Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
COORDINATION STUDY
PhD
in
Electical and Electronics Engineering
By
RAVIPUDI SUDHIR
MAY 2020
Contents
List Of Figures ii
1 INTRODUCTION 1
INTRODUCTION
The study aims at verifying the adequacy of the Sub-Station insulation to survive the
worst possible Over Voltages taking into consideration acceptable failure probability. Ma-
jor Over Voltages originating on Power Systems can be classified as temporary, slow, fast,
very fast front Over Voltages, each having its corresponding comparison criteria as appli-
cable.
1. Temporary Over Voltage (TOV): This can originate from faults, switching oper-
ations such as load rejection, resonance conditions, non-linearity (Ferro-resonance),
or by a combination of these. TOV should not exceed the fundamental frequency
withstand voltage for any equipment.
2. Slow-front Overvoltages (SOV): These can originate from the switching oper-
ations of the overhead lines. Switching includes energization and re-energization of
the overhead lines. 98 % out of the statistical switching for any switching operation
should not exceed 80% of the BSL (Switching Impulse Withstand limit).
3. Fast-Front Overvoltages (FFO): These can originate from the lightning strike
on the overhead transmission lines. This includes Direct stoke and Back flashover.
For both direct stroke and back flashover events, the maximum determined over
voltage at any equipment should not exceed 80% of the BIL of the equipment.
4. Very Fast Front Overvoltages (VFFO):These can originate from fault /switch-
ing operation of the dis-connector or circuit breaker in the Gas Insulated Switchgear
(GIS).
The simulation is a trial to best fit the measured results, where equipment modeling can be
different from one study to another study. Constructing proper model for the substation
under study is the key behind obtaining logic results. The resulting waves are compared
– roughly, the wave peak value – with the % of BIL /BSL as mentioned above.
According to IEC 60071, The system voltages exiting in a power system can
be summarized as follows: Generally, the following points shall be useful for under-
standing and performing the insulation coordination studies:-
1. The general criterion for the insulation study concept ever is: the maximum stress
equal to minimum strength.
2. The separation distance of the surge arrestors and protected equipment shall be as
short as possible.
3. Tower footing resistance shall be as lower as possible in order to dissipate the light-
ning surges.
4. Shielding failure rate / probability is dependent on lightning flashes per year as well
as the tower shielding angle.
5. Usually one surge arrestor is sufficient to protect the substation (mostly the outdoor
SA. However, in some cases with longer separation distance to critical equipment
usually Power Transformer another surge arrestor is required in front of equipment
to be protected.
8. The lightning impulse withstand is dependent on the wave tail time (t2), while the
switching impulse withstand is dependent on the wave front time (t1), correction
factor may be applied.
9. Surge Arrestor parameters for proper insulation study should be taken into consid-
eration where applicable as follows:
10. Back-flashover is more severe than direct flash, as it injects large amount of cur-
rent(especially with higher tower footing resistance) into the station surge impedance,
resulting in higher voltage values/energy dissipation through Surge Arresters.
11. In terms of probability and risk estimation, starting with the shield failure proba-
bility of the OHTL (for direct strokes) which is dependent of its construction and
the lightning current distribution recorded in the certain geographic region where
the Transmission Line exists ( only the 5-10 towers near to the station under study
as for longer distances, the line corona effect will deform/attenuate the steepness of
the travelling surge).
12. Usually the lightning current considered for direct flash is: 20 kA, and 200 kA
for back-flash. Double concave wave shall be used for more realistic results (CI-
GRE/IEC).
13. While carrying out the system study, knowledge about the system operation shall
be taken care(switching sequence, auto-reclosure scheme, application of single-phase
14. VFTO is a maximum when the switch under operation (CB or DS) is biased with
an opposite polarity trapped/residual charge prior to its operation i.e. phase peak
voltage represented as -1 p.u. shall be applied behind the switching device and
removed just before the commencement of switch operation (the charge shall be
removed from the circuit in order to enable the natural, not forced, oscillation of
system due to switch motion/striking).
15. During operation of the switch, depending on how fast is the separation / connection,
the trapped charge is consumed i.e. the faster the switch, the greater the mean value
the trapped charge voltage can reach.
16. Switching studies (slow front) aren’t applicable for system voltages ¡ 300 kV, how-
ever, the same is required for some cases like reactors, capacitors or extra-long lines.
17. The switching overvoltage is dependent on line configuration as well as length, the
longer the line, the higher the switching voltages on its remote end; this is due to
the effect of line capacitances / Ferranti effect.
18. Statistical switching shall be carried out with a repeated pattern to cover complete
power frequency cycle (1/60 = 16.6 ms), 100-200 times results shall be listed and
the maximum parameter for 98% level shall be less than 80% BSL.
1. Determining the over voltage stresses from the system. Over voltages have to be
determined by system simulation using EMTDC/PSCAD software. Therefore, a
close to the actual model of the system has to be build as explained below.
2. Knowing the strength of the insulation of specific equipment in the substation. The
insulation criteria have to be fulfilled against all possible over voltages.
reactors etc. A system equivalent reflects the rest of the system has to be modeled as
well. Sensitivity for some uncertain parameters has to be adopted.
2. Tower and take-off structure: Proper model has to be considered for the towers
and take-off structures. Footing resistance 20 ohms will be considered for the study.
3. System Equivalent: One bus away from the substation of concern have to be
modeled and system equivalent for the rest of the system is to be collected.
All the network elements required for over voltage analysis purposes shall be designed/modeled
in detail and the design/modeling criteria shall be supported by well-recognized literature
and references.
• Phase to Earth Faults: Single line to Ground, Double line to Ground, 3 Phase to
Ground.
• Load Rejection
• Ferranti Effect.
Combination of temporary over voltage origins such as earth fault with load rejection
• Load Rejection
Switching (Slow-front) over voltages play a role in determining the energy duty of surge
arresters and in the selection of required withstand voltages of equipment as well as the
air gap insulation for transmission line towers. Statistical switching approach for different
configuration has to be simulated where the actual closing time is statically chosen using a
random-flat distribution within a one-cycle window. The pole span of the breaker is chosen
to be 5 ms with 2.5 ms standard deviation. The switching over voltages is determined for
100-200 simulation.
The effects of such over voltages are of great concern when the transmission voltage
is greater than 300kV. However, below 300kV, some causes of these over voltages, that
require simulation, are:
• Resonance effects when switching transformer feeders, or cables and overhead lines.
• Ferro resonance encountered on transformer feeder double circuits, when one circuit
is switched out but the other parallel feeder remains energized
• Line Energization may cause switching surges especially at the remote end of the
line that is being energized.
to select their required withstand level in relation to protective device configuration and
tower earthing, and to evaluate line and station performance.
The two types of lightning have to be considered are direct stroke to the phase con-
ductors and the back flashover. The magnitude of lightning current for both the cases
shall be estimated using proper techniques and shall be explained. Consider a varying
tower footing resistance from 0 to 20 ohms regardless of measured value.
• Temporary over voltages (TOV): should not exceed the fundamental frequency with-
stand voltage for any equipment.
• Switching over voltages: 98% out of the statistical switching for any switching
operation should not exceed 80% of the BSL ( switching Impulse Withstand limit)
• Lightning over voltages: for both direct stroke and back flashover events, the max-
imum determined over voltage at any equipment should not exceed 80% of the BIL
of that equipment.
• Very Fast Transient over voltages (VFTO): Internal transients and external tran-
sients (TEV) and its mitigation techniques.
In all cases, the surge arrestor measured energy absorption should be with the surge
arrestor energy capability/class.
Ferro resonance is a non-linear resonance phenomena occurring in a low loss electric cir-
cuit containing a non-linear inductance, capacitor and voltage sources. Power network is
example of such an electrical circuits, where non-linear inductances are due to magnetiz-
ing impedances of power transformers, measurement inductive voltage transformers and
capacitances are due to cables, EHV lines, CVTs, Series capacitors etc. Hence, certain
switching actions, operating conditions and a few system configurations may cause occur-
rence of Ferro resonances. Some examples of switching actions are transformer-switching,
capacitor switching etc. Some of the configurations/conditions that may cause Ferro
resonance are;
1. Transformer supplied through a long transmission line or cable with low short-
circuit power
2. Opening of one or two phases of a cable feeding the primary side of a lightly loaded
transformer
3. Transformer energized through the grading capacitance of one or more open circuit
breakers
10. Cable damage and manual switching during construction of underground cable sys-
tems,
A detailed study is required to explore all the sources (not restricted to above conditions)
of Ferro-resonance in a power system and to be explained in the report.
6. Damage of electrical equipment (capacitor banks, VT, CVT etc.) due to thermal
effect or insulation breakdown. A characteristic symptom of VT destruction by
Ferro resonance is a destroyed primary winding and an intact secondary winding.
Owing to the stochastic manner of Ferro resonance, detailed digital modeling of the system
and computer simulations are required for the prediction of Ferro resonance occurrence. It
is required to use frequency dependent complex model for the cable circuits incorporating
the transpositions, cross-bonding etc. for the study.
• List out the different sources of Ferro resonance in the power system and the miti-
gation methods to be adopted.
• The magnitude and the time duration of the oscillations, which exist during the
Ferro-resonance. The frequency of the oscillations shall also be provided in the
conclusion.
• Advise for the protection of EHV and HV equipments in case of over voltages and
Ferro-resonance.