Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
___________________________________________________________________
CONTENTS
1.0 SCOPE.......................................................................................................................... 3
2.0 REFERENCE................................................................................................................ 3
1.0 SCOPE
This Specification defines the criteria for the power generation and distribution systems for
QATARGAS II LNG ONSHORE PROJECT. It shall include the main generation sizing basis, the
utility control philosophy, power system analysis, and distribution equipment.
2.0 REFERENCE
The documents referred to herein are as follows:
QGX/20/00/EL/SW/NA/003 Electrical Design Criteria
QGX/24/91/EL/DP/NA/001 Power Generation and Distribution Operating Philosophy
QGX/20/91/EL/DR/SD/001 One Line Diagram for Electric System (Overall)
QGX/24/91/EL/DP/NA/003 Plant Load Shedding & Motor Auto Restart Philosophy
QGX/20/00/EL/SW/NA/011 Electrical System Studies
QGX/20/00/EL/LI/NA/001 Electrical Load List and Load Summary
QGX/29/91/EL/DB/NA/002 Distributed Control System for Electrical Power System
QGX/29/91/EL/DB/NA/003 Electrical Power Generation System Control Functional Design
Basis
QGX/20/91/EL/DR/SD/031 Relaying Diagram 66kV & 33kV (33kV Switchgear)
QGX/20/91/EL/DR/SD/032 Relaying Diagram 66kV & 33kV (33kV Switchgear for VFDG)
QGX/20/91/EL/DR/SD/033 Relaying Diagram 66kV & 11kV (Steam Turbine Generator)
QGX/20/91/EL/DR/SD/034 Relaying Diagram 66kV & 33kV (Qatargas Main Substation etc.)
QGX/20/91/EL/DR/SD/036 Relaying Diagram 33kV & 6.6kV (6.6kV Switchgear)
QGX/20/91/EL/DR/SD/037 Relaying Diagram 33kV & 11kV (Captive Transformer)
QGX/20/91/EL/DR/SD/041 Relaying Diagram 6.6kV & 415V (Circuit Breaker Feeder)
QGX/20/91/EL/DR/SD/042 Relaying Diagram 6.6kV & 415V (Fused Contactor Feeder)
3.0
4.1.3 Generated power by steam turbine generators and gas turbine generator, 11kV is stepped up to
66kV main switchboard through 11/66kV individual generator transformers. The 66kV main power
will be distributed through 66/33kV step-down transformer to 33kV switchboards for VFD drives
and balance of the plant by dual redundant 66kV underground feeders as shown on the One Line
Diagram for Electrical System (Overall) QGX/20/91/EL/DR/SD/001.
4.1.4 33kV power distributes by dual redundant underground feeders to all substations.
For utilization, the power is transformed down to 6.6kV and 415V in the following area:
1) Utilities (incl. main substation)
2) Process units
3) Off-plot facilities
Some smaller substations are supplied with power distributed at 6.6kV.
4.1.5 Operator consoles of Electrical Integrated Control System (ELICS) are installed in Electrical
Control Room in New Main Substation no. SS-2901 and existing Main Control Room to monitor
and control the electric power system. The detail of functionality including interface philosophy with
the Emerson DCS (which will control the process motors through ELICS platform) shall be referred
to ELICS specification QGX/29/91/EL/DB/NA/002.
4.2 Main Power Generation
4.2.1 Steam turbine generators and gas turbine generator are provided for supplying power to the LNG
process, utilities and off-plot facilities loads.
4.2.2 The existing QATARGAS electrical power is imported for initial start up and for black start of Trains
4 / 5.
4.2.3 Each steam turbine generator and gas turbine generator is connected to the 66kV main switchgear
through captive transformers. The captive transformers are rated to permit each generator to
deliver its maximum MVA capacity without forced cooling. The impedance rating of the captive
transformers are selected to limit generator short circuit contribution.
4.2.4 Excess power from three Frame 9 gas turbine from each of Trains 4 and 5 (six Frame 9s in all)
when driving helper motor/generators used for the C3, MR and N2 compressors of each Train. The
amount of excess power will be a function of seasonal and daily temperature.
4.2.5 Each of the two substations for each of Trains 4 and 5 (four substations in all) shall have local
power from two VSCF liquid expander generators (eight units in all).
4.3 Normal Power Distribution
4.3.1 66kV main switchgear is located in New Main Substation SS-2901 for the Trains 4 / 5 and shall be
of double bus bar design.
4.3.2 66kV electric power is distributed through 66/33kV step-down transformers and connect to 33kV
switchgear in process train substation SS-2401 & SS-2501 for VFD power supply and also connect
to 33kV switchgear in main substation SS-2901 for balance of plant power supply by dual
redundant feeders except to BOG Compressor motor’s captive transformers in LNG Storage Tank
Substation.
4.3.3 Other smaller substations such as sulfur area substation and aux. electrical power for main
substation, power for these substations are fed by 6.6kV feeders in utility area substation.
4.4 Emergency Power Supply System
4.4.1 Initial start, black start or re-start power will be imported from existing QATARGAS through
33/66kV redundant tie-line OLTC transformers.
Date : NovAug. 248, POWER GENERATION AND QGX/29/91/EL/DB/NA/001
2006
4.4.2 The connection to existing QATARGAS are also applied for emergency power supply to QGII
plant.
4.4.3 Emergency power supply flow from existing QATARGAS will be monitored and controlled by QGII
ELICS at inter-tie connection at 66kV main switchboard to limit the imported power from existing
QATARGAS within pre-determined value.
4.5 Utilization Voltages
4.5.1 Electrical system and utilization voltage are as follow;
successful start-up, control will be transferred to the generator control panel located in the
electrical control room of New Main Substation no.SS-2901 for synchronizing, monitoring and
controlling.
4.6.5 The ELICS/PMS shall contain facilities for remote monitoring of the flow of emergency power
imported from existing QATARGAS generators comparing pre-determined allowable limit.
4.6.6 Substations, including the main 66kV substation, will be unmanned. All power generation and
distribution control is from the ELICS Operator’s Workstations located the Main Control Room.
Normal operation is to maintain the main generator switchboard at 100% of nominal voltage.
4.6.7 66kV for primary power distribution are made at 66kV double bus bar design switchboard with bus-
coupler with normally close, 33kV switchgear for balance of plant as well as 6.6kV and 415 V
switchgear have secondary selective provision and are operated with bus tiebreakers normally
open.
4.7 Protective Relaying
4.7.1 To prevent injury to personnel, minimize damage to the component as well as limit to extent and
duration of service interruption whenever the equipment failure and/or human error, protective
relaying system shall be designed and provided so that such failure can be removed from the
healthy network.
4.7.2 The protective relaying system shall cover following electrical system in QG-II Plant including the
interface in-between;
5.3 Load Flow , Transient Stability Studies and Motor starting studies
5.3.1 Actual data for the project steam turbine generators and gas turbine generator will be used for load
flow and stability. Results of the studies shall be reflected into the electrical design such as adding
instantaneous relaying to insure short circuits are cleared without exceeding the system critical
switching times.
Note: While preliminary studies will have to be completed based on the data available, actual
machine data shall be used by CONTRACTOR to arrive at the simulation of the power system and
its response to transient disturbances for final analysis.
5.3.2 Starting of large motors, to demonstrate that the selected motors will operate successfully under all
conditions shall be performed utilizing worst case generator operating conditions.
5.3.3 Stability studies shall be prepared to show the effects of faults on the system, of loss of equipment
(generators, etc.) to show the stability of the system, and to calculate the parameters needed for
the load shedding logic, settings of frequency relays, etc.
5.3.4 Load flow shall be investigated in conjunction with the Transient Stability Study and Motor Starting
Study.
5.4 Load Shedding Studies
5.4.1 Load shedding is initiated in the event one or more generator trips or trip of tie-line with
QATARGAS or a system fault occurs, and the remaining load exceeds the capacity of the
remaining generators in operation.
5.4.2 The stability of the system shall be examined including a worst case scenario for load shedding.
5.4.3 Load shedding is accomplished using a function of ELICS that compares system load condition
with the turbine and VFD generator total spinning capacity. The function uses input from kW
transducers connected to the 33kV and 6.6kV switchgear through current transformers and voltage
transformers and serial data links from the control devices of steam turbine generators Frame 9
VFDs and Liquid Turbine VSCFs.
5.4.4 The scheme shall be suitable for all operating loading levels, with automatic load shedding, in
stages, of low and medium priority loads. A list of priorities is to be established for shedding load.
Load shedding shall be accomplished by tripping medium voltage breakers or contactors.
5.4.5 Hard-wired dF/dt backup relays shall be provided for load shedding. Relays shall be two (2) rate of
change of frequency with adjustable time delay that trip the outgoing 33kV circuits, in case the
system frequency was to drop below a set point and two (2) absolute frequency relays with fixed
set points.
5.5 Re-acceleration Studies
5.5.1 The medium and low voltage motors and static loads, if required for process continuity, shall be
equipped with automatic restart facilities using plug-in type automatic restart modules or
microprocessor based protection relays with similar features. As a general principle, manual restart
shall be kept to a minimum due to the small number of operating staff and the large area occupied
by the LNG Plant. Manual restart for large medium voltage motors can be initiated from the main
control building.
5.5.2 Re-acceleration studies to demonstrate the capability of the system to handle the re-acceleration
of inductive loads under all conditions. For Load shedding and restarting philosophy is described in
Specification titled “Plant Load shedding and automatic restart philosophy”
QGX/29/91/EL/DP/NA/003
5.6 Power System Protection Studies
Date : NovAug. 248, POWER GENERATION AND QGX/29/91/EL/DB/NA/001
2006
5.6.1 Power System Protection / Coordination studies shall be performed at all levels of protection /
coordination studies, this will include main power generation and distribution, and essential power
generation and distribution. It will also include distribution of UPS power, DC power and small
power.
5.6.2 Protective relay devices, solid state primarily, with definite or inverse time current characteristics
manufactured to IEC standards shall be defined with IEEE device numbers.
5.6.3 Coordination for phase and earth faults shall be verified for the following scenarios using approved
protective devices including the following:
a) Largest 415V motor or largest protective device on one 415V switchgear / MCC versus the
incoming protective devices and coordination at all levels down to final distribution panels.
b) Protective devices on a 6.6kV feeder versus the protective device on the 415V incomer
indicated in a above. Transformer protection shall be included.
c) Protective device on incomer for the 6.6kV MCC connected to the largest transformer
versus the largest 6.6kV motor and its protective device, including back-up earth fault
protection.
d) Protective devices on a 33kV feeder versus the protective device on the 6.6kV incomer
indicated in c above. Transformer protection shall be included.
e) Protective device on incomer for the 33kV distribution switchgear connected to the largest
transformer versus the largest 6.6kV motor energized by 33kV distribution switchgear via
captive transformer and its protective device, including back-up earth fault protection.
f) Protective devices on a 66kV feeder of 66kV main switchgear versus the protective device
on the 33kV incomer of 33kV distribution switchgear indicated in e above through 66/33kV
step-down transformers.
g) Protective device on a 66kV feeder versus the protective devices for the steam turbine
generator as well as gas turbine generator captive transformer and generator.
h) Protective devices on 6.6kV power recovery generators versus protective devices on
6.6kV feeders.
i) Protective devices on all UPS systems, including feeders, SCR fuses, etc and distribution
system from the UPS to final loads.
j) Protective devices on all DC systems, including battery, chargers, distribution system and
end user.
k) Protective device on 66kV feeder versus the protective devices for outgoing feeders on the
existing QATARGAS 33kV switchgear through 66/33kV inter-tie transformer.
5.6.4 Secondary ampere rating of current transformers which applied for differential protection containing
long cable runs shall be of one ampere, tripping shall be via pilot wire relaying using fiber optic
cables for long runs.
5.7 Harmonic analysis
The acceptable limits of Harmonics are in accordance with BS EN 50160 519. Consultant shall
determine if the stated harmonics levels can be exceeded but still allow operation of all site
equipment without malfunction. In particular, the following shall be identified and a level of
harmonic generation determined such that the effects described below do NOT occur.
- Excessive heating of machines
Date : NovAug. 248, POWER GENERATION AND QGX/29/91/EL/DB/NA/001
2006
6.1.1 Electronic protective relays (Multilin or equivalent) shall be utilized for all circuit breaker and
medium voltage motor protection functions. CONTRACTOR shall insure that all protective devices
are properly selected and coordinated.
6.1.2 A transient events disturbance recorder shall be provided to record the voltage and frequency on
66kV buses and the steam turbine generators for Trains 4 / 5. The recorder shall be 125 VDC
powered. The transient disturbance recorder functionality shall be covered by microprocessor
based protective relays at associated switchgear panels, and the relay shall have communication
capability with laptop PC (supplied as part of ELICS) via serial link so that the transient disturbance
analog waveform record can be transferred from the relay to the laptop PC at Substation.
6.1.3 Transformers installed in pairs as part of a secondary selective substation arrangement shall be
sized to so that either transformer may supply the total maximum continuous demand load or peak
demand that exists without exceeding self cooled rating. Maximum continuous demand shall
include all EPC design growth allowances.
6.1.4 Distribution and Power Transformers installed as individual units shall be sized so that the
maximum continuous demand load and peak demand load do not exceed the self-cooled rating.
Maximum continuous demand shall include all EPC design growth allowances.
6.1.5 Protective relaying and system protection schemes are represented on the relaying diagrams.
CONTRACTOR shall provide a fully engineered and functional system of primary and secondary
protection for all equipment and circuits.
6.1.6 The equipment and feeder numbering system shall follow Electrical Numbering Procedure
specification and be submitted for COMPANY approval.
6.1.7 The one line diagrams shall also reflect the actual physical arrangement of the switchgear when
possible. Feeder circuit breakers physically on the left side of the tiebreaker shall be drawn on the
left side of the tiebreaker. The feeder breakers shall be shown on the one line diagram in the
correct sequence. When facing the front of the switchgear and looking at the one line diagram, the
one line diagram shall correspond to the actual physical arrangement of the switchgear.
6.2 Substations
6.2.1 All switchgear, junction boxes, motor control centers, etc. except bus-duct entry shall be designed
for bottom entry as far as practical.
6.2.2 Firewalls and oil containment shall be provided for all oil-immersed transformers 500kVA and
larger as a minimum. Firewalls shall extend at least 305mm (12 inches) above and 610mm (24
inches) beyond the transformers. The walls shall be masonry block construction.
6.2.3 Selection of site and arrangement of equipment shall permit transformer removal without requiring
service interruptions to other equipment of or facilities.
6.2.4 Transformer areas shall be enclosed with sturdy industrial-type chain link fences meeting safety
requirements for height and construction.
Personnel gates shall be provided at opposite ends with padlock. Transformer area shall have
adequate facility for drainage of rain water to prevent water logging.
6.2.5 High-voltage warning signs shall be prominently displayed on all sides of the fence enclosure,
personnel gates, building exterior doors and on individual sections of equipment.
6.2.6 The substation transformer areas shall be graded and surfaced with 150mm stone or COMPANY
approved equivalent. Equipment and structures shall have foundations or pads.
6.2.7 IEC Standard conditions of 35oC average over 24 hours with 40oC as maximum design ambient
temperature should be used for the design rating of equipment located indoors in the air-
Date : NovAug. 248, POWER GENERATION AND QGX/29/91/EL/DB/NA/001
2006
conditioned buildings.
All equipment located in substations must be suitable for operation in a 50 oC high humidity
atmosphere as this will be the situation during installation and commissioning.
In addition, all major indoor power generation and distribution equipment such as 33kV, 6.6kV, and
415V switchgear and MCC's, and control equipment shall be capable of operating at 50 oC ambient
temperature with derated capacity, where applicable. Any derated capacity should be indicated.
The DC and AC UPS system, however, shall be designed to operate at ambient temperature range
of 10oC to 50oC without derating. Equipment installed outdoors shall be suitable for severe site
condition.
6.2.8 Substation buildings shall not be located within classified hazardous areas of the plant site,
however elevated concept shall be acceptable. Substations shall be oriented to reduce feeder
cable lengths as much as practicable. Attention to be paid to transformer auxiliaries.
6.2.9 The underfloor space shall be fenced on three sides with heavy gauge galvanized steel chain link
fencing. The underfloor space on the transformer side shall be closed with a masonry firewall rated
for three hours. When transformers are located on two adjacent walls of a substation, the firewalls
protecting the cables below the substation shall not impede the flow of air below the substation
trapping hazardous vapors.
6.2.10 Insulated mats shall be provided in front of all indoor equipment. They shall be designed to
minimize obstruction of the withdrawal or insertion of equipment.
6.2.11 All cables entering and leaving the building shall be through the floor via cable glands through
galvanized steel floor plates or boxes.
6.2.12 Framed safety notes, one line diagrams, layout drawings etc. shall be provided for all equipment
including DC, small power panel etc. in all substations and in the Electrical Control Room of New
Main Substation.
6.2.13 Fire extinguishers shall be provided at all doorways.
6.3 System Special Control
6.3.1 An automatic load-sharing unit shall be specified to enable active and reactive load to be shared
equally between all steam turbine generators, gas turbine generator and Frame 9 VFDs, without
the need for further adjustment by the operator. The unit shall be capable of compensating for load
changes by raising the system frequency and voltage to a set point after a load change has taken
place. It shall be able to automatically load an incoming machine after it has been synchronized.
6.3.2 Quadrature droop compensation shall be provided. For the Steam Turbine Generator ‘s and gas
turbine generator it is intended to control of the 66kV voltage. This may be achieved by 66kV
voltage sensing or by some form of current and impedance compensation. Vendor to detail in his
proposal how this will be achieved, and how quickly such compensation will operate, and how
accurately the 66kV be maintained including transient motor starting conditions.
6.3.3 Manual Follower circuit (i.e. stand-by DVR shall follow the manual set-point given by primary DVR
to machine) shall be provided for the duplicate DVR (Digital Voltage Regurator).
6.3.4 The closing of all breakers between two different voltage sources shall be enabled by a synchro-
check relay. Control shall be by operator via local or ELICS system.
6.3.5 For steam turbine generator protection, CONTRACTOR shall take into account the following
requirements:
a) For internal faults associated with the generator zones; the protective scheme shall trip the
generator circuit breaker and the steam turbine generator.
Date : NovAug. 248, POWER GENERATION AND QGX/29/91/EL/DB/NA/001
2006
b) External faults and system upset shall trip the generator breaker only.
6.3.6 Pilot wire relaying shall be used for 33kV feeders connected to 33kV distribution switchgear.