Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Appendix “C”
(COMPENSATION)
Page 1 of 12
ITT-20-QAI-PRJ-0017
APPENDIX “C”
COMPENSATION
1. COMPANY shall compensate CONTRACTOR for the WORK performed under the CONTRACT, as the total Lump Sum Price of USD
………………………….. amount in figures (………………... amount if words) in accordance with the following Cost Breakdown:
UNIT PRICE
SR# ITEM DESCRIPTION UNIT QTY. TOTAL (USD) REMARKS
(USD)
1.0 PIPING WORKS
Works include shifting from store and placing of pipes &
fittings at required location for welding or threading as
indicated in project drawings or as per site requirement.
Making weld joints / thread as per ANSI B 31.3 in joining pipe
lengths and welded pipe fittings such as flanges, bends,
10% of Radiography
1.1 reducers, tees etc. The work also includes gas cutting/cold
also included .
cutting as per requirement, grinding, beveling etc. the
welding of both the faces of slip-on Flanges will be
considered as one welding joint where used, complete in all
respect as per project specifications, drawings, relevant
international/codes and tender documents.
Page 2 of 12
ITT-20-QAI-PRJ-0017
Page 3 of 12
ITT-20-QAI-PRJ-0017
CONTRACTOR shall
provide all material and
Hydrostatic testing of piping as per ASME B-31.3 for Product equipment required for
4.1 Piping of the following sizes as per project specification and hydrostatic testing,
COMPANY requirements. including supply of
potable water and
electricity for test.
i Dia. 16" m 83
ii Dia. 12" m 207
iii Dia. 8" m 48
iv Dia. 6" m 359
v Dia. 4" m 83
vi Dia. 3" m 14
vii Dia. 2" m 7
vii Dia. 1" m 14
viii Dia. 3/4" m 7
5.0 INSTALLATION OF TRV
Installation of TRV includes the placing of TRV between
5.1 flanges and bolting up with gasket. Work also includes Lifting Jobs 12
and Transportation from store and unloading at work site.
Installation of PUMS:
Installation of product pumps with all accessories on
proposed foundation. Installation of instruments tubing and
valves, testing, inspection, start-up & commissioning,
complete in all respect, as per COMPANY requirements,
scope of works, drawings, tender documents, etc. and
6.0 Jobs 4
manufacturer recommendation. Works include loading,
transportation, unloading at proposed location, placing on
foundation, leveling, supply and placing of cementitious
grouting and shims if required, hot and cold alignment,
bolting up with piping, complete in all respect as per Engineer
instruction and manufacturer recommendation.
Page 4 of 12
ITT-20-QAI-PRJ-0017
Page 5 of 12
ITT-20-QAI-PRJ-0017
UNIT
SR# ITEM DESCRIPTION UNIT QTY. TOTAL REMARKS
RATE
1.0 PIPING WORKS
Page 6 of 12
ITT-20-QAI-PRJ-0017
Works include shifting from store and placing of pipes & fittings at
required location for welding or threading as indicated in project 10% of
drawings or as per site requirement. Making weld joints / thread as Radiography also
per ANSI B 31.3 in joining pipe lengths and welded pipe fittings included for new
1.1 such as flanges, bends, reducers, tees etc. The work also work and shall be
includes gas cutting/cold cutting as per requirement, grinding, as per ASME 31.3
beveling etc. the welding of both the faces of slip-on Flanges will and project
be considered as one welding joint where used, complete in all specifications
respect as per project specifications, drawings, relevant
international/codes and tender documents.
i Dia. 12" m2 1
ii Dia. 6" m2 348
Page 7 of 12
ITT-20-QAI-PRJ-0017
Page 8 of 12
ITT-20-QAI-PRJ-0017
CONTRACTOR
shall provide all
material and
Hydrostatic testing of piping as per ASME B-31.3 for Product equipment required
4.1 Piping of the following sizes as per project specification and for hydrostatic
COMPANY requirements. testing, including
supply of potable
water and
electricity for test.
Page 9 of 12
ITT-20-QAI-PRJ-0017
Page 10 of 12
ITT-20-QAI-PRJ-0017
SUB TOTAL
TOTAL
S.NO NOTE:
The Quantities taken in this BOQ are estimated, only for bidding purpose. CONTRACTOR is responsible to estimate the
1
quantities as per site requirements, drawings & tender documents.
CONTRACTOR is responsible to add any missing / required item as per scope of works, drawings, specifications & tender
2
documents.
CONTRACTOR is responsible to estimate the quantities before going to purchase the supply items except ITEMs provided by
3
COMPANY. Any Leftover / balance items may not be taken by COMPANY.
CONTRACTOR is responsible to estimate the quantities before going to execute the job. Payments shall be made on actual work
4
done.
2. COMPANY shall compensate CONTRACTOR for the WORK performed under the CONTRACT, as follow:
Page 11 of 12
ITT-20-QAI-PRJ-0017
Note 1 Payment shall be made by COMPANY on successful completion of Performance Test in accordance with the
requirements/specifications/details included in the CONTRACT and issuance of PROVISIONAL ACCEPTANCE CERTIFICATE.
Note 2 Payment shall be made by COMPANY on expiry of the warranty period and issuance of FINAL ACCEPTANCE CERTIFICATE.
Page 12 of 12