LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: 26 September 2018 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04
2 BOUNDARY WALL
Total Boundary Wall Length M 1,128.35
1 Excavation M3 680.30 486.00 615.00 666.00 666.00 97.90%
2 Gravel Material M3 184.45 143.65 175.00 180.00 180.00 97.59%
3 Common Filling M3 418.26 150.00 300.00 350.00 406.00 97.07%
4 PCC Footing M3 185.42 81.01 152.78 160.00 180.00 97.08%
5 RCC in Foundation, Class- A1 M3 99.76 60.66 98.53 99.76 99.76 100.00%
6 RCC in Super Structure, Class- A1 M3 292.32 92.00 149.23 167.23 280.00 95.79%
7 Reinforcement Ton 51.41 23.03 43.37 46.36 50.00 97.26%
8 Brick Work M3 594.89 43.00 470.00 485.00 579.00 97.33%
Page 1 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: 26 September 2018 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04
3 WORKSHOP
Total Covered Area M2 4,369.15
Page 2 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: 26 September 2018 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04
5 OFFICE BUILDING
Total Covered Area M2 5,210.43
Page 3 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: 26 September 2018 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04
6 DRAIN NO. 07
Total Length M 625.00
4 RCC of Drain Bed, Walls & Slab M3 632.00 316.00 380.00 60.13%
5 Reinforcement Ton 60.77 36.00 37.28 61.35%
6 Water Stopper M 1,300.00 90.00 1,052.68 80.98%
7 Rest Area's (Male & Female)
Total Covered Area M2 1,230.00
Contractor: Consultant:
ANHUI-CALSON JV MM PAKISTAN.
Page 4 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: January 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04
TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Dec Executed In
2018 Jan 2019 Total Executed
2 BOUNDARY WALL
Total Boundary Wall Length M 1,128.35
1 Excavation M3 680.30 666 - 680.30 100.00%
2 Gravel Material M3 184.45 180 - 184.45 100.00%
3 Common Filling M3 418.26 414 - 418.26 100.00%
4 PCC Footing M3 185.42 182 - 185.42 100.00%
5 RCC in Foundation, Class- A1 M3 99.76 99.76 - 99.76 100.00%
6 RCC in Super Structure, Class- A1 M3 292.32 285 - 292.3155 100.00%
7 Reinforcement Ton 51.41 50.5 - 51.41 100.00%
8 Brick Work M3 594.89 580.4 1.89 593.00 99.68%
Page 5 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: January 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04
TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Dec Executed In
2018 Jan 2019 Total Executed
9 Pointing M2 2,764.77 2690.4 64.77 2,700.00 97.66%
10 Plastering M2 2,764.77 2552.42 64.77 2,700.00 97.66%
3 WORKSHOP
Total Covered Area M2 4,369.15
Page 6 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: January 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04
TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Dec Executed In
2018 Jan 2019 Total Executed
5 OFFICE BUILDING
Total Covered Area M2 5,210.43
Page 7 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: January 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04
TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Dec Executed In
2018 Jan 2019 Total Executed
6 DRAIN NO. 07
Total Length M 625.00
RCC of bed, Walls & Slab CM 1943.17 1386 32.00 1,418.00 72.97%
PVC Class D 150mm Dia Ducting RM 2555.01 490 560.00 1,050.00 41.10%
PVC Class D 100mm Dia Ducting RM 4304.84 392 588.00 980.00 22.77%
Page 8 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: January 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04
TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Dec Executed In
2018 Jan 2019 Total Executed
2 Gravel Material M3 319.14 100.00%
Contractor: Consultant:
ANHUI-CALSON JV MM PAKISTAN.
Page 9 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: Feb 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04
TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Dec Executed In Executed In Executed In
2018 Jan 2019 Feb 2019 March 2019 Total Executed
Page 10 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: Feb 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04
TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Dec Executed In Executed In Executed In
2018 Jan 2019 Feb 2019 March 2019 Total Executed
9 Pointing M2 4,651.48 2,700.00 - 64.77 2,764.77 59.44%
10 Plastering M2 4,651.48 2,700.00 - 64.77 2,764.77 59.44%
3 WORKSHOP
Total Covered Area M2 4,369.15
6 RCC in Super Structure M3 1,837.55 1,125.22 536.00 86.09 28.70 1,747.31 95.09%
7 Reinforcement Ton 682.11 439.00 156.00 11.25 3.75 606.25 88.88%
8 Bitumen paint (Coverage 7 Kg / 10 Sqm) M2 3,402.10 3,402.00 - - - 3,402.00 100.00%
9 Sand Filling M3 3,796.13 3,616.00 180.00 - - 3,796.00 100.00%
10 Brick masonary Ratio 1:4 (225mm thick) M3 500.00 - 173.00 240.00 80.00 413.00 82.60%
10 Brick masonary Ratio 1:4 (112mm thick) M2 189.00 - 148.58 40.95 148.58 78.61%
Cement Plaster M2 5,580.00 2,790.00 2,511.00 2,790.00 50.00%
Page 11 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: Feb 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04
TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Dec Executed In Executed In Executed In
2018 Jan 2019 Feb 2019 March 2019 Total Executed
5 OFFICE BUILDING
Total Covered Area
6 RCC in Super Structure M3 1,726.13 164.00 372.00 340.89 227.26 876.89 50.80%
8 RCC in Super Structure Auditorium & Shear M3 143.50 28.20 18.80 28.20 19.65%
walls
9 Reinforcement Ton 1,000.00 314.00 8.00 134.40 89.60 456.40 45.64%
10 Brick masonary Ratio 1:4 (225mm thick) M3 1,785.00 294.60 196.40 294.60 16.50%
11 Brick masonary Ratio 1:4 (112mm thick) M2 478.00 74.40 49.60 74.40 15.56%
Page 12 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: Feb 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04
TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Dec Executed In Executed In Executed In
2018 Jan 2019 Feb 2019 March 2019 Total Executed
12 Bitumen paint (Coverage 7 Kg / 10 Sqm) M2 4,642.00 2,993.00 1,649.00 - - 4,642.00 100.00%
Page 13 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: Feb 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04
TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Dec Executed In Executed In Executed In
2018 Jan 2019 Feb 2019 March 2019 Total Executed
6 DRAIN NO. 07
Total Length
4 RCC of Drain Bed, Walls & Slab M3 698.00 689.45 - - - 689.45 98.78%
5 Reinforcement Ton 69.00 68.67 - - - 68.67 99.52%
6 Water Stopper M 1,300.00 1,274.00 6.00 - - 1,280.00 98.46%
7 Rest Area's (Male & Female)
Total Covered Area M2
Page 14 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: Feb 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04
TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Dec Executed In Executed In Executed In
2018 Jan 2019 Feb 2019 March 2019 Total Executed
PCC Footing CM 272.43 234.00 - - - 234 85.89%
RCC of bed, Walls & Slab CM 1,943.17 1,386.00 32.00 - - 1,418 72.97%
PVC Class D 150mm Dia Ducting RM 2,555.01 490.00 560.00 766.50 720.00 1,817 71.10%
PVC Class D 100mm Dia Ducting RM 4,304.84 392.00 588.00 1,291.45 2,000.00 2,271 52.77%
Manhole Covers Each 35.00 - - - - - 0.00%
7 Inspection Area
1 Excavation CM 56.00 56.00 - - - 56.00 100.00%
4 RCC of Pit, Bed & Wall CM 73.00 23.00 50.00 - - 73.00 100.00%
2 Pipe Casing 8'' Internal Dia (UPVC Class 'D' RFT 400.00 400.00 - 400.00 100.00%
Page 15 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: Feb 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04
TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Dec Executed In Executed In Executed In
2018 Jan 2019 Feb 2019 March 2019 Total Executed
3 Lean Concrete CM 34.00 17.33 11.00 5.50 - 33.83 99.50%
4 Reinforcement of Bed, Wall & Column TON 27.00 7.07 15.00 4.20 - 26.27 97.30%
5 RCC Bed, Wall & Column CM 288.00 32.52 153.00 98.00 - 283.52 98.44%
7 UGWT & OHWT
1 Excavation CM 558.69 446.00 - 446.00 79.83%
5 Steel UGWT & OHWT Ton 85.00 55.00 12.75 13.60 67.75 79.71%
Contractor: Consultant:
ANHUI-CALSON JV MM PAKISTAN.
Page 16 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: March 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04
TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Dec Executed In Executed In Executed In
2018 Jan 2019 Feb 2019 March 2019 Total Executed
Page 17 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: March 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04
TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Dec Executed In Executed In Executed In
2018 Jan 2019 Feb 2019 March 2019 Total Executed
9 Pointing M2 4,651.48 2,700.00 - 64.77 35.00 2,799.77 60.19%
10 Plastering M2 4,651.48 2,700.00 - 64.77 35.00 2,799.77 60.19%
3 WORKSHOP
Total Covered Area M2 4,369.15
6 RCC in Super Structure M3 1,837.55 1,125.22 536.00 86.09 28.70 1,776.00 96.65%
7 Reinforcement Ton 682.11 439.00 156.00 11.25 3.75 610.00 89.43%
8 Bitumen paint (Coverage 7 Kg / 10 Sqm) M2 3,402.10 3,402.00 - - - 3,402.00 100.00%
9 Sand Filling M3 3,796.13 3,616.00 180.00 - - 3,796.00 100.00%
10 Brick masonary Ratio 1:4 (225mm thick) M3 500.00 - 173.00 240.00 80.00 493.00 98.60%
10 Brick masonary Ratio 1:4 (112mm thick) M2 189.00 - 148.58 40.95 189.53 100.28%
Cement Plaster M2 5,580.00 2,790.00 2,511.00 5,301.00 95.00%
Page 18 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: March 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04
TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Dec Executed In Executed In Executed In
2018 Jan 2019 Feb 2019 March 2019 Total Executed
5 OFFICE BUILDING
Total Covered Area
6 RCC in Super Structure M3 1,726.13 164.00 372.00 340.89 227.26 1,104.15 63.97%
8 RCC in Super Structure Auditorium & Shear M3 143.50 28.20 18.80 47.00 32.75%
walls
9 Reinforcement Ton 1,000.00 314.00 8.00 134.40 89.60 546.00 54.60%
10 Brick masonary Ratio 1:4 (225mm thick) M3 1,785.00 294.60 196.40 491.00 27.51%
11 Brick masonary Ratio 1:4 (112mm thick) M2 478.00 74.40 49.60 124.00 25.94%
Page 19 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: March 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04
TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Dec Executed In Executed In Executed In
2018 Jan 2019 Feb 2019 March 2019 Total Executed
12 Bitumen paint (Coverage 7 Kg / 10 Sqm) M2 4,642.00 2,993.00 1,649.00 - - 4,642.00 100.00%
Page 20 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: March 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04
TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Dec Executed In Executed In Executed In
2018 Jan 2019 Feb 2019 March 2019 Total Executed
6 DRAIN NO. 07
Total Length
4 RCC of Drain Bed, Walls & Slab M3 698.00 689.45 - - - 689.45 98.78%
5 Reinforcement Ton 69.00 68.67 - - - 68.67 99.52%
6 Water Stopper M 1,300.00 1,274.00 6.00 - - 1,280.00 98.46%
7 Rest Area's (Male & Female)
Total Covered Area M2
Page 21 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: March 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04
TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Dec Executed In Executed In Executed In
2018 Jan 2019 Feb 2019 March 2019 Total Executed
Excavation CM 5,550.43 3,150.00 2,350.00 - - 5,500.00 99.09%
RCC of bed, Walls & Slab CM 1,943.17 1,386.00 32.00 - - 1,418.00 72.97%
PVC Class D 150mm Dia Ducting RM 2,555.01 490.00 560.00 766.50 720.00 2,536.50 99.28%
PVC Class D 100mm Dia Ducting RM 4,304.84 392.00 588.00 1,291.45 2,000.00 4,271.45 99.22%
Manhole Covers Each 35.00 - - - - - 0.00%
7 Inspection Area
1 Excavation CM 56.00 56.00 - - - 56.00 100.00%
4 RCC of Pit, Bed & Wall CM 73.00 23.00 50.00 - - 73.00 100.00%
2 Pipe Casing 8'' Internal Dia (UPVC Class 'D' RFT 400.00 400.00 - 400.00 100.00%
Page 22 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: March 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04
TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Dec Executed In Executed In Executed In
2018 Jan 2019 Feb 2019 March 2019 Total Executed
1 Excavation CM 1,954.00 1,679.00 186.00 89.00 - 1,954.00 100.00%
4 Reinforcement of Bed, Wall & Column TON 27.00 7.07 15.00 4.20 - 26.27 97.30%
5 RCC Bed, Wall & Column CM 288.00 32.52 153.00 98.00 - 283.52 98.44%
7 UGWT & OHWT
1 Excavation CM 558.69 446.00 - 446.00 79.83%
5 Steel UGWT & OHWT Ton 85.00 55.00 12.75 13.60 81.35 95.71%
Contractor: Consultant:
ANHUI-CALSON JV MM PAKISTAN.
Page 23 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: April 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04
TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Executed In
March 2019 April 2019 Total Executed
Page 24 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: April 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04
TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Executed In
March 2019 April 2019 Total Executed
9 Pointing M2 4,651.48 2,799.77 558.18 3,357.95 72.19%
10 Plastering M2 4,651.48 2,799.77 558.18 3,357.95 72.19%
3 WORKSHOP
Total Covered Area M2 4,369.15
Page 25 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: April 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04
TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Executed In
March 2019 April 2019 Total Executed
5 OFFICE BUILDING
Total Covered Area
8 RCC in Super Structure Auditorium & Shear M3 143.50 47.00 - 47.00 32.75%
walls
9 Reinforcement Ton 1,000.00 546.00 - 546.00 54.60%
10 Brick masonary Ratio 1:4 (225mm thick) M3 1,785.00 350.00 141.94 491.94 27.56%
Page 26 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: April 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04
TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Executed In
March 2019 April 2019 Total Executed
11 Brick masonary Ratio 1:4 (112mm thick) M2 478.00 100.00 24.00 124.00 25.94%
12 Bitumen paint (Coverage 7 Kg / 10 Sqm) M2 4,642.00 4,642.00 4,642.00 100.00%
Page 27 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: April 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04
TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Executed In
March 2019 April 2019 Total Executed
Cement Plaster M2 15,000.00 3,000.00 2,000.00 5,000.00 33.33%
6 DRAIN NO. 07
Total Length
4 RCC of Drain Bed, Walls & Slab M3 698.00 689.45 689.45 98.78%
5 Reinforcement Ton 69.00 68.67 68.67 99.52%
6 Water Stopper M 1,300.00 1,280.00 1,280.00 98.46%
7 Rest Area's (Male & Female)
Total Covered Area M2
TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Executed In
March 2019 April 2019 Total Executed
Aluminium door /window M2 216.00 70.00 60.00 130.00 60.19%
Marble on Stairs complete in all respects M² 52.00 - - - 0.00%
6 Cable Trench
Total Length M
RCC of bed, Walls & Slab CM 1,943.17 1,418.00 150.00 1,568.00 80.69%
Page 29 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: April 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04
TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Executed In
March 2019 April 2019 Total Executed
1 Boring RFT 400.00 400.00 400.00 100.00%
2 Pipe Casing 8'' Internal Dia (UPVC Class 'D' RFT 400.00 400.00 400.00 100.00%
4 Reinforcement of Bed, Wall & Column TON 27.00 26.27 26.27 97.30%
5 Steel UGWT & OHWT Ton 85.00 81.35 2.00 83.35 98.06%
7 Internal Roads & BS 00
Internal Roads
Excavation of unsuitable Material CM 11,525.90 11,525.90 - 11,525.90 100.00%
Granular Filling (River Bed Material) M3 8,537.70 6,969 500.00 7,469.17 87.48%
Page 30 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
DAILY PROGRESS REPORT
Date: April 2019 Weather: Sunny 31◦ᴄ ҉ DPR Ref No: 04
TOTAL Executed by
Sr. No DESCRIPTION UNIT QTY % Achieved
the end of Executed In
March 2019 April 2019 Total Executed
Granular Sub-Base CM 4,268.85 2,512 900.00 3,411.77 79.92%
Dowels with PVC Pipe Each 3,374.68 2,400.00 200.00 2,600.00 77.04%
Steel Welded Mesh in Rigid Pavement M2 12,933.10 10,098.16 90.00 10,188.16 78.78%
Contractor: Consultant:
ANHUI-CALSON JV MM PAKISTAN.
Page 31 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CO
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONT
%
U
p
1 BUS PARKING AREA t
o
1 Excavation M3 42,054.91###
M
2 Gravel Material M3 a
31,386.73###
y
3 Sub Base M3 15,611.22###
4 Agreegate Base M3 15,611.22###
5 Lean Concrete M3 5,206.34###
6 Rigid Pavement M3 15,619.02###
7 Saw cut of Contraction Joint RM 10,406.00###
8 Saw cut of Construction Joint RM 14,233.00###
9 Filling of Contraction Joint RM 10,406.00###
10 Filling of Construction Joint RM 14,233.00###
11 Expansion Joint Treatment RM 1,180.00###
Page 32 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CO
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONT
%
U
8 Brick Work M3 p
1,000.85###
t
9 Pointing M2 o
4,651.48###
10 Plastering M2 M
4,651.48###
a
11 Barbed Wire Fence and Razor Wire M y
1,800.00###
3 WORKSHOP
Total Covered Area
1 Excavation M3 4,814.00###
Page 33 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CO
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONT
%
U
19 SS Railing M2 p
85.96###
t
o
M
a
y
Page 34 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CO
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONT
%
U
20 Baskit Ball Courtyard Fence RM p
154.00###
t
21 Weather Shield M2 1,278.00###
o
22 Emulsion Paint M2 10,514.00###
M
4 PARK & RIDE a
y
1 Excavation M3 16,756.14###
2 Anti Termite M2 3,716.87###
3 Granular Material M3 2,538.24###
4 Lean Concrete M3 320.06###
5 Back Filling M3 2,700.00###
6 Reinforcement Concrete In Foundation M3 3,500.00###
7 Reinforcement Concrete In Super Structure M3 7,596.26###
8 Reinforcement Steel Tonne 2,200.00###
9 Bitumen paint (Coverage 7 Kg / 10 Sqm) M2 1,651.00###
10 Brick Masonary M3 1,600.00###
5 OFFICE BUILDING
Total Covered Area
1 Excavation M3 7,495.43###
U
RCC in Super Structure Auditorium & Shear p
8 walls M3 143.50###
t
o
9 Reinforcement (Revised) Ton 700.00###
M
a
y
Page 36 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CO
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONT
%
U
p
10 Brick masonary Ratio 1:4 (225mm thick) M3 1,785.00###
t
o
11 Brick masonary Ratio 1:4 (112mm thick) M2 478.00###
M
12 Bitumen paint (Coverage 7 Kg / 10 Sqm) M2 4,642.00###
a
y
13 Cement Plaster M2 24,000.00###
14 Aluminium Doors Windows M2 850.00###
Granitto tile floor on Stairs M2 700.00###
1 Excavation M3 2,424.00###
Page 37 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CO
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONT
%
U
p
Total Covered Area t
o
1 Excavation M3 1,886.00###
M
2 Gravel Material M3 a
377.00###
y
3 PCC Footing M3 144.00###
6 Cable Trench
Total Length
1 Excavation CM 5,550.43###
U
p
3 PCC Footing CM 272.43###
t
o
4 RCC of bed, Walls & Slab CM 1,943.17###
M
5 Reinforcement Ton a
540.00###
y
6 Sand Filling CM 2,200.00###
2 Pipe Casing 8'' Internal Dia (UPVC Class 'D' RFT 400.00###
Page 39 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CO
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONT
%
U
p
1 Excavation CM 1,954.00###
t
o
2 Gravel Material CM 256.00###
M
3 Lean Concrete CM a
35.26###
y
4 Reinforcement of Bed, Wall & Column TON 33.29###
Page 40 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CO
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONT
%
U
p
Dowels with PVC Pipe Each 3,374.68###
t
o
Steel Welded Mesh in Rigid Pavement M2 11,242.00###
M
TUFF TILES M2 a
2,400.00###
y
Kerb stone (18''x6'') M 4,184.28###
Bus Station 00 & Rest/ Toilet Block
BS STRUCTURAL STEEL WORKS SM 2,500.00###
Page 41 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
Total Executed Upto Executed in April Total Executed Upto % Achieved Upto Feb
March 2020 2020 April 2020 2020
Page 42 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
Total Executed Upto Executed in April Total Executed Upto % Achieved Upto Feb
March 2020 2020 April 2020 2020
Page 43 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
Total Executed Upto Executed in April Total Executed Upto % Achieved Upto Feb
March 2020 2020 April 2020 2020
Page 44 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
Total Executed Upto Executed in April Total Executed Upto % Achieved Upto Feb
March 2020 2020 April 2020 2020
Total Executed Upto Executed in April Total Executed Upto % Achieved Upto Feb
March 2020 2020 April 2020 2020
Page 46 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
Total Executed Upto Executed in April Total Executed Upto % Achieved Upto Feb
March 2020 2020 April 2020 2020
Page 47 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
Total Executed Upto Executed in April Total Executed Upto % Achieved Upto Feb
March 2020 2020 April 2020 2020
Total Executed Upto Executed in April Total Executed Upto % Achieved Upto Feb
March 2020 2020 April 2020 2020
Page 49 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
Total Executed Upto Executed in April Total Executed Upto % Achieved Upto Feb
March 2020 2020 April 2020 2020
Page 50 of 51
CONSTRUCTION OF BUILDING INFRASTRUCTURE UNDER PESHWAR SUSTAIBALE BUS DEPOT RAPID TRANSIT CORRIDOR PROJECT
LOT 2: CHAMKANI BUS DEPOT, PARK & RIDE, TRANS PESHWAR OFFICE AND BRT CONTROL CENTER
Total Executed Upto Executed in April Total Executed Upto % Achieved Upto Feb
March 2020 2020 April 2020 2020
Page 51 of 51