METHOD STATEMENT FOR:

FORMWORK OF FIRST FLOOR SLAB

PROJECT: THREE STOREY COMMUNITY MALL (K MALL) PROJECT

VENG SRENG BLVD, TRO PEANG TLERNG VILLAGE,


LOCATION: SANGKART CHOM CHAO, KHAN POR SEN CHEY, PHNOM
PENH, CAMBODIA.

ISSUER: CAMATEC ENGINEERING & CONSTRUCTION CO., LTD.


REFERENC
E:
CHECKED BY
ISSUED BY CAMATEC: APPROVED BY UBL:
CAMATEC:
……………………….. ………………………..
………………………..

SIGN: SIGN: SIGN:

DATE: DATE: DATE:

REMARK DATE DESCRIPTION


0
THREE STOREY COMMUNITY MALL Ref. : CMT-KMH-
(K-MALL) PROJECT KMALL-MS-004-00

Revision : 0
METHOD STATEMENT:
Date : 01-APR-2020
FORMWORK OF FIRST FLOOR SLAB
Page : 2 of 10

TABLE OF CONTENTS

1. CONTRACT DETAILS...............................................................................................3

2. SCOPE OF WORKS..................................................................................................3

3. SEQUENCE OF WORKS..........................................................................................3

3.1. SITE PREPARATION....................................................................................3

3.2. STEP 1.......................................................................................................... 3,4

3.3. STEP 2.......................................................................................................... 4

3.4. STEP 3.......................................................................................................... 4

3.5. STEP 4.......................................................................................................... 5

3.6. STEP 5.......................................................................................................... 5

4. EQUIPMENTS AND TOOLS.....................................................................................5

5. PERSONNEL............................................................................................................ 5

6. SAFETY, HEALTH & ENVIRONMENT......................................................................6-7

6.1. PERSONNEL.................................................................................................7

6.2. EQUIPMENT..................................................................................................7

6.3. MATERIALS...................................................................................................7

7. RISK ASSESSMENT ANALYSIS............................................................................8-9


THREE STOREY COMMUNITY MALL Ref. : CMT-KMH-
(K-MALL) PROJECT KMALL-MS-004-00

Revision : 0
METHOD STATEMENT:
Date : 01-APR-2020
FORMWORK OF FIRST FLOOR SLAB
Page : 3 of 10

1 CONTRACT DETAILS

EMPLOYER Urbanland City Development Co., Ltd.


MAIN-CONTRACTOR Camatec Engineering & Construction Co., Ltd.
 Date of starting work:
 Schedule:
 Working hours*: 07.00am – 05.00PM (Monday until Sunday)
* The working hours could be extended during the accepted working days (Overtime
might be applied)

2 SCOPE OF WORKS

The structural scope of work will be:


- Installing formwork of first floor slab

3 SEQUENCE OF WORKS

4 Site Preparation:

a. Before commencing the work, the area shall be clean isolate from other work.
Material to be used shall be kept nearby in one place.
b. Toolbox Meeting shall be implemented for all personnel who involve in this scope
work(scaffolder).
c. Any related work permit such as permit to working at height shall be approved
before commencing the work.
d. Safe access to for working area shall be maintain and well preparation
e. Temporary fall protection on working area shall be constructed to prevent any
falling hazard.
f. Trained operator or flagman will be engaged to control or operate heavy
equipment.
g. Ensure the source of supply to ready mix and grade of concrete is confirmed.

5 Step 1:
a. Before installing beam formwork, rebar reinforcement and casting concrete
suspended slabs, we have to erect scaffolding structure in order to support the
bottom of floor and beam.
b. Before starting the work. Survey or site in charge supervisor shall be survey the
area to locate the base point which will stand on the jack base.
c. After that we will deploy scaffold on each jack base.
d. We have two option of scaffolding which erect for support beam and scaffolding
for support concrete floor slab, For scaffolding support beam we will erect in 3
layer of scaffolding, First layer (type:1.7m), Second layer (type:1.2m), and third
layer (type: 0.9m). for scaffolding support slab we will erect in 3 layer of
THREE STOREY COMMUNITY MALL Ref. : CMT-KMH-
(K-MALL) PROJECT KMALL-MS-004-00

Revision : 0
METHOD STATEMENT:
Date : 01-APR-2020
FORMWORK OF FIRST FLOOR SLAB
Page : 4 of 10

scaffolding. First layer (type:1.7m), second layer (type:1.2m), and third layer
(type:1.2m).
e. Each layer of scaffold will be equipped with X-bracing for chaining from a scaffold
to another scaffold. Horizontal tubular bracing will be applied also for
straightening the position of entire scaffolding. Horizontal bracing shall be
equipped from 2 meters from bottom and continue up until reach below roof slab.
f. While we are erecting the scaffolding. Safe access for worker working shall be
applying simultaneously during erect scaffolding. Steel ladder and platform will be
in place for area of erecting scaffolding.
g. Once the scaffolding erected on top layer. We will installing the U-head jack on
hole top of scaffold. U-head jack could be squeeze up or down for support the
steel joist on top.
h. The gap of U-head jack from one to another shall be 0.6m to 0.7m.
i. Once U-head jack is installed and joist was in place. We will deploy formwork of
roof floor slab.

6 Step2:
a. Once base of scaffold is completed and secure, we will lift bottom formwork of
beam to plot on its marked position by crane, Signal man and lifting supervisor
will be at place for this operational.
b. Once bottom formwork are secure and on right position, beam rebar
reinforcement will be lift by crane and plot on between both secure column
accordingly.
c. After that we will install both of beam side one by one with secure welded support
steel tube (50x50@1.6mm) and welding between bottom formwork and beam
side formwork steel tube (50x100@1.6mm) will be weld and attached on head
tree and align with beam formwork which will be able for strut to be stand on for
building (welding between beam formwork and below steel tube).

7 Step 3:
a. Once scaffold is secured and stable with horizontal and vertical bracing, we will plot
steel tube (50mm x 100mm) as stringer attached on U-head jack. Top level of
stringer shall be same level of top inner of floor beam. Shoring and props shall be
added to support stringer.
b. After that we will lay steel mesh (6mm x 200) above stringer. Note: location and
cover steel mesh shall be followed to construction drawing of floor beam and slab.
c. Steel mesh shall be lift by crane to drops on floor position and lifting supervisor will
be supervising at place to secure the safety operational.
THREE STOREY COMMUNITY MALL Ref. : CMT-KMH-
(K-MALL) PROJECT KMALL-MS-004-00

Revision : 0
METHOD STATEMENT:
Date : 01-APR-2020
FORMWORK OF FIRST FLOOR SLAB
Page : 5 of 10

8 Step 4:

a. When scaffolding, beam formwork, are secure and follow construction drawing
design, we will cast the concrete.
b. Access way for concrete truck and pump truck have to be maintain and exclusion
from non-personnel.

9 Step 5:

a. After 16-24h concreted casted. Curing shall be take place in order to feeding the
concrete slab and straighten quality of casted concrete.
b. Beam formwork, scaffolding, props and shoring shall be remove out. Once the
concrete testing result is passed for 7days 14days, and 28day,

1 Scaffolding for support beam and slab


THREE STOREY COMMUNITY MALL Ref. : CMT-KMH-
(K-MALL) PROJECT KMALL-MS-004-00

Revision : 0
METHOD STATEMENT:
Date : 01-APR-2020
FORMWORK OF FIRST FLOOR SLAB
Page : 6 of 10

Scaffolding layout

5 EQUIPMENT & TOOLS:

- Concrete mixer - Welding machine


- Pumping truck - Drilling machine
- Hand tools - Cutting rebar machine
- Hand saw - Mounted crane
- Wire cutter, Brush - Scaffolding
- Shovel
- Vibrators
- Concrete float

6 PERSONNEL

Qualification Numbe Responsibility


r
Site Manager 1 Monitor site
Supervisor/Foreman 1 Monitor site
Safety Officer 1 Implementing &
overseeing safety at
work
Workers (Flow of worker according to scale of job) 30 Field work
THREE STOREY COMMUNITY MALL Ref. : CMT-KMH-
(K-MALL) PROJECT KMALL-MS-004-00

Revision : 0
METHOD STATEMENT:
Date : 01-APR-2020
FORMWORK OF FIRST FLOOR SLAB
Page : 7 of 10

7 SAFETY, HEALTH & ENVIRONMENT

7.1 Information to personnel


a. Before job start to check if protective & safety requirements are provide.
b. Appropriate PPE (Personal Protective Equipment) must be used by personal
doing task.
c. Pre-job talk must be done all personal assigned to do the task must understand
the hazard associated with the job and the control measures in place
d. Safety induction must be given to all the personnel prior to entering the site and
adequate supervision by safety officer and site supervisor to ensure the job is
carried out in the safety way possible.
e. Non-essential personnel will be kept well away from the area of operation and
Bank-men will be provided where necessary.
f. Always wear harness for scaffolding during erection.

7.2 Use of PPE


a. All personnel will be issued with and instructed to always maintain safe working
practices and the civil engineer shall be responsible to ensure safety
procedures are followed.
b. Safety Helmets must be used by everyone, in area, where there is a potential is
of falling objects or when passing under congested pipe and equipment.
c. Personnel working in the vicinity of loading operation will wear safety helmets,
safety footwear and high-visibility vests.
THREE STOREY COMMUNITY MALL Ref. : CMT-KMH-
(K-MALL) PROJECT KMALL-MS-004-00

Revision : 0
METHOD STATEMENT:
Date : 01-APR-2020
FORMWORK OF FIRST FLOOR SLAB
Page : 8 of 10

7.3 Hand Tools and Equipment


a. All tool and equipment shall be in good working condition.
b. Operator shall be instructed in the safe use of the equipment by Camatec team
engineer/safety personnel prior to use.
c. All equipment shall be mechanically checked prior using on site.

Quality Supervisor: Safety Supervisor:


Name: Sokhan Sonoreakchieth Name: Johnny Soupaspas
Position: QA/QC Engineer Position: HSE
Phone number: 010 454 674 Phone number: 098 866 966
Signature : Signature :
c. RISK ASSESSMENT ANALYSIS

Risk assessment
(Infrastructure)
Hazard identification Risk evaluation Risk control
Re Possible Existing risk Implementat

RPN

RPN
Work activity Hazard injury / Ill S L Additional controls S L Date
f controls ion person
health
a) Site Tripping Injury to 1. Daily
preparation hazard worker housekeeping.
Site N.A
2. Raise in TBM
01 2 2 4 supervisor/ (Contin
regarding to
Site manager uously)
housekeeping at
work.
Unidentified Damage 1. MEP and technical
underground underground team have to verify
system system safe work
N.A
regarding to Site
4 1 4 (Contin
existing supervisor
uously)
underground
system before
operate work.
Scaffolding Fallen object Fatal injuries 1. Do not keeping 1. Install toe board to 5 1 5 Site N.A
installation unused material on prevent fallen object supervisor/ (Contin
02 scaffold 3 3 6 2. Provide training for Site manager uously)
2. Use proper PPEs work at height
3. Install handrail
Lean/collaps Death/fatal 1. Use only minimum Site N.A
e of injuries weight of material supervisor/ (Contin
scaffolding 2. Strengthening Site manager uously)
support and 5 1 5
bracing of
scaffolding
structure
Use Falling from Fatal injury to 1. Apply PTW 1. Fall protection must
Scaffolding height person 2. Scaffold to be be provided
directly checked by 2. Open side barricade
involved in scaffold supervisor must effective
operation weekly guardrail
3. Proper PPE 3. Conduct regular
Site N.A
(safety harness) TMB discuss safety
03 5 2 10 5 1 5 supervisor/ (Contin
must be worn at height
Site manager uously)
4. Keep out 4. Life line to be
unauthorized provided for
personnel anchorage if there is
no other anchorage
point

Tools fall by Foot injury to 1. Proper PPE (hand


mishandling worker gloves) to be worn Site N.A
when using hand 3 1 3 supervisor/ (Contin
tools Site manager uously)