Sei sulla pagina 1di 8

Project Time Management

Sequence Activities Estimate Activity Resources


Define Activities
Inputs Inputs
Inputs
 Activity list  Activity list
 _____________ (1)
 Activity attributes  Activity attributes
 Enterprise environmental factors
 Milestone list  Resource calendars
 Organizational process assets
 _____________ (6) statement  Enterprise environmental factors
Tools and Techniques
 Organizational process assets  Organizational process assets
 ______________ (2)
Tools and Techniques Tools and Techniques
 __________ (3) planning
 _________________ (7)  Expert judgment
 Templates
diagramming method (PDM)
 Expert judgement  ________________ (10) analysis
 ______________ (8) determination
Outputs  Published ______________ (11)
 Applying leads and lags
 Activity ___________ (4)  Bottom-up estimating
 Schedule network __________ (9)
 Activity attributes  Project management software
Outputs
 _____________ (5) list Outputs
 Project schedule network diagrams
 Activity resource ___________ (12)
 Project document updates
 Resource breakdown structure
 Project document updates

Estimate Activity Durations Develop Schedule


Inputs Inputs Control Schedule
 Inputs
 Activity list Activity list
  Project management plan
 Activity attributes Activity attributes
  Project schedule
 Activity resource Project schedule network __________
requirements (15)  Work performance information
 Resource calendars  Activity resource requirements  Organizational process assets
 Tools and Techniques
 Project scope statement Resource calendars
  ___________ (20) reviews
 Enterprise environmental Activity duration estimates
factors  Project scope statement  Variance analysis
 Organizational process  Enterprise environmental factors  Project management software
assets  Organizational process assets  Resource leveling
Tools and Techniques Tools and Techniques  What-if scenario analysis
 Expert judgment  __________ (16) analysis  __________ (21) leads and lags
 _______________ (13)  Critical path method  Schedule compression
estimating  Critical chain method  Scheduling tool
 Parametric estimating  Resource __________ (17) Outputs
 Three-point estimates  What-if scenario analysis  Work performance _________
 __________ (14) analysis (22)
 Applying leads and lags
Outputs  Organizational process assets
 Schedule ___________ (18)
 Activity duration estimates updates
 Scheduling tool
 Project document updates  Change requests
Outputs
 Project management plan updates
 Project schedule
 Project document updates
 Schedule baseline
 Schedule ________ (19)
 Project document updates

CAMPUS
Project Time Management

Define Activities Define Activities: Tools and Techniques

 The ______________ (23) process  The Define Activities process defines the final
identifies the deliverables at the lowest outputs as _____________ (25) rather than
level in the Work Breakdown Structure _____________ (26), as done in the Create
(WBS), work package. WBS process.
 Project work packages are typically  The activity list, WBS, and WBS dictionary can
decomposed into smaller components be developed either ______________ (27) or
called _____________ (24). ______________ (28).
 A standard activity list or a portion of an activity
list from a previous project is often usable as a
__________ (29) for a new project.
 Templates can also be used to identify typical
_____________ (30) milestones.
 Rolling Wave Planning is a form of
__________________ (31) planning.
 In rolling wave planning the work to be
accomplished in the ____________________
(32) term is planned in detail and
_____________ (33) is planned at a higher level
of the WBS.
Define Activities: Outputs

 The ____________ (34) is a


comprehensive list including all schedule
activities required on the project.
 The activity list includes the
_______________ (35) and a
_______________ (36) description for
each activity.
 The components for each activity evolve
over ______________ (37).
 During the initial stages of the project
activity attributes include the Activity ID,
____________ (38) ID, and Activity Name.
 When the project is completed they may
include activity _________ (39), activity
______________ (40), predecessor
activities, successor activities, logical
relationships, leads and lags, resource
requirements, __________ (41) dates,
constraints, and assumptions.
 The number of attributes varies by
_____________ (42)
 A ______________ (43) is a significant
point or event in the project.
 A milestone list identifies all milestones
and indicates whether the milestone is
___________________ (44), or optional.

CAMPUS
Project Time Management

Sequence Activities: Tools and Techniques


Sequence Activities
 Precedence Diagramming Method (PDM) – is used in
 Activities are sequenced using _____________ _________________ (51) methodology for constructing
(45) relationships. a project schedule network diagram that uses boxes or
 Every activity and milestone except the rectangles, referred to as _______ (52), to represent
_____________ (46) and ____________ (47) activities, and connects them with arrows that show the
are connected to at least one predecessor and logical relationships that exist between them.
one successor.  PDM is also called _____________ (53).
 It may be necessary to use ___________ (48)  ______________ (54) templates are especially useful
or ___________ (49) time between activities to when a project includes several identical or nearly
support a realistic and achievable project identical deliverables.
schedule.  Mandatory Dependencies are those that are
 Sequencing can be performed by using ________________ (55) in the nature of the work.
________________ (50) or by using manual or  Mandatory Dependencies are also sometimes referred
automated techniques. to as _____________ (56) logic.
 Mandatory dependencies often involve
_______________ (57) limitations.
 Discretionary Dependencies are sometimes referred to
as preferred logic, preferential logic or __________ (58)
logic.
 Discretionary Dependencies are established based on
knowledge of ____________ (59) within a particular
application area.
Project Time Management
 Discretionary dependencies should be fully documented
since they can create arbitrary ___________ (60)
values.
 External Dependencies involve a _________ (61)
between project activities and non-project activities.
 A lead allows an _____________ (62) of the successor
Sequence Activities: Outputs activity.
 A lag directs a _______ (63) in the successor activity.
 Project schedule network
diagrams are schematic displays
of the project’s schedule activities
and the logical relationships
among them, also referred to as
____________ (64).

CAMPUS
Project Time Management

Estimate Activity Resources:


Tools and Techniques
Estimate Activity Resources
 Many schedule activities have
 Estimate Activity Resources is the ___________________ (68) methods of
process of estimating the __________ accomplishment.
(65) and ____________ (66) of  Several companies routinely publish
material, people, equipment, or updated production rates and
supplies required to perform each ___________ (69) of resources.
activity.  The resource needs are estimated.
 The Estimate Activity Resource These estimates are then
process is closely coordinated with the _____________________ (70) into a
_______________ (67) process. total quantity for each of the activity’s
resources.

Project Time Management

Estimate Activity Durations:


Estimate Activity Durations
Tools and Techniques
 The duration estimate is progressively
 Analogous Estimating: Uses__________________ (73) from elaborated, and the process considers
a previous, similar project as the basis for estimating the same _____________ (71) and availability of
parameter or measure for a future project. the input data.
 It is a _____________ (74) estimating approach, sometimes  The duration estimate can be assumed
adjusted for known differences in project complexity. to be progressively more
 Parametric Estimating: Activity durations can be quantitatively _____________ (72).
determined by multiplying the _________________ (75) of
work to be performed by ________________ (76) per unit of
work.
 It calculates an estimate for activity parameters, such as cost,
__________ (77), and duration.
 Three-Point Estimates – _____________ (78) uses the
following three estimates to define an approximate range for an
activity’s duration:
_________________ (79)
Optimistic
Pessimistic
 Reserve Analysis- Duration estimates may include
______________ (80), (sometimes referred to as time reserves
or __________) (81).

Estimate Activity Durations: Outputs

 Activity Duration Estimates are _______________ (82)


assessments of the likely number of work periods that will be
required to complete an activity.

CAMPUS
Project Time Management

Develop Schedule
Develop Schedule: Tools and Techniques
 Developing an acceptable project schedule is
 The schedule flexibility is measured by the positive difference often an __________ (83) process.
between early and late dates, and is termed _________ (87). 
 Critical Paths have either a ____________ (88) or negative Develop Schedule: Tools and Techniques
total float and schedule activities on a critical path are called  Schedule network analysis is a technique that
_________________ (89) activities. generates the project schedule. It employs various
 ____________ (90) float – The amount of time that a activity __________________ (84) techniques.
can be ____________ (91) without delaying the early start date  The ____________ (85) method calculates the
of any immediate _____________ (92) activity within the theoretical early start and finish dates and late
network path. start and finish dates, for all activities.
 The resource-constrained critical path is known as the  The resulting early and late start and finish dates
____________ (93). are not necessarily the __________ (86).
 Additional buffers are known as ____________ (94).
 Resource Leveling can be used when shared or critical
required ________________ (95) are only available at certain
times
 Crashing: Crashing does not always produce a ____________
(96) alternative and may result in ________________ (97)
and/or cost.
 Fast Tracking: A schedule compression technique in which
phases or activities normally performed in sequence are
performed in parallel. Fast tracking may result in
____________ (98) and increased risk.
 ______________ (99) involves calculating multiple project
durations with different sets of activity assumptions.

CAMPUS
Project Time Management

Develop Schedule: Outputs


 Milestone Charts are similar to bar charts, but
only identify the scheduled start or completion of
major ___________________ (100) and key
external interfaces.
 Bar Charts are relatively easy to read, and are
frequently used in
____________________________ (101).
 Project Schedule Network Diagrams, with
activity date information, usually show both the
project ___________________ (102) and the
project’s ________________ (103) schedule
activities.
 A Schedule Baseline is a specific version of the
project schedule developed from the
_______________________________ (104). It
is accepted and approved by the project
management team as the schedule
______________ (105) with baseline start dates
and baseline finish dates.
 The________________ (106) data for the Control Schedule: Tools and Techniques
project schedule includes at least the schedule
milestones, schedule activities, activity attributes,  ________________ (107) measure,
and documentation of all identified assumptions compare, and analyze schedule
and constraints. performance such as actual start and finish
dates, percent complete, and remaining
duration for work in progress.
 The difference between the buffer
_________ (108) and the buffer
______________ (109) can determine
whether corrective action is appropriate.
 Variance Analysis: – Important aspects of
Project Time Management project schedule control include determining
the _____________ (110) and
___________ (111) of variance relative to
the schedule baseline and deciding whether
corrective or preventive action is required.
 _________________ (112) techniques are
used to find ways to bring project activities
Control Schedule: Outputs
that are behind into alignment with the plan.
 The __________________ (113) may be
updated to reflect changes caused by
compression or crashing techniques.
 An updated project schedule will be generated
from the updated __________ (114) to reflect
the schedule changes and manage the project.

CAMPUS
Project Time Management

Project Time Management

Answers

1. Scope baseline 31. Progressive 62. Acceleration 89. Critical


2. Decomposition elaboration 63. Delay 90. Free
3. Rolling wave 32. Near 64. Dependencies 91. Delayed
4. List 33. Future work 65. Type 92. Successor
5. Milestone 34. Activity list 66. Quantities 93. Critical chain
6. Project scope 35. Activity identifier 67. Estimate Costs 94. Feeding buffers
7. Precedence 36. Scope of work 68. Alternative 95. Resources
8. Dependency 37. Time 69. Unit costs 96. Viable
9. Templates 38. WBS 70. Aggregated 97. Increased risk
10. Alternatives 39. Codes 71. Quality 98. Rework
11. Estimating data 40. Description 72. Accurate 99. Simulation
12. Requirements 41. Imposed 73. Parameters
13. Analogous 42. Application area 74. Gross value 100. Deliverables
14. Reserve 43. Milestone 75. Quantity
15. Diagrams 44. Mandatory 76. Labor hours 101. Management
16. Schedule Network 45. Logical 77. Budget presentations
17. Leveling 46. First 78. PERT
18. Compression 47. Last 79. Most likely 102. Network logic
19. Data 48. Lead 80. Contingency
20. Performance 49. Lag reserves 103. Critical path
21. Adjusting 50. Project 81. Buffers
22. Measurements management 82. Quantitative 104. Schedule network analysis
23. Create WBS software 83. Iterative
24. Activities 51. Critical Path 84. Analytical 105. Baseline
25. Activities 52. Nodes 85. Critical path
26. Deliverables 53. Activity-On-Node 86. Project 106. Schedule
27. Sequentially 54. Subnetwork schedule
28. Concurrently 55. Inherent 87. Total float 107. Performance reviews
29. Template 56. Hard 88. Zero
30. Schedule 57. Physical 108. Needed
58. Soft
59. Best practices 109. Remaining
60. Total Float
61. Relationship 110. Cause

111. Degree

112. Schedule compression

113. Cost baseline

114. Schedule data

CAMPUS
CAMPUS

Potrebbero piacerti anche