Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
OF TECHNOLOGY
CIVIL ENGINEERING
Nitrogen content
It may occur in one or more of the following forms:
a) Free ammonia
b) Organic nitrogen
c) Nitrites
d) Nitrates
The presence of nitrogen in sewage indicates the presence
of organic matter.
Presence of fats, oils & greases
These are derived in sewage from the discharges of animals,
kitchens of hotels, industries.
In order to determine the amount of fats, greases etc, a
sample of sewage is first evaporated.
The residual solids left are then mixed with ether and the
solution is then evaporated, leaving behind the fat, grease
as a residue.
Biological oxygen demand (BOD)
It is defined as the amount of oxygen required by the aerobic
bacteria to fully decompose the organic matter.
The instrument directly records BOD reading at every 24
hour. After that the bottles are preserved in the incubators
for days as per need of study.
TESTED PARAMETERS OF
SEWAGE
S.NO. PARAMETERS CALCULATED PERMISSIBLE
VALUE LIMITS
1 pH 7.125 7-8.5
Preliminary Treatment:-
Consists simply of separating of floating materials and also the
heavy settleable inorganic solids. It also helps in removing oils &
greases etc from the sewage.
This treatment reduces about 15-30% BOD of the wastewater.
The processes involved in preliminary treatment are-
SCREENING
SECONDARY TREATMENT
SCREENING -
• Shape of bars = M.S. Bars
• Size = 10mm x 50mm with clear spacing of 30mm
•Velocity of flow = 0.8m/sec
•No. of bars required = 33
•Size of Screen = 1.32m x 0.8m
• The screening produced are disposed of either by burning, or by burial
(Composting)
GRIT CHAMBER -
• Critical horizontal velocity (Vc) = 0.228m/s
•Flow velocity (V) = 0.2m/s (V< Vc)
•Detention time = 60sec
•Size of Grit Chamber = 12m x 3m x 1.5m
• The grit deposited at bottom can be either incinerated with sludge or
disposed in low lying areas.
SKIMMING TANK –
• Detention time = 4 min
• Compressed air required = 1000 m3 per million liter
• Size of tank = 27m x 27m
• The oil & greasy material removed from tanks can be disposed either
by burning or burial.
• It is generally too polluted for any economic use.
PRIMARY SEDIMENTATION TANK –
• In this design, continuous flow tank is to be provided.
• Velocity of flow through the tank = 0.3m/min
• Size of rectangular sedimentation tank = 36m x13m x6m.
• Since the tank is provided with mechanical cleaning arrangement, no
space at bottom is required for sludge zone.
AERATION TANK –
• Providing conventional aeration process.
• No. of aeration tanks = 2
• BOD entering STP = 189mg/l
• BOD left at effluent = 25mg/l
• Minimum efficiency required in activated plant = 86.77% (85-92%)
• F/M Ratio = 0.3
• MLSS = 2500mg/l
• Sludge retention time = 5days
• Aeration tank dimension = 37m x 20m x 5.5m
AERATOR SIZE –
• Oxygen requirement = 1kg/kg BOD applied
• Provide 10 Generators of 30 HP, with 1 generator at standby.
SECONDARY CLARIFIER
• Recirculated flow(assuming 50% of total flow) = 15000m3/day.
• Surface loading rate of flow = 30m3/m2/hr.
• Solid loading rate = 112.5kg/day/m2.
• Size of secondary clarifier = 35m diameter with overall depth of 5.5m
SLUDGE DIGESTION TANK –
• Mass of suspended solids in 30MLD wastewater = 12840kg/day
• Volume of digested sludge at 75% moisture content = 32.89 m3/day
• Digestion period = 30 days
• Provide a cylindrical sludge digestion tank 6m deep and of 22m diameter.
ESTIMATION OF GAS PRODUCED FROM DIGESTER TANK –
• Total quantity of gas produced = 3154.79 cu. m.
• Assuming that gas produced contains 65% methane and 30% CO2.
Methane produced = 2050.6 cu. m.
CO2 produced = 1104.18 cu. m.
• Total fuel value = 73.82 MKJ.
• Assuming boiler efficiency is 80%, heat produced by boiler =59.06 MkJ
which is equal to 14.335 million kilo Calories.
• The gas collected may be utilized for operating engines, and for heating
sludge to promote quick digestion.
LAYOUT OF SEWAGE TREATMENT PLANT
SCOPE FOR FUTURE
As per future perspective of this project, the characteristics
of different units designed in this project can be compared
with alternate treatments units and their treatment
efficiencies can be calculated for designing of STP.
For example – We choose activated sludge process in
secondary treatment, but any other treatment processes like
trickling filters, aerated lagoons, oxidation ponds, RBCs etc
can also be taken as secondary treatment unit and is
designed. The design values & other parameters related to it
are compared and the graphs are plotted accordingly. The
best alternative should be selected as the final one.
REFERENCES
Manual on water supply and treatment, C.P.H.E.E.O., Ministry
of Urban Development; Government of India, New Delhi.
Manual on Sewerage and Sewage Treatment,
C.P.H.E.E.O.,Ministry of Urban Development; Government of
India,New Delhi.
Jayshree Dhote, Sangita Ingole (2012); Review on Wastewater
Treatment Technologies Published in International Journal of
Engineering Research and Technology. pp. 2-5.
IS: 3025 (PART 10) – 1984, Methods of sampling and test for
water and wastewater.
IS: 4764 – 1973, Permissible limits for sewage effluents in
waste water.
A.K. Jain; Environmental Engineering, Khanna Publishing
House.
S.K. Garg; Water supply and Sewage Disposal Engineering Vol
1&2, Khanna Publishing House.