Project Name Construction of Warehouse 3 Extension

PO amount P6,800,000.00
PO Date June 3, 2019 started mobilize
Release of 20%DP June 20 2019
40% completion APV Oct 30 2019
70% completion APV Nov 31 2019
Confirmation of 100% completion March 3, 2020
Daily Penalty based 70% completion
onwards
₱ 2,040.00

Total No of days
of construction
June 6 2019 -
215
March 6, 2020

No of days in
contract 90

No of days for
allowance (annual
Inventory, soil 20
density testing,
etc)

No of days for
penalty 105
₱ 214,200.00
Less : cost of out of scope works
(labor - electrical supply line, repair of
roll up door, additional line for cctv,
etc) ₱ 147,560.00
TOTAL PENALTY ₱ 66,640.00