Project Name | SIT Execution Timeline

Execution Date Plan Execution Plan Passed Total Testers


22-Oct-18 274 219 4
23-Oct-18 279 223 4
24-Oct-18 806 645 4
25-Oct-18 520 416 4
26-Oct-18 1505 1204 4
27-Oct-18 0 0
28-Oct-18 0 0
29-Oct-18 1189 951 4
30-Oct-18 536 429 4
31-Oct-18 510 408 4
1-Nov-18 395 316 4
2-Nov-18 0 300 4
3-Nov-18 0 0
4-Nov-18 0 0
5-Nov-18 0 301 4
6-Nov-18 0 301 4
7-Nov-18 0 301 4
6014 6014 4

Regresion SIT BI 2.0

Execution Date Plan Execution Plan Passed Total Testers


8-Nov-18 300 150 4
9-Nov-18 100 4
300 250 4
Feasibility List of Testers
FEASIBLE No Tester Name
FEASIBLE 1 Raghav
FEASIBLE 2 Subhransu
FEASIBLE 3 Tamil
NOT FEASIBLE 4 Rishi

NOT FEASIBLE
FEASIBLE
FEASIBLE
FEASIBLE
FEASIBLE

FEASIBLE
FEASIBLE
FEASIBLE

Feasibility
FEASIBLE
FEASIBLE
[BI 2.0 Ingestion and Reporting] | UAT Execution Timeline
50

Cycle 1
Execution Date Plan Execution Plan Passed Total Testers
12-Nov-18 589 500 5
13-Nov-18 589 500 5
14-Nov-18 589 500 5
15-Nov-18 589 500 5
16-Nov-18 589 500 5
17-Nov-18 0 0
18-Nov-18 0 0
19-Nov-18 589 500 5
20-Nov-18 0 0
21-Nov-18 589 500 5
22-Nov-18 589 500 5
23-Nov-18 587 500 5
24-Nov-18 0 0
25-Nov-18 0 0
Total: 5299 4500 0

Cycle 2 : Re-test Bugs Fixing


Execution Date Plan Execution Plan Passed Total Testers
26-Nov-18 350 350 5
27-Nov-18 250 250 5
28-Nov-18 199 199 5
Total: 799 0

Regression Test
Execution Date Plan Execution Plan Passed Total Testers
29-Nov-18 250 250 5
30-Nov-18 100 100 5
Total: 350 350 0
Feasibility List of Testers
NOT FEASIBLE No Tester Name
NOT FEASIBLE 1 Hamdan
NOT FEASIBLE 2 Arum
NOT FEASIBLE 3 Putri
NOT FEASIBLE 4 Nastiti
5 Reza

NOT FEASIBLE

NOT FEASIBLE
NOT FEASIBLE
NOT FEASIBLE

Feasibility
NOT FEASIBLE
FEASIBLE
FEASIBLE

Feasibility
FEASIBLE
FEASIBLE