WiMAX Outdoor Compact BTS

E9230 Quick Installation Guide


R1.0
(2010-10)
LEGAL INFORMATION

By accepting this certain document of ZTE CORPORATION you agree to the following terms.
If you do not agree to the following terms, please notice that you are not allowed to use this
document.

Copyright © 2010 ZTE CORPORATION. Any rights not expressly granted herein are
reserved. This document contains proprietary information of ZTE CORPORATION. Any
reproduction, transfer, distribution, use or disclosure of this document or any portion of this
document, in any form by any means, without the prior written consent of ZTE
CORPORATION is prohibited.

and are registered trademarks of ZTE CORPORATION. ZTE’s company name,


logo and product names referenced herein are either trademarks or registered trademarks
of ZTE CORPORATION. Other product and company names mentioned herein may be
trademarks or trade names of their respective owners. Without the prior written consent of
ZTE CORPORATION or the third party owner thereof, anyone’s access to this document
should not be construed as granting, by implication, estopped or otherwise, any license or
right to use any marks appearing in the document.

The design of this product complies with requirements of environmental protection and
personal security. This product shall be stored, used or discarded in accordance with product
manual, relevant contract or laws and regulations in relevant country (countries).

This document is provided “as is” and “as available”. Information contained in this document
is subject to continuous update without further notice due to improvement and update of
ZTE CORPORATION’s products and technologies.

ZTE CORPORATION

Address: NO. 55
Hi-tech Road South
ShenZhen
P.R.China
518057
Website: http://dms.zte.com.cn
Email: doc@zte.com.cn
E9230 Quick Installation Guide R1.0

Revision History

Reason for
Product Version Document Version Serial Number
Revision
V3.0, V4.0 R1.0 First published

Author

Date Document Version Prepared by Reviewed by Approved by


Wang huarong
Yi hua
2010-11-12 1.0 Liu Zhe Niu Ruifeng Ma Wenguang
Zheng Weijun
Wang Wenhui

II
Tools
Auxiliary Materials

Antenna Components
GPS Feeder Connector Two-feeder Fixer
GPS Antenna

Grounding Bar
Grounding Clip Copper Pig Nail Sunshade Installation

Components (Optional)

Pole-mounting Installation
Components
Pole-mounting (for two E9230s in one
Installation Pole-mounting
pole) Installation
Installation Components Components
(for one E9230 in one Components
pole) (for three E9230s in one
pole)

Outdoor Ultraviolet
Outdoor Waterproof
Cable Tie Indoor Cable Tie Indoor Label Paper
Label
Auxiliary Materials

Grounding Cable RF Feeder Cable GPS Feeder


Power Cable

Ethernet Cable
PVC Insulation Tape Waterproof Gum
Fiber Optic Cable

Ultraviolet Tape
E9230 Overview

Engineering Indexes
Item Index
370mm×320mm×198mm(height x width x
Dimension
depth)
Weight <18kg
Power
-48VDC,(-57VDC~-40VDC)
Supply
Overall
Power <120W
Consumption
Temperature -40℃~+55℃
Relative
5%RH~95%RH
Humidity
Grounding ≤10Ω

Appearance
Typical Installation Scenarios

One E9230 and an antenna installed on one Pole

One E9230 installed on one L-bar


E9230 Cabinet Installation

Installation Step: Preparation

Fixing Brackets

For One E9230 on One Pole/L-bar For Two E9230s on One Pole For Three E9230s on One Pole

Notes:
 Two kinds of bolts are available for clip component of two E9230s on one pole:
80 mm and 120 mm long, which should be selected according to the diameter of the pole.
 It is recommended to use a pole with a diameter ranging from 60 mm to 120 mm.
For the pole whose diameter ranges from 60 mm to 90 mm, the 80 mm long bolt should be used.
For the pole whose diameter ranges from 90 mm to 120 mm, the 120 mm long bolt should be used.

Supporting Panel

Notes: The sunshade components are optional!


E9230 Cabinet Installation
Installation Step (1): Installing one E9230 on one pole
E9230 Cabinet Installation
Installation Step (2): Installing one E9230 on one L-bar
E9230 Cabinet Installation
Installation Step (3): Installing E9230 on a Tower
E9230 Cable Installation
Cable Connection: System Connection Diagram
E9230 Cable Installation
Cable Connection (1): Power Cable
E9230 Cable Installation
Cable Connection (2): ETH Cable
E9230 Cable Installation
Cable Connection (3): Fiber Optic Cable (Optional)
E9230 Cable Installation
Cable Connection (4): Grounding Cable
E9230 Cable Installation

Cable Connection (5): GPS Feeder Cable


E9230 Cable Installation
Cable Connection (6): RF Feeder Cable
E9230 Cable Installation
Water-proof Treasure
E9230 Cable Installation

Water-proof Treasure for Unused Sockets on the bottom of E9230 Cabinet

After cable installation, the unused sockets on the bottom of E9230 cabinet should also be
sealed by the way of “1+3+3”. Please follow the operations as below:

①Tighten the protection cover on the socket firstly;

②Start wrapping from the bottom of the protection cover. The horizontal wrapping direction

should be the same as the screw direction, and the vertical direction should face the socket
direction from the socket below;

③Fix the tapes with the black cable tie at the base of the socket.
Installation Acceptance

Cables

1 Any cable is forbidden to be coiled and should be tied in the wiring channel and be placed casually.

2 All cables should be laid straightly, and they should not intertwine with each other or hang in the air.

The radio cables (microwave cables, antenna feeders, main antenna feeders, GPS feeders and so on)
3
are prohibited to be lied at an angle of 90 degree.
The cable ties are bound orderly, with proper tightness. The interval between cable ties is no more than
4
0.5 m and all ties face the same direction.

5 In the room, after a cable tie is bound, the extra part is cut completely smoothly, without any spur.

Outside the room, after a cable tie is bound, 1~2 mm surplus is reserved and the cable is cut smoothly
6
without any spur.
Labels with correct contents are attached at both ends of a cable. The labels face right after
7
attachment.
The VSWR test should be done before the waterproof measures are taken to the feeders. Besides, the
8
feeders should be marked.
The used and unused connectors at the bottom of E9230 cabinet should be sealed in the way of “1
9
layer of insulation tape + 3 layers of waterproof tape + 3 layers of ultraviolet tape”.

As for the outdoor DC shielded power cable or the RF feeder, If it is shorter than 5 m, the shielded layer
of the power cable or the RF feeder should be grounded at one point; if it is between 5 m and 20 m, the
shielded layer should be grounded at two points; if it is longer than 20 m, the shielded layer should be
grounded at three points: the point where it leaves the iron tower platform, the point where it
10 approaches the outdoor cable tray and the point 1 m from the equipment room. If the cable length on
the iron tower exceeds 60 m, a grounding point should be added every 20 m. The grounding cable
should be laid downward as the feeder (equipment room direction) and its inclination angle with the
feeder should not exceed 15°.
Note: The grounding clip is used when the cable is grounded!

E9230 Cabinet

1 The main pole should be vertical, with an error less than 2°.
The interface between the jumper and E9230 cabinet is screwed up with a torque spanner of 1.7 Nm ~2 Nm;
2
The interface between the GPS feeder and E9230 cabinet is screwed up with a torque spanner of 1Nm.

3 The jumper is correctly connected to the connection terminal at the bottom of the cabinet.

The pole for equipment (except antenna) installation should be placed in the roof or within the fence of iron
4
tower.
All installation assembly should be firmly fixed, resisting the hurricane or meeting other specific
5
requirements. It is recommended to use poles of 4 ~ 6mm depth and with a diameter of 60mm ~ 120mm.
6 The cabinet must be reliably grounded and installed within 45° protection range of a lightning rod.