Analisa Data

A. Debit Pada Saluran Tersier

NFR = 1.65 l/dt. Ha


Eff = 0.8
C = 1

C x NFR x A
Q =
Eff

1 x 1.65 x 95
Q SL2Ka = = 195.94 l/dt
0.8

1 x 1.65 x 100
Q SL2Ki = = 206.25 l/dt
0.8

1 x 1.65 x 90
Q SL1Ka = = 185.63 l/dt
0.8

1 x 1.65 x 100
Q SL1Ki = = 206.25 l/dt
0.8

1 x 1.65 x 100
Q PL1Ka = = 206.25 l/dt
0.8

1 x 1.65 x 100
Q PL2Ki = = 206.25 l/dt
0.8

1 x 1.65 x 90
Q SL4Ka = = 185.63 l/dt
0.8

1 x 1.65 x 100
Q SL4Ki = = 206.25 l/dt
0.8

1 x 1.65 x 75
Q SL3Ka = = 154.69 l/dt
0.8

1 x 1.65 x 85
Q SL3Ki = = 175.31 l/dt
0.8

1 x 1.65 x 100
Q PL2Ki = = 206.25 l/dt
0.8
1 x 1.65 x 100
Q PL3Ka = = 206.25 l/dt
0.8

1 x 1.65 x 55
Q PL3Ki = = 113.44 l/dt
0.8

B. Debit Pada Saluran Sekunder

NFR = 1.65 l/dt. Ha


Eff = 0.9
Eff = 0.8
C = 1

C x NFR x A
Q =
Eff
PERHITUNGAN RLS2

ARSL2 = ASL2Ka+ASL2ki
= 95 + 100 = 195 Ha

QSL2ka+QSL2Ki
QRSL2 =
Eff
195.94 + 206.25
= = 446.88 l/dt
0.9

atau

C x NFR
QRSL2 = x ASL2Ka+ASL2ki
Eff1 x Eff2

1 x 1.65
QRSL2 = x 195 = 446.88 l/dt
0.72

PERHITUNGAN RSL1

ARSL1 = ASL2Ka+ASL2ki+ASL1Ka+ASL1Ki
= 90+100+95+100 = 385 Ha

QSL1ka+QSL1Ki
QRSL1 = + QRSL2
Eff

186 + 206
QRSL1 = + 446.88 = 882.29 l/dt
0.9
atau

C x NFR
QRSL1 = x ASL2Ka+ASL2ki+ASL1Ka+ASL1Ki
Eff

= 1 x 1.65
QRSL1 x 385 = 882.29 l/dt
0.72

PERHITUNGAN RSL4

ARSL4 = ASL4Ka+ASL4ki
= 90 + 100 = 190 Ha

QSL4ka+QSL4Ki
QRSL4 =
Eff
185.63 + 206.25
= = 435.42 l/dt
0.9

atau

C x NFR
QRSL4 = x ASL4Ka+ASL4ki
Eff

1 x 1.65
QRSL4 = x 190 = 435.42 l/dt
0.72

PERHITUNGAN RSL3

ARSL3 = ASL3Ka+ASL3ki+ASL4Ka+ASL4Ki
= 75+85+90+100 = 350 Ha

QSL3ka+QSL3Ki
QRSL3 = + QRSL4
Eff

154.69 + 175.31
QRSL3 = + 435.42 = 802.08 l/dt
0.9

atau

C x NFR
QRSL3 = x ASL3Ka+ASL3ki+ASL4Ka+ASL4Ki
Eff

1 x 1.65
QRSL3 = x 350 = 802.08 l/dt
0.72
C. Debit Pada Saluran Primer

NFR = 1.65
Eff = 0.9
Eff = 0.9
Eff = 0.8
C = 1

C x NFR x A
Q =
Eff

PERHITUNGAN RPL3

ARPL3 = APL3Ka + APL3Ki


= 100 + 55 = 155 Ha

QPL3Ka+QPL3Ki
QRPL3 =
Eff

206.25 + 113.44
QRPL3 = = 355.21 l/dt
0.9

Atau

C x NFR
QRPL3 = x APL3Ka + APL3Ki
Eff

1 x 1.65
QRPL3 x 155.0 = 355.2 l/dt
= 0.72
0.3552

PERHITUNGAN RPL 2

ARPL2 = ARPL3+APL2Ki+ARSL3
= 155 + 100 + 350
= 605 Ha

Q RSL3 + QPL2Ki
QRPL2 = + QRPL3
Eff

802.08333 + 206
QRPL2 = + 355.2 = 1475.6 l/dt ok
0.9
PERHITUNGAN RPL1 1190

Q RSL1 + QPL1Ki+QPL1Ka
QRPL1 = + QRPL2
Eff

882.29167 + 412.50
QRPL1 = + 1475.6 = 2914 l/dt ok
0.9
2.91423611111
ARPL1 = ARPL2+APL1Ki+APL1Ka+ARSL1
= 605 + 200 + 385
= 1190 Ha
195.94
206.25
185.63
206.25
206.25
206.25
185.63
206.25
154.69
175.31
206.25
206.25
113.44
605

ok
CEK RT2
229.167
891.204
355.2
1475.58
ok
CEK RT2
229.167
229.167
980.324
1475.58
2914
Tabel A.2.1 Karakteristik Saluran yang Dipakai

Q
m n
m3/dt
0.15 - 0.30 1.0 1.0
0.30 - 0.50 1.0 1.0 - 1.2
0.50 - 0.75 1.0 1.2 - 1.3
0.75 - 1.00 1.0 1.3 - 1.5
1.00 - 1.50 1.0 1.5 - 1.8
1.50 - 3.00 1.5 1.8 - 2.3
3.00 - 4.50 1.5 2.3 - 2.7
4.50 - 5.00 1.5 2.7 - 2.9
5.00 - 6.00 1.5 2.9 - 3.1
6.00 - 7.50 1.5 3.1 - 3.5
7.50 - 9.00 1.5 3.5 - 3.7
9.00 - 10.00 1.5 3.7 - 3.7
10.00 - 11.00 2.0 3.7 - 4.2
11.00 - 15.00 2.0 4.2 - 4.9
15.00 - 25.00 2.0 4.9 - 6.5
25.00 - 40.00 2.0 6.5 - 9.0

Rumus Strickler
V=k.R2/3.I1/2
Q= V.A

KET :
Q = Debit Rencana (m3/dt)
k=Koefisien Kekasaran Stickler
I=Kemiringan Rencana
m=Kemiringan Talud
n=b/h (perbandingan Lebar Dasar & Kedalaman Air)
A= bh+mh2 =h2(n+m)
P= b+2h √1+m2=h(n+2√1+m2)
A h(n+m)
R = =
P h(n+2√1+m2)

Menghtung nilai h dan b dengan cara coba-coba


1. Andaikan kedalaman h=h0

2. Hitung Kecepatan yang Sesuai V0 =

3. Hitung Luas basah Yang Diperlukan A 0=

4. Dari Ao Hitung Kedalaman Air Yang baru h1 =

5. Bandingkan h1 dengan H0
Jika h1 -h0 < 0.005 maka h1 =hrencana
Jika h1 -h0 > 0.005 maka Ambil h1 sebagai kedalaman Air dan Andai
yang baru lalu Hitung kembali sesuai Prosed
sampai h1-h0 < 0.005
6. Hitung Lebar dasar b = brencana
Tabel A.2.1 Karakteristik Saluran yang Dipakai

35
35
35
35
40
40
40
40
42.5
42.5
42.5
42.5
45
45
45
45

n=b/h (perbandingan Lebar Dasar & Kedalaman Air)


h(n+m)
h(n+2√1+m2)

Menghtung nilai h dan b dengan cara coba-coba

2/3 1/2
2. Hitung Kecepatan yang Sesuai V0 = h(n+m)
k I
n+2√1+m

3. Hitung Luas basah Yang Diperlukan A 0= Q


V0
A0 1/2
4. Dari Ao Hitung Kedalaman Air Yang baru h1 =
n+m

Jika h1 -h0 < 0.005 maka h1 =hrencana


Ambil h1 sebagai kedalaman Air dan Andaikan
yang baru lalu Hitung kembali sesuai Prosedur
sampai h1-h0 < 0.005
Ruas RSL2
Berdasarkan hasil hitung Q pada hitungan Debit maka QRSL2
Lihat Tabel
m = 1.0
n = 1.15
k = 35
I = 0.001 (asumsi)
Q = 0.446875
a. h=h0 = 0.400 andaikan

b. V0 =

c. A0 = =

d. h1 = =

e. h1-h0 = 0.3228 >

jadi diambil kedalaman air yang baru,dan Perbandingan


Selanjutnya ditabulasikan dalam tabel berikut:

h0 V0
0.4000 0.398
0.5000 0.462
0.6000 0.522
0.6100 0.528
0.6222 0.535
Jadi
h= 0.6222 m
b= 0.7136 m
A= bh+mh2 =
P= =
R= =

V= =

Ruas RSL1
Berdasarkan hasil hitung Q pada hitungan Debit maka QRSL2
Lihat Tabel
m = 1.0
n = 1.41
k = 35
I = 0.001 (asumsi)
Q = 0.882292
Ambil h1 sebagai kedalaman Air dan Andaikan h=h0 = 0.400 andaikan
yang baru lalu Hitung kembali sesuai Prosedur
V0 =

A0 = =

h1 = =

h1-h0 = 0.5432 >

jadi diambil kedalaman air yang baru,dan Perbandingan


Selanjutnya ditabulasikan dalam tabel berikut:

h0 V0
0.4000 0.412
0.5000 0.478
0.6000 0.540
0.7000 0.599
0.7575 0.631
Jadi
h= 0.7575 m
b= 1.0649 m
A= bh+mh2 =
P= =
R= =

V= =

Ruas RSL4
Berdasarkan hasil hitung Q pada hitungan Debit maka QRSL4
Lihat Tabel
m = 1.0
n = 1.14
k = 35
I = 0.001 (asumsi)
Q = 0.435417
h=h0 = 0.400 andaikan
V0 =

A0 = =

h1 = =

h1-h0 = 0.3159 >

jadi diambil kedalaman air yang baru,dan Perbandingan


Selanjutnya ditabulasikan dalam tabel berikut:

h0 V0
0.4000 0.398
0.5000 0.462
0.6000 0.521
0.6100 0.527
0.6180 0.532

Jadi
h= 0.6180 m
b= 0.7017 m
A= bh+mh2 =
P= =
R= =

V= =

Ruas RSL3
Berdasarkan hasil hitung Q pada hitungan Debit maka QRSL3
Lihat Tabel
m = 1.0
n = 1.34
k = 35
I = 0.001 (asumsi)
Q = 0.802083
h=h0 = 0.400 andaikan
V0 =

A0 = =

h1 = =
h1 = =

h1-h0 = 0.5152 >

jadi diambil kedalaman air yang baru,dan Perbandingan


Selanjutnya ditabulasikan dalam tabel berikut:

h0 V0
0.4000 0.409
0.5000 0.475
0.6000 0.536
0.7000 0.594
0.7410 0.617

Jadi
h= 0.7410 m
b= 0.9942 m
A= bh+mh2 =
P= =
R= =

V= =

Ruas RPL3
Berdasarkan hasil hitung Q pada hitungan Debit maka QRPL3
Lihat Tabel
m = 1.0
n = 1.06
k = 35
I = 0.001 (asumsi)
Q = 0.355208
h=h0 = 0.400 andaikan
V0 =

A0 = =

h1 = =

h1-h0 = 0.2631 >

jadi diambil kedalaman air yang baru,dan Perbandingan


Selanjutnya ditabulasikan dalam tabel berikut:

h0 V0
0.4000 0.393
0.4500 0.425
0.5000 0.456
0.5500 0.486
0.5840 0.506

Jadi
h= 0.5840 m
b= 0.6162 m
A= bh+mh2 =
P= =
R= =

V= =

Ruas RPL2
Berdasarkan hasil hitung Q pada hitungan Debit maka QRPL2
Lihat Tabel
m = 1.5
n = 1.79
k = 40
I = 0.001 (asumsi)
Q = 1.475579
h=h0 = 0.400 andaikan
V0 =

A0 = =

h1 = =

h1-h0 = 0.5259 >

jadi diambil kedalaman air yang baru,dan Perbandingan


Selanjutnya ditabulasikan dalam tabel berikut:

h0 V0
0.4000 0.523
0.5000 0.607
0.6000 0.685
0.7000 0.759
0.7500 0.795

Jadi
h= 0.7500 m
b= 1.3439 m
A= bh+mh2 =
P= =
R= =

V= =
Ruas RPL1
Berdasarkan hasil hitung Q pada hitungan Debit maka QRPL1
Lihat Tabel
m = 1.5
n = 2.27
k = 40
I = 0.001 (asumsi)
Q = 2.914236
h=h0 = 0.400 andaikan
V0 =

A0 = =

h1 = =

h1-h0 = 0.7981 >

jadi diambil kedalaman air yang baru,dan Perbandingan


Selanjutnya ditabulasikan dalam tabel berikut:

h0 V0
0.4000 0.538
0.6000 0.705
0.8000 0.855
0.9000 0.924
0.9100 0.931

Jadi
h= 0.9100 m
b= 2.0670 m
A= bh+mh2 =
P= =
R= =

V= =
Berdasarkan hasil hitung Q pada hitungan Debit maka QRSL2 = 0.4469 m3/dtk

(asumsi) 1.1

andaikan

= 0.39847 m/dtk

0.45 = 1.12147 m2
0.40

0.7228

0.005

jadi diambil kedalaman air yang baru,dan Perbandingan


Selanjutnya ditabulasikan dalam tabel berikut:

A0 h1 h1-h0
1.121 0.723 0.3228
0.966 0.671 0.1709
0.856 0.631 0.0314
0.846 0.628 0.0179
0.835 0.624 0.0016
0.831 m2
2.473 m
0.336 m

0.535 m/dt

Berdasarkan hasil hitung Q pada hitungan Debit maka QRSL2 = 0.8823 m3/dtk

(asumsi) 1.1

andaikan

= 0.41219 m/dtk

0.88
= 2.14048 m2
0.41

0.9432

0.005

jadi diambil kedalaman air yang baru,dan Perbandingan


Selanjutnya ditabulasikan dalam tabel berikut:

A0 h1 h1-h0
2.140 0.943 0.5432
1.845 0.876 0.3756
1.633 0.824 0.2240
1.474 0.783 0.0827
1.398 0.762 0.0049

1.380 m2
3.207 m
0.430 m

0.631 m/dt

Berdasarkan hasil hitung Q pada hitungan Debit maka QRSL4 = 0.4354 m3/dtk

(asumsi) 1.1

andaikan
= 0.39782 m/dtk

0.44
= 1.09451 m2
0.40

0.7159

0.005

jadi diambil kedalaman air yang baru,dan Perbandingan


Selanjutnya ditabulasikan dalam tabel berikut:

A0 h1 h1-h0
1.095 0.716 0.3159
0.943 0.665 0.1646
0.835 0.625 0.0254
0.826 0.622 0.0120
0.819 0.619 0.0013

0.816 m2
2.450 m
0.333 m

0.532 m/dt

Berdasarkan hasil hitung Q pada hitungan Debit maka QRSL3 = 0.8021 m3/dtk

(asumsi) 1.1

andaikan
= 0.40897 m/dtk

0.80
= 1.96122 m2
0.41

0.9152
0.9152

0.005

jadi diambil kedalaman air yang baru,dan Perbandingan


Selanjutnya ditabulasikan dalam tabel berikut:

A0 h1 h1-h0
1.961 0.915 0.5152
1.690 0.850 0.3496
1.497 0.799 0.1995
1.351 0.759 0.0594
1.300 0.745 0.0042

1.286 m2
3.090 m
0.416 m

0.617 m/dt

Berdasarkan hasil hitung Q pada hitungan Debit maka QRPL3 = 0.3552 m3/dtk

(asumsi) 1.1

andaikan
= 0.39312 m/dtk

0.36
= 0.90357 m2
0.39

0.6631

0.005

jadi diambil kedalaman air yang baru,dan Perbandingan


Selanjutnya ditabulasikan dalam tabel berikut:

A0 h1 h1-h0
0.904 0.663 0.2631
0.835 0.638 0.1875
0.779 0.616 0.1155
0.731 0.596 0.0463
0.702 0.584 0.0005

0.701 m2
2.268 m
0.309 m

0.506 m/dt

Berdasarkan hasil hitung Q pada hitungan Debit maka QRPL2 = 1.4756 m3/dtk
(asumsi) 1.1

andaikan
= 0.5229 m/dtk

1.48
= 2.82193 m2
0.52

0.9259

0.005

jadi diambil kedalaman air yang baru,dan Perbandingan


Selanjutnya ditabulasikan dalam tabel berikut:

A0 h1 h1-h0
2.822 0.926 0.5259
2.432 0.860 0.3595
2.154 0.809 0.2088
1.943 0.768 0.0683
1.856 0.751 0.0008

1.852 m2
4.048 m
0.457 m

0.751 m/dt
Berdasarkan hasil hitung Q pada hitungan Debit maka QRPL1 = 2.9142 m3/dtk

(asumsi) 1.1

andaikan
= 0.53832 m/dtk

2.91
= 5.41359 m2
0.54

1.1981

0.005

jadi diambil kedalaman air yang baru,dan Perbandingan


Selanjutnya ditabulasikan dalam tabel berikut:

A0 h1 h1-h0
5.414 1.198 0.7981
4.131 1.047 0.4466
3.410 0.951 0.1509
3.153 0.914 0.0143
3.130 0.911 0.0010
3.123 m2
5.348 m
0.584 m

0.884 m/dt
l hitung Q pada hitungan Debit maka QRSL2 = 0.4469 m3/dtk

Ket
> 0,005 Ganti
> 0,005 Ganti
> 0,005 Ganti
> 0,005 Ganti
< 0,005 Ok
l hitung Q pada hitungan Debit maka QRSL2 = 0.8823 m3/dtk

Ket
> 0,005 Ganti
> 0,005 Ganti
> 0,005 Ganti
> 0,005 Ganti
< 0,005 Ok

l hitung Q pada hitungan Debit maka QRSL4 = 0.4354 m3/dtk


Ket
> 0,005 Ganti
> 0,005 Ganti
> 0,005 Ganti
> 0,005 Ganti
< 0,005 Ok

l hitung Q pada hitungan Debit maka QRSL3 = 0.8021 m3/dtk


Ket
> 0,005 Ganti
> 0,005 Ganti
> 0,005 Ganti
> 0,005 Ganti
< 0,005 Ok

l hitung Q pada hitungan Debit maka QRPL3 = 0.3552 m3/dtk


Ket
> 0,005 Ganti
> 0,005 Ganti
> 0,005 Ganti
> 0,005 Ganti
< 0,005 Ok

l hitung Q pada hitungan Debit maka QRPL2 = 1.4756 m3/dtk


Ket
> 0,005 Ganti
> 0,005 Ganti
> 0,005 Ganti
> 0,005 Ganti
< 0,005 Ok
l hitung Q pada hitungan Debit maka QRPL1 = 2.9142 m3/dtk

Ket
> 0,005 Ganti
> 0,005 Ganti
> 0,005 Ganti
> 0,005 Ganti
< 0,005 Ok
0.447
1.15

0.84
3.928427125
0.357580414
0.031622777
0.395768995
A T2-T3 (F3) = 11 Ha
NFR = 1.65 l/dt.Ha
Kemiringan Talud m = 1
Perbandingan Lebar Saluran n= b/h = 1
Koef. Kekasaran = 35
Kemiringan Rencana I = 0.00045
Panjang Saluran = 300 m

Qsaluran = A x NFR = 18.15 l/dt


0.01815
Berdasarkan Grafik Diperoleh

b= 0.23 m
h= 0.23 m

h=h0 = 0.23
Lalu Masukkan Pada Persamaan Berikut :

V0 = = 0.180786 m/dtk

A0 0.018
= = = 0.100395 m2
0.18

h1 = = 0.2240

h1-h0 = -0.0060 > 0.005

jadi diambil kedalaman air yang baru,dan Perbandingan


Selanjutnya ditabulasikan dalam tabel berikut:

h0 V0 A0 h1 h1-h0 Ket
0.2300 0.181 0.100 0.224 -0.0060 < 0.005 Ok
0.2250 0.178 0.102 0.226 0.0007 < 0.005 Ok
0.2200 0.176 0.103 0.227 0.0074 > 0.005 Ganti

Jadi
b=h= 0.2250 m
A = bh+mh2 = 0.10125
P= = 0.861396
R= = 0.117542
V= = 0.178157 m/dt

A T1-T2 = 29 Ha
NFR = 1.65 l/dt.Ha
Kemiringan Talud m = 1
Perbandingan Lebar Saluran n= b/h = 1
Koef. Kekasaran = 35
Kemiringan Rencana I = 0.00045
Panjang Saluran = 300 m

Qsaluran = A x NFR = 47.85 l/dt


0.05
Berdasarkan Grafik Diperoleh

b= 0.31 m
h= 0.31 m

h=h0 = 0.31
Lalu Masukkan Pada Persamaan Berikut :

V0 = = 0.220591 m/dtk

A0 0.0479
= = = 0.216917 m2
0.22

h1 = = 0.3293

h1-h0 = 0.0193 > 0.005

jadi diambil kedalaman air yang baru,dan Perbandingan


Selanjutnya ditabulasikan dalam tabel berikut:

h0 V0 A0 h1 h1-h0 Ket
0.3100 0.221 0.217 0.3293 0.0193 > 0.005 Ganti
0.3200 0.225 0.212 0.3259 0.0059 > 0.005 Ganti
0.3230 0.227 0.211 0.3249 0.0019 < 0.005 Ok
Jadi
b=h = 0.3230 m
A = bh+mh2 = 0.208658
P= = 1.236582
R= = 0.168738

V= = 0.226716 m/dt

A T1-T4 = 71 Ha
NFR = 1.65 l/dt.Ha
Kemiringan Talud m = 1
Perbandingan Lebar Saluran n= b/h = 1
Koef. Kekasaran = 35
Kemiringan Rencana I = 0.00045
Panjang Saluran = 300 m

Qsaluran = A x NFR = 117.15 l/dt

Berdasarkan Grafik Diperoleh

b= 0.449 m
h= 0.449 m

h=h0 = 0.449 m
Lalu Masukkan Pada Persamaan Berikut :

V0 = = 0.282387 m/dtk

A0 0.117
= = = 0.414856 m2
0.282

h1 = = 0.4554

h1-h0 = 0.0064 > 0.005

jadi diambil kedalaman air yang baru,dan Perbandingan


Selanjutnya ditabulasikan dalam tabel berikut:
h0 V0 A0 h1 h1-h0 Ket
0.4490 0.282 0.415 0.455 0.0064 > 0.005 Ganti
0.4500 0.283 0.414 0.455 0.0051 > 0.005 Ganti
0.4510 0.283 0.414 0.455 0.0038 < 0.005 Ok

Jadi
b=h = 0.4510 m
A = bh+mh2 = 0.406802
P= = 1.726621
R= = 0.235606

V= = 0.283225 m/dt

A T4-T5 = 50 Ha
NFR = 1.65 l/dt.Ha
Kemiringan Talud m = 1
Perbandingan Lebar Saluran n= b/h = 1
Koef. Kekasaran = 35
Kemiringan Rencana I = 0.00045
Panjang Saluran = 300 m

Qsaluran = A x NFR = 82.50 l/dt

Berdasarkan Grafik Diperoleh

b= 0.397 m
h= 0.397 m

h=h0 = 0.397 m
Lalu Masukkan Pada Persamaan Berikut :

V0 = = 0.26014 m/dtk

A0 0.08
= = = 0.317137 m2
0.26

h1 = = 0.3982
h1-h0 = 0.0012 > 0.005

jadi diambil kedalaman air yang baru,dan Perbandingan


Selanjutnya ditabulasikan dalam tabel berikut:

h0 V0 A0 h1 h1-h0 Ket
0.3970 0.260 0.317 0.398 0.0012 < 0.005 Ok
0.3980 0.261 0.317 0.398 -0.0001 < 0.005 Ok
0.3990 0.261 0.316 0.398 -0.0015 < 0.005 Ok

Jadi
b=h = 0.3970 m
A = bh+mh2 = 0.315218
P= = 1.519886
R= = 0.207396

V= = 0.26014 m/dt

A T5-T6 = 35 Ha
NFR = 1.65 l/dt.Ha
Kemiringan Talud m = 1
Perbandingan Lebar Saluran n= b/h = 1
Koef. Kekasaran = 35
Kemiringan Rencana I = 0.00045
Panjang Saluran = 300 m

Qsaluran = A x NFR = 57.75 l/dt

Berdasarkan Grafik Diperoleh

b= 0.35 m
h= 0.35 m

h=h0 = 0.35 m
Lalu Masukkan Pada Persamaan Berikut :

V0 = = 0.239181 m/dtk

A0 0.06
= = = 0.241449 m2
0.24
h1 = = 0.3475

h1-h0 = -0.0025 > 0.005

jadi diambil kedalaman air yang baru,dan Perbandingan


Selanjutnya ditabulasikan dalam tabel berikut:

h0 V0 A0 h1 h1-h0 Ket
0.3500 0.239 0.241 0.347 -0.0025 < 0.005 Ok
0.3450 0.237 0.244 0.349 0.0041 < 0.005 Ok
0.3400 0.235 0.246 0.351 0.0108 > 0.005 Ganti

Jadi
b=h = 0.3450 m
A = bh+mh2 = 0.23805
P= = 1.320807
R= = 0.180231

V= = 0.236897 m/dt

A T6-T7 = 22 Ha
NFR = 1.65 l/dt.Ha
Kemiringan Talud m = 1
Perbandingan Lebar Saluran n= b/h = 1
Koef. Kekasaran = 35
Kemiringan Rencana I = 0.00045
Panjang Saluran = 300 m

Qsaluran = A x NFR = 36.30 l/dt

Berdasarkan Grafik Diperoleh

b= 0.29 m
h= 0.29 m

h=h0 = 0.29 m
Lalu Masukkan Pada Persamaan Berikut :

V0 = = 0.210999 m/dtk
V0 = = 0.210999 m/dtk

A0 0.04
= = = 0.172039 m2
0.21

h1 = = 0.2933

h1-h0 = 0.0033 > 0.005

jadi diambil kedalaman air yang baru,dan Perbandingan


Selanjutnya ditabulasikan dalam tabel berikut:

h0 V0 A0 h1 h1-h0 Ket
0.2900 0.211 0.172 0.293 0.0033 < 0.005 Ok
0.3000 0.216 0.168 0.290 -0.0100 < 0.005 Ok
0.3100 0.221 0.165 0.287 -0.0232 < 0.005 Ok

Jadi
b=h = 0.2900 m
A = bh+mh2 = 0.1682
P= = 1.110244
R= = 0.151498

V= = 0.2110 m/dt
A F3 = 13 Ha
NFR = 1.65 l/dt.Ha
Kemiringan Talud m = 1
Perbandingan Lebar Saluran n= b/h = 1
Koef. Kekasaran = 35
Kemiringan Rencana I = 0.00035
Panjang Saluran = 300 m

Qsaluran = A x NFR = 21.45 l/dt

Berdasarkan Qsaluran dan I, pada Gbr. A.1.2 ternyata titik potong (pertemuan) garisnya
diluar dimensi yang diijinkan (bmin= 0.30m) jadi diambil b=0.30m.

Jika titik potong diluar Grafik dimensi yang diijinkan maka lebar b tidak lagi sama dengan
kedalaman air, untuk menentukan kedalaman air dengan lebar dasar 0.30m dapat
digunakan tabel A.1.1
Q
Perhitungan F = =
I1/2
b= 0.302 m
h= 0.302 m

h=h0 = 0.302
Lalu Masukkan Pada Persamaan Berikut :

V0 = = 0.191182 m/dtk

A0 0.02
= = = 0.112197 m2
0.19

h1 = = 0.2369

h1-h0 = -0.0651 > 0.005

jadi diambil kedalaman air yang baru,dan Perbandingan


Selanjutnya ditabulasikan dalam tabel berikut:

h0 V0 A0 h1 h1-h0 Ket
0.3020 0.191 0.112 0.237 -0.0651 < 0.005 Ok
0.3090 0.194 0.110 0.235 -0.0740 < 0.005 Ok
0.2370 0.163 0.132 0.257 0.0198 > 0.005 Ganti
Jadi
b=h = 0.2370 m
A = bh+mh2 = 0.112338
P= = 0.907337
R= = 0.123811

V= = 0.162657 m/dt
Hitung Bangunan Bagi

Q = Cd x 1.45x b xh3/2
Dimana:
Cd = Koef. Debit = 0.85
b = Lebar Ambang
h = Muka Air Hulu (m)

Untuk S2Ki
Q = 0.21 m3/dt
h = 0.15 m (asumsi kedalaman air diatas ambang (h)

0.21 = 0.85 x 1.65 x b x 0.15


b= 0.98 m
1.) Gorong-gorong pada Ruas RSL3
Q = 0.802 m3/dt
Dari abel 5-5 dalam KP-04 Standar Perencanaan Irigsi
b = B = 1.5
BT = 1.8
H(h+w) = 1.4
HT = 1.79
t1 = 0.2
t2 = 0.2
t3 = 0.2
t4 = 0.2
Hf = 0.15
2.) Bangunan Terjun Ruas RSL4
Q = 0.4354 m3/dt h = 0.618 m
v = 0.5316646 m/dt Z = 1.25

Lebar Bukaan Efektif


v1
H = h1 +
2g
0.532
= 0.618 +
19.62
= 0.65 m

Q
B =
1.71 m H ^3/2
0.4354
B =
1.71 1 0.65 ^3/2
= 1.90 m

Tinggi ambang di hilir

Q^2
dc =
(g.B^2)^1/3
= 0.0577906
a = 0.0288953
Panjang kolam olakan L

C1 = 2.5 + 1,1 (dc/Z) + 0,7(dc/Z)^3


= 2.5509249
L = C1.Z.dc+0,25
= 0.4342743
3.) Talang pada RW3
NFR 1.65

RPL1 RPL2

PL1Ka PL2Ki
100 Ha 206.25 l/dt 100 Ha 206.25 l/dt

SL1Ka SL1Ki SL3Ka


90 Ha 185.63 l/dt 100 Ha 206.25 l/dt 75 Ha 154.69

SL2Ka SL2Ki SL4Ka


95 Ha 195.94 l/dt 100 Ha 206.25 l/dt 90 Ha 185.63

T1 T2 T3

F1 F2 F3
10 8 11

T4 T5 T6

F4 F5 F6 F7
9 12 15 13
RPL3

PL2Ki PL3Ka PL3Ki


100 Ha 206.25 l/dt 100 Ha 206.25 l/dt 55 Ha 113.44 l/dt

SL3Ka SL3Ki
l/dt 85 Ha 175.31 l/dt

SL4Ka SL4Ki
l/dt 100 Ha 206.25 l/dt

T7

F8 F9
11 11
A1 100 Ha
A2 100 Ha
A3 100 Ha
A4 90 Ha
A5 95 Ha
A6 100 Ha
A7 100 Ha
A8 75 Ha
A9 85 Ha
A10 90 Ha
A11 100 Ha
A12 100 Ha
A13 55 Ha

F1 10 Ha
F2 8 Ha
F3 11 Ha
F4 9 Ha
F5 12 Ha
F6 15 Ha
F7 13 Ha
F8 11 Ha
F9 11 Ha