Raja Ram Construction


AXLE LOAD SPECTRUM DATA

Name of Work : -- Construction of Umranala-Mohkhed-Saori-Mujawar-


Mordongari- Umreth-Khirsadoh road of length 35.00 KM

Rear Single Axle Rear Tandem Axle Rear Tridem Axle


S.No.
Load Group Mid-Point Frequency Load Group Mid-Point Frequency Load Group Mid-Point Frequency
of Load of Load of Load
(kN) Group (kN) (%) (kN) Group (kN) (%) (kN) Group (kN) (%)

1 185-195 190 18.15 380-400 390 14.50 530-560 545 5.23


2 175-185 180 17.43 360-380 370 10.50 500-530 515 4.85
3 165-175 170 18.27 340-360 350 3.63 470-500 485 3.44
4 155-165 160 12.98 320-340 330 2.50 440-470 455 7.12
5 145-155 150 2.98 300-320 310 2.69 410-440 425 10.11
6 135-145 140 1.62 280-300 290 1.26 380-410 395 12.01
7 125-135 130 2.62 260-280 270 3.90 350-380 365 15.57
8 115-125 120 2.65 240-260 250 5.19 320-350 335 13.28
9 105-115 110 2.65 220-240 230 6.30 290-320 305 4.55
10 95-105 100 3.25 200-240 210 6.40 260-290 275 3.16
11 85-95 90 3.25 180-200 190 8.90 230-260 245 3.10
12 < 85 80 14.15 < 180 170 34.23 < 230 215 17.58
100 100 100.00

Front Single Axles and Rear Tridem Axles not considered for bottom-up analysis.

Design for Bonded Pavement Option

Sub-Grade CBR (%) =8

Granular Sub-Base Thickness (mm) = 250

Effective k-Value from Tables 2 and 3 (Mp a/m) = 72

For k of 72.0 MP a/m and for

Doweled joint and Tied Concrete Shoulders Slab Thickness (m) = 0.3
M/s. Rajaram Construction
CALCULATION OF HYDRAULIC DISCHARGE AND DESIGN OF OPENING

Name of Work : -- Construction of Umranala-Mohkhed-Saori-Mujawar-


Mordongari- Umreth-Khirsadoh road of length 35.00 KM

1. Chainage of C.D.
2. Description of catchments 0.2 Sq Km. or Acre 49.40
3. Height of fill permitted 0.6 Mtr. Hectares 20
4. Pipe Diameter proposed 1 Mtr. No 3

Catchment Area Diameter of pipe


(Hectares) (mm)
PROCEDURE ADOPTED : Up to 10 Hect. 1000 Single ROW
10 to 20 1200 Single ROW
A. For finding discharge Dickens's formula is adopted 20 to 50 1000 or 1200 (2 to 3R)
(For M.P. Plain Terrain) 50 to 60 1000 or 1200 (4R)
B. For M.P. Terrain Cofficient of discharge = 14 to 19 As Per S.P. - 20

Q= CM3/4
= 17 * (0.2) 3/4
= 5.084186 cum/sec

PROPOSAL : 1 Mtr. Dia NP-4 Hume pipe is proposed to provide

Length of pipe L= 12.50


For Squar entry Ke = 1.107 (R)^0.5 = 0.783 As per article 32 (22.5e) of IRC SP 13
Kf = 0.00394 L/R^1.2 = 0.039 Kf as per figure 22 of IRC SP 13
Velocity v = 4.43* (H/1+Ke+Kf)^0.5 = 2.542
Area of one pipe A = π d^2/4 =0.785 Up to 7 Hect. 1 No
8 to 18 2 No
Discharge by one pipe Q = A *v = 2.00 19 to 32 3 No
33 to 47 4 No

No of pipe required
As Per This Design
Water way required = 5.084186 / v = 2.000 Sqm

Area of one 1000mm of pipe = π/4 (d)2


= 1/4 * 3.14*(d)^2 =0.785 Sqm
No. of pipe required = Total water way/area of one pipe
= 2.000028/0.785 = 2.5478
No. Say 3

Hence provide : 3 Rows of 1 Mtr. Dia NP-4 pipes


M/s. Rajaram Construction
CALCULATION OF HYDRAULIC DISCHARGE AND DESIGN OF OPENING

Name of Work : -- Construction of Umranala-Mohkhed-Saori-Mujawar-


Mordongari- Umreth-Khirsadoh road of length 35.00 KM

1. Chainage of C.D.
2. Description of catchments 0.08 Sq Km. or Acre 19.76
3. Height of fill permitted 0.06 Mtr. Hectares 8
4. Pipe Diameter proposed 1 Mtr. No 2

Catchment Area Diameter of pipe


(Hectares) (mm)
PROCEDURE ADOPTED : Up to 10 Hect. 1000 Single ROW
10 to 20 1200 Single ROW
A. For finding discharge Dickens's formula is adopted 20 to 50 1000 or 1200 (2 to 3R)
(For M.P. Plain Terrain) 50 to 60 1000 or 1200 (4R)
B. For M.P. Terrain Cofficient of discharge = 14 to 19 As Per S.P. - 20

Q= CM3/4
= 17 * (0.08) 3/4
= 2.55721 cum/sec

PROPOSAL : 1 Mtr. Dia NP-4 Hume pipe is proposed to provide

Length of pipe L= 12.50


For Squar entry Ke = 1.107 (R)^0.5 = 0.783 As per article 32 (22.5e) of IRC SP 13
Kf = 0.00394 L/R^1.2 = 0.039 Kf as per figure 22 of IRC SP 13
Velocity v = 4.43* (H/1+Ke+Kf)^0.5 = 2.542
Area of one pipe A = π d^2/4 =0.785 Up to 7 Hect. 1 No
8 to 18 2 No
Discharge by one pipe Q = A *v = 2.00 19 to 32 3 No
33 to 47 4 No

No of pipe required
As Per This Design
Water way required = 2.55721 / v = 1.006 Sqm

Area of one 1000mm of pipe = π/4 (d)2


= 1/4 * 3.14*(d)^2 =0.785 Sqm
No. of pipe required = Total water way/area of one pipe
= 1.005961/0.785 = 1.2815
No. Say 2

Hence provide : 2 Rows of 1 Mtr. Dia NP-4 pipes


M/s. Rajaram Construction
CALCULATION OF HYDRAULIC DISCHARGE AND DESIGN OF OPENING

Name of Work : -- Construction of Rajegaon-Kirnapur-Lanji-Amgaon Road


of length 57.400 KM

1. Chainage of C.D.
2. Description of catchments 0.06 Sq Km. or Acre 14.82
3. Height of fill permitted 0.06 Mtr. Hectares 6
4. Pipe Diameter proposed 1 Mtr. No 1

Catchment Area Diameter of pipe


(Hectares) (mm)
PROCEDURE ADOPTED : Up to 10 Hect. 1000 Single ROW
10 to 20 1200 Single ROW
A. For finding discharge Dickens's formula is adopted 20 to 50 1000 or 1200 (2 to 3R)
(For M.P. Plain Terrain) 50 to 60 1000 or 1200 (4R)
B. For M.P. Terrain Cofficient of discharge = 14 to 19 As Per S.P. - 20

Q= CM3/4
= 17 * (0.06) 3/4
= 2.060926 cum/sec

PROPOSAL : 1 Mtr. Dia NP-4 Hume pipe is proposed to provide

Length of pipe L= 12.50


For Squar entry Ke = 1.107 (R)^0.5 = 0.78 As per article 32 (22.5e) of IRC SP 13
Kf = 0.00394 L/R^1.2 = 0.04 Kf as per figure 22 of IRC SP 13
Velocity v = 4.43* (H/1+Ke+Kf)^0.5 = 2.54
Area of one pipe A = π d^2/4 =0.79 Up to 7 Hect. 1 No
8 to 18 2 No
Discharge by one pipe Q = A *v = 2.00 19 to 32 3 No
33 to 47 4 No

No of pipe required
As Per This Design
Water way required = 2.060926 / v = 0.8107 Sqm

Area of one 1000mm of pipe = π/4 (d)2


= 1/4 * 3.14*(d)^2 =0.785 Sqm
No. of pipe required = Total water way/area of one pipe
= 0.810732/0.785 1.0328
No. Say 1

Hence provide : 1 Rows of 1 Mtr. Dia NP-4 pipes


M/s. Raja Ram Construction
DESIGN HYDRAULIC CALCULATION AS PER IRC:13:2004 PF SLAB CULVERT

Name of Work : -- Construction of Umranala-Mohkhed-Saori-Mujawar-


Mordongari- Umreth-Khirsadoh road of length 35.00 KM

Hydraulic Calculation
1. Location = 7940
2. Constant 'C' = 16.00
3. Catchment Area 'M' = 0.645 SqKm
4. HFL = 82.86 m
5. Bed Level =81.395 m
6. Hydraulic mean depth "R" = 0.81
7. Slop of Nala =0.010
8. Regocity Coeficient of 'n' =0.035

Constant "C" =16.00


Catchment Area "M" =0.645
Discharge by Dickens formula "Q" = C (M)3/4

"Q" =11.52 CUMEC

Velocity of Flow "V" = 1/n x R2/3 x S1/2


"V" = 2.48 m/sec.

Discharge by Mannings formula "Q" = Calculated Area x Velocity


Cal Area "A" = 8.45
Velocity "V" = 2.48
Hence Discharge (Q = A x V) = 8.45 x 2.48
= 20.93

= 20.93 CUMEC
Abopt Max discharge for calculated by MANNING's FORMULA
The Linear Water Way

1) By Area Velocity Method Avg. Depth = HFL - Avg bed level

Avg. Bed Level = 82.021 m


Avg. Depth = 0.83 m
Max. Discharge (Q)/Velocity X Depth

= 20.93 / 2.48 X 1.46


= 5.79 m

Proposed Bridge of Spam =6m


No. of Span = 1 No.
Proposed Length of Bridge =6m