issue of FINAL ACCEPTANCE CERTIFICATE (Note 2) 10%


Total 100%

(*) Percentage of the total CONTRACT PRICE, as defined in the CONTRACT.

Note 1 Payment shall be made by COMPANY on successful completion of Performance Test in accordance with the
requirements/specifications/details included in the CONTRACT and issuance of PROVISIONAL ACCEPTANCE CERTIFICATE.

Note 2 Payment shall be made by COMPANY on expiry of the warranty period and issuance of FINAL ACCEPTANCE CERTIFICATE.

Page 12 of 12