Sei sulla pagina 1di 12

International Site Review

1/2002

Rapid progress with Doka

M2 Medway
bridge,
Kent, UK

Kent: Mauritius: Atlantic City: Berlin:


M2 Medway Bridge Midlands Dam Harrah’s Extension Olympic Stadium

rapid progress with cost savings in only 7 months fair faced concrete
Page 3 Page 5 Page 8 Page 11
Editorial
Looking through this latest edition of
Formwork News, you’ll be able to inform
yourself on a number of very interesting
forming assignments where superb re-
sults have been achieved worldwide with
the aid of Doka formwork systems and
planning work.
Particular attention should be drawn
to the forming assignments on the Med-
way Bridge in Kent, UK,
and (with composite
superstructure form-
work) on the Havel During pouring, the elements of the outside formwork are anchored to the
Bridge in Germany, and forming carriage. For repositioning, the elements are simply lowered.
to the climbing-form-
work assignment on
the towers of the Vistu- Havel Bridge in Plaue, Germany:
la Bridge in Poland. The
use of Doka automatic
Werner Haring climbing formwork on
the 26-storey Harrah’s
Hotel and Casino Extension in Atlantic
Step by step …
City, N.J., USA is also worthy of mention.
However, the high-quality results
… a well-planned cycle sequence
achieved on these and many other pro-
jects are only possible using modern e.g.: in the bridging of the River Havel: In Plaue, just west of the
formwork systems which are available at town of Brandenburg, a 240 m long steel composite bridge is
short notice, and with efficient formwork being built across the River Havel. The contractor is Porr Techno-
planning. Here, only a dependable and cap- bau of Berlin.
able formwork partner can possibly fulfil
all the essential requirements that must
be met if in-situ concrete construction is
to proceed smoothly and successfully.
F or structural design reasons, the
13.0 m wide concrete carriage-
way cannot be cast progressively
time in the “back-step” sequence.
After all, there was a distance of
75 m to cover between each of the
In today’s competitive situation, it is working from one end towards the pouring cycles.
vital to locate – and utilise efficiently – all other. This means that rapid reposi- Thanks to the well thought-out
possible rationalisation potential in con- tioning of differently sized sections, Doka systems, repositioning (i.e.
struction operations. It is a proven fact along the entire length of the moving the carriage forward or
that even today, with the right formwork bridge, was called for here. back) took only a few hours each
system, optimum formwork service and a The “traffic manager”, foreman H. time. “We are most satisfied with
capable formwork partner, significant Bähr, came up with a valuable time- the results that have been
cost-reductions are possible on construc- saving idea: Using just one centrally achieved. Working together with
tion sites. positioned chain, it was possible to project manager Carsten Beer and
It is not only on major projects, howev- shift 80 tonnes of weight. Without Doka field officer Thomas Schnei-
er, that innovative formwork ideas are to having to adjust between left and der, it was possible to optimise the
be found. Many of the articles in this edi- right towing devices, either when ad- forming carriage for our particular
tion show excellent examples of con- vancing or reversing – which saves project so that we could use it in
struction companies and formwork engi- just the way that we had in mind”
neers working together to develop very Easy repositioning of the formwork says site engineer Thomas Thiel. ■
efficient cost-saving formwork solutions. has ensured that construction can
We know, and know well, that form- move ahead swiftly. Contractors: Porr Technobau
work-related services are becoming an
increasingly significant factor in day-to-
day construction operations. This is a
challenge that we respond to with combi-
Formwork News 1| 2002

nations of products and services that are


tailor-made for the construction project in
question.

Werner Haring
Chairman of
2 Doka Group Management
New motorway bridge across the River Medway:

Rapid progress with Doka


A 17 km stretch of the A2/M2 motorway route between London
and the Kent coast is currently being widened. This has necessi-
tated the building of a new bridge across the River Medway, at
the western end of the widening project. The new Medway
Bridge will be completed by the summer of this year, using Doka
formwork. It is located between the existing M2 motorway
bridge and the recently completed railway bridge built as part
of the Channel Tunnel Rail Link. Britain’s Highways Agency
awarded the construction contract for this £ 20 m (€ 33 m) 3 Doka edge beam forming wagons
bridge project to the “CSM Joint Venture” of Costain, Skanska coupled together to make a traveller.
and Mowlem.

T he balanced cantilever works, to


be carried out on the river spans
of the bridge, comprise the con-
The superstructure is finally
completed with the casting of the
edge beams along the outer edges
WITO, who were responsible for
the design of the balanced-can-
tilever works. This made it possi-
struction of 16 sections of super- of the cantilevering cover slab. ble – despite the difficult nature of
structure, of varying heights and This was done in a highly stream- the task – to elaborate a highly effi-
lengths, on either side of each of lined manner using Doka edge cient formwork scheme which en-
the Medway Bridge’s two river beam forming travellers. abled work to progress smoothly
piers. The Doka formwork for this The concept for the superstruc- and swiftly. ■
was designed in such a way that it ture formwork was developed by
can adapt to continuous reductions Doka in close collaboration with
in the section height. Over 20 m the contractors CSM Joint Venture Contractors:
wide to accommodate 4 lanes of (Costain, Skanska & Mowlem) and CSM JV (Costain, Skanska & Mowlem)
traffic, the bridge superstructure
has a section height of 10 m at the The completed bridge superstructure will have a clear span of 152.5 m
piers, which tapers to nearly one between the piers and will be 30 m above water-level.
third of this height (3.50 m) by mid-
span. While the heights of the su-
perstructure sections progressively
decrease, their lengths increase
from 3.10 m to 6 m towards mid-
span, to make optimum use of the
load-bearing capacity of the can-
tilever construction traveller and to
speed up the progress of work.

The tensile stresses occurring in


the cover slab of the superstructure
during the construction stage, and
in the soffit slab following comple-
tion, are sustained by post-ten-
sioned cables anchored to concrete
corbels. For these prismatic ten-
sioning anchorages in the soffit
slab and cover slab, Doka offered a
simple – yet efficient – formwork
solution which enables the form-
Formwork News 1| 2002

work to be erected and struck with-


out difficulty, and to be quickly
repositioned. This solution had to
allow for the fact that the external
post-tensioned cables have to be
installed after concreting, but be-
fore the formwork is struck. 3
The elements of the outside formwork, each measuring 170 m2, are pulled forward on the launching girder, on both
sides simultaneously.

Austrian cut-and-cover tunnel being


cast monolithically formwork are hydraulically ad-
vanced by the length of one section.
The reinforcement is now placed for
A 2.3 km long twin-tube tunnel with 2 lanes per tube is currently the floor of the next section.
under construction for Austria’s A8 autobahn in the Aiterbach
Valley near Wels, in a weekly cycle. Because the cut-and-cover On the Monday, the concrete has
tunnel stands in groundwater, it is being built as a “white tank”, cured sufficiently for the formwork
meaning that its foundation, walls and cover slab have to be to be struck. Once again, the central
cast monolithically (i.e. in one single pour). hydraulic control unit is used for
repositioning the outside form-

T he contractors, Strabag Bau AG,


required not only the shortest
possible cycle sequence during
work. Then the inside formwork is
put into the travelling position, and
the 63 cm haunched elements on
pouring, but also comprehensive the base slab are tilted up out of the
mechanisation of the formwork in way. The tunnel-tube on the inside
order to save on labour. Between of the curve is the first to be reposi-
them, the Strabag staff in charge of tioned – an area of formwork mea-
the planning work and the Doka suring 510 m2 and weighing 150 t is
Formwork Experts from Amstetten now moved into the new position.
came up with the ideal solution:
Every Tuesday, the centre-wall
Two Doka travelling formwork reinforcement is completed. The re-
carriages, working from the middle inforcement for the outside walls is
of the future tunnel towards either placed after the second half of the
end, each allowing a small crew to inside formwork has been pulled
pour 24 m long sections. In this forward.
All these actions are initiated from a way, a total of 48 m of tunnel can be
central control unit – e.g. tilting up the completed every working week. It On the Wednesday, the finishing
haunched elements in the floor- will take a total of 50 cycles towards touches are put to the reinforce-
Formwork News 1| 2002

slab/wall transition zone, or retracting one end of the tunnel, and 50 cycles ment and the form-ties.
the wall-formwork elements when towards the other, to complete the
striking the formwork. In only 5 work- full length of the tunnel. Each of On the Thursday, approx. 1000 m2
ing days, all the operations needed for these cycles runs according to the of concrete has to be poured within
one entire section – including striking, following schedule: Every Friday, around 14 hours. ■
advancing, formwork erection and the two huge launching girders sus-
4 pouring – have been completed. pended in the portals of the inside Contractors: Strabag
48,000 m3 of concrete for the Midlands Dam on Mauritius:

Precisely co-ordinated formwork


saves (transport) costs:
The brief given to the form-
work planners for the spillway
on the Midlands Dam is actu-
ally one that is relevant for
any site: To use only as much
formwork as strictly neces-
sary. This is particularly true of
sites at remote locations,
where transport costs for ma-
terials and equipment play a
not insignificant role.

T his dam project necessitated


many and frequent adaptations.
Starting with the huge floor blocks,
then in the rising sidewalls and the
centre pier, right the way through
to the blocks of the spillway with its
inclined surfaces. Careful, thorough
planning is particularly worthwhile
in a case like this.
Doka dam formwork and Doka folding platforms K were used alongside (and behind)
And here is what it led to: For the one another – the former without through-ties, the latter as a tied wall formwork.
approx. 48,000 m3 of concrete in-
volved here, the contractors used The use of Doka large-area form- tion blocks were also fitted with
only 1750 m2 of formwork – helped work Top 50, in lengths of 3.00, 4.50 Doka dam formwork D22 compo-
by an exact utilisation plan which and 6.00 m, provided a uniform nents. This made it possible to con-
minimised down-time for the form- spacing for the supporting con- tinue raising the sidewalls and the
work and scaffolds. struction frames used on the starter centre pier with dam formwork
blocks, and for the bracket and an- D22, seamlessly and without
All the supports – both the sup- chor spacings in the “climbed” through-ties. The stiffening but-
porting construction frames and pouring-sections. The formwork tress walls in this zone were, how-
the D22 brackets – followed the grid was designed for block heights of ever, executed with through-ties,
pattern of the formwork elements. 3.0 m and a concrete pressure of 35 using the Doka climbing formwork
kN/m2. K as a scaffold unit. The formwork
The cornerstone of this versatili- elements were always the same,
ty was the well thought-out grid of For this reason, the supporting which permitted large numbers of
the formwork elements. construction frames for the founda- repeat uses. This, in turn, made for
low total quantities of formwork –
and low costs.

Within the next 36 months, the


2450 m long earth dam will also be
finished. Covering an area of 300
ha, up to 25.5 million m3 of water
Formwork News 1| 2002

will then be available for irrigation


and potentially also for processing
into drinking water. ■

Contractors:
DTP Terrassement - Bouygues TP J.V. 5
Brazil:

Tough formwork
challenge
T he 1.25 km long viaduct VD7 on the 16 km
long “Segunda pista da Rodovia dos Imi-
grantes” expressway in Brazil is being built
using Doka climbing formwork 150 F for the pier
shafts and Doka large-area formwork Top 50 for
the pier-heads and carriageway decks, and with
Site: VD 7 viaduct, Brazil a free-cantilevering carriage with a capacity of
Contractors: Consórcio Imigrantes - JV CR Almeida (Brazil) & Impregilo (Italy) 120 tonnes. ■

Singapore:

On schedule, and within budget


U sing Doka wall and floor-slab
formworks, the two 18-storey ad-
ministration buildings for the Singa-
pore Port Services Agency were
completed in an exceedingly short
construction period of only 12
months. This was made possible by
the use of Doka large-area formwork
Top 50 for the walls and columns,
and of Doka load-bearing towers d2,
of which a sufficient quantity was
commissioned for one-and-a-half
times the area of each floor. ■

Site: Port Services Agency, Singapore


Main Contractor: Samsung

Portugal:

One cycle every 8 days D oka supplied formwork for the


Perna Seca viaduct on the A2
motorway “Auto-Estrada do Sul” in
Portugal.
A 60 m long trussed box section
with swivel side drop panels served
as a launching girder on which – in
Formwork News 1| 2002

a 2nd operation – Top 50 formwork


was mounted on top. ■

Site: Perna Seca viaduct


Contractors: Contacto, Ecop, Somec e
6 Gabriel Couto
World site round-up

Lebanon:

A comprehensive
assignment
W ork on the shell of the Hajj Bahaeddin Hariri
Mosque was recently completed with the form-
ing operations on the dome, which has a diameter of
25 m and a clear height of 35 m. All the in-situ concret-
ing works, including the two minarets, were performed
successfully using Doka formwork equipment. ■

Site: Hajj Bahaeddin Hariri Mosque, Lebanon


Contractors: Betabat

Ireland:

Staxo: simply better


T he ease and simplicity with which the Staxo load-
bearing tower can be erected and dismantled were
greatly appreciated by subcontractor McNally Brothers
on its bridge construction site at Batter Lane, Swords,
Co. Dublin, on Ireland’s Northern Motorway. In order to
speed up operations, each of the load-bearing towers
were pre-assembled on the ground before being lifted
into position by crane. ■

Site: Bridge on Northern Motorway at Batter Lane, Swords, Co. Dublin.


Main Contractor: Siac Construction
Subcontractor: McNally Brothers

Dubai:

Formwork handling
made easy
T he 43-storey, 250-room Shangri-La Hotel is current-
ly under construction in Dubai. Doka has supplied
Formwork News 1| 2002

this project with 66 automatic climbers SKE 100, which


“climb” the outside of the façade and carry a rising
scaffold. Both the outside and inside formworks (as-
sembled from large-area formwork Top 50) are sus-
pended from this scaffold. ■

Site: Shangri La Hotel, Dubai 7


Contractor: Al Habtoor Murray & Roberts JV
Atlantic City:

Harrah’s Extension finished in only 7 months


Thanks to an optimised form-
work concept, it was possible
to complete the shell of the
26-storey Harrah’s Hotel and
Casino Extension in Atlantic
City, New Jersey, within a
mere 7 months.

T he walls of the lower storeys


are rather higher and were
formed – highly efficiently – with
large-area gangs of Framax
framed formwork. And Top 50
large-area formwork, which was
delivered to the site pre-assem- As the floor slabs had already been cast, the remaining formwork had
bled, did a superb job on the outer to be struck by hand – a task for which the lightweight Alu-Framax panels
façades of the end walls, and on proved highly advantageous.
the lift shafts and stairwells. The
outside walls of the 2.90 m high situ concrete layer with which the poured. What is more, this had to
typical floors were raised using 24 planned filigree floors were to be be done without any assistance
automatic climbers SKE 50. covered had to be poured “in one from the crane. With the light-
go” along with the walls and weight 60 cm wide Alu-Framax
For the opposing formwork on columns. For this reason, it was not panels that were used here by the
the inside, and for all the columns, possible to strike the formwork contractors, FABI Construction, this
easy-to-handle Alu-Framax panels from the walls and columns until was no problem to accomplish.
were used, as the 15 cm thick in- after the floor slabs had been
The formwork concept elaborat-
ed by Doka’s US representatives
Conesco, in collaboration with con-
tractors FABI Construction, enabled
an average forming cycle of one
week per typical storey. This made it
possible for the shell, on which work
had commenced only in May 2001,
to be completed by the end of 2001.

No wonder, then that General


Superintendant Hugh McCarron
was so satisfied with how all the
forming operations had gone, and
that this success convinced FABI
President and owner Al Zappone to
purchase the Alu-Framax, Top 50
and MF 240 equipment from this
project for use on his next project in
Atlantic City. ■

Contractors:
Formwork News 1| 2002

FABI Construction, New Jersey

Doka automatic climbing formwork


in action on the exterior façades
of the 90 m tall Harrah’s Hotel and
8 Casino Extension.
Amsterdam:

Formwork and concrete


placing boom “in one go”
HBG Utiliteitsbouw had been
awarded the contract to erect
a 19-storey, 79 m tall office
tower in the centre of Amster-
dam. In order to be able to
meet the tight time deadlines,
it was decided – in collabora-
tion with Doka Nederland and
Doka T&S Amstetten – to use
Doka automatic climbers SKE
50 and SKE 100.

T he core and outside walls of the


entire structure were formed
with automatic climbing technolo-
gy, in 21 cycles. In order to achieve
the most efficient cycle possible, no
account was taken of the heights of
the storeys themselves. The layout
of the office tower corresponds to
an elongated rectangle enclosing a
narrow inside rectangle, and with
three projecting walls.
The pouring cycles were all kept
The formwork area, totalling the same size; this, plus the preci-
530 m2, was designed and broken sion climbing sequence, ensured
down accordingly; it consisted of that work progressed rapidly.
13 elements to be moved, on nine
Doka climbing platforms MF 240
and three shaft platforms. For form- This ensures that climbing takes
work erection and removal, the place uniformly and smoothly.
elements were advanced and re-
tracted with the Doka travelling unit ● Work on placing the reinforce-
MF 240. Where space was tight, the ments is finished. The gap to shaft
wall formwork was suspended 1 is closed.
from a steel support construction. ● The concrete placing boom
In this way, it was possible to lift the “hitches a ride” with the final lift of
formwork without using a crane in the automatic climbers SKE 100,
these situations as well. thereby arriving at the top at the
same time. The boom stands on an
Using Doka automatic climbers, integral grillage, and thus needs no
things moved upwards in the fol- separate platform of its own. This
lowing regular cycle: in turn saves an extra lift and
means that the boom can be made
● The SKE 50 automatic climbers considerably shorter. Higher ma-
Formwork News 1| 2002

lift one shaft formwork element up- noeuvrability and appreciable cost- The elements are lifted one at a time,
ward. Work begins on placing the savings are the result. in line with the progress of the rein-
reinforcements. forcement work. This picture clearly
● The entire outside formwork now In this way, by taking account of shows the generous room for ma-
follows. The central control unit is all the issues involved, this cycle se- noeuvre that is left for these operations.
connected to all the automatic climb- quence made it possible to meet the
ers via a circular tube (ring main). tight deadlines imposed here. ■ Contractors: HBG Utiliteitsbouw 9
Doka not only supplied all the form-
New Oil Sector Complex, Kuwait: work systems, but also provided com-
prehensive scheduling to go with it.

Complex logistical challenges The outside formwork of the walls


also serves as the perimeter form-
work for the floor-slabs.
The new joint central administration complex of the Kuwaiti Oil Ministry The floor-slabs follow in a fort-
and the Kuwait Petroleum Corporation comprises two high-rise struc- nightly cycle, with sufficient form-
tures. One of these is 17 storeys tall and the other 21 storeys tall. There work equipment for two complete
is also a third tower with a semi-elliptical cross-section that houses the storeys being commissioned for
stairwell and lift shafts, and from which access is provided to the two of- each of the two office towers. A
fice towers via aerial walkways. In addition, a 5500 m2 podium - a single- total of approx. 5600 m2 of
storey and two-storey low-rise structure - is being built: Dokaflex 20 is in use. In the areas
that are open to the outside, d2
tableforms are used, for safety

T he contractors, a joint venture


of Alghanim International and
LG Engineering, are building this
storeys ahead of the floor slabs,
making it possible to “de-link”
operations on the vertical and
reasons.
The walls of the semi-elliptical
stairwell and lift-shaft core are
administration complex using the horizontal parts of the structure also “climbed ahead” in their en-
whole spectrum of Doka equip- and thus saving construction time. tirety. The floor-slabs and aerial
ment, and with wide-ranging Doka For the outside walls of the trian- walkways to the two office towers
planning assistance. gular zone of the office towers, a follow approx. two storeys be-
Office Towers A and B each complete set of outside formwork hind. Some 650 m2 of large-area
contain two cores, consisting of has been commissioned, and for formwork Top 50 is in use here, to-
stairwell and lift-shaft groups. the inside walls, a one-half set gether with climbing formwork
These cores are “climbed” two which is shifted once per storey. 150 F with trailing platforms and
shaft platforms. Here too, work is
proceeding in a weekly cycle. It
has taken very extensive planning
work by Doka Kuwait to master
the complex logistical challenges
presented here. The project also
calls for intensive on-site presence
and assistance from Doka, which
has been greatly appreciated by
the site engineers. ■
Formwork News 1| 2002

Contractors: Alghanim International –


LG Engineering

Doka carried out extensive planning


10 work to master the logistical challenges.
Warming up hall for Berlin Olympic Stadium:

Fair-faced concrete with Doka


Dating from 1936, the Berlin Olympic Stadium is being altered and
renovated in keeping with its status as a listed monument – all
the time alongside ongoing use of the stadium. By 2004, it will
have been upgraded into a modern event arena, not least for the
finals of the football World Cup which Germany is to host in 2006.

I n January 2002, work got under-


way on the building of a new,
two-storey “warming-up hall”: With
crete surface with the specified
formwork pattern. In this connec-
tion, the Doka Formwork Experts
Floor beams shored by Staxo load-
bearing towers.

lorry parking spaces and technical co-operated with the contractors


service installations in the approx. and the planner to recommend
5 m high sub-basement level, and a suitable formwork stacking config-
4.60 m high warming-up hall for the urations, which had to be approved
sportsmen and sportswomen in the by the client.
basement level. The 96 m long and
35 m wide reinforced concrete For important key locations, this
structure is built entirely under- was done with reference to eleva-
ground, under a 40 cm cover slab. tion plans which explained the pro-
After completion, the structure will posals.
be completely hidden from view be-
neath a large area of lawn. 380 m2 of Framax framed form- Framax for fair-faced concrete.
work – newly faced with form-ply for
Framed formwork Framax was use on the fair-faced concrete walls proceeded smoothly on the walls.
chosen to achieve fair-faced con- – ensured that forming operations This formwork was supplemented
by 135 m2 of newly re-faced circular
formwork H 20 for the curved sec-
tions of the supply tunnel.

The 30 cm thick floor between


the two basement levels is punctu-
ated at regular intervals by floor-
beams with a cross-section of 110 x
80 cm and with steel girders on the
inside. 1500 m2 of Dokaflex 1-2-4
with rented Dokadur panels serve
as the floor-slab formwork, and the
floor-beams are shored by Staxo
load-bearing towers. ■

General contractor: Walter Bau


in concert with Dywidag, Augsburg
Dokaflex 1-2-4 serve as the floor-slab formwork, and the floor beams are Forming operations:
shored by Staxo load-bearing towers. Bold GmbH & Co. KG Baubetriebe Berlin

UK: USA:
Doka UK Conesco Industries Ltd.
Formwork Technologies Ltd. 214 Gates Road
Formwork News 1| 2002

Monchelsea Farm, Heath Road Little Ferry, New Jersey 07643


Boughton Monchelsea Phone: (201) 6 41 65 00
Maidstone, Kent, ME17 4JD Fax: (201) 6 41 62 54
Austria: Phone: (01622) 74 90 50 E-Mail: dest@conesco.com
Österreichische Doka Schalungstechnik GmbH Fax: (01622) 74 90 33
A 3300 Amstetten, Reichsstrasse 23 E-Mail: UK@doka.com
Phone: +43-7472-605-0
Fax: +43-7472-64430 Ireland:
E-Mail: Oest.Doka@doka.com Doka Ireland For the Doka address nearest you, please see
Formwork Technologies Ltd. our web-site: http://www.doka.com, or phone
Germany: Tinure Industrial Complex or fax Doka in Austria or Germany. 11
Deutsche Doka Schalungstechnik GmbH Monasterboice, Drogheda
D 82216 Maisach, Frauenstrasse 35 County Louth
Phone: +49-8141-394-0 Phone: (041) 68 61 620
Fax: +49-8141-394405 Fax: (041) 68 61 525
E-Mail: Deutsche.Doka@doka.com E-Mail: Ireland@doka.com
“Most Siekierkowski” bridge across the Vistula in Warsaw:

Making optimised use of formwork leads


to efficient construction sequences
A new 830 m long cable-stayed bridge is being built across the cation above the top kink, where a
River Vistula just south of Warsaw’s Old Quarter, with twin 27 m long hollow steel profile had
towers to support and stay its 33 m wide carriageway deck, to be embedded inside each of the
which has a 250 m span. The contract to supply the formwork pier shafts.
for the two slender, 92 m tall bridge-towers went to Doka Polska.
The Top 50 formwork for the bot-
tom cross-beam rested safely on a

F orming bridge-towers such as


these cost-effectively is a fas-
cinating challenge: Massive spring-
heavy special profiles on the piers
(which had to be formed without
using form-ties), the walings of the
truss made of 20 tonnes of steel
profiles, which was used a total of
four times: First for the two bottom
ers, inclined towards the outside at Top 50 elements were stiffened cross-beams, and then for the two
an angle of 75° to the perpendicular with trusses. One set of springer top ones.
and conically tapering as they rise. formwork, assembled from Top 50,
Then, at a height of 12 m, a pre- was used to form the bases of all As the exemplary concept em-
stressed concrete cross-beam to four piers in succession. ployed here clearly shows: With
support the carriageway decks. good planning, even out-of-the-or-
Above this, two slender piers: Up to Four sets of Top 50 formwork dinary challenges can be mastered
a height of 62 m, these are hollow were then “climbed” on MF 240 both economically and in record
boxes and are inclined inwards at climbing platforms to form the four time. ■
an angle of 7°; above the 62 m rising pier shafts, in 17 casting sec-
mark, they rise exactly in the per- tions up to the finished height of
pendicular. At the kink in the piers at 92 m. All this was done with only a Contractors: JV of Mostostal Warszawa
a height of 62 m, there is a second very few crane cycles and – in the S.A., WARBUD S.A and Campenon
Formwork News 1| 2002

cross-beam. inclined sections – with a special Bernard SGE


overhang lifting unit, supplemented
Remarkably small quantities of by a single-sided inside formwork
equipment, most of it from the in the hollow-box zones.
standard product range – this is the
secret of optimum cost efficiency The four sets of formwork contin-
12 here. In order not to have to use ued to be used without any modifi-

Potrebbero piacerti anche