Sei sulla pagina 1di 12

Design and Construction of 3 units FD type and 2 units FC Type

PROJECT LVQ Project -PHASE 2


CLIENT Gulf Warehousing Company Consultant: Gulf Engineering&Industrial Consultancy
Main Contractor Al Bader Construction and Steel Structure
Sub Contractor Ref. No.
Quality Control Checklist Quality Form Ref: GM/CL/004

Building Name :
Excavation ITR Ref. Number:

Description of the Activity/ Item

Discipline: (Tick Which ever applicable) Civil Mechanical Electrical Arch.


Reference Drawings: Rev.
Rev.

SI Report No/Result Results Verified By:


Inspection / Check Point SUB- Remarks
No. Date
(OK/RJ/NA) CONTRACTOR CONTRACTOR GEIC
1 Position and Marking is OK?
2 Depth of Excavation as per Contract Drawing?
Excavated formation level acceppatbale
3 (attach laboratory test report from)
4 level certified by surveyor/Site Engineer
Input Data Level
5 Ground Elevation (DATUM) Level
6 Bottom of Excavation Level:
7 Water Table Level and Presence of Water?
8 Excavated Soil Contaminated? (Yes/No)
Type of Excavate Material
9 (soil / clay / soft rock / hard rock, etc):
10 Ready for Lean Concrete / Blinding?
Bedding for U/G Piping or Cables
11 (attach test report if any)

Legend: Accepted (OK) Rejected with Remarks (RJ) Not Applicable (NA)

Comments form Main Contractor:

Comments form Client/Consultant:

Subcontractor Main Contractor Client / Consultant


Signatures Name
Register:
Signature

CheckList - GEIC Prepared By:Eng. Yousry I. Farag


Ver (0) PMP,LEED
Design and Construction of 3 units FD type and 2 units FC Type
PROJECT LVQ Project -PHASE 2
CLIENT Gulf Warehousing Company Consultant: Gulf Engineering&Industrial Consultancy
Main Contractor Al Bader Construction and Steel Project Ref:
Sub Contractor Contract No.
Quality Control Checklist Quality Form Ref: GM/CL/008
Building Name:
Pre-Concrete Check Sheet ITR Ref. Number:
Description of the Activity/ Item

Discipline: (Tick Which ever applicable) Civil Mechanical Electrical Arch.


Reference Drawings: Rev.
Rev.
SI Report No/Result Results Verified By:
Inspection / Check Point SUB- Remarks
No. Date
(OK/RJ/NA) CONTRACTOR CONTRACTOR GEIC
1 Formation Level Approved?
2 AFC Drgs used & all materials approved?
3 Setting out & Layout?
4 level certified by surveyor/Site Engineer
5 Screed over w/p, Level & Grade
6 Formwork Checkpoints
Dimensions, Line, Levels & Position
Concrete Level & Charmfer
Form oil and Cleanliness
Support for Formworks
Formworks within acceptable tolerances
7 Reinforcement Check
Rebars sizes and spacings as per drgs
Rebars arrangement as per drgs
Laps position and lengths as per drgs
Dowels and starter bars as drgs
Rebars clean of dust, oil and rust

Rebars covers as per drgs


8 Ensure approval of MEP services
9 Construction joint/water bar location
10 Approval for Casting

11 Adequate & safe access


12 Final Inspection carried out

Legend: Accepted (OK) Rejected with Remarks (RJ) Not Applicable (NA)

Comments form Main Contractor:

Comments form Client/Consultant:

Subcontractor Main Contractor Client / Consultant


Signatures Name
Register:
Signature

CheckList - GEIC Prepared By:Eng. Yousry I. Farag


Ver (0) PMP,LEED
Design and Construction of 3 units FD type and 2 units FC Type
PROJECT LVQ Project -PHASE 2
CLIENT Gulf Warehousing CompGulf WareConsultant: Gulf Engineering&Industrial Consultancy
Main Contractor Al Bader Construction aAl Bader Project Ref:
Sub Contractor Contract No.
Quality Control Checklist Quality Form Ref: GM/CL/005
Building Name:
Backfilling ITR Ref. Number:

Description of the Activity/ Item

Discipline: (Tick Which ever applicable) Civil Mechanical Electrical Arch.


Reference Drawings: Rev.
Rev.
SI Report No/Result Results Verified By:
Inspection / Check Point SUB- Remarks
No. (OK/RJ/NA) Date CONTRACTOR CONTRACTOR GEIC
Confirm approval for filling / approval from
1 MEP Subcontractors (if any)
2 Filling / Backfilling Material's approved?
3 Excavation Level _______________
4 No. of Layer Required:_____________

Sand bed application (required for cables


/sleeves/trenches) and thickness as per QCS
5
Field density test been carried out as per
6 QCS requirment.
Maximum dry density of the backfill
7 material _____________________
8 FDD Standard:____________________
9 Frequency of density test ____________
Cable tiles / warning tape laid over sand
10 bedding?
11 Any other (Please specify).

Legend: Accepted (OK) Rejected with Remarks (RJ) Not Applicable (NA)

Comments form Main Contractor:

Comments form Client/Consultant:

Subcontractor Main Contractor Client / Consultant


Signatures Name
Register:
Signature

CheckList - GEIC Prepared By:Eng. Yousry I. Farag


Ver (0) PMP,LEED
Design and Construction of 3 units FD type and 2 units FC Type
PROJECT LVQ Project -PHASE 2
CLIENT Gulf Warehousing CompGulf WareConsultant: Gulf Engineering&Industrial Consultancy
Main Contractor Al Bader Construction aAl Bader Project Ref:
Sub Contractor Contract No.
Quality Control Checklist Quality Form Ref: GM/CL/009
Building Name:
Post Concrete Check Sheet ITR Ref. Number:

Description of the Activity/ Item

Discipline: (Tick Which ever applicable) Civil Mechanical Electrical Arch.


Reference Drawings: Rev.
SI
No. Inspection / Check Point
1 2 3 4 5 6 7

1 Grade of Concrete

2 Truck No.

3 Delivery Ticket No.


Volume of Batch (cu.mt)
4

5 Time of Concrete Mixer in Site

6 Concrete Temp(°C)

7 Actual Slump in Site (mm)

8 Slump in Batching Plant (mm)

9 Starting Time of Concrete

10 Finishing Time of Concrete

11 Number of Cubes Collected (Ref. nos.)

12 Curing of Concrete -------------- days

13 Finishing of Concrete Satisfactory?

Legend: Accepted (OK) Rejected with Remarks (RJ) Not Applicable (NA)

Comments form Main Contractor:

Comments form Client/Consultant:

Subcontractor Main Contractor Client / Consultant


Signatures Name
Register:
Signature

CheckList - GEIC Prepared By:Eng. Yousry I. Farag


Ver (0) PMP,LEED
Design and Construction of 3 units FD type and 2 units FC Type
PROJECT LVQ Project -PHASE 2
CLIENT Gulf Warehousing CompaGulf WareConsultant: Gulf Engineering&Industrial Consultancy
Main Contractor Al Bader Construction an Al Bader Project Ref:
Sub Contractor Contract No.
Quality Control Checklist Quality Form Ref:
Building Name:
Pre-Pour Notice ITR Ref. Number:

Description of the Activity/ Item

Discipline: (Tick Which ever applicable) Civil Mechanical Electrical Arch.


Reference Drawings: Rev.
Rev.
Nos.of
SI Grade of QTY
Date Loction of Pour Trucks Made of Pour Remarks
No. Concrete Cumulative
Expected

1
2
3
4
5
6
7
8
9
10

11
12
13

Legend: Accepted (OK) Rejected with Remarks (RJ) Not Applicable (NA)

Comments form Main Contractor:

Comments form Client/Consultant:

Subcontractor Main Contractor Client / Consultant


Signatures Name
Register:
Signature

CheckList - GEIC Prepared By:Eng. Yousry I. Farag


Ver (0) PMP,LEED
Design and Construction of 3 units FD type and 2 units FC Type
PROJECT LVQ Project -PHASE 2
CLIENT Gulf Warehousing Company Consultant: Gulf Engineering&Industrial Consultancy
Main Contractor Al Bader Construction and Steel Structur Project Ref.
Sub Contractor Contract No.
Quality Control Checklist Quality Form Ref:

Concrete Cube Test Log


Concrete Suppliers Name: Site:
Area / Section: Date:
Structure / MemberNo. / Description:
Drawing No.: Rev.
Specified
Sample Ref. Age
Location/ Member Date Cast Date Crushed Strength Mpa @ Actual Strenght Mpa Remarks
No. (Days)
28 days

Subcontractor Main Contractor Client / Consultant


Name
Signatures
Register:

Signature

CheckList - GEIC Prepared By:Eng. Yousry I. Farag


Ver (0) PMP,LEED
Design and Construction of 3 units FD type and 2 units FC Type
PROJECT LVQ Project -PHASE 2
CLIENT Gulf Warehousing Company Consultant: Gulf Engineering&Industrial Consultancy
Main Contractor Al Bader Construction and Steel Structure Project Ref.
Sub Contractor Contract No.
Quality Control Checklist Quality Form Ref:

Cube Data Form


Concrete Suppliers Name: Site:
Area / Section: Date:
Structure / MemberNo. / Description:
Drawing No.: Rev.
Pre-Concrete Release Note No.:
Cement Type:
Concrete Class/Strength in Mpa: Stone Size:
Slump in mm: Admixture:
Date Made: Time: Temperature:
Specimen made By: Date Dispatched to Lab:

Date Tested Age in Days Mass in Kgs Dia Reading Strength in Mpa Average Strength

Note: Failure of any cube to be reported to Site Manager

Sub Contractor: Name: Signature: Date: Time:


Remarks:

Reported Reviwed by:

Name: Signature: Date: Time:

CheckList - GEIC Prepared By:Eng. Yousry I. Farag


Ver (0) PMP,LEED
Design and Construction of 3 units FD type and 2 units FC Type
PROJECT LVQ Project -PHASE 2
CLIENT Gulf Warehousing Company Consultant: Gulf Engineering&Industrial Consultancy
Main Contractor Al Bader Construction and Steel Project Ref:
Sub Contractor Contract No.
Quality Control Checklist Quality Form Ref:
Building Name:
Erection Control Form
(Sub-Main Switch Board) ITR Ref. Number:

Description of the Activity/ Item

Delivery Note No (Attached)


Discipline: (Tick Which ever applicable) Civil Mechanical Electrical Arch.
Reference Drawings: Rev.
Rev.
Report No/Result Results Verified By:
SI
Inspection / Check Point Remarks
No. Date SUB-
(OK/RJ/NA) CONTRACTOR CONTRACTOR GEIC
1 Check all Materials
2 Check Location
3 Check for any Damages
4 Check all Installation as per Drawings
5 Check Fixation of Distribution Board

6 Check for Earthing


7 Check for Cabling Arrangement
8 Check for Cable Fitting
9 Check for Cable Connection as per Drgs
10 Cleanliness
11 Check Fixing Height
Check MCB's/MCCB/ELCB Rating as per
12 Drawings
13 Check for Level
14 Duct Arrangement for Cables

Legend: Accepted (OK) Rejected with Remarks (RJ) Not Applicable (NA)

Comments form Main Contractor:

Comments form Client/Consultant:

Subcontractor Main Contractor Client / Consultant


Signatures Name
Register:
Signature

CheckList - GEIC Prepared By:Eng. Yousry I. Farag


Ver (0) PMP,LEED
Design and Construction of 3 units FD type and 2 units FC Type
PROJECT LVQ Project -PHASE 2
CLIENT Gulf Warehousing Company Consultant: Gulf Engineering&Industrial Consultancy
Main Contractor Al Bader Construction and Steel Project Ref:
Sub Contractor Contract No.
Quality Control Checklist Quality Form Ref: GM/CL/010
Building Name:
Block Work ITR Ref. Number:

Description of the Activity/ Item

Discipline: (Tick Which ever applicable) Civil Mechanical Electrical Arch.


Reference Drawings: Rev.
Rev.
SI Report No/Result Results Verified By:
Inspection / Check Point SUB- Remarks
No. (OK/RJ/NA) Date CONTRACTOR CONTRACTOR GEIC
1 Approval of all Material to be ensured
2 Layout as per approved shop Drawing?
Approved Proportion of mortar mix used and
3 obtained consistend mix?
Metal Lath provided every Alternatieve
4 Course
Wall Ties and other Accessories Provided in
5 correct Location?
6 Confirm all the MEP Services Provided
Doors and Window Openings are as per Shop
7 Drawings
All the Joints are Completely Filled with
8 Mortar
Block work Joints are Racked Uniformely
9 to 10mm (min.)
Expansion Joint b/w Bottom of Beam & Top of
10 Block Work
Confirm Final Inspection cariied out and Work
11 Under Tolerance

Legend: Accepted (OK) Rejected with Remarks (RJ) Not Applicable (NA)

Comments form Main Contractor:

Comments form Client/Consultant:

Subcontractor Main Contractor Client / Consultant


Signatures Name
Register:
Signature

CheckList - GEIC Prepared By:Eng. Yousry I. Farag


Ver (0) PMP,LEED
Design and Construction of 3 units FD type and 2 units FC Type
PROJECT LVQ Project -PHASE 2
CLIENT Gulf Warehousing Company Consultant: Gulf Engineering&Industrial Consultancy
Main Contractor Al Bader Construction and Steel Project Ref:
Sub Contractor Contract No.
Quality Control Checklist Quality Form Ref: GM/CL/017
Building Name:
Plastering Works ITR Ref. Number:

Description of the Activity/ Item

Discipline: (Tick Which ever applicable) Civil Mechanical Electrical Arch.


Reference Drawings: Rev.
Rev.
SI Report No/Result Results Verified By:
Inspection / Check Point SUB- Remarks
No. Date
(OK/RJ/NA) CONTRACTOR CONTRACTOR GEIC
1 Approval of all Material to be ensured
2 Curing of Block work?

All the Plastering accessories are fixed, Level


3 Pads are in Place and Ready to Receive Plaster
4 Plaster Beads and Stops Correctly Fixed
Confirm Mechanical Embedded Items are
5 Completed?
6 Confirm all the MEP Services Provided
7 Mixing, Application of Rush Coat
8 Curing of Rush Coat
9 Mixing,Application of Finish Coat

10 Curing for Finish Coat of Plastering


Plastered Surface is Smooth, in Plumb and away
11 from Cracks

12 Final Inspection Carried Out

Legend: Accepted (OK) Rejected with Remarks (RJ) Not Applicable (NA)

Comments form Main Contractor:

Comments form Client/Consultant:

Subcontractor Main Contractor Client / Consultant


Signatures Name
Register:
Signature

CheckList - GEIC Prepared By:Eng. Yousry I. Farag


Ver (0) PMP,LEED
Design and Construction of 3 units FD type and 2 units FC Type
PROJECT LVQ Project -PHASE 2
CLIENT Gulf Warehousing Company Consultant: Gulf Engineering&Industrial Consultancy
Main Contractor Al Bader Construction and Steel Project Ref:
Sub Contractor Contract No.
Quality Control Checklist Quality Form Ref: GM/CL/015
Building Name:
Painting - External - Internal ITR Ref. Number:

Description of the Activity/ Item

Discipline: (Tick Which ever applicable) Civil Mechanical Electrical Arch.


Reference Drawings: Rev.
Rev.
SI Report No/Result Results Verified By:
Inspection / Check Point SUB- Remarks
No. Date
(OK/RJ/NA) CONTRACTOR CONTRACTOR GEIC
1 Approval of all Material to be ensured
2 Type of application Roller/Spray
Angle of Spray/ Application as per Manufacturer
3 Recommendation
Surface Moisture is whithin Permissible Limits
4 (<4%)
Surface is Free From Cracks & Repairing done as
5 Necessary
6 Application of Primer--------------
Sufficient Curing Period Allowed as per
7 Manufacturer Recommendation
8 First Coat & Specified DFT?
9 Application of Stucco Filler--------------
Sufficient Curing Period Allowed as per
10 Manufacturer Recommendation
11 Application of First Coat & DFT------------

12 Application of Final Coat & DFT---------

13 Final Inspection?

Legend: Accepted (OK) Rejected with Remarks (RJ) Not Applicable (NA)

Comments form Main Contractor:

Comments form Client/Consultant:

Subcontractor Main Contractor Client / Consultant


Signatures Name
Register:
Signature

CheckList - GEIC Prepared By:Eng. Yousry I. Farag


Ver (0) PMP,LEED
Design and Construction of 3 units FD type and 2 units FC Type
PROJECT LVQ Project -PHASE 2
CLIENT Gulf Warehousing Company Consultant: Gulf Engineering&Industrial Consultancy
Main Contractor Al Bader Construction and Steel Project Ref:
Sub Contractor Contract No.
Quality Control Checklist Quality Form Ref: GM/CL/013
Building Name:
Flooring & Wall Tiling Works ITR Ref. Number:

Description of the Activity/ Item

Discipline: (Tick Which ever applicable) Civil Mechanical Electrical Arch.


Reference Drawings: Rev.
Rev.
SI Report No/Result Results Verified By:
Inspection / Check Point SUB- Remarks
No. Date
(OK/RJ/NA) CONTRACTOR CONTRACTOR GEIC
1 Approval of all Material to be ensured
Floor/wall is cleaned, dry & substrata is
2 ready foo to receive finishing works
3 Embedded plumbing works completed
4 Embedded electrcial works completed
5 Adhesive / mortar application & curing
Layout and locations of pedestals and
6 surfaces (for raised floors)

Fixing of pedestals over the floors with steel


7 expansion anchors (for raised floors)
Raised floor pannels are firmly fixed to the
8 pedestals
Flooring/tile works done in level & confirm PVC
9 spacers for joint are uniform
Flooring and wall tiles are completed and work is
10 satisfactory
Area is clean and protected after completion of
11 work

12 Skirting for floor & wall joint provided

Legend: Accepted (OK) Rejected with Remarks (RJ) Not Applicable (NA)

Comments form Main Contractor:

Comments form Client/Consultant:

Subcontractor Main Contractor Client / Consultant


Signatures Name
Register:
Signature

CheckList - GEIC Prepared By:Eng. Yousry I. Farag


Ver (0) PMP,LEED

Potrebbero piacerti anche