Sei sulla pagina 1di 6

QUALITY ASSURANCE DEPARTMENT

KRA-KPI Of December, 2019


Name ID: KRA KPI Weight Target Ach. Unit

Assuring finished goods transfer as per approved weight range 10 100 97


Percent
Md. Jahirul Islam

20161102 Assuring process loss as per approved level during finishing 10 100 84.2 Percent
Quality Assurance Assuring process loss as per approved level during production 10 11.5 6.06 Percent
Check chemical and RM quality 5 100 99 Percent
Ensure quality assurance of machine production 40 98 94 Percent
Keeping Customer complain maximum 100 MT of total Sales 10 1 Percent
Coordination and Administration Coordinate and cooperate with various department 5 100 98 Percent
Reporting Ensure all reporting timely 10 100 96 Percent
Total 100 611
QUALITY ASSURANCE DEPARTMENT
KRA-KPI Of November, 2019
Name ID: KRA KPI Weight Target Ach. Unit

Assuring finished goods transfer as per approved weight range 10 100 96


Percent
Md. Jahirul Islam

20161102 Assuring process loss as per approved level during finishing 10 100 90.4 Percent
Quality Assurance Assuring process loss as per approved level during production 10 11.5 9.6 Percent
Check chemical and RM quality 5 100 98 Percent
Ensure quality assurance of machine production 40 98 94 Percent
Keeping Customer complain maximum 100 MT of total Sales 10 1 Percent
Coordination and Administration Coordinate and cooperate with various department 5 100 98 Percent
Reporting Ensure all reporting timely 10 100 96 Percent
Total 100 611
QUALITY ASSURANCE DEPARTMENT
KRA-KPI OfOctober, 2019
Name ID: KRA KPI Weight Target Ach. Unit

Assuring finished goods transfer as per approved weight range 10 100 96


Percent
Md. Jahirul Islam

20161102 Assuring process loss as per approved level during finishing 10 100 91.07 Percent
Quality Assurance Assuring process loss as per approved level during production 10 11.5 8.1 Percent
Check chemical and RM quality 5 100 98 Percent
Ensure quality assurance of machine production 40 98 95 Percent
Keeping Customer complain maximum 100 MT of total Sales 10 1 Percent
Coordination and Administration Coordinate and cooperate with various department 5 100 99 Percent
Reporting Ensure all reporting timely 10 100 98 Percent
Total 100 611
QUALITY ASSURANCE DEPARTMENT
KRA-KPI Of September, 2019
Name ID: KRA KPI Weight Target Ach. Unit

Assuring finished goods transfer as per approved weight range 10 100 96


Percent
Md. Jahirul Islam

20161102 Assuring process loss as per approved level during finishing 10 100 89.82 Percent
Quality Assurance Assuring process loss as per approved level during production 10 11.5 9.15 Percent
Check chemical and RM quality 5 100 98 Percent
Ensure quality assurance of machine production 40 98 94 Percent
Keeping Customer complain maximum 100 MT of total Sales 10 1 Percent
Coordination and Administration Coordinate and cooperate with various department 5 100 97 Percent
Reporting Ensure all reporting timely 10 100 95 Percent
Total 100 611
QUALITY ASSURANCE DEPARTMENT
KRA-KPI Of August, 2019
Name ID: KRA KPI Weight Target Ach. Unit

Assuring finished goods transfer as per approved weight range 10 100 98


Percent
Md. Jahirul Islam

20161102 Assuring process loss as per approved level during finishing 10 100 90.94 Percent
Quality Assurance Assuring process loss as per approved level during production 10 11.5 10.09 Percent
Check chemical and RM quality 5 100 98 Percent
Ensure quality assurance of machine production 40 98 96.33 Percent
Keeping Customer complain maximum 100 MT of total Sales 10 1 Percent
Coordination and Administration Coordinate and cooperate with various department 5 100 98 Percent
Reporting Ensure all reporting timely 10 100 95 Percent
Total 100 611
QUALITY ASSURANCE DEPARTMENT
KRA-KPI Of July, 2019
Name ID: KRA KPI Weight Target Ach. Unit

Assuring finished goods transfer as per approved weight range 10 100 98


Percent
Md. Jahirul Islam

20161102 Assuring process loss as per approved level during finishing 10 100 91.57 Percent
Quality Assurance Assuring process loss as per approved level during production 10 11.5 9.86 Percent
Check chemical and RM quality 5 100 98 Percent
Ensure quality assurance of machine production 40 98 90 Percent
Keeping Customer complain maximum 100 MT of total Sales 10 1 Percent
Coordination and Administration Coordinate and cooperate with various department 5 100 98 Percent
Reporting Ensure all reporting timely 10 100 95 Percent
Total 100 611

Potrebbero piacerti anche