Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Table of Contents
Document Number Rev. Document Title Page
Number
A133-086-VV-MR- A ENQUIRY DOCUMENT 4
6141-31-RFQ
A133-086-VV-MR- A CS VESSELS (UPTO 25 THK) 78
6141
A133-086-16-46-DS- B DEBUTANIZER OVERHEAD RECEIVER (86-C-27) 82
3018
A133-086-16-46-DS- B DEBUTANIZER OVERHEAD RECEIVER (86-C-27) SHEET 2 83
3018A2
A133-086-16-46-DS- B CLOSED BLOWDOWN DRUM (86-C-51) 84
3029
A133-086-16-46-DS- B CLOSED BLOWDOWN DRUM (86-C-51) SHEET 2 85
3029A2
A133-086-16-46-DS- B CLOSED BLOWDOWN DRUM (86-C-51) SHEET 3 86
3029A3
A133-086-16-46-DS- B COKER UNIT FEED SURGE DRUM 86-C-21 87
3012
A133-086-16-46-DS- B COKER UNIT FEED SURGE DRUM 86-C-21 SHEET 2 88
3012A1
A133-087-16-46-DS- B SAND FILTER FOR NAPHTHA+DSO (87-C-08) 89
3008
A133-087-16-46-DS- B SAND FILTER FOR NAPHTHA+DSO (87-C-08) SHEET 2 90
3008A2
A133-087-16-46-DS- B SAND FILTER FOR TREATED LPG (87-C-09) 91
3009
A133-087-16-46-DS- B SAND FILTER FOR TREATED LPG (87-C-09) SHEET 2 92
3009A2
A133-086-16-46- A VDR FOR VDR COMPILATION 93
VDR-6141
A133-086-16-46-UR- A UNIT RATES FOR ADDITION AND DELETION 97
6141
A133-16-46-TQS- A TECHNICAL QUESTIONAIRE 104
A133-16-46-TR-6141 A INSTRUCTIONS TO VENDOR/ TECHNICAL REQUIREMENTS 106
A133-16-46-LL-6141 A LIST OF ATTACHMENTS 115
A133-16-46-SS-6141 A SCOPE OF WORK AND SUPPLY 121
INDVSD052 0 Recommended Weld edge Preparation for But welds 126
INDVSD007 0 Detail of Skirt Base for Vessel & column 127
INDVSD045 0 Support For Internal distributor pipes 128
INDVSD002 0 Manway Davit (for vertical manhole) 129
44NC-4600-0000- 0 General specification for PMI at vendor's works 130
V.02-0100-A4
7-12-0030 4 Name plate for small equipment. 137
INDVSD024 Model 0 Nozzle projection 138
(1)
44NC 4600 0 COMPLIANCE STATEMENT 139
(Compliance
Statement)
44NC-4600- A Quality management system 140
000/N.02/0040/A4
Annesure 1 to V
INDVSD050 0 LIFTING LUG FOR HORIZONTAL VESSELS 146
44NC-4600-0000- 1 General Specification for Painting 147
V.02-0111-A4
INDVSD020 0 Name Plate Bracket 192
INDVSD064 0 Inlet deflector baffle 193
INDVSD046 0 Support For Internal feed pipes 194
INDVSD043 0 Ladder Rungs Inside Vessels and columns 195
Page 1 of 434
Table of Contents
Document Number Rev. Document Title Page
Number
INDVSD022 0 INSULATION SUPPORT FOR VESSELS (HOT) 196
INDVSD058 0 INSULATION SUPPORT FOR HORIZONTAL VESSELS 197
INDVSD033 0 Vortex Breakers (Flush Type Nozzles) 198
INDVSD009 0 SADDLE SUPPORT FOR HORIZONTAL VESSELS 199
7-12-0019 5 Vortex breakers. 206
INDVSD030 0 Internal plate flange 207
INDVSD080 0 Earthing lug 208
44NC-4600-0000- 0 General Spec for Materials 209
V.02-0114
INDVSD012 0 Minimum Nozzle Wall Thickness 226
44NC-4600-0000- 0 Standard Specification for BQ plates 227
V.02-0117-A4
INDVSD040 0 Standard Bolt hole Orientation 232
INDVSD003 0 Manway Davit (for Horizntal manhole) 233
INDVSD006 0 Detail of skirt Opening for vessel & column 234
44NC-4600-0000- 0 GENERAL NOTES CS KCS VESSELS 235
V.02-0164
INDVSD018 0 Reinforcing Plates for Nozzles (C.A. 3mm) 236
INDVSD047 0 Support For Internal feed pipes 237
INDVSD021 0 Name plate for vessel 238
44NC 4600 (Drawing 0 DRAWING TITLE SAMPLE 239
Title Sample)
INDVSD019 0 R. PAD FOR NOZZLES (C.A. - 1.5MM) 240
INDVSD048 0 Lifting lug top head type 241
INDVSD034 0 Vortex Breakers (Nozzle with internal Projection) 242
44NC-4600- A Quality management system 243
000/N.02/0040/A4
44NC-4600-0000- 0 Supp spec for CS vessels 250
V.02-0120-A4
INDVSD051 0 Typ.nozzle flange to neck joint 255
INDVSD049 0 LIFTING LUG FOR VERTICAL VESSELS 256
44NC-4600-0000- A JOB SPECIFICATION - VESSELS 257
V.02-0141-A4
INDVSD004 0 Detail of Vessel/column Top davit 280
INDVSD062 Model 0 Fire proofing support 281
(1)
INDVSD001 0 Generl tolerances for pressure vessels 282
44NC-4600-0000- 0 LICENSOR SPECIFICATION 285
V.02-0101-A4
44NC-4600- B Standard grating (Type I & II) & staircase tread details (Sheet 1 of 326
0000/S.01/0008/A4 8)
(Sheet 1 of 8)
44NC-4600- B Standard grating (Type I & II) & staircase tread details (Sheet 2 of 327
0000/S.01/0008/A4 8)
(Sheet 2 of 8)
44NC-4600- B Standard grating (Type I & II) & staircase tread details (Sheet 3 of 328
0000/S.01/0008/A4 8)
(Sheet 3 of 8)
44NC-4600- B Standard grating (Type I & II) & staircase tread details (Sheet 4 of 329
0000/S.01/0008/A4 8)
(Sheet 4 of 8)
44NC-4600- B Standard grating (Type I & II) & staircase tread details (Sheet 5 of 330
0000/S.01/0008/A4 8)
(Sheet 5 of 8)
44NC-4600- B Standard grating (Type I & II) & staircase tread details (Sheet 6 of 331
0000/S.01/0008/A4 8)
(Sheet 6 of 8)
Page 2 of 434
Table of Contents
Document Number Rev. Document Title Page
Number
44NC-4600- B Standard grating (Type I & II) & staircase tread details (Sheet 7 of 332
0000/S.01/0008/A4 8)
(Sheet 7 of 8)
44NC-4600- B Standard grating (Type I & II) & staircase tread details (Sheet 8 of 333
0000/S.01/0008/A4 8)
(Sheet 8 of 8)
44NC-4600- B Circular platform for hot vessels (Sheet 1 of 6) 334
0000/S.01/0011/A4
(Sheet 1 of 6)
44NC-4600- B Circular platform for hot vessels (Sheet 2 of 6) 335
0000/S.01/0011/A4
(Sheet 2 of 6)
44NC-4600- B Circular platform for hot vessels (Sheet 3 of 6) 336
0000/S.01/0011/A4
(Sheet 3 of 6)
44NC-4600- B Circular platform for hot vessels (Sheet 4 of 6) 337
0000/S.01/0011/A4
(Sheet 4 of 6)
44NC-4600- B Circular platform for hot vessels ( For E>100mm) (Sheet 5 of 6) 338
0000/S.01/0011/A4
(Sheet 5 of 6)
44NC-4600- B Circular platform for hot vessels (Sheet 6 of 6) 339
0000/S.01/0011/A4
(Sheet 6 of 6)
44NC-4600- B Circular platform for cold vessels (Sheet 1 of 4) 340
0000/S.01/0012/A4
(Sheet 1 of 4)
44NC-4600- B Circular platform for cold vessels (Sheet 2 of 4) 341
0000/S.01/0012/A4
(Sheet 2 of 4)
44NC-4600- B Circular platform for cold vessels (Sheet 3 of 4) 342
0000/S.01/0012/A4
(Sheet 3 of 4)
44NC-4600- B Circular platform for cold vessels (Sheet 4 of 4) 343
0000/S.01/0012/A4
(Sheet 4 of 4)
6-68-0001 4 Standard specification civil and structural works - general scope. 344
44NC-4600- B Specification for Structural Steelwork 348
0000/C.02/0015/A4
44NC-4600- B Standard ladder & cage typical details for step through ladder 366
0000/S.01/0009/A3 (Sheet 1 of 2)
(Sheet 1 of 2)
44NC-4600- B Standard ladder & cage typical details for step through ladder 367
0000/S.01/0009/A3 (Sheet 2 of 2)
(Sheet 2 of 2)
A133-086-16-48- A SOR FOR LADDER & PLTF FOR 87-C-08 & 87-C-09 368
SOR-6141
A133-086-16-48- A SOQ FOR LADDER & PLTF FOR 87-C-08 & 87-C-09 371
SOQ-6141
A133-086-16-48- A SOW FOR LADDER & PLTF FOR 87-C-08 & 87-C-09 374
SOW-6141
44NC-4600- B Specification for Miscellaneous 381
0000/C.02/0025/A4
44NC-4600- 1 GENERAL SPECIFICATION FOR SHOP AND FIELD PAINTING 387
0000/V.02/0111/A4
A133-00-000--ITP- A INSPECTION AND TEST PLAN (JOB SPECIFIC) 432
015A
Page 3 of 434
0Regd. Office: Engineers India Bhawan, 1-Bhikaiji Cama Place, New Delhi-110066, India
Phone No. : 00 91 11 26762121 ; Fax No. : 00 91 11 26191714, 26167664
REQUEST FOR QUOTATION (RFQ)-(INDIGENOUS / FOREIGN / GLOBAL)
(e-Tendering)
Date: 27.12.2013
M/s Client Chennai Petrochemical Corporation Limited
For Limited Enquiry Only:
The Suppliers to whom this RFQ is Project Coker Block of Resid Upgradation Project at Manali
issued are only required to quote. Refinery, Chennai
RFQ No. RC/ A1 3 3 - 0 8 6 - V V - M R - 6 1 4 1 /31
Category II
Due Date 16.01.2014 [Up to 1200 Hrs. (IST)]
UNPRICED BID OPENING: At 1400 Hrs.(IST) on final bid due date
(In case the bid due date happens to fall on Holiday, the next working day
shall be deemed to be due date)
Gentlemen,
1. Chennai Petroleum Corporation Limited (CPCL), a subsidiary of Indian Oil Corporation Limited has
existing Refinery Facilities at Manali, Chennai, Tamil Nadu (India). The present capacity of CPCL at Manali
Refinery is 9.5 MMTPA. CPCL is currently implementing a Revamp of existing units to increase the crude
processing capacity by 1 MMTPA to take the overall complex capacity to 10.5 MMTPA unit.
Chennai Petroleum Corporation Limited (CPCL) has awarded the work of Resid Upgradation Project-
Coker Block to Engineers India Limited (EIL) and EIL is the CONTRACTOR for this Project.
2. Bids are requested for the captioned item in complete accordance with enquiry documents and its
attachments.
3. The complete RFQ can be downloaded from the EIL website (http://tenders.eil.co.in) or e-tender site of
EIL's ASP (Authorized service provider) https://www.tenderwizard.com/eil or from CPP portal
http://eprocure.gov.in/cppp.
4. Bidders are invited under single stage two part system in e-tendering portal
(https://www.tenderwizard.com/eil) in accordance with the instructions and terms & conditions enclosed
with this RFQ Covering letter.
iii) Duly filled-in, signed & stamped Annexure I to Prefilled ATC giving basic details on
transportation charges, taxes/ duties etc.
iv) Bank Certified Mandate Form as per Annexure-II to Prefilled ATC, duly signed and
stamped with the Banker’s certification alongwith cancelled cheque.
vi) Unpriced copy of unit rate for addition/ deletion in the format enclosed with MR/RFQ
indicating “ Q “ .
vii) Unpriced copy of schedule of rates for structural component in format enclosed with
MR/RFQ indicating “Q” in place of Prices.
ix) List of Commissioning spares (vendor’s recommended) and Special Tools & tackles
(vendors recommended), included in the quoted prices of main items.
Containing only prices filled in the prescribed price schedule excel format and other formats
provided in the RFQ Document, consisting of the following priced documents:
i) Prices in Price Schedule Format (only as per the Excel format uploaded on E-tendering
website https://www.tenderwizard.com/eil).
ii) Priced copy of unit rate for addition/ deletion, in the format enclosed in the MR/RFQ.
iii) Priced copy of schedule of rates for structural component in the format enclosed in the
MR/RFQ
Note:
a) Bidders are required to have a VALID digital signature of class IIIB issued by C.C.A. (Controller
of certifying authority, India) for participation in e-tendering.
c) Deviations to terms and conditions, presumptions etc shall not be stipulated in Price part of bid
and price bids shall not contain any stapled slips. In case of any conditions stipulated in price
bids or the price bid containing any stapled slips, the bids of such bidders shall be summarily
rejected and shall not be considered for further evaluation. Evaluation shall be carried out
excluding such bidder(s.)
5. Offers received through Fax / Telex / Telegraphic / E-Mail / hard form (other than the documents
specifically required in hard form) shall not be considered.
The bidders who have submitted their bid will be able to view online the name & status of all the bidders at
their respective windows, after unpriced bid opening by EIL.
Similarly, all technically and commercially acceptable bidders will be advised of date and time of online
priced bid opening. Aforesaid Bidders, will be able to view online the price sheets of other techno-
commercially acceptable bidders at their respective windows, after priced bid opening by EIL.
7. Please furnish your response to our RFQ either through EIL’s website http://tenders.eil.co.in or by
sending email/fax to EIL as per Proforma of Reply/ Acknowledgement Letter enclosed, by the pre-bid
meeting.
If not bidding, please return enquiry documents along with regret letter within the due date with reason(s)
of not participating in the RFQ.
The bidders should respond to this enquiry either by submitting their bids or by explaining the reason for
non-submission of the offer. In case there is no response either way continuously, the bidder shall
be liable for suitable action including review of their enlistment with EIL for that particular item.
8. Offer Validity : Offer shall be valid for 3 Months from the final / extended bid due date.
9. PAYMENT TERMS
Indigenous Supplier:
For Supply: As per clause No. 1.1.1 (vi) of Instruction to Bidders
For Mandatory spares, all consumables and First fill of lubricants, quoted separately as per MR : As per
clause No. 1.1.2 of Instruction to Bidders.
For other scope of MR: As per Instruction to Bidders
(REKHA CHOUDHARY)
Asst. General Manager (C&P)
Enclosures :
Material Requisition
MR No. A1 3 3 - 0 8 6 - V V - M R - 6 1 4 1 Rev A
Dear Sirs,
We acknowledge with thanks receipt of your above cited RFQ alongwith enclosures. We undertake that the
contents of the above RFQ shall be kept confidential including all the drawings, specifications and documents
and the said documents shall be used only for the purpose, for which they are intended.
a. _____________________________________________________
b. _____________________________________________________
Thanking you,
Page 1 of 1
Page 8 of 434
PROFORMA OF LETTER OF AUTHORITY FOR ATTENDING PRE-BID CONFERENCE
No. Date:
To,
ENGINEERS INDIA LIMITED
1, Bhikaiji Cama Place
R.K. Puram,
New Delhi 110066(India)
Attn . Ms. Rekha Choudhary, Asst. General Manager (C&P)
Dear Sirs,
We confirm that we shall be bound by all and whatsoever our representative (s) shall commit.
Yours faithfully,
Signature ……………………………
Note :
This Letter of Authority should be on the letter head of the bidder and should be signed by a person
competent and having the power of attorney to bind the bidder.
Page 1 of 1
Page 9 of 434
TECHNO-COMMERCIAL COMPLIANCE TO BID REQUIREMENT
We hereby agree to fully comply with, abide by and accept without variation, deviation or reservation
to all technical, commercial and other conditions whatsoever of the RFQ documents and Amendment/
Addendum to the RFQ Documents, if any, for subject RFQ.
Page 1 of 1
Page 10 of 434
Page 11 of 434
FOR BIDDERS’ QUERIES
NOTE: The Pre-Bid Queries may be sent on fax numbers 0091-11-26187664 and also by e-mail to concern person of EIL.
Page 1 of 1
Page 12 of 434
Page 13 of 434
EXCEPTIONS AND DEVIATIONS
NOTE: This shall be submitted separately for Commercial & Technical Sections.
Page 1 of 1
Page 14 of 434
Page 15 of 434
PRESENT COMMITMENTS AS ON …………………………………..
(Due Date for submission of Bid)
Page 1 of 1
Page 16 of 434
Page 17 of 434
Page 1 of 1
Page 18 of 434
1. Bids complete in all respects should be successfully Submitted online on or before the bid due date
and time specified above.
2. Technical specifications should be strictly as per the material requisition attached.
3. As Purchaser intends to contract directly with suppliers of the goods for which bids are invited, the
bids should be prepared by the suppliers and submitted directly. Purchaser reserves the right to
reject offers made by intermediaries.
4. The bidder shall bear all costs associated with the preparation and submission of its bid, and the
Purchaser shall in no case be responsible or liable for these costs regardless of the conduct or
outcome of the bidding process.
5. Bidders who are enlisted with EIL are required to quote as per their capabilities registered with EIL.
6. EIL reserves the right to use in-house information for assessment of bidder’s capability for
consideration of bid.
7. EIL reserve the right to make any changes in the terms and conditions of purchase and to reject
any or all the bids.
8. The order, if placed will be issued by EIL.
9. Net Worth of the Bidder shall be positive as per the immediate preceding year’s Audited financial
results. Bidder is therefore requested to furnish the latest Audited Financial Statement including
Profit & Loss Account.
In case, the bidder’s Net Worth is negative, their bid shall not be evaluated further. However
this criteria will not be applicable for Indian Central Public Sector Undertaking/Enterprises.
10. Purchaser reserves the right to allow purchase preference to Central Public Sector
Undertakings/enterprises, as admissible under prevailing policy of Government of India.
11. Preference to MSEs
Deleted (Not Applicable)
12. In case any bidder is found to be involved in cartel formation, his bid will not be considered for
evaluation / placement of order. Such bidder will also be debarred from bidding in future.
13. In case a supplier seeks any suo-moto price increase subsequent to the bid due date and which is
not as a result of any change in scope of supply or terms and conditions, the bid of such a supplier
shall be rejected for the items in which such suo-moto increase is sought.
14. FRAUDULENT PRACTICES
The Owner requires that Bidders/ Vendors/ Contractors observe the highest standard of ethics
during the award/ execution of Contract. "Fraudulent Practice" means a misrepresentation of facts
in order to influence the award of a Contract to the detriment of the Owner, and includes collusive
practice among bidders (prior to or after bid submission) designed to establish bid prices at artificial
non-competitive levels and to deprive the owner of the benefits of free and open competition.
a) The owner will reject a proposal for award if it determines that the bidder recommended for
award has engaged in fraudulent practices in competing for the Contract in question.
Bidder is required to furnish the complete and correct information/ documents required for
evaluation of their bids. If the information/ documents forming basis of evaluation is found to
be false/ forged, the same shall be considered adequate ground for rejection of bids and
forfeiture of Earnest Money Deposit.
b) In case, the information/ document furnished by the Bidder/ Vendor/ Contractor forming basis
of evaluation of his bid is found to be false/ forged after the award of the contract, Owner shall
have full right to terminate the contract and get the remaining job executed at the risk & cost of
Page 19 of 434
such Bidder/ Vendor/ Contractor without any prejudice to other rights available to Owner under
the contract such as forfeiture of CPBG/ Security Deposit, withholding of payment etc.
c) Incase, this issue of submission of false documents comes to the notice after execution of
work, Owner shall have full right to forfeit any amount due to the Bidder/ Vendor/ Contractor
along with forfeiture of CPBG/ Security Deposit furnished by the bidder/vendor/ contractor.
d) Further, such bidder/ vendor/ contractor shall be put on Blacklist/ Holiday/ Negative List of
owner debarring them from future business with Owner for a time period, as per the prevailing
policy in EIL.
15. Submission of authentic documents is the prime responsibility of the bidder. Wherever EIL has
concern or apprehension regarding the authenticity/correctness of any document, EIL reserves a
right of getting the document cross verified from the document issuing authority.
Page 20 of 434
If some information is already contained in TRC, the bidder shall not be required to
provide that information in Form no. 10F but even then Form no. 10F is required to be
provided by the bidder.
However, the bidder may write Not Applicable in the relevant column in case that
information is already contained in TRC.
The above shall be furnished before release of any payment or within one month of the
release of Order, whichever is earlier.
Failing submission of the above information, any additional tax liability on purchaser, will be
deducted from the payment due to the supplier.
17. SHIFTING OF ORDER
Based on the lowest evaluated item wise prices out of the techno-commercial acceptable
bidders, the shifting of order shall be carried out provided the following conditions are met:
a) Shifting shall be done only if shifting cost of each order is up to Rs.1, 00,000/-.
b) Shifting shall not be resorted to if the value is more than 25% of the total order value
of the recommendation (i.e. total order valued for MR/RFQ). However, this ceiling will
not be applicable where total order value of recommendation is up to Rs. 4, 00,000/-.
c) In case the order value on L1 bidder is more than Rs. 2, 00,000/- then shifting shall
not be resorted.
With above shifting the selected bidder for award will be deemed to be L1 bidder
18. CLARIFICATION REQUESTS FROM BIDDERS
A bidder may seek clarification regarding the bidding document provisions, bidding process and / or
rejection of his bid. EIL shall respond to such requests with in a reasonable time.
19. SETTLEMENT OF DISPUTE BETWEEN GOVT. DEPT./ PUBLIC SECTOR UNDERTAKING
In the event of any dispute or difference relating to the interpretation and application of the
provisions of the contracts, such dispute or difference shall be referred by either party for
Arbitration to the sole Arbitrator in the Department of Public Enterprises to be nominated by the
Secretary to the Government of India in-charge of the Department of Public Enterprises. The
Arbitration and Conciliation Act, 1996 shall not be applicable to arbitration under this clause. The
award of the Arbitrator shall be binding upon the parties to the dispute, provided, however, any
party aggrieved by such award may make a further reference for setting aside or revision of the
award to the Law Secretary, Department of Legal Affairs, Ministry of Law & Justice, Government of
India. Upon such reference the dispute shall be decided by the Law Secretary or the Special
Secretary/Additional Secretary, when so authorized by the Law Secretary, whose decision shall
bind the Parties finally and conclusively. The Parties to the dispute will share equally the cost of
arbitration as intimated by the Arbitrator.
20. PRE BID MEETING
DELETED
Page 21 of 434
However please note that in case of Reverse Auction, Rebate offered on Total Evaluated Price of
item/Group shall be prorated for all quoted prices of particular Items / Groups, which were considered
for evaluation and accordingly ordering shall be carried out.
Page 22 of 434
INSTRUCTION TO BIDDERS (ITB)
Document No.
[ CPCL – LSTK ] A133-01- ITB Rev. 0
Page 1
1 PAYMENT TERMS
1.1.1 Supply:
(i) Where the MR is for supply of materials and there is no Vendor Data
requirement (VDR) specified in the MR:
- 90% against despatch documents directly to EIL on pro-rata basis together
with full taxes, duties and transportation charges and on submission of
Performance Bank Guarantee valid for the 3 (Three) Months beyond
guarantee period.
- 10% on receipt and acceptance of last consignment of materials at site and
and on submission of E1/E2 Form (wherever applicable).
(ii) Where the MR is for supply of materials and calls for Vendor Data
requirement: (Without site work):
- 5% against approval of drawings, wherever required (identified in
Purchase Requisition) at least in Code-2 and manufacturing Schedule.
.
- 80% (85% in cases where drawing approval is not required) against
despatch documents directly to EIL on prorate basis together with full
taxes, duties and transportation charges and on submission of Performance
Bank Guarantee valid for the 3 (Three) Months beyond guarantee period.
(iii) Where the MR is for supply of materials and calls for Vendor Data
requirement: (With site work)
- 5% against approval of drawings, wherever required (identified in
Purchase Requisition) at least in Code-2 and manufacturing Schedule.
Page 23 of 434
INSTRUCTION TO BIDDERS (ITB)
Document No.
[ CPCL – LSTK ] A133-01- ITB Rev. 0
Page 2
- 10%. on successful completion of Site Work and on submission of E1/E2
Form (wherever applicable).
Note: In case site is not available upto 6 (Six) months after receipt of all
supplies at site, the last 10% payment shall be released against submission
of additional Bank Guarantee of equivalent amount valid for 1 (One) year or
such extended period as may required.
(iv) Where the MR is for Packages (with significant Bought out item) and
calls for Vendor Data requirement: (Without site work)
- 5% on approval of drawings, wherever required (identified in Purchase
Requisition), in at least Code-2 and manufacturing schedule.
-10% against placement of sub-order for specified major raw material (to be
identified by PEM and PM before issue of enquiry) against submission of
equivalent Bank Guarantee.
- 70% against dispatch documents directly to EIL on prorate basis together with
full taxes, duties and transportation charges and on submission of
Performance Bank Guarantee valid for the 3 (Three) Months beyond
guarantee period.
(v) Where the MR is for Packages (with significant Bought out item) and
calls for Vendor Data requirement: (With site work)
- 5% on approval of drawings, wherever required (identified in Purchase
Requisition), in at least Code-2 and manufacturing schedule.
.
-10% against placement of sub-order for specified major raw material (to be
identified by PEM and PM before issue of enquiry) against submission of
equivalent Bank Guarantee.
- 70% against dispatch documents directly to EIL on prorate basis together with
full taxes, duties and transportation charges and on submission of Performance
Bank Guarantee valid for the 3 (Three) Months beyond guarantee period and
on submission of Performance Bank Guarantee valid for the 3 (Three) Months
beyond guarantee period.
Page 24 of 434
INSTRUCTION TO BIDDERS (ITB)
Document No.
[ CPCL – LSTK ] A133-01- ITB Rev. 0
Page 3
number of copies/sets/CDs as per VDR specified in Purchase Requisition.
Note: In case site is not available up to 6 (Six) months after receipt of all
supplies at site, the last 10% payment shall be released against submission
of additional Bank Guarantee of equivalent amount valid for 1 (One) year or
such extended period as may required.
- 15% against receipt and identification of specified major raw materials and
against submission of equivalent BG.
- 65% against dispatch documents directly to EIL on prorate basis together
with full taxes, duties and transportation charges and on submission of
Performance Bank Guarantee valid for 3 months beyond guarantee period
- 5% on receipt of Final/As built Drawings/Documents/Data/Manual in
requisite number of copies/sets/CDs as per VDR specified in Purchase
Requisition.
- 10% on receipt and acceptance of goods/ materials at Site on submission of
E1/E2 Form (wherever applicable).
Major Raw Material for payment against receipt & identification of raw
materials:
Columns and Vessels Plates and Forgings
Heat Exchangers : Plates, Forgings and Tubes
Pumps : Castings
Compressors : Castings / Forgings
- 15% against receipt and identification of specified major raw materials and
against submission of equivalent BG..
- 65% against dispatch documents directly to EIL on prorate basis together with
full taxes, duties and transportation charges and on submission of Performance
Page 25 of 434
INSTRUCTION TO BIDDERS (ITB)
Document No.
[ CPCL – LSTK ] A133-01- ITB Rev. 0
Page 4
Bank Guarantee valid for 3 months beyond guarantee period
Note: In case site is not available upto 6 (Six) months after receipt of all supplies at
site, the last 10% payment shall be released against submission of additional Bank
Guarantee of equivalent amount valid for 1 (One) year or such extended period as
may required.
Major Raw Material for payment against receipt & identification of raw materials:
Columns and Vessels : Plates and Forgings
Heat Exchangers: Plates, Forgings and Tubes
Pumps : Castings
Compressors : Castings / Forgings
- 15% after receipt of identified raw materials at fabrication yard and against
certification by TPIA against Hypothecation Bond.
- 20% after receipt of tax invoice along with taxes & duties and after submission of
final technical documentation and drawings as per Purchase Requisition and on
transportation of completed column from fabrication yard/ assembly yard to
erection site, delivery of column up to equipment foundation and handing over
to Engineer-in-charge at site.
Terms of Delivery shall be delivery of column up to equipment foundation and
handing over to Engineer-in-charge at site.
Page 26 of 434
INSTRUCTION TO BIDDERS (ITB)
Document No.
[ CPCL – LSTK ] A133-01- ITB Rev. 0
Page 5
certified by Engineer-in-charge.
1.1.5 Training
- 100 % on successful completion of Training duly certified by PURCHASER,
as per Purchase Requisition.
(ii) Where the MR is for supply of materials and calls for Vendor Data
requirement: (Without site work)
- 5% against approval of Drawings, wherever required (identified in Purchase
Requisition) in at least in Code-2 & manufacturing schedule through Wire
Transfer.
- 90% (95% in cases where drawing approval is not required) against shipping
documents through irrevocable Letter of Credit .
(iii) Where the MR is for supply of materials and calls for Vendor Data
requirement: (With site work)
Page 27 of 434
INSTRUCTION TO BIDDERS (ITB)
Document No.
[ CPCL – LSTK ] A133-01- ITB Rev. 0
Page 6
through wire transfer.
Note: In case site is not available upto 6 (Six) months after receipt of all supplies
at site, the last 10% payment shall be released against submission of additional
Bank Guarantee of equivalent amount valid for 1 (One) year or such extended
period as may required.
(iv) Where the MR is for Packages (with significant Boughtout item) and
calls for Vendor Data Requirement: (Without site work)
- 10% against placement of sub orders for specified major raw materials, against
submission of equivalent bank guarantee through wire transfer.
(v) Where the MR is for supply Packages (with significant Boughtout item)
and calls for Vendor Data Requirement: (With site work)
- 10% against placement of sub orders for specified major raw materials, against
submission of equivalent bank guarantee through wire transfer.
Note: In case site is not available upto 6 (Six) months after receipt of all
supplies at site, the last 10% payment shall be released against submission
of additional Bank Guarantee of equivalent amount valid for 1 (One) year or
such extended period as may required.
T&C FOR ED COMMITTEE APPL- LSTK-A133
Page 28 of 434
INSTRUCTION TO BIDDERS (ITB)
Document No.
[ CPCL – LSTK ] A133-01- ITB Rev. 0
Page 7
- 15% against receipt and identification of specified major raw materials against
submission of equivalent BG through wire transfer.
- 75% (80% in cases where drawing approval is not required) against shipping
documents through irrevocable Letter of Credit.
Major Raw Material for payment against receipt & identification of raw materials:
Columns and Vessels Plates and Forgings
Heat Exchangers : Plates, Forgings and Tubes
Pumps : Castings
Compressors : Castings / Forgings
- 15% against receipt and identification of specified major raw materials against
submission of equivalent BG through wire transfer.
- 65% (70% in cases where drawing approval is not required) against shipping
documents through irrevocable Letter of Credit.
Note: In case site is not available upto 6 (Six) months after receipt of all supplies at
site, the last 10% payment shall be released against submission of additional Bank
Guarantee of equivalent amount valid for 1 (One) year or such extended period as
may required.
Major Raw Material for payment against receipt & identification of raw materials:
Columns and Vessels Plates and Forgings
T&C FOR ED COMMITTEE APPL- LSTK-A133
Page 29 of 434
INSTRUCTION TO BIDDERS (ITB)
Document No.
[ CPCL – LSTK ] A133-01- ITB Rev. 0
Page 8
Heat Exchangers : Plates, Forgings and Tubes
Pumps : Castings
Compressors : Castings / Forgings
1.2.5 Training:
- 100% through Wire Transfer on successful completion of Training duly
certified by PURCHASER, as per Purchase Requisition (PR).
Page 30 of 434
INSTRUCTION TO BIDDERS (ITB)
Document No.
[ CPCL – LSTK ] A133-01- ITB Rev. 0
Page 9
bank, bank account no. etc., duly attested by BIDDER’s bank must be
submitted along with the offer.
(vi) Status of bills after submission can be viewed on our website
http://www.engineersindia.com.
(vii) Foreign bidders are required to submit contract cum Performance Bank
Guarantee within 30 days of FOA/PO.
(viii) Irrevocable Letter of Credit for payment to Foreign SUPPLIERs shall be
established in favour of the supplier in a bank in his country, for an
appropriate amount (in line with Payment Terms). L/C shall be opened
within 45 days of receipt of acknowledgement of FOA/PO along with PBG
(wherever applicable). In case confirmed L/C is insisted by supplier, L/C
confirmation charges shall be to supplier’s account.
(ix) Payment to foreign SUPPLIERs against Site Work and Supervision/Training
shall be through wire transfer.
(x) All payments (other than through L/C) shall be released within 30 days of
receipt of invoice and all requisite documents, complete in all respects.
(xi) All bank charges of respective bankers shall be to respective account.
(xii) Seller shall submit Billing Schedule within three weeks after placement of
FOA/PO ( whichever is issued earlier ) for PURCHASER’s approval
(wherever applicable).
(xiii) Sellers requiring multiple despatches will restrict the number of despatches to
maximum three, unless agreed otherwise by Project Manager.
(xiv) All progressive advances to foreign as well as Indian bidders (except the
milestone payment against drawing approval) shall be against equivalent
bank guarantees. The progressive advances shall be paid through wire
transfer to foreign bidder.
(xv) Other than the payment terms given above, no other advance payments shall
generally be payable. However, if any Seller insists on advance payments, such
advance payment (other than the payment terms given in RFQ) shall be interest
bearing @ SBI PLR + 2% per annum (simple interest) on reducing balance, up to
delivery period and shall be released only against equivalent Bank Guarantee,
which shall be valid up to contractual delivery date plus three months. Interest shall
be adjusted while releasing the payment against despatch documents.
2 TERMS OF DELIVERY
2.1 INDIGENIOUS ENQUIRIES: Terms of delivery are FOT Project site on freight
prepaid & door delivery basis. The date of receipt of material at site shall be
considered as the date of delivery.
2.2 FOREIGN ENQUIRIES: Terms of delivery are FOB international sea port of exit
basis. The Date of On Board Bill of Lading shall be considered as date of
Delivery.
2.3 GLOBAL ENQUIRIES:
T&C FOR ED COMMITTEE APPL- LSTK-A133
Page 31 of 434
INSTRUCTION TO BIDDERS (ITB)
Document No.
[ CPCL – LSTK ] A133-01- ITB Rev. 0
Page 10
2.3.1 For Indigenous Suppliers: Terms of delivery are FOT Despatch point on
freight to pay basis. The date of LR/GR shall be considered as the date of delivery.
2.3.2 For Foreign Suppliers: Terms of delivery are FOB international sea port of
exit basis. The Date of On Board Bill of Lading shall be considered as date of
Delivery.
3 TRANSPORTATION
In case of MRs containing supplies as well site work, a single order, covering the
supply part as well site work, shall be placed. Split ordering will not be permitted.
In case, a foreign SUPPLIER requests for a separate order on his Indian sub-
T&C FOR ED COMMITTEE APPL- LSTK-A133
Page 32 of 434
INSTRUCTION TO BIDDERS (ITB)
Document No.
[ CPCL – LSTK ] A133-01- ITB Rev. 0
Page 11
SUPPLIER, the same shall not be accepted. However, payment to Indian sub-
SUPPLIER shall be released directly in Indian Rupees against invoices duly
certified by the Foreign SUPPLIER.
For this purpose, the Indian sub-SUPPLIER’s name, material and corresponding
price in Indian Rupees, shall be clearly spelt out in the purchase order on foreign
SUPPLIER.. In case a Foreign supplier sources supplies/ services within India, the
applicable terms & conditions shall be modified to the extent as per Annexure-1
enclosed.
7 GUARANTEE PERIOD
GUARANTEE PERIOD:
For all items having CDD up to Dec 2014 :
18 Months from the date of successful Commissioning or 36 Months from the
date of shipment, whichever is earlier.
For all items having CDD beyond Dec 2014 :
18 Months from the date of successful Commissioning or 30 Months from the
date of shipment, whichever is earlier.
Page 33 of 434
INSTRUCTION TO BIDDERS (ITB)
Document No.
[ CPCL – LSTK ] A133-01- ITB Rev. 0
Page 12
Purchase Order includes supply and site work, Purchase Order will be divided
into supply and service portion separately , no VAT on work contracts is
envisaged, however VAT on work contract on site work portion if applicable
shall be included in the bidder’s quoted price & no statuary variation is payable
on the same.
9.2 Entry Tax and Terminal taxes are presently not applicable. If applicable at a
later date, same shall be payable extra at actual on production of necessary
Documentary evidence. Road permit shall be issued to supplier by CPCL for
material consigned to CPCL.
9.3 All payments on account of Excise Duty, Service Tax, TNVAT on finished
goods shall be released on receipt of CENVATABLE ( Duplicate Copy of
Excise Invoice) /VATTABLE copy of corresponding invoice and documents
valid for availing CENVAT / VAT credit.
9.4 PURCHASER shall be able to avail 100% credit against TNVAT(i.e. VAT on
sale of finished goods). PURCHASER will not issue any concessional form for
TNVAT.
TN VAT on sale of goods shall not be loaded for evaluation.
9.5 EIL shall issue concessional form-C for central sales tax.
CST against inter state sale shall be loaded during evaluation at the applicable
rates.
9.6 Since Cenvat Credit shall be available against Excise Duty and Service Tax
(excluding service tax on freight) & the same shall not be considered for
comparison purpose.
9.7 Indigenous SUPPLIER’s shall issue E1/E2 form on quarterly basis within 60
days after completion of each quarter based on “C” form no. provided by
PURCHASER. PURCHASER will provide original “C” form in exchange of
original E1/E2 form.
Statutory Variations are eligible only on Service Tax, cenvatable excise duty,
and VAT amount for which input tax credit is available to the OWNER under
TNVAT Act subject to SUPPLIER producing documentary evidence for the
above . Statutory Variations are eligible on CST also.
Statutory variations on non-cenvatable excise duty and VAT amount for which
input tax credit is not available to the OWNER/PURCHASER under TN VAT
Act shall be to SUPPLIER’s account.
9.9 All non-cenvatable /non-vattable taxes/duties shall be considered for
evaluation.
9.10 All new taxes/duties/cess/levies notified after the last date of submission of
final price bid/price implication, but within contractual delivery /completion
period, shall be to EIL’s account. These shall be reimbursed against
documentary evidence.
However, in case of delay on account of supplier, any new or additional taxes
and duties imposed after contractual delivery shall be to supplier’s account.
10 CUSTOMS DUTY/EPCG LICENSE
10.1 OWNER is obtaining an EPCG license for this project. In view of this
concessional rate of Custom Duty shall be applicable to imports from foreign
BIDDER’s for the goods directly consigned to CPCL.
10.2 Indigenous BIDDER’s will be required to quote price considering only merit
rate of duty, for their built in import content, in their bid and evaluation shall be
T&C FOR ED COMMITTEE APPL- LSTK-A133
Page 34 of 434
INSTRUCTION TO BIDDERS (ITB)
Document No.
[ CPCL – LSTK ] A133-01- ITB Rev. 0
Page 13
done accordingly. No PAC/EC/INVALIDATION LETTER shall be issued to
Indigenous BIDDER’s.
11 FIRM PRICES
11.1 The prices shall be firm and fixed and not subject to any variation,
whatsoever. In case of Cables, variation in prices shall be admissible as per
IEEMA Price Variation Clause.
11.2 For 2 years O&M spares, prices shall be kept valid for a period of 2 years
from the date of order of main equipment along with annual % escalation ( to
be indicated by the bidder) for subsequent two years.
12 PRICE REDUCTION SCHEDULE
12.1 In case of MRs other than packages, Price Reduction Schedule shall be
@1/2% of value of delayed equipment/ item per week of delay or part thereof
subject to a maximum of 5% of total order value.
12.2 For packages and critical items, with or without site work, the Price Reduction
Schedule shall be @1/2% of total order value per week of delay or part
thereof subject to a maximum of 7.5% of total order value.
12.3 Wherever the supply period and site work are indicated as two separate
periods and notice of site readiness is required for site work, intervening
period, if any, shall be excluded, while calculating the price reduction for
delay.
Note : it shall be endeavor to split the period ,i,e., a separate period for supply
and site work.
12.4 Price reduction shall be effected in the Invoice value before presenting for
payment. The Purchaser reserves the right to cancel the Purchase Order for
any delay exceeding the period of maximum reduction and the Seller shall be
liable to all consequences thereof.
Deleted: ¶
¶
13 INSPECTION ¶
All items shall be inspected by a Third Party Inspection agency as follows:
13.1 INDIGENOUS BIDDER’s: CEIL shall be appointed as Third Party Inspection
for the indigenous materials & accordingly the charges for the same shall be borne
by EIL. The quoted price of Bidder shall be exclusive of TPI charges.
13.2 FOREIGN BIDDERs: The quoted price shall be inclusive of TPI charges
(out of M/s.Lloyds Register (Country of origin), M/s.Bureau Veritas(BV) and
M/s.TUV Nord)
Suppliers will be informed the following:
a) QAP will be approved by Third Party Inspection agency incorporating
requirements of ITP, Technical specifications and approved documents. Approval of
QAP will not be carried out by EIL.
b) The Inspection release note issued by the Third party inspection agency shall
clearly stipulate that materials/equipment have been inspected as per Code-1
approved drawings, wherever applicable and approved QAP.
Page 35 of 434
INSTRUCTION TO BIDDERS (ITB)
Document No.
[ CPCL – LSTK ] A133-01- ITB Rev. 0
Page 14
certificate.
Page 36 of 434
INSTRUCTION TO BIDDERS (ITB)
Document No.
[ CPCL – LSTK ] A133-01- ITB Rev. 0
Page 15
- Firm freight as quoted by BIDDER’s.
In case, firm freight is not quoted by BIDDER ( For Bulk Items as well
as Packages/equipments/pipes & plates), freight shall be taken from
Transchart through shipping Dept. and loading shall be done with the
same. In case of ordering, transportation shall be done by the
Transchart only.
16.2.2 Cost of mandatory spares identified in the Material Requisition,
Commissioning Spares and special tools & tackles will be included for
evaluation of bids, but costs of Spares for two years operation shall be
excluded.
16.2.3 AMC charges shall be considered for evaluation wherever AMC is required.
16.2.4 Supervision (man days as indicated in MR as well as TBA ) and Training
charges shall be considered for evaluation, wherever, supervision and
training are required.
16.2.4 (i) Service tax on Reverse charge and withholding tax ( in case it is not
included in bidder’s price) basis, wherever applicable shall be added for bid
evaluation purpose only.
16.2.5 Commercial loading shall be considered for evaluation of bids.
16.2.6 Technical loading, if any, shall be considered for evaluation of bids.
16.2.7 For global enquiries, evaluation of offer shall be done considering foreign
exchange rate, on the date of priced bid opening. Deleted: i.e., 1 USD = Rs. 56.13.
Page 37 of 434
INSTRUCTION TO BIDDERS (ITB)
Document No.
[ CPCL – LSTK ] A133-01- ITB Rev. 0
Page 16
(iii) Landing Charges @ 1% of CIF Value i.e S.No. (i).
(iv) Custom clearance, Port Handling and Inland Freight (from Port of Entry
(CHENNAI) to CPCL project site) charges @ 3% of CIF value including
L/C Charges, i.e., S. No. (i) plus (ii).
(v) Landed Cost = S.No. (i) to (iv).
NOTE :
- Site Work, wherever applicable, shall be considered for evaluation.
- Transit insurance for Indigenous and Foreign BIDDERs, will not be loaded..
16.4 GENERAL
16.4.1 Taxes and duties will be cost loaded as quoted by the bidder. However, if a
SUPPLIER states that taxes/duties are not applicable at present and will be
charged as applicable at the time of delivery then his bid shall be loaded by
the maximum rate of taxes/duties applicable at the time of evaluation of
Bids.
16.4.2 In case of pipes, if a foreign BIDDER has not quoted or not included
stowage charges, the same shall be loaded @ 10% of BIDDER’s quoted
Ocean Freight.
17 LOADING/REJECTION CRITERIA
10% for differential period : 10% * differential period /total period ,i.e,
(guarantee period + claim period)
Page 38 of 434
INSTRUCTION TO BIDDERS (ITB)
Document No.
[ CPCL – LSTK ] A133-01- ITB Rev. 0
Page 17
Page 39 of 434
INSTRUCTION TO BIDDERS (ITB)
Document No.
[ CPCL – LSTK ] A133-01- ITB Rev. 0
Page 18
(ii) Drawing approval : 80% of the delivery period
(iii) Order on sub Vendors : 75% of the delivery period
(iv) Receipt of raw material at Vendor’s works : 50% of the delivery period
(v) %age payment against dispatch : Interest for Three month
Documents instead receipt & acceptance
at Site (Specified in RFQ)
(vi) % age payment against dispatch : Interest for One month
document instead of Final document
as per Purchase Requisition
(Specified in RFQ)
PBG shall be required along with the Dispatch documents, in cases where there is
no further milestone payment of 10% or more left.
17.6 DELIVERY
17.6.1 FOR IDENTIFIED CRITICAL EQUIPMENTS (TO BE IDENTIFIED BY THE
PROJECT):
Delivery/Completion period longer than required in enquiry shall be liable for
rejection..
17.6.2 FOR BALANCE ITEMS/EQUIPMENTS (OTHER THAN CRITICAL
EQUIPMENTS) :
(i) FOR ENQUIRIES WITH DELIVERY/COMPLETION PERIOD UPTO 6
MONTHS
Delivery/Completion period longer than required in enquiry shall be loaded
@ 1/2% per week up to a maximum of four (4) weeks. In case, a SUPPLIER
quotes delivery longer than four (4) weeks from required, the bid shall be
rejected. One (1) month shall be construed as equal to four (4) weeks for the
purpose of such evaluation.
Page 40 of 434
INSTRUCTION TO BIDDERS (ITB)
Document No.
[ CPCL – LSTK ] A133-01- ITB Rev. 0
Page 19
@ 1/2% per week upto a maximum of six (6) weeks. In case, a SUPPLIER
quotes delivery longer than six (6) weeks from required, the bid shall be
rejected. One (1) month shall be construed as equal to four (4) weeks for the
purpose of such evaluation.
NOTE: In case under clause no. 2.1, indigenous bidder offers a deviation
against the terms of delivery basis, their bid shall be rejected.
17.7 OFFER VALIDITY:
In case a SUPPLIER offers shorter validity of the bid against RFQ requirement, the
bid shall be rejected.
18 INVOICING INSTRUCTIONS
For imported goods, The Invoices shall be billed to CPCL a/c EIL. Consignee on
the invoices and bill of lading issued by the foreign supplier shall be in the name of
CPCL, COKER BLOCK OF RESID UPGRADATION PROJECT, MANALI REFINERY, and
CHENNAI. For Indigenous Goods, the invoices shall be billed to EIL a/c CPCL.
However, the consignee in the tax invoices shall be CPCL A/C EIL, COKER BLOCK
OF RESID UPGRADATION PROJECT, MANALI REFINERY, CHENNAI to avail input
credit of Excise duty by CPCL.
Page 41 of 434
INSTRUCTION TO BIDDERS (ITB)
Document No.
[ CPCL – LSTK ] A133-01- ITB Rev. 0
Page 1
Annexure I
TERMS & CONDITIONS FOR INDIAN SOURCED COMPONENTS / SERVICES BY FOREIGN BIDDER
Foreign bidder may source components / sub-supplies and services from India, if allowed as
per Material Requisition. For such sub-supplies / services ,Commercial Terms & Conditions of
the RFQ shall stand modified to the following extent:
1. PRICING:
1.1 Unit and total price on FOT Despatch Point basis including packing and forwarding
charges.
1.2 Details of Taxes and duties (rates) payable extra on the finished goods, applicable on
Indian sub-suppliers. Purchaser shall issue ‘C’ form for Concessional rate of Central sales
tax.
1.3 Separate and clear break-up of charges for inland transportation excluding Entry Tax &
Terminal Tax. Entry Tax and Terminal Tax, if applicable, shall be reimbursed at actuals by
EIL on submission of documentary evidence.
1.4 Materials if ordered against the RFQ/Bidding Document are required to be dispatched
on door delivery basis through a reliable bank approved Road Transport Company.
1.5 Transit insurance of Indian sub supplies shall be borne and arranged by the EIL.
2. CURRENCY OF QUOTE:
The quoted price of sub-supplies / services shall be in Indian Rupees only.
3. AWARD OF ORDER:
Foreign Principal shall be the single point responsible Vendor and separate order on
Foreign supplier and Indian sub-supplier / sub-contractor is not acceptable. Single
Purchase order shall be issued on the Foreign principal clearly indicating the sub-
supplier’s / sub-contractor’s name, material and corresponding price in Indian Rupees.
4. DELIVERY:
The delivery period for sub-supplies shall be on FOT site basis within specified delivery
period for Foreign bidder as per Terms of RFQ/Bidding document.
6. PAYMENT TERMS:
6.1 Indian sub-supplies:
90% through E-Payment with taxes and duties will be paid against receipt of Indian
sourced goods/material at project site.
Page 42 of 434
INSTRUCTION TO BIDDERS (ITB)
Document No.
[ CPCL – LSTK ] A133-01- ITB Rev. 0
Page 2
10% against receipt & Acceptance on delivery of main equipments by Foreign
principal and as well as Indian supplies at site as per Terms of bidding document.
Payment of Indian sub supplies/Services shall be released directly to Indian counterpart
against Invoices raised by Indian counterpart duly certified by Foreign principal.
6.2 Foreign principals: Payment terms of Foreign bidder shall be modified and 5% payment
out of payment against shipping documents through L/c shall be released after receipt
on delivery of main equipments by Foreign principal as well as Indian supplies at site as
per Terms of bidding document through wire transfer.
6.3 The payments shall be made after Adjustment of Price Reduction Schedule.
Page 43 of 434
INSTRUCTIONS TO BIDDERS FOR E-TENDERING
Bidders who wish to participate for RFQs/ Tenders which are uploaded on EIL’s Authorised service
provider’s website (i.e. www.tenderwizard.com/eil ) should follow the following instructions which
shall permit them to Search, View, Download and Submit their Electronic Bids online in a secure manner
ensuring confidentiality. These Instructions for E-Tendering shall be read in conjunction with various
instructions, wherever appearing with the RFQ/ Bidding Document. The conditions & instructions
mentioned here in under shall supersede and shall prevail over the conditions & instructions enumerated
elsewhere in the RFQ/ Bidding Document.
1) PARTICIPATION IN E-TENDERING, REQUEST FOR USER ID and PASSWORD:
To participate in E-Tendering, it is Mandatory to the Bidders have a user id and password on e-
tendering portal. Bidders are required to be registered on E-Tendering website to obtain user id &
password (password will be system generated). However for the tenders issued on limited basis,
bidders are already registered by EIL and after their registered, user id & password were
communicated to bidders at their e-mail id available in EIL. The bidders who are already registered
may contact to concern person of EIL to get their user id and password.
For tender issued on NIT/ Press advertisement basis, bidders are required to registered themselves
by using the link of registration provide on the home page of e-tendering website. The bidders are
required to fill the online registration form with all required details. The bidder should indicate correct
information including their e-mail since all system generated correspondences will be send on these e-
mail ids. Digital signature of class 3b individual or class 3 organization is a mandatory requirement for
e-tendering, right from log-in into the system. Hence, during registration, bidders shall fill the details
of their digital Signature (serial No.) to save time and avoid mapping of Digital Signature details to the
bidders user ID at the bid uploading stage. Otherwise, bidders are required to furnish their DC details
to EIL for mapping the same to their user id by Service provider. Once, the online registration form is
submitted with all required field and documents like pan card, registration or any other document of
company, the system will generate the user id and password for the bidder.
However, to use this user id, the bidders are required to get their user id enabled (activate) through
concerned engineer for the tender in EIL. Accordingly, after registration, bidder shall send a request to
EIL to activate their user id by providing user id and bid reference number.
Note : Bidders who are already registered in any earlier tender of EIL, need not to create new user id,
as the same user id can be used for all the tenders issued to them by EIL on this e-tendering portal.
User id and password are unique to each bidder and the bidder shall use the same to
view/download/participate in all e-tenders of EIL. Bidders are required to change the password during
their first login into the system. There will be single user id permission for each bidder in the system
for their company/Organization.
Bidders in their own interest are requested to register on e- tendering portal and upload/submit their
bid well in time. Bidders should avoid the last hour rush to the website for registration of user id &
password, enabling of user id and mapping of digital signature serial number etc. since this exercise
require activities from EIL & M/s Antares System (Service Provider) and needs time. In the event of
failure in bidder’s connectivity with EIL/Service Provider during the last few hours, bidder is likely to
miss the deadline for bid submission. Due date extension request due to above reason may not be
entertained.
EIL/EIL’s ASP will not be responsible for any delay/ non-availability of USER ID or Password or any last
minute request for enabling /resetting the same by the Bidders.
Any bidder intends to modify their bid they should use “‘MODIFY” instead of “WITHDRAW“.
Caution : ONCE BID IS WITHDRAWN BY THE BIDDER WILLINGLY OR UNWILLINGLY , SYSTEM WILL
NOT ALLOW THEM TO RESUBMIT THEIR BID.
6) SUBMISSION OF BID :
Bidders are required to upload the bid along with all supporting documents & Priced part on the E-
Tendering website (www.tenderwizard.com/eil) only. However, documents required to be submitted
physically, viz., Bid Document Fee, EMD, etc., need to be submitted in a sealed envelope as per the
provisions of RFQ/ Bidding Document.
Bidders shall ensure that all the required documents are uploaded in time and failure to upload the
same before bid submission date & time is the sole responsibility of bidder. Under no circumstances,
EIL shall entertain any request for acceptance of bid documents in physical form or any other form,
which are required to be uploaded on E- Tendering Website.
Also bidders are suggested to check the uploaded documents to verify the uploaded documents are
opening correctly or not by clicking on the download link.
The bidders needs to submit prices on-line strictly as per the Price Schedule format provided in our E-
Tender.
Bidders can submit their Bids on-line only after digitally signing the bid/documents with the Digital
Signatures used for log-in.
The Authenticity of above digital signatures may be verified through authorized CA after bid opening
and in case the digital signature is not authorized/valid, the bid will be rejected. Bidder shall be
responsible for ensuring the validity of digital signatures and proper usage of the same by responsible
persons.
Contact Persons:
1. Mr. Santosh Srivastava
Contact no: 08800591739
Email: santoshkumar.s@antaressystems.com
2. Mr. Sachin
Contact no: 8401982112
Email: sachin.t@antaressystems.com
A133-01-GPC (Ind.)-R0
Page 49 of 434 Page 1 of 7
PART – A: GENERAL PURCHASE CONDITIONS (INDIGENOUS)
“Contractual Delivery Date”: Contractual Delivery The terms and conditions of the Purchase Order shall
Date is the date on which goods shall be delivered constitute the entire Agreement between the parties
F.O.T dispatching point/destination in accordance with hereto. Changes will be binding only if the amendments
the terms of the Purchase Order. The contractual are made in writing and signed by an authorized
delivery date/period is inclusive of all the lead time for representative of the Purchaser.
engineering, procurement of raw materials,
manufacturing, inspection, testing packing and any 6. INSPECTION-CHECKING-TESTING:
other activities whatsoever required to be accomplished
for effecting the delivery at the agreed delivery point. The equipment, materials and workmanship covered by
the Purchase Order are subject to inspection and
“Procurement co-coordinators /Managers”: testing at any time prior to shipment and/or despatch
Purchaser’s authorized representative appointed as and to final inspection within a reasonable time after
procurement co-ordinators/ manager. arrival at the place of delivery. Inspectors shall have the
right to carry out the inspection and testing which will
“INSPECTORS”: Inspectors Inspectors deputed / include the raw materials at manufacturer’s shop, at
authorized by Purchaser including Third Party fabricator’s shop and at the time of actual despatch
Inspection Agency. before and after completion of packing.
CLIENT: client means Chennai Petroleum Corporation All tests, mechanical and others as specified in the
Limited. Purchase Requisition and particularly those required by
codes will be performed at Seller’s expenses and in
PROJECT: Resid Upgradation Project- Coker Block accordance with Inspector’s instructions. The Seller will
at Manali Refinery of Chennai Petroleum Corporation also bear the expenses concerning preparation and
Limited. rendering of tests required by Boiler Inspectorate or
such other statutory testing agencies or by Lloyds
PROJECT MANAGEMENT CONSULTANT” or Register of Shipping and Industrial Services as may be
“PMC” or “CONSULTANT” shall mean any person(s) required.
nominated by the OWNER as the Project
Management Consultant for the Project. The words The salaries and fees of Inspectors and their travelling,
“PROJECT MANAGEMENT CONSULTANT”, “PMC”& lodging and boarding expenses will not be borne by the
“CONSULTANT” are synonymous. M/s Jacobs Seller unless inspection becomes anfractuous due to
Engineering India Private Limited is the PMC for this any omission or commission on the part of the Seller.
Project. Before shipping or despatch, the equipment and/or
materials will have to be checked and stamped by
2. REFERENCE FOR DOCUMENTATION: Inspectors who are authorized also to forbid the use
A133-01-GPC (Ind.)-R0
Page 50 of 434 Page 2 of 7
and despatch of any equipment and/or materials which Inspectors to maintain Schedule and delay, if any, in
during tests and inspection fail to comply with the this process will not be taken into consideration as a
specification, codes and testing requirements. cause of Force Majeure.
- Inform Procurement Coordinator/Managers at The first filling of oils and lubricants, if any, required for
least eight days in advance of the exact place, every equipment shall be supplied inline with MR. The
date and time of rendering the equipment or Seller shall also recommend the quality / quantity of oils
materials for required inspection. and lubricants required for one-year continuous
operation.
- Provide free access as required to Inspectors
during normal and / or extended working hours 9. SPARE PARTS:
to Seller’s or his/its sub-Supplier’s works and
place at their disposal all useful means of The Seller must furnish item wise and priced list of
performing, checking, marking, testing, spare parts required for two years normal operation and
inspection and final stamping. maintenance of the equipment and prime movers also.
Even if the Inspections and tests are fully carried out, The Seller shall provide the necessary cross - sectional
Seller would not be absolved to any degree from his drawing to identify the spare parts numbers and their
responsibilities to ensure that all equipment and location as well as an inter-changeability chart.
material supplied comply strictly with requirements as
per agreement both during manufacturing, at the time of 10. TRANSIT RISK INSURANCE:
delivery, inspection, on arrival at site and after its
erection or start-up and guarantee period as stipulated The Purchaser against its/ Client’s Open General Policy
in Clause 23 herein. (The name of the Insurance Co. will be conveyed
subsequently) shall cover transit Risk Insurance. The
The Seller’s responsibility will not be lessened to any Seller shall advise the dispatch particulars to the
degree due to any comments made by Procurement Insurance Company under advice to the Procurement
Coordinators/Managers and Inspectors on the Seller’s Coordinators / Managers before shipment.
drawings or specifications or by inspectors witnessing
any chemical or physical tests. In any case, the 11. RESPECT FOR DELIVERY DATES:
equipment must be in strict accordance with the
Purchase Order and/or its attachments failing which the Time of delivery as mentioned in the Purchase Order
Purchaser shall have the right to reject the goods and shall be the essence of the agreement and no variation
hold the Seller liable for non-performance of contract. shall be permitted except with prior authorization in
writing from the Purchaser. Goods should be delivered
7. OFFICIAL INSTITUTIONAL TESTING: securely packed and in good order and condition at the
place and within the time specified in the Purchase
In addition to testing and inspection by Inspectors Order for their delivery. The Purchaser reserves the
mentioned above, Lloyds register Industrial services or right to defer the period of delivery in writing.
similar institutional agencies like Boiler-Inspectorate
may be assigned for official testing of all coded 12. DELAYED DELIVERY:
equipment. The Seller shall ensure that all Procedures
for preparation and Performance of test prescribed by The time and date of delivery of materials / equipment
such institution shall be complied scrupulously. as stipulated in the Order shall be deemed to be the
essence of the contract. In case of delay in execution
The Seller is required to send to such institutions as of the order beyond the date of delivery stipulated in the
may be designed by the Purchaser at least three sets of order or any extensions sanctioned, the Purchaser may
fabricated / manufactured drawings for each equipment at his option either:
and calculations. All manufacturer’s mill test certificates
and analytical reports from material laboratories in (i) Accept delayed delivery at prices reduced by as per
respect of all raw material and components employed Price Reduction Schedule Clause of RFQ.
shall have to be presented to such Institution’s
Inspectors in the number of copies required. Seller (ii) Cancel the order in part or full and purchase such
shall be responsible for any delay in submission of cancelled quantities from elsewhere on account and at
necessary certificates. The Seller shall maintain close risk and cost of the Seller, without prejudice to its right
liaison with Procurement Co-ordinators and Institution’s under (i) above in respect to goods delivered.
A133-01-GPC (Ind.)-R0
Page 51 of 434 Page 3 of 7
13. DELAYS DUE TO FORCE MAJEURE: The transfer of property shall be deemed to have taken
place as follows subject to the provisions herein
In the event of causes of Force Majeure occurring within contained:
the agreed delivery terms, the delivery dates can be
15.1 F.O.T. despatch point: On handing over the
extended by the Purchaser on receipt of application
equipment to the carrier against receipt and
from the Seller without imposition of penalty. Only
such receipt having been passed over to the
those causes which depend on natural calamities, wars
Purchaser.
and national strikes which have duration of more than
seven consecutive calendar days and Government Acts 15.2 Equipment sent freight/ carriage paid to the
and other direct legislative enforcement are considered
Refinery site: On receipt of goods at site.
the causes of Force Majeure.
15.3 Equipment erected by the Seller; on
The Seller must advise the Purchaser by a registered acceptance at job site.
letter duly certified by a local Chamber of Commerce or
15.4 Equipment commissioned by the Seller: On
statutory authorities, the beginning and the end of such
taking over by the Purchaser for regular
causes of delay immediately, but in no case later than
operation after test run at maximum capacity
10 days from the beginning and end of each cause of
for specified period satisfactorily performed.
such Force Majeure condition defined above.
16. PRICE:
The extension of time for completion of the work or any
part of the work or any operation(s) involved therein Unless otherwise agreed to in the terms of the
shall be the sole remedy of the Seller for any cause or Purchase Order, the price shall be:
event of delay and the Seller shall not be entitled in
addition to or in lieu of such extension to claim any a) Firm and not subject to escalation for any reasons
damages or compensation for extended stay or whatsoever till the execution of entire order even though
otherwise whether under the law governing contracts or it might be necessary for the order execution to take
quasi-Seller or any other relationship, and the Seller longer than the delivery period specified in the order.
hereby waives and disclaims any and all contrary rights.
b) Inclusive of adequate road worthy packing and
14. REJECTION, REMOVAL OF REJECTED forwarding charges upto effecting delivery at F.O.T.
GOODS AND REPLACEMENT: despatch point in all cases whenever F.O.T destination
delivery terms are agreed to but exclusive of transit
In case the testing and inspection at any stage by insurance.
Inspectors reveal that the equipment, material and
workmanship do not comply with the specification and c) Exclusive of Central/State Sales Tax, Excise Duty
requirements, the Seller at his/its own expense and risk and or such imposts which are leviable by law on sales
shall remove the same within the time allowed by the of finished goods to Purchaser and/or Octroi duty, if
Purchaser. The Purchaser shall be at liberty to dispose any, leviable at destination/ project site. The nature and
of such rejected goods in such a manner, as he may extent of such levies shall be shown separately.
think appropriate. In the event the Seller fails to remove
the rejected goods within the period as aforesaid, all 17. TERMS OF PAYMENT:
expenses incurred by the Purchaser for such disposal
shall be to the account of the Seller. The freight paid by Payment terms shall be as specified in the Inquiry /
the Purchaser, if any, on the inward journey of the Purchase Order.
rejected materials shall be reimbursed by the Seller to
the Purchaser before the rejected materials are Seller shall claim their invoice excluding Excise Duty.
removed by the Seller. The Excise Duty shall be released separately on receipt
of documents including Transporters copy of Invoice,
The Seller shall have to proceed with the replacement valid for availing CENVAT. In the event CPCL is not
of that equipment or part of the equipment at able to claim CENVAT, the amount of Excise Duty to
Purchaser’s stores / site, if so required by the that extent shall be recovered from the Seller.
Purchaser, without claiming any extra payment. The
time taken for replacement in such event will not be Seller shall ensure submission of proper documents for
added to the contractual delivery period. availing CENVAT/ VAT benefits of Service Tax/ VAT. In
case the documents are not found to be in order,
15. TRANSFER OF PROPERTY FROM THE amount of Service Tax/ VAT will be recovered from the
SELLER TO THE PURCHASER. Seller.
A133-01-GPC (Ind.)-R0
Page 52 of 434 Page 4 of 7
The Seller shall furnish to the Purchaser bank owned by the Seller.
guarantee / Cash Security. Bank Guarantee shall be
from a Scheduled/ Nationalized Bank in a form Upon receipt of the cancellation notice the Seller shall
approved by the Purchaser for an amount of 10% of the discontinue all work on the Purchase Order and matters
contract value as security for the due performance of all connected with it.
the Seller’s liability in terms of and/or in connection with
the contract. This security will be released after the The Purchaser in that event will be entitled to procure
expiry of the period of performance guarantee. the requirement in the open market and recover the
excess payment over the Vender’s agreed price, if any,
The financial settlement of Seller’s Invoice is liable to be from the Seller, reserving to itself the right to forfeit the
withheld in the event the Seller has not complied with security deposit, if any, made by the Seller against the
submission of drawing, data and such documentation contract. The Seller is aware that the said goods are
as called for in Purchase Order and/or as required required by the Purchaser for the ultimate purpose of
otherwise. material production and that non delivery may cause
loss of production and consequently loss or profit to the
18. RECOVERY OF SUMS DUE: Purchaser. In this event of the Purchaser exercising the
option to claim damages for non-delivery other than by
Whenever any claim against the Seller for payment of way of difference between the market price and the
sum of money arises out of or under the contract, the contract price, the Seller shall pay to the Purchaser, the
Purchaser shall be entitled to recover such sums from fair compensation to be agreed upon between the
any sum then due or which at any time thereafter may Purchaser and the Seller.
become due from the Seller under this or any other
contract with the Purchaser including right to encash the The provision of this clause shall not prejudice the right
PBG. In the event of encashment of PBG, the same of the Purchaser from invoking the provisions of clause
shall be re-stored to its original amount by the Seller “Delayed Delivery” as aforesaid.
and should this sum be not sufficient to cover the
recoverable amount, the Seller shall pay to the 21. PATENTS AND ROYALTIES:
Purchaser on demand the balance remaining due.
On acceptance of this order, the Seller will be deemed
19. CHANGES to have entirely indemnified the Purchaser and
Procurement Coordinators/Managers from any legal
The Purchaser has the option at any time to make action or claims regarding compensation for breach of
changes in quantities ordered or in specifications and patent rights which the Seller deems necessary to apply
drawings. If such changes cause an increase or for manufacturing the ordered equipment and/or
decrease in the price or in the time required for supply, materials or which can in any way be connected in the
an equitable, adjustment under this provision must be manufacture.
finalized within 10 days from the date when the change
is ordered. 22. CONTROL REGUALTIONS:
iii) The Seller becomes bankrupt or goes into The Seller shall guarantee that any and all materials
liquidation. used in execution of the Purchase Order shall be in
strict compliance with characteristics, requirements and
iv) The Seller makes a general assignment for specifications agreed upon and that the same shall be
the benefit of creditors. free from any defects. Checking of the Seller’s drawings
by Procurement Co-coordinators/ Managers and their
v) A receiver is appointed for any of the property approval and permission to ship or despatch the
A133-01-GPC (Ind.)-R0
Page 53 of 434 Page 5 of 7
equipment and materials guaranteed by Inspectors 27. SELLER’S DRAWING AND DATA
shall not relieve the Seller from any part of his/its REQUIREMENT:
responsibilities of proper fulfillment of the requirement.
The Seller will guarantee that all materials and The Seller shall submit drawings, data and
equipment shall be repaired or replaced as the case documentation in accordance with but not limited to
may be, at his own expense in case the same have what is specified in the requisition and/or in the Seller
been found to be defective in respect of materials, drawings and data form attached to the Purchase
workmanship or smooth and rated operation within Requisition and as called for in Clause 8, viz. Expediting
Guarantee Period as stipulated in the RFQ document. above. Types, quantities and time limits of submitting
this must be respected in its entirety failing which the
The guarantee period for the replaced parts shall be 18 Purchase Order shall not be deemed to have been
months starting from the date on which the executed for all purposes including settlement of
replacements are put in service or period as specified payment since the said submission is an integral part of
above in case of critical items, whichever is later. Purchase Order execution.
Acceptance by the Purchaser or Inspectors of any
equipment and materials or their replacement will not 28. TECHNICAL INFORMATION:
relieve the Seller of his/its responsibility concerning the
above guarantee. Drawings, specifications and details shall be the
property of the Purchaser and shall be returned by the
The Seller shall furnish a Bank Guarantee for 10% of Seller on demand. The Seller shall not make use of
total of total order value (as per proforma hereunder) to drawings and specifications for any purpose at any time
support Seller’s performance. This bank guarantee save and except for the purpose of the Purchaser.
shall remain in force for the entire period covered in
Performance Guarantee plus three months. The Seller shall not disclose the technical information
furnished to or gained by the Seller under or by virtue of
24. NON-WAIVER: or as a result of the implementation of the Purchase
Order to any person, firm or body or Corporate authority
Failure of the Purchaser / Procurement Coordinators/ and shall make all endeavours to ensure that the
Managers to insist upon any of the terms or conditions technical information is kept CONFIDENTIAL. The
incorporated in the Purchase Order or failure or delay to technical information imparted and supplied to the
exercise any rights or remedies herein or by law or Seller by the Purchaser shall at all times remain the
failure to properly notify Seller in the event of breach, or absolute property of the Purchaser.
the acceptance of or payment of any goods hereunder
or approval of design shall not release the Seller and 29. PROGRESS CHART AND EXPEDITING:
shall not be deemed a waiver of any right of the
Purchaser / Procurement Coordinators/Managers to The Seller shall submit to EIL within four (4) weeks from
insist upon the strict performance thereof or any of his the date of Fax Of Acceptance a BAR CHART showing
or their rights or remedies as to any such goods start and finish dates for various activities forming part
regardless of when goods are shipped received or of the execution of the order and identifying the delivery
accepted nor shall any purported oral modification or dates to this activity schedule. Seller shall update this
revisions of the order by Purchaser/ Procurement bar chart every fortnight showing the actual
Coordinators/Managers act as waiver of the terms performance of the activities and if and how the delivery
hereof. date has been affected thereby. Copies of the updated
bar chart will also be submitted for review of the
25. NON ASSIGNMENT: progress of the order.
The Seller without obtaining prior written consent of the Procurement Coordinator/Managers have been
Purchaser shall not assign the Purchase Order to any assigned to expedite both manufacture and shipment of
other agency. equipment and materials covered by the Purchase
Order. The Procurement Co-coordinator/ Managers
26. PART ORDER/ REPEAT ORDER shall have free access to Seller’s shop and/or sub-
Supplier’s shop at any time and they shall be provided
Seller hereby agrees to accept part order at Purchasers all the necessary assistance and information to help
option without any limitation whatsoever and also them perform their job.
accept repeat order(s) during a period of 6 months from
the date of original purchase order on same unit prices, In order to facilitate over-all execution of the order within
terms and conditions. the contractual delivery date, Seller shall furnish to
Procurement Coordinator / Manager within 4 weeks of
A133-01-GPC (Ind.)-R0
Page 54 of 434 Page 6 of 7
receipt of Purchase Order in required number of copies c) The Seller shall give a firm and binding list of
of documents / detailed drawings such as but not Purchasers issue of materials which shall be duly
limited to schedule/PERT chart, unpriced copies of sub reviewed & approved by EIL and the desired schedule
orders/sub contracts, phased program of itemize of its delivery to shop floor strictly in accordance with
manufacturing, testing and delivery and any other the sequence of fabrication vis-a-vis the contractual
information/documentation as may be called for by the delivery period.
Procurement Coordinators/Managers. All post order
correspondence shall be addressed to the DGM d) Unused materials or scrap from material supplied by
(Inspection), with a copy to the Project Manager, the Purchaser to the Seller shall be returned by the
Engineers India Ltd., New Delhi. Seller to the Purchaser or if the Purchaser so directs the
Seller may dispose of the same by sale or otherwise on
30. SERVICES OF SELLER’S PERSONNEL: such terms and conditions as the Purchaser may
stipulate and the Seller shall pay to the Purchaser the
Upon three week advance notice, the Seller shall sale proceeds of the material so disposed off by sale
depute the necessary personnel along with required deducting there from expenses incurred by the Seller on
Tools & Tackles to site for supervision of erection and such sale, the quantum of such deduction to be
start up of the equipment and train a few of the IOCL/ mutually agreed upon in advance between the
EIL’s personnel for the operation and maintenance of Purchaser and the Seller.
the equipment, if required by the Purchaser. The terms
and conditions for the services of the Seller shall be 33. HEADINGS:
mutually settled.
The headings of the conditions hereof shall not affect
31. SELLER’S LIABILITIES construction thereof.
A133-01-GPC (Ind.)-R0
Page 55 of 434 Page 7 of 7
Page 56 of 434
Page 57 of 434
Page 58 of 434
Page 59 of 434
Page 60 of 434
Page 61 of 434
Page 62 of 434
PROFORMA OF BANK GUARANTEE
(PERFORMANCE)
(On non-judicial stamp paper of appropriate value)
(For Indigenous Suppliers)
To
Engineers India Limited
Engineers India Bhawan
1 Bhikaiji Cama Place
R.K. Puram
New Delhi – 110 066
Kind Att.: Head (LSTK-Finance)
RFQ NO.: _______________________
Dear Sirs,
In consideration of the Engineers India Limited, 1 Bhikaiji Cama Place, R.K. Puram, New Delhi-110066 (hereinafter
called – “the Purchaser” which expression shall include its successors and assigns having awarded
________________________________ work to M/s (Name) _______________________________________
(Constitution) ___________________________ (Address) _____________________________ (hereinafter referred
to as “the Supplier” which expression shall wherever the subject or context so permits include its successors and
assigns) a supply contract in terms inter-alia, of the Purchaser’s Letter No. ______________________ dated
__________ hereinafter referred to as the “Contract” and the general purchase conditions of the purchaser and upon
the condition of Supplier’s furnishing security for the Performance of the Supplier’s obligations and/or discharge of the
Supplier’s liabilities under and/or in connection with the said supply contract for a sum of Rs.
_______________________ only amounting to 10% (ten percent) of the total contract value.
1. This Guarantee/Undertaking shall be a continuing Guarantee/Undertaking and shall remain valid and
irrevocable for all claims of the Purchaser and liabilities of the Supplier arising upto and until ___________
plus claim period of 3 months.
2. This Guarantee/Undertaking shall be in addition to any other guarantee or security whatsoever that the
Purchaser may now or at any time have in relation to the Supplier’s obligations liabilities under and/or in
connection with the said supply contract and the Purchaser shall have full authority to take recourse to or
reinforce this security in preference to the other security(ies) at its sole discretion, and no failure on the part
of the Purchaser in enforcing or requiring enforcement of any other security shall have the effect of releasing
the Bank from its full liability hereunder.
3. The Purchaser shall be at liberty without reference to the Bank and without affecting the full liability of the
Bank hereunder to take an other security in respect of the Supplier’s obligation and/or liabilities under or in
connection with the said supply contract and to vary the terms vis-à-vis the Supplier of the said supply
contract or to grant time and/or indulgence to the Supplier or to reduce or to increase or otherwise vary the
prices of the total contract value or to release or to forebear from enforcement of all or any of the obligations
of the Supplier under the said supply contract and/or the remedies of the Purchaser under any other
Guarantee(s) or Security(ies) now or hereafter held by the Purchaser and no such dealing(s), variation(s),
reduction(s) or other indulgence(s) or arrangement(s) with the Supplier or release or forbearance whatsoever
shall have the effect of releasing the Bank from its full liability to the Purchaser hereunder or of prejudicing
rights of the Purchaser against the Bank.
4. This Guarantee/Undertaking shall not be determined or affected by the liquidation or winding up, dissolution,
or change of constitution or insolvency of the Supplier or any change in the legal constitution of the Bank or
of the Purchaser.
Page 63 of 434
5. Bank hereby waives all rights at any time inconsistent with the terms of this Guarantee/Undertaking and the
obligations of the Bank in terms hereof shall not be anywise affected or suspended by reasons of any dispute
or disputes having been raised by the Supplier (whether or not pending before any Arbitrator, Officer,
Tribunal or Court) or any denial of liability by the Supplier or any other order for Communication whatsoever
by the Supplier stopping or preventing or purporting to stop or prevent any payment by the Bank to the
Purchaser in terms hereof.
(a) The Bank’s liability under this Guarantee/Undertaking shall not exceed Rs._____________ (In
figures) ______________________ (In words) ____________________________ only).
(b) This Guarantee/Undertaking shall remain in force upto _____________ and any extension(s)
thereof, if any; and
(c) The Bank shall be released and discharged from all liability under this Guarantee/Undertaking
unless a written claim or demand is issued to the Bank on or before _____________ plus 3 months
period or the date of expiry of any extension(s) thereof if this guarantee/undertaking has been
extended.
7. The Bank doth hereby declares that Shri ______________________ (name & designation of the person
authorized to sign on behalf of the Bank) is authorized to sign this Guarantee/Undertaking on behalf of the
Bank and to bind the Bank thereby.
Yours faithfully,
(Signature)
NOTE
1. This Guarantee is required to be stamped as an agreement according to the Stamp Duty Act.
2. The Performance Bank Guarantee shall be strictly as per above proforma and shall be through Indian or
Foreign Branches of Indian Scheduled Banks (other than Cooperative Bank)/Nationalized Bank or Indian
Branches of Foreign Banks.
3. The bank shall provide details viz contact person, telephone number, fax number, e-mail address and
address of the Controlling/Regional Office of issuing bank for verification of authenticity of Bank Guarantee.
4. This Guarantee is required to be sent by Seller’s Bankers directly to the Head (LSTK-Finance), Engineers
rd
India Limited, EI Bhawan, 3 Floor, 1, Bhikaiji Cama Place, New Delhi-110066.
Page 64 of 434
PROFORMA OF BANK GUARANTEE
ADVANCE (INDIGENOUS)
(On non-judicial stamp paper of appropriate value)
To
Engineers India Limited
1 Bhikaiji Cama Place
New Delhi – 110 066
Attn.: Head (LSTK-Finance)
Project ______________________
RFQ No. _____________________
Dear Sirs,
Engineers India Limited, 1, Bhikaiji Cama Place, New Delhi-110066 (hereinafter called – “the Purchaser” which
expression shall include its successors and assigns) has awarded M/s ____________________________________
(hereinafter called “The Supplier” which expression shall include its successors and assigns) the work of designing,
manufacturing, fabricating and supply of ______________________ in terms of a contract as constituted by Purchase
Order No. ____________________ dated _________________ issued by the Purchaser to the Supplier (hereinafter
called “The Contract” which expression include all the amendments and/or modifications of the Purchase Oder).
AND WHEREAS the Purchaser has agreed to advance the Supplier a sum of Rs._________________ (Rupees
_________________________________________________) hereinafter called “The Advance” as financial
assistance to the Supplier under the Contract on the condition, inter alia, that the advance shall be secured by a Bank
Guarantee as hereinafter appearing:
(i) The Purchaser shall have the fullest liberty without reference to the Bank and without affecting in any way the
liability of the Bank under this Guarantee/Undertaking, at any time and/or from time to time to anywise vary
the Contract and/or any of terms and conditions thereof or of or relative to the advance and to extend time for
the performance of the Contract and/or repayment of the advance or to postpone for any time or from time to
time the obligations of the Supplier and to waive or postpone exercise of any of the rights available to the
Purchaser against the Supplier or to forebear from enforcing any of the terms or conditions of the Contract
and/or the advance or any security(ies) available to the Purchaser, AND the liability of the Bank shall remain
in full force and effect notwithstanding any exercise by the Purchaser of the liberty with reference to any or all
the matters aforesaid or by reason of time being given to the Supplier or any forbearance, waiver, act or
omission on the part of the Purchaser or any indulgence by the Purchaser to the Supplier or any other act,
matter or thing whatsoever which under the law relating to sureties would have the effect of releasing the
Bank from its liability hereunder or any part thereof, AND the BANK DOTH HEREBY waive all rights at any
time inconsistent with the terms of this Guarantee/Undertaking.
(ii) It shall not be necessary for the Purchaser to proceed against the Supplier before proceeding against the
Bank and this guarantee/undertaking shall be enforceable against the Bank as principal debtor
notwithstanding the existence of any other security for any indebtedness of the Supplier to the Purchaser
(including relative to the advance) and notwithstanding that any such security shall at the time when claim is
made against the Bank or proceedings taken against the Bank be outstanding or unrealized.
(iii) As between the Bank and the Purchaser for the purpose of this guarantee/undertaking the amount claimed
by the Purchaser from the Bank with reference to this guarantee/ undertaking shall be final and binding upon
the bank as to the amount payable by the Bank to the Purchaser hereunder.
Page 65 of 434
(iv) The liability of the Bank to the Purchaser under this guarantee/undertaking shall remain in full force and
effect notwithstanding the existence of any difference or dispute between the Supplier and the Purchaser,
the Supplier and the Bank and/or the Bank and the Purchaser, or otherwise howsoever touching or affecting
these presents or the liability of the Supplier to the Purchaser, and notwithstanding the existence of any
instructions or purported instructions of the Supplier or any other person(s) to the Bank not to pay or for any
cause withhold or defer payment to the Purchaser under these presents with the intent that notwithstanding
the existence of such difference, dispute or instruction, the Bank shall be and remain liable to make payment
to the Purchaser.
(v) This guarantee/undertaking shall not be affected by any change in the constitution of the Bank or that of the
Supplier or the Purchaser, or any irregularity in the exercise of borrowing powers by or on behalf of the
Supplier.
(vi) This guarantee/undertaking shall be valid for all claims/demands made by the Purchaser to or upon us upto
____________________ provided always that if for any reasons, the Supplier is unable to complete supplies
under the Contract, the Bank shall at the request of the Purchaser and without recourse to the Supplier
extend the validity of this guarantee/undertaking for a further period of six months. For the purpose of this
clause, the Purchaser’s statement that the Supplier is unable to complete supplies under the contract shall
be conclusive and final binding on us.
(a) The Bank’s liability under this Guarantee/Undertaking shall not exceed Rs. _______ (Rupees
__________________________________only).
(b) This Guarantee/Undertaking shall remain in force upto ______________ and any extension(s)
thereof; and
(c) The Bank shall be released and discharged from all liability under this Guarantee/ Undertaking
unless a written claim or demand is issued to the Bank on or before ________ plus 3 months claim
period, or the date of expiry of any extension(s) thereof if this guarantee/undertaking has been
extended.
(viii) The Bank DOTH HEREBY declare that Mr. ______________ (name of the person signing on behalf of the
Bank) who is _____________ (his designation), is authorized to sign this guarantee/undertaking on behalf of
the Bank and to bind the Bank thereby.
Dated this ________________________ day of ______________
Yours faithfully,
For _____________________________________________
Signature ________________________________________
NOTE
1. This Guarantee is required to be stamped as an agreement according to the Stamp Duty Act.
2. The Performance Bank Guarantee shall be strictly as per above proforma and shall be through Indian or
Foreign Branches of Indian Scheduled Banks (other than Cooperative Bank)/Nationalized Bank or Indian
Branches of Foreign Banks.
3. The bank shall provide details viz contact person, telephone number, fax number, e-mail address and
address of the Controlling/Regional Office of issuing bank for verification of authenticity of Bank Guarantee.
4. This Guarantee is required to be sent by Seller’s Bankers directly to the Head (LSTK-Finance), Engineers
rd
India Limited, EI Bhawan, 3 Floor, 1, Bhikaiji Cama Place, New Delhi-110066.
Page 66 of 434
JOB NO. A133
ENGINEERS INDIA LIMITED
RESID UPGRADATION PROJECT – COKER BLOCK OF CPCL, CHENNAI
PRE-FILLED AGREED TERMS & CONDITIONS (FOR INDIGENOUS SUPPIERS)
BIDDER’s NAME : M/s._____________________________________________________________________________
RFQ No.: ________________________________________________________________________________________
Bidder’s Offer Ref. No. :____________________________________________________________________________
Tel No. : ____________________________________ Fax No.:_____________________________________________
Contact Person :________________________E-Mail:______________________Mobile No:_____________________
Present rate of Excise Duty + Education Cess payable extra against Indicated
b)
documentary evidence on finished products (including spares). (Refer ANNEXURE – I
Indicated
c) Maximum rate applicable (If present rate is nil or concessional)
2 (Refer ANNEXURE – I)
Clarify whether Excise Duty + Education Cess will be applicable on freight Indicated
d)
charges also. (Refer ANNEXURE – I)
Please indicate following break-up
Indicated
e) I) Cenvatable [Excise Duty + Educational Cess]
(Refer ANNEXURE – I)
II) Non Cenvatable
Sales Tax:
Indicated
a) Sales tax payable extra Specify CST/ Tamilnadu VAT (TN VAT) on sale of
(Refer ANNEXURE – I)
goods.
*In case of CST, C form shall be provided.
3 b)
In case of TN VAT, no concessional form shall be provided. TN VAT shall be Confirmed
reimbursed to bidder subject to submission of requisite documents
enabling owner to avail “INPUT CREDIT’ for the same.
EIL/CPCL shall avail credit of 100% of TN VAT on sale of goods. TN VAT shall
c) be reimbursed to bidder subject to submission of requisite documents Confirmed
enabling EIL/IOCL to avail ‘INPUT CREDIT’ for the same.
Page 67 of 434
S. No. DESCRIPTION BIDDER’S CONFIRMATION
Clarify whether CST / TN VAT on sale of goods will be applicable on freight Indicated
d)
charges also. (Refer ANNEXURE – I)
Indigenous suppliers shall issue E1/E2 form on quarterly basis within 60
days after completion of each quarter based on “C” form no. provided by
e) Confirmed
PURCHASER. PURCHASER will provide original “C” form in exchange of
original E1/E2 form.
In case Excise Duty / CST / TN VAT are stated as not applicable on freight
charges presently, and if they are applicable at the time of delivery due to
4 Confirmed
any reasons other than statutory, the same will be borne by the Bidder.
Confirm compliance.
Only statutory variations, if any, in the present rate of Service Tax,
cenvatable excise duty, Central Sales Tax and VAT amount for which input
a) Confirmed
tax credit is available to the EIL under TN VAT Act etc. shall be to EIL’s
account subject to documentary evidence to be furnished by the bidder.
5 Statutory variations on non-cenvatable excise duty shall be to SUPPLIER’s
b) Confirmed
account.
However, any variation in Excise duty + Ed. Cess at the time of supplies for
c) any reasons, other than statutory, including variations due to turnover, Confirmed
shall be borne by bidder.
VAT on Works Contract:
Confirmed
a) Wherever site job is involved, bidders to quote their prices inclusive of TN
VAT on work contracts (if applicable).
Only single order covering complete scope of supply & services will be
6 b) issued (indicating supply and services portion separately). Order for supply Confirmed
and services shall not be split.
Any statutory variation on TN VAT on work contracts or change in rate of
c) TN VAT due to wrong assessment by supplier shall be to supplier’s Confirmed
account.
Service Tax:
a) Service Tax on freight charges shall be included in the quoted Freight Confirmed
Charges.
Percentage of Cenvatable Service Tax applicable extra on Site Work Indicated (Refer Annexure I)
Charges, , if applicable as per MR.
b)
Service tax shall be paid only against a cenvatable invoice issued in Confirmed
accordance with Service Tax rules.
Percentage of Cenvatable Service Tax applicable extra on Supervision Indicated (Refer Annexure I)
Charges, if applicable as per MR.
c)
7 Service tax shall be paid only against a cenvatable invoice issued in Confirmed
accordance with Service Tax rules.
Percentage of Cenvatable Service Tax applicable extra on AMC Charges, if Indicated (Refer Annexure I)
applicable as per MR.
d)
Service tax shall be paid only against a cenvatable invoice issued in Confirmed
accordance with Service Tax rules.
Percentage of Cenvatable Service Tax applicable extra on Training Indicated (Refer Annexure I)
Charges, if applicable as per MR.
e)
Service tax shall be paid only against a cenvatable invoice issued in Confirmed
accordance with Service Tax rules.
Page 68 of 434
S. No. DESCRIPTION BIDDER’S CONFIRMATION
Entry Tax and Octroi:
Entry Tax / Octroi and Terminal Taxes are presently not applicable. If
8 a) applicable at a later date, same shall be payable extra at actual on Confirmed
production of necessary Documents/Invoices and information. Confirm
Compliance.
All new taxes/duties/cess/levies notified after the last date of submission
of final price bid/price implication, but within contractual delivery
/completion period, shall be to EIL’s account. These shall be reimbursed
a) against documentary evidence. Confirmed
9 However, in case of delay on account of supplier, any new or additional
taxes and duties imposed after contractual delivery shall be to supplier’s
account. Confirm compliance.
Any errors of interpretation of applicability of taxes/duties by bidders shall
b) Confirmed
be to bidders’ account.
Price Reduction Schedule:
a) Acceptance of applicable Price Reduction Schedule for delayed delivery as Confirmed
10 specified in RFQ.
In case of delay in delivery, bills shall be submitted after deducting price
b) Confirmed
reduction for delay.
Delivery Period / Completion Period:
11 Please confirm delivery/completion period as specified in RFQ Covering Confirmed
Letter.
Payment Terms:
a) Confirmed
Acceptance of applicable Payment terms as specified in RFQ.
Payment shall be released through Electronic Clearing System (ECS).
12 Furnished
In view of this, confirm that necessary details such as name of bank, bank
b) account no. etc. as per Mandate Form enclosed with RFQ, has been
furnished duly attested by your bank alongwith a cancelled cheque, along (Refer ANNEXURE – II)
with your offer (as per Annexure-II to ATC).
Part Order:
a) Confirmed
Acceptance of Part Order as per GPC (Indigenous).
13
Any charges quoted extra as lumpsum shall be applicable prorata on value
b) Confirmed
basis in the event of part order.
Repeat Order:
14 Acceptance of repeat order as per the clause specified in GPC (Indigenous), Confirmed
if applicable as per RFQ covering letter.
Performance Bank Guarantee:
a) Submission of Performance Bank Guarantee for 10% of total order value as Confirmed
15 per General Purchase Conditions (GPC)/ Instructions to Bidders.
Indemnity Bond/Corporate Guarantee in lieu of PBG shall not be
b) Confirmed
considered.
Guarantee :
16 Confirm acceptance of Guarantee period & terms as per Instruction to Confirmed
Bidders/General Purchase Conditions (Indigenous).
Firmness of prices:
17 The prices shall be firm and fixed and not subject to any variation, Confirmed
whatsoever.
Page 69 of 434
S. No. DESCRIPTION BIDDER’S CONFIRMATION
CIF Value of Built in Import Content and Import Duties:
a) In case of any Built-in import content considered in your offer, details of Confirmed
items to be furnished in Annexure-I.
Confirm that quoted prices are based on Merit rate of Customs duty, CVD,
b) Confirmed
Educational Cess and SAD as applicable.
18
Quoted prices shall remain firm and fixed on account of FE variation and
c) Confirmed
Custom Duty Variation, till complete execution of the order.
d) EIL shall not provide any import license. Noted
Quoted prices are after considering the benefit of CENVAT on CVD
e) Confirmed
including Edu. Cess.
Testing charges:
19 Confirm that quoted prices are inclusive of all testing charges as per Confirmed
Material Requisition.
Third Party Inspection charges:
a) Goods and services shall be subject to stagewise and final inspection by Confirmed
CEIL.
The TPI charges for Certification Engineers India Ltd. (CEIL) as TPI agency
20 b) Confirmed
shall be borne by EIL.
All built in import content shall be subject to inspection by TPI (out of M/s.
Lloyds Register (Country of origin), M/s.Bureau Veritas(BV) and M/s.TUV
c) Confirmed
Nord) for which charges are included in quoted price and no additional
charges shall be paid by EIL.
Validity:
a) Confirm that the Offer is valid for period as mentioned in RFQ covering Confirmed
letter from the bid due date/ extended due date.
21 For 2 years O&M spares, prices shall be kept valid for a period of 2 years
b) Confirmed
from the date of order of main equipment.
Confirm that Annual % escalation for subsequent two years beyond the
c) validity of 2 years for O&M spares have been quoted in format for prices Confirmed
for O&M spares.
Confirm acceptance in totality to the following :
General Purchase Conditions (GPC) indigenous Confirmed
Instructions to Bidders Confirmed
Terms & Conditions for supervision of Erection, Testing & Confirmed
22
Commissioning (if applicable).
Terms & Conditions for site work (if applicable). Confirmed
Terms & Conditions for Annual Maintenance Contract (if applicable). Confirmed
All other terms & conditions of RFQ covering letter. Confirmed
Confirm that you have furnished the following documents in the offer:
a) Integrity Pact Furnished
23
b) Solvency Certificate Furnished
c) Concurrent / Present Commitment Furnished
Page 70 of 434
S. No. DESCRIPTION BIDDER’S CONFIRMATION
Confirm the list, wherever required as per MR, has been submitted for
following :
a) Mandatory Spares (if specified in MR) Confirmed
b) Commissioning Spares (as included in main item) Confirmed
24
c) Special tools & tackles (if required) Confirmed
d) Recommended Spares for two years normal operation & maintenance (if Confirmed
required)
e) First fill of consumables, lubricant, etc Confirmed
Confirm that you have quoted strictly for items based on your registration
25 Confirmed
/ approval with EIL on the date of issue of RFQ.
Furnish Annual Report containing Balance Sheet & Profit & Loss Statement
26 Enclosed
for last one (01) years along with your unpriced offer.
Confirm that net worth of your company (bidder) during the last financial
27 Confirmed
year is positive.
Whether any of the Directors of Bidder is a relative of any Director of EIL
or the Bidder is a firm in which any Director of EIL or his relative is a
28 No
partner of the Bidder or a private company in which any Director of EIL is a
Director.
Please confirm you have not been banned or delisted by any Government
29 or Quasi Government agencies or PSUs. If you have been banned, then this Confirmed
fact must be clearly stated.
Deviations to Terms & Conditions shall lead to loading of prices or
30 Confirmed
rejection of offer as per Instructions to Bidders. Please confirm.
Printed terms and conditions, if any, appearing in quotation, shall not be
applicable in the event of order. In case of contradiction between the
31 Confirmed
confirmations given above and terms & conditions mentioned elsewhere
in the offer, the confirmation given herein above shall prevail.
Page 71 of 434
ANNEXURE – I TO PRE-FILLED AGREED TERMS & CONDITIONS (FOR INDIGENOUS SUPPIERS)
NAME OF BIDDER : _______________________________________________________________________
OFFER REFERANCE: ________________________________________________ DATED ________________
RFQ NO.: _______________________________________________________________________________
ITEM : ________________________________________________________________________________
PROJECT : RESID UPGRADATION PROJECT – COKER BLOCK OF CPCL, CHENNAI
16.
(a) The bidder is a Micro or Small Enterprise under the Micro, Small & YES NO
Medium Enterprises Development Act, 2006.
(b) Documentary evidence required as per RFQ to avail preference to FURNISHED
MSEs.
Page 72 of 434
ANNEXURE - II TO AGREED TERMS & CONDITONS (INDIGINEOUS)
MANDATE FORM
1. Bidder Name :
2. Bidder Code: :
I/ we declare that the particulars given above are correct and complete and I/ we accord our consent for
receiving all our payments through Electronic Mechanism.
____________________________________________________
(Signature and designation of the Authorised person(s) of Bidder)
BANK CERTIFICATION
Certified that the particulars furnished above are correct as per our records.
Place :
Date :
______________________________________
Signature of the Authorised Official of the Bank
Bank’s Stamp
Page 73 of 434
Appendix ‐ A to ITB
Terms and conditions for Reverse Auction
1 Owner / Purchaser reserves the right to go in for reverse auction among the
technically and commercially acceptable bidders. The decision to conduct reverse
auction or not, will be conveyed to short listed bidders prior to opening of price bid.
In view of this, the bidders must quote most competitive prices in the first instance
itself.
2 Once the decision to conduct Reverse Auction is conveyed to the bidders, it will be
mandatory for the bidders to participate in Reverse Auction, failing which, the
bidder shall be liable for punitive action including but not limited to rejection of
offer, encashment of bid security, wherever applicable, etc. For this purpose, even
log‐in to the system shall be construed as participation.
3 Schedule for Reverse Auction
The Reverse Auction shall be scheduled for a duration of two hours. If a bidder
places a Bid in the last 5 minutes of scheduled closing time of the Auction, the
Auction time shall get extended automatically for another 5 minutes from the time
of the last Bid placed. In case, there is no Bid in the last 5 minutes of closing of the
Auction, the Auction shall be closed automatically without any extension.
The above provision shall apply to the bids in extended time also.
4 Auction process
- Each Bidder shall be assigned a Unique User Name & Password. The Bidders are
requested to change the Password and edit the information in the Registration
Page after the receipt of initial Password. All bids using the Login ID given to
the bidder will be deemed to have been submitted by the bidders. During the
auction, bidders will be referred by proxy names as B1, B2, B3, etc. and identity
will not be disclosed.
- The Reverse Auction shall be conducted based on the lowest evaluated price
out of all the techno‐commercially acceptable bidders, based on the prices
submitted along with the bid, as the opening price. The Bidder shall be able to
bid lower than the opening price in multiples of the decrement, but a Bidder
must always bid lower than the Lowest Bid.
- Only one bidder shall be at a particular position / rank, which means only one
L1.
Page 1 of 4
Page 74 of 434
- The Bidder shall be able to view the following on his screen along with the
necessary fields:
i) Opening Price.
ii) Leading Bid in the Auction, i.e., the lowest bid.
iii) Bid placed by him.
At no point of time will any bidder see the names of other bidders, or the
prices of bidders other than the lowest bid.
- A bidder can continue to revise his bid till the auction ends. However, the
Bidder cannot quote / Bid equal to the Leading / Lowest Bid. He must always
quote lower than the Leading / Lowest Bid.
- The evaluation criteria is based on Price alone. The Bidder who quotes the
lowest evaluated Price is determined as the lowest bidder.
- However, if Reverse Auction does not lead to any bid, EIL shall reserve the right
to award the job based on the lowest prices quoted in sealed envelope.
- Apart from the participating bidders, the Reverse Auction shall be visible, while
in progress to authorized officials of Owner / Purchaser, who are monitoring
the process.
5 Bid Price
The price shall be based on the scope, technical specifications and commercial
terms & conditions and other part of Bidding document agreed upto the date of
reverse auction.
The Opening Price and the Bid Decrement shall be displayed on the auction site at
the start of the auction. However, the bidders shall be able to view the auction
details, generally, 15 to 30 minutes before the start of actual auction.
6 Bid Decrement
Shall be 0.1% of the Opening Price. The bidder to lower the bid in multiples of the
bid decrement.
7 Bidding Currency
Bidding will be conducted in Indian Rupees (INR).
Page 2 of 4
Page 75 of 434
8 Bid Validity
The Bid Price submitted in the reverse auction shall be firm and valid for
acceptance for a period of 15 days from the date of reverse auction and shall not be
subject to any change whatsoever.
9 Bids once placed, binding on the Bidder
The bid of the bidder will be taken to be an offer to sell. Bids once submitted by
the bidder cannot be cancelled. The bidder is bound to sell the material/services at
the price that they bid. Should any bidder back out and not accept the order as per
the rates quoted, Owner / Purchaser reserves the right to take action as considered
appropriate, including encashment of bid security and placement on Holiday /
Negative list etc.
10 Lowest bid of a Bidder
During the process of reverse auction, the bidder may submit several bids. In case
the bidder submits such multiple bids, the lowest bid will be considered as the
bidder’s final offer to sell.
11 Submission of final prices by successful bidder
Successful bidder shall be required to submit the final prices, quoted during the
Reverse Auction in an appropriate format within two days of the completion of
Auction to EIL, duly signed and stamped as token of acceptance without any new
condition. However, in case the reverse auction is for a package, within 2 working
days after completion of the online event of Reverse Auction, the successful bidder
would submit their cost break down as per the price format for the final price
arrived at after reverse auction.
12 General
- The bidders may quote from their own offices/ place of their choice. Internet
connectivity shall have to be ensured by each agency on its own. In extreme
case of failure of internet connectivity, (due to unforeseen circumstances other
than power failure), communication shall have to be sent by fax/E‐mail/ phone
immediately. Owner / Purchaser shall extend the bidding time, in such a case,
appropriately (generally by half an hour) but not more than once per bidder.
- The Bidder, himself or any of his representatives, shall not involve in Price
manipulation of any kind directly or indirectly by communicating with other
bidder.
Page 3 of 4
Page 76 of 434
- The Bidder shall not divulge either his Bids or any other exclusive details of
Owner / Purchaser to any other party.
- Bidders agree to non‐disclosure of trade information regarding the purchase,
identity of EIL, bid process, bid technology, bid documentation and bid details.
- Owner / Purchaser can decide to extend, reschedule or cancel any Auction. No
bidder can claim any kind of compensation on account of the same.
- Owner / Purchaser shall not have any liability to Bidders for any interruption or
delay in access to the site irrespective of the cause.
- Owner / Purchaser shall not be responsible for any direct / indirect /
consequential losses / damages, on account of systems problems, inability to
use the system, loss of electronic information etc.
- Owner / Purchaser shall be at liberty to cancel the reverse auction process /
tender at any time, before ordering, without assigning any reason.
- Owner / Purchaser’s decision on award of Contract shall be final and binding on
all the Bidders.
Page 4 of 4
Page 77 of 434
Page 78 of 434
Page 79 of 434
Page 80 of 434
Page 81 of 434
NOZZLES AND CONNECTIONS GENERAL NOTES SPECIFICATIONS DESIGN DATA
MARK QTY
NOM.
SCH./THK
FLANGES PROJECTION PAD
SERVICE
UNLESS STATED OTHER WISE X DENOTES APPLICABLITY CODE ASME SEC. VIII DIV.1 2010+ADDENDA 2011
DIA CLASS TYPE FACING NOTE-4 WxT 1 ALL DIMENSIONS ARE IN MM UNLESS STATED OTHER WISE. WORKING PRESSURE (kg/cm2g) 13.9
INT:
SEE 2 ALL ANCHOR BOLT HOLES TO STRADDLE N/S CENTRE LINE. DESIGN PRESSURE (NOTE-11) (kg/cm2g) 16.8 EXT F.V. @ 190°C
1 1 600 22 THK. 300 WN RF 255X22 MANHOLE + B.F.+DAVIT 0
TOP/
DWG. 3 NORTH DIRECTION WHEREVER SHOWN IS WITH RESPECT TO PLAN VIEW. WORKING TEMPERATURE ( C) 40
4 (A) FOR NOZZLES ON SHELL PROJECTIONS ARE REFERRED FROM VESSEL JACOBS SPECIFICATIONS DESIGN TEMPERATURE
0
( C) 85
7 1 80 160 300 WN RF 1525 55X22 VAPOR OUTLET TO 86-E-06 CENTER LINE TO FLANGE CONTACT FACE.
X GENERAL SPECIFICATION FOR PRESSURE VESSELS 44NC-4600-0000-V.02.-0101-A4 MDMT (0C) 18
37 1
50
160 300 WN RF 1525
_
PRESSURE CONTROLLER
EASILY.
X SADDLE SUPPORT FOR HORIZONTAL VESSEL(7 SHEETS) IND VSD 009 HYDROSTATIC TEST (kg/cm2g) HORIZONTAL / VERTICAL (AT TOP)
(HOLD) 11 2
VESSEL IS SUBJECTED TO STEAM OUT CONDITION OF 0.5 Kg/Cm (g) AT LUG SUPPORTS (2 SHEETS) IND VSD 010 PRESSURE (NEW & COLD) 21.84
45 50 SEE 1900C PIPE LEG SUPPORT IND VSD 011 INSPECTION BY EIL CIB X TPI
2 160 300 WN RF _ LEVEL GLASS / GAUGE
A-B (HOLD) DWG. 12 ALL NOZZLE FABRICATED FROM PLATES SHALL BE 100% RADIOGRAPHED. X MINIMUM NOZZLE WALL THICKNESS IND VSD 012
MATERIAL OF CONSTRUCTION
47
2
80
160 300 WN RF
SEE
55X22 LEVEL CONTROLLER
13 ALSO REFER 44NC-4600-00/V.02/0164/A3 FOR OTHER APPLICABLE NOTES. X REINFORCING PLATES FOR NOZZLES. (C.A. 3mm) IND VSD 018 (AS PER ASME / IS OR EQUIVALENT)
A-B (HOLD) DWG. 14 VENDOR SHALL INDICATE C.G OF EQUIPMENT IN FABRICATION DWGS. X NAME PLATE BRACKET IND VSD 020
45
2
50
XXS 300 WN RF
SEE
_ LEVEL GLASS / GAUGE
15 MANDATORY & COMISSIONING SPARES SHALL BE SUPPLIED BY FABRICATOR. X STANDARD NAME PLATE FOR VESSEL IND VSD 021 SHELL /BOOT SA 516 GR.60 *
C-D (HOLD) DWG. INSULATION SUPPORTS FOR VESSELS (HOT) IND VSD 022 REINFORCEMENT PAD/INSERT PLATE SA 516 GR.60
47
2
80
XXS 300 WN RF
SEE
55X22 LEVEL CONTROLLER
16 HARDNESS OF BASE METAL, WELD & HAZ SHALL NOT EXCEED 200 BHN X STANDARD NOZZLE PROJECTION IND VSD 024 HEADS /BOOT HEAD SA 516 GR.60 *
C-D (HOLD) DWG. AFTER PWHT. LIFTING TRUNNIONS IND VSD 025 SHELL FLANGES -
SEE _ 17 MOUNT 2" VENT NOZZLE `50' ON THE BLIND FLANGE OF VENTILATION HANDHOLE WITH HINGED COVER IND VSD 029 NOZZLE FLANGES/LWN NOZZLES/BF SA 105 *
50 1 50 160 300 WN RF VENT (NOTE-17) NOZZLE-8.
DWG. STANDARD INTERNAL PLATE FLANGES IND VSD 030 NOZZLE NECK UPTO 300 NB SA 106 GR.B * (SEAMLESS)
18 FULL RADIOGRAPHY IMPLIES 100% RADIOGRAPHY OF ALL BUTT WELDS. VORTEX BREAKERS (FLUSH TYPE NOZZLES) IND VSD 033 NOZZLE NECK ABOVE 300 NB SA 516 GR.60 *
19 THE EQUIPMENT IS IN SOUR SERVICE. NACE MR 0103 REQUIREMENT X VORTEX BREAKERS (NOZZLE WITH INTERNAL PROJECTION) IND VSD 034 PIPE FITTINGS SA 234 GR. WPB *
TO BE METIN ADDITION TO REQUIREMENT AT CLAUSE 1.1 OF STANDARD DEMISTERS TYPE-I (VESSEL DIA<800mm) IND VSD 036 SPIRAL WOUND GASKET WITH SS 316L
SPECIFICATION OF 44 NC-4600-0000-V.02-0114-A4 STANDARD DEMISTERS TYPE-II(VESSEL DIA> 800mm) IND VSD 037 METAL WINDINGS AND NON ASBOSTOS
GASKET EXTERNAL
STANDARD DEMISTERS TYPE-III IND VSD 038 FILLER MATERIAL WITH SS 316L OUTER &
STANDARD DEMISTERS TYPE-IV IND VSD 039 INNER RING AS PER ASME B16.20
TYPE
MAX MOMENT AT BASE (M)
MAX. SHEAR FORCE AT BASE (H) (kg) X NOZZLE ORIENTATIONS X SIZE OF NOZZLES 33,37,45A-D & 47A-D APPROXIMATE WEIGHT (kgs)
X NOZZLE ELEVATIONS(AS MARKED) X PIPE SUPPORT CLEATS
(kgm) (PER ITEM)
Page 82 of 434
Page 83 of 434
JOB NO.: A133 UNIT-86
CLIENT : M/S CPCL fMC;wVsukbtj
PLANT : COKER BLOCK, CPCL
vksojgsM fjlhoj
NOZZLES AND CONNECTIONS GENERAL NOTES SPECIFICATIONS DESIGN DATA
MARK QTY
NOM.
SCH./THK
FLANGES PROJECTION PAD
SERVICE
UNLESS STATED OTHER WISE X DENOTES APPLICABLITY CODE ASME SEC. VIII DIV.1 2010+ADDENDA 2011
DIA CLASS TYPE FACING NOTE-4 WxT 1 ALL DIMENSIONS ARE IN MM UNLESS STATED OTHER WISE. WORKING PRESSURE (kg/cm2g) 0.1-1.7
INT:
SEE 2 ALL ANCHOR BOLT HOLES TO STRADDLE N/S CENTRE LINE. DESIGN PRESSURE (kg/cm2g) 3.5 EXT FV
C1 1 200 100 150 WN RF 95X18 INLET 0
TOP/
DWG. 3 NORTH DIRECTION WHEREVER SHOWN IS WITH RESPECT TO PLAN VIEW. WORKING TEMPERATURE ( C) 40-180
SEE 4 (A) FOR NOZZLES ON SHELL PROJECTIONS ARE REFERRED FROM HORIZONTAL JACOBS SPECIFICATIONS DESIGN TEMPERATURE
0
( C) 200
C2 1 50 XXS 150 WN RF _ VENT WITH BLIND FLAGE
DWG. PLANE TO FLANGE CONTACT FACE.
X GENERAL SPECIFICATION FOR PRESSURE VESSELS 44NC-4600-0000-V.02.-0101-A4 MDMT (0C) 18
C3 1 80 XXS 150 WN RF
SEE
_ VENT TO FLARE
4 (B) FOR NOZZLES ON HEAD PROJECTIONS ARE REFERRED FROM VERTICAL PLANE X GENERAL SPECIFICATION FOR SHOP & FIELD PAINTING 44NC-4600-0000-V.02.-0111-A4 CORROSION ALLLOWANCE (MM) 6 (INT) 1.5 (EXT)
DWG. TO FLANGE CONTACT FACE. GENERAL SPECIFICATION FOR INSULATION 44NC-4600-0000-V.02.-0112-A4 TYPE OF HEAD 2:1 ELLIPSOIDAL
C4 1 50 XXS 150 WN RF
SEE
_ STEAM OUT/UC
5 THE INDICATED THICKNESS IS THE MINIMUM ACCEPTABLE AFTER X GENERAL SPECIFICATION - MATERIAL SPECIFICATIONS 44NC-4600-0000-V.02.-0114-A4 JOINT EFFICIENCY SHELL 1.0 HEAD 1.0
DWG. CONSTRUCTION.
X STANDARD SPECIFICATION FOR BQ CS PLATES 44NC-4600-0000-V.02.-0117-A4 RADIOGRAPHY (NOTE-11 & 16) SHELL FULL HEAD FULL
DESIGNED AND DETAILED OUT BY FABRICATOR. QUOTED PRICE SHOULD X TYP. NOZZLE FLANGE TO NECK JOINT IND VSD 051 CLIPS & ATTACHMENTS (EXT.) WELDED OVER PAD IS 2062 Gr.B
INCLUDE THE SAME INCLUDING COIL SUPPORT. X RECOMMENDED WELD EDGE PREPARATION FOR BUTT WELDS IND VSD 052 PAD FOR EXTERNAL ATTACHMENTS SA 516 GR.60
21 THE EQUIPMENT IS IN SOUR SERVICE. NACE MR0103 REQUIREMENTS ALLOY LINER DETAIL (2SHEETS) IND VSD 053 NAME PLATE SS 304
TO BE MET IN ADDITION TO REQUIREMENTS AT CL.1.1 OF SUPPORT RING AND BOLTING BAR IND VSD 055 NAME PLATE BRACKET SA 516 GR.60
SPECIFICATION 44NC-4000-0000-V.02-0114-A4.
SUPPORT RING SIZES FOR PACKED TOWERS IND VSD 056 WRAPPER PLATE SA 516 GR.60
22 PRIMER AND FINISH PAINT SHALL BE DONE BY VENDOR AND SHALL BE AS INSULATION SUPPORTS FOR VERTICAL VESSEL IND VSD 057 LIFTING LUGS IS 2062 Gr.B
PER PAINTING SPECIFICATION. INSULATION SUPPORTS FOR HORIZONTAL VESSEL IND VSD 058 BRACKET SA 516 GR.60
MANWAY DAVIT
23 HARDNESS OF BASE METAL, WELDS & HAZ SHALL NOT EXCEED 200 BHN FIRE PROOFING SUPPORT IND VSD 062 ALL OTHER PARTS IS 2062 Gr.B
AFTER PWHT. INLET DEFLECTOR BAFFLE IND VSD 064
24 THE BOOT DIMENSION TO BE FINALISED BY CONSIDERING ATLEAST 300MM X EARTHING LUG IND VSD 080
LIQUID LEVEL AVAILABLE BETWEEN VESSEL BTL AND EYE OF IMPELLER.
25 STIFFENER RING SHALL NOT BE WELDEDTO SHELL TILL ALL THE FOULING EIL REFERENCE DRAWINGS
W.R.T. THE PIPING AND STRUCTURAL CLIPS ARE CLEARED / RESOLVED. NOZZLE ORIENTATIONS
LADDERS/PLATFORM CLEATS N.A. *NACE (REFER NOTE-21 & 23)
PIPE SUPPORT CLEATS N.A.
PMC REVIEW
RECORDS
CLIENT : M/s. CPCL CLOSED BLOWDOWN DRUM DyksTM CyksMkmu Mªe A133-086-16-46-DS-3029 B
NEW DELHI B 30.09.2013 REVISED AND ISSUED FOR BIDS/ENGG. GCP SUU/PKP BBC
A 20.06.11 ISSUED FOR BIDS/ENGG. GCP AY/PKP TG
PLANT : COKER BLOCK, CPCL
REV DATE REVISION BY CHECKED APPROVED
ITEM NO. 86-C-51 86&lh&51 SHEET 1 OF 3
FORMAT NO.3-1646-0113 REV.1 (22.12.2009) A3-420 X 297
Page 84 of 434
Page 85 of 434
JOB NO.: A133 UNIT - 86
CLIENT : M/S. CPCL
PLANT :
CATHODIC PROTECTION CLEAT (TOTAL 4NOS.)
Page 86 of 434
A133 UNIT - 86
M/S. CPCL
The drawing, design and details given below on this format are the property of ENGINEERS INDIA LIMITED. They are merely loaned on the borrower's express agreement that they will not be reproduced, copied, exhibited, or used, except in the limited way permitted by written consent given by the lender
50 1 50 160 150 WN RF
SEE _
VENT NOZZLE (NOTE-18)
FABRICATOR.
X STANDARD NOZZLE PROJECTION IND VSD 024 HEADS SA 516 GR.70
DWG. 16 PIPE TO PIPE, PIPE TO FLANGE PIPE TO FITTING & FITTING TO FLANGE JOINT LIFTING TRUNNIONS IND VSD 025 SHELL FLANGES -
SHALL BE WELDED WITH SAME TECHNIQUE USED FOR MAIN EQUIPMENT HANDHOLE WITH HINGED COVER IND VSD 029 NOZZLE FLANGES/LWN NOZZLES/B.F. SA 105
WELDING.
STANDARD INTERNAL PLATE FLANGES IND VSD 030 NOZZLE NECK UPTO 300 NB SA 106 GR.B (SEAMLESS)
17 WHEREVER FULL RADIOGRAPHY IS SPECIFIED SHALL IMPLY 100% X VORTEX BREAKERS (FLUSH TYPE NOZZLES) IND VSD 033 NOZZLE NECK ABOVE 300 NB SA 516 GR.70
RADIOGRAPHY OF ALL BUTT WELDS. VORTEX BREAKERS (NOZZLE WITH INTERNAL PROJECTION) IND VSD 034 PIPE FITTINGS SA 234 GR. WPB
18 VENT NOZZLE `50' SHALL BE MOUNTED ON BLIND FLANGE OF VENTILATION STANDARD DEMISTERS TYPE-I (VESSEL DIA<800mm) IND VSD 036 SPIRAL WOUND GASKET WITH SS 304 METAL
NOZZLE `8'. STANDARD DEMISTERS TYPE-II(VESSEL DIA> 800mm) IND VSD 037 WINDINGS AND GRAFOIL FILLER MATERIAL
GASKET EXTERNAL
STANDARD DEMISTERS TYPE-III IND VSD 038 WITH SS 304 INNER & OUTER RING AS PER
STANDARD DEMISTERS TYPE-IV IND VSD 039 ASME B16.20
APPROVAL
PMC REVIEW
RECORDS
STATUTORY REGULATIONS
LICENSORS SPECIFICATIONS INDIAN BOILER REGULATIONS (IBR)
FOUNDATION LOADING DATA (OPERATING CONDITION) HOLD UPS
to the borrower for the intended use.
LICENSORS STANDARDS
TYPE
MAX MOMENT AT BASE (M)
MAX. SHEAR FORCE AT BASE (H) (kg) X NOZZLE ORIENTATIONS X SIZE OF NOZZLES 20,33,36,45A-B,47A-B,49A-B APPROXIMATE WEIGHT (kgs)
X NOZZLE ELEVATIONS X PIPE SUPPORT CLEATS
(kgm) (PER ITEM)
CLIENT : M/s. CPCL COKER UNIT FEED SURGE DRUM dksdj ;wuhV QhM ltZ Mªe A133-086-16-46-DS-3012 B
NEW DELHI B 23.09.2013 REVISED AND ISSUED FOR BIDS/ENGG. GCP SUU/PKP BBC
A 29.04.2011 ISSUED FOR BIDS/ENGG. SBS AB/PP TG
PLANT : COKER BLOCK, CPCL
REV DATE REVISION BY CHECKED APPROVED
ITEM NO. 86-C-21 86&lh&21 SHEET 1 OF 2
FORMAT NO.3-1646-0113 REV.1 (22.12.2009) A3-420 X 297
Page 87 of 434
Page 88 of 434
JOB NO.: A133 UNIT-86
CLIENT : M/S CPCL dksdj ;wuhV
PLANT : COKER BLOCK, CPCL
NOZZLES AND CONNECTIONS GENERAL NOTES SPECIFICATIONS DESIGN DATA
MARK QTY
NOM.
SCH./THK
FLANGES PROJECTION PAD
SERVICE
UNLESS STATED OTHER WISE X DENOTES APPLICABLITY CODE ASME SEC. VIII DIV.1 2010+ADDENDA 2011
DIA CLASS TYPE FACING NOTE-4 WxT 1 ALL DIMENSIONS ARE IN MM. UNLESS STATED OTHER WISE WORKING PRESSURE (kg/cm2g) TOP 8.7 BOT _
INT:
2 ALL ANCHOR BOLT HOLES TO STRADDLE N/S CENTRE LINE. DESIGN PRESSURE (kg/cm2g) 18.5 EXT _
F 1 50 160 300 WN RF 1040 _ INLET 0
TOP/
3 NORTH DIRECTION WHEREVER SHOWN IS WITH RESPECT TO PLAN VIEW. WORKING TEMPERATURE ( C) TOP 47 BOT _
4 (A) FOR NOZZLES ON SHELL PROJECTIONS ARE REFERRED FROM VESSEL JACOBS SPECIFICATIONS DESIGN TEMPERATURE
0
( C) 67
B 1 50 160 300 WN RF 1040 _ BOTTOM OUTLET CENTER LINE TO FLANGE CONTACT FACE.
X GENERAL SPECIFICATION FOR PRESSURE VESSELS 44NC-4600-0000-V.02.-0101-A4 MDMT (0C) 18
D 1 40 160 300 WN RF
SEE
_ DRAIN
4 (B) FOR NOZZLES ON HEAD PROJECTIONS ARE REFERRED FROM HEAD T.L TO X GENERAL SPECIFICATION FOR SHOP & FIELD PAINTING 44NC-4600-0000-V.02.-0111-A4 CORROSION ALLLOWANCE (MM) 3
DWG. FLANGE CONTACT FACE. GENERAL SPECIFICATION FOR INSULATION 44NC-4600-0000-V.02.-0112-A4 TYPE OF HEAD 2:1 ELLIPSOIDAL
5 THE INDICATED THICKNESS IS THE MINIMUM ACCEPTABLE AFTER GENERAL SPECIFICATION - MATERIAL SPECIFICATIONS 44NC-4600-0000-V.02.-0114-A4 JOINT EFFICIENCY SHELL 1.0 HEAD 1.0
LG1,2 2 50 (H) 160 300 WN RF 1040 _ LEVEL GAUGE CONSTRUCTION.
X STANDARD SPECIFICATION FOR BQ CS PLATES 44NC-4600-0000-V.02.-0117-A4 RADIOGRAPHY (NOTE-10 & 18) SHELL FULL HEAD FULL
V 1 50 160 300 WN RF
SEE
_ VENT
8 ID OF WELD NECK FLANGES SHALL MATCH WITH CORRESPONDING ID OF X GENERAL TOLERANCES FOR PRESSURE VESSELS IND VSD 001 WIND SPECIFICATION IS 875
DWG. NOZZLE PIPE. X MANWAY DAVIT (FOR VERTICAL/HORIZONTAL MANHOLE) IND VSD 002/003 SEISMIC IS 1893 & SITE SPECTRA
SV 1
203.2
- 300 LWN RF
SEE
40X18 SAFETY VALVE
10 ALL FABRICATED NOZZLES FROM PLATES SHALL BE 100% RADIOGRAPHED. X DETAIL OF SKIRT BASE FOR VESSEL & COLUMN IND VSD 007 INSULATION THICKNESS (mm) NO HOT COLD
I/D (H) DWG. 11 VESSEL IS SUBJECTED TO STEAM OUT CONDITION OF 0.5Kg/Cm (g)
2
AT LEG SUPPORT FOR VERTICAL VESSEL (2 SHEETS) IND VSD 008 FIRE PROOFING (BY OTHERS) X YES NO
190°C. SADDLE SUPPORT FOR HORIZONTAL VESSEL(7 SHEETS) IND VSD 009 HYDROSTATIC TEST (kg/cm2g) HORIZONTAL / VERTICAL (AT TOP)
SK1-4 4 100 80 AS PER JACOB'S STD. SKIRT VENT
12 SS SCREEN SHALL BE SUPPORTED WITH GRID (GRATING) AND SHALL BE LUG SUPPORTS (2 SHEETS) IND VSD 010 PRESSURE (NEW & COLD) 24.05
WIRED TO THE GRATINGS. MAXIMUM SIZE OF EACH OPENING AND % OPEN PIPE LEG SUPPORT IND VSD 011 INSPECTION BY EIL CIB X TPI
AO 1 600 I.D. 10 THK. AS PER JACOB'S STD. ACCESS OPENING AREA SHALL BE 0.025" (0.635MM) AND 23% RESPECTIVELY.
X MINIMUM NOZZLE WALL THICKNESS IND VSD 012
MATERIAL OF CONSTRUCTION
13 HARDNESS SURVEY OF WELD, HAZ & BASE METAL SHALL BE CARRIED OUT X REINFORCING PLATES FOR NOZZLES. (C.A. 3mm) IND VSD 018 (AS PER ASME / IS OR EQUIVALENT)
AFTER PWHT. HARDNESS SHALL NOT EXCEED 200 BHN. X NAME PLATE BRACKET IND VSD 020
14 ALL INTERNALS SHALL BE SIZED TO PASS THROUGH MANHOLE. X STANDARD NAME PLATE FOR VESSEL IND VSD 021 SHELL SA 516 GR.60
INSULATION SUPPORTS FOR VESSELS (HOT) IND VSD 022 REINFORCEMENT PAD SA 516 GR.60
15 ALSO REFER 44NC-4600-00/V.02/0164/A3 FOR OTHER APPLICABLE NOTES. X STANDARD NOZZLE PROJECTION IND VSD 024 HEADS SA 516 GR.60
LIFTING TRUNNIONS IND VSD 025 SHELL FLANGES -
16 VENDOR SHALL INDICATE C.G OF EQUIPMENT IN FABRICATION DWGS. HANDHOLE WITH HINGED COVER IND VSD 029 NOZZLE FLANGES/LWN NOZZLES/B.F. SA 105
(H) HOLD
17 MANDATORY & COMISSIONING SPARES SHALL BE SUPPLIED BY FABRICATOR. X STANDARD INTERNAL PLATE FLANGES IND VSD 030 NOZZLE NECK UPTO 300 NB SA 106 GR.B (SEAMLESS)
VORTEX BREAKERS (FLUSH TYPE NOZZLES) IND VSD 033 NOZZLE NECK ABOVE 300 NB SA 516 GR.60
18 FULL RADIOGRAPHY SPECIFIED SHALL IMPLY 100% RADIOGRAPHY VORTEX BREAKERS (NOZZLE WITH INTERNAL PROJECTION) IND VSD 034 PIPE FITTINGS SA 234 GR. WPB
19 SCREEN WITH GRID SUPPORT SHALL BE PROCURED FROM ONE OF THE NOZZLE INTERNAL BAFFLE (FOR INSTRUMENT) IND VSD 035 SPIRAL WOUND GASKET WITH SS 316 METAL
SUPPLIERS LISTED AT NOTE-21 & INSTALLED BY VESSEL FABRICATOR. STANDARD DEMISTERS TYPE-II(VESSEL DIA> 800mm) IND VSD 037 WINDINGS AND NON ASBESTOS FILLER
THE PROFILE WIRE SCREEN & GRID/GRID SUPPORT SYSTEM (INCLUDING GASKET EXTERNAL
STANDARD DEMISTERS TYPE-III IND VSD 038 MATERIAL WITH SS 316 OUTER & INNER
BEAMS , BEAM SEAT & SUPORT RING SHALL BE DESIGNED WITH FOLLOWING RING AS PER ASME B16.20
CONDITIONS: STANDARD DEMISTERS TYPE-IV IND VSD 039
X STANDARD BOLT HOLE ORIENTATION IND VSD 040 GASKET INTERNAL NON ASBESTOS
(i)THE WET SAND DENSITY SHALL BE CONSIDERED AS 1600 KG/M3. TAILING LUG IND VSD 042 EXTERNAL STUDS/BOLTS/NUTS SA 193 GR.B7 / SA 194 GR.2H
(ii)THE VESSEL IS FULL OF LIQUID OF DENSITY 780KG/CM3. X LADDER RUNGS INSIDE VESSELS AND COLUMNS IND VSD 043 INTERNAL STUDS/BOLTS/NUTS SS 316
(iii)THE PRESSURE DROP SHALL BE CONSIDERED AS 0.3 KG/CM2 FOR DIRTY FOUNDATION TEMPLATE (2 SHEETS) IND VSD 044 SKIRT/ SUPPORT SA 516 GR.60/IS 2062 Gr.B
SERVICE & 0.15 KG/CM3 FOR CLEAN CONDITION.(HOLD)
X SUPPORT FOR INTERNAL DISTRIBUTOR PIPES IND VSD 045 SKIRT/ SUPPORT BASE IS 2062 Gr.B
(iv)THE GRID SUPPORT RING SHALL BE MIN 20 THK SUPPORTS FOR INTERNAL FEED PIPE IND VSD 046/047 INTERNAL PARTS (WELDED) SA 516 GR.60
20 THE NOZZLE B SHALL BE ORIENTED UNDER THE BAFFLE X LIFTING LUG TOP HEAD TYPE IND VSD 048 INTERNAL PARTS (BOLTED) SS 316
21 SUPPLIERS OF PROFILE WIRE SCREEN (GRID):(HOLD) LIFTING LUG FOR HORIZONTAL VESSEL IND VSD 050 CLIPS & ATTACHMENTS ((EXT.) DIRECTLY WELDED SA 516 GR.60
A).JOHNSON SCREEN X TYP. NOZZLE FLANGE TO NECK JOINT IND VSD 051 CLIPS & ATTACHMENTS (EXT.) WELDED OVER PAD IS 2062 Gr.B
B).NAGAOKTA INTL. CORPORATION,JAPAN OR EQUIVALENT X RECOMMENDED WELD EDGE PREPARATION FOR BUTT WELDS IND VSD 052 PAD FOR EXTERNAL CLIPS ATTACHMENTS SA 516 GR.60
C).EUROSLOTS ALLOY LINER DETAIL (2SHEETS) IND VSD 053 DEMISTER/GRID -
22 DESIGN OF ALL INTERNALS SHALL BE CARRIED OUT AS CONSIDERING SUPPORT RING AND BOLTING BAR IND VSD 055 WEAR PLATE -
LOADS AS SPECIFIED IN NOTE-19 ABOVE.
X SUPPORT RING SIZES FOR PACKED TOWERS IND VSD 056 NAME PLATE SS 304
A).ALLOWABLE STRESSES IN BENDING SHALL BE 0.66 OF YIELD STRESS AT INSULATION SUPPORTS FOR VERTICAL VESSEL IND VSD 057 NAME PLATE BRACKET SA 516 GR.60
DESIGN TEMPERATURE. INSULATION SUPPORTS FOR HORIZONTAL VESSEL IND VSD 058 SUPPORT GRID SS 316
B)ALLOWABLE DEFLECTION OF BEAM SHALL BE L/360 X FIRE PROOFING SUPPORT IND VSD 062 BEAMS FOR GRID SS 316
23 ONE NO. MONKEY LADDER SHALL BE PROVIDED IN SKIRT AS PER ATTACHED X INLET DEFLECTOR BAFFLE IND VSD 064 WIRE MESH SS 316
SKETCH.
X EARTHING LUG IND VSD 080
24 ALL STAINLESS STEEL SURFACES SHALL BE PICKLED AND PASSIVATED AS BRACKET SA 516 GR.60
PER ASTM A380.PROCEDURE SHALL BE SUBMITTED FOR JACOBS REVIEW EIL REFERENCE DRAWINGS MANWAY/PIPE DAVIT
ALL OTHER PARTS IS 2062 Gr.B
NOZZLE ORIENTATIONS LIFTING LUGS SA 516 GR.60
LADDERS/PLATFORM CLEATS EARTHING LUGS IS 2062 Gr.B
PIPE SUPPORT CLEATS
DEMISTER DATA SHEET NA
X MONKEY LADDER A133-000-16-46-SK-01
APPROVAL
PMC REVIEW
RECORDS
DBE 31300 4200 X SUPPORT HEIGHT X LADDER/PLATFORM CLEATS ERECTION 8100 OPERATING 28700
SEISMIC X DETAILS OF INTERNALS TRAY SUPPORT/BOLTING BARS
MCE 50800 6850 X PIPE DAVIT HYDROTEST(SHOP) 19000 HYDROTEST ( FIELD ) 29300
CLIENT : M/s. CPCL SAND FILTER FOR NAPHTHA+DSO lS.M fQYVj QWkj ukQFkk$Mh ,l vks A133-087-16-46-DS-3008 B
NEW DELHI B 10.09.2013 REVISED AND ISSUED FOR BIDS/ENGG. GCP SUU/PKP BBC
A 24.05.2011 ISSUED FOR BIDS/ENGG. SBS AB/PP TG
PLANT : COKER LPG CFC TREATING UNIT
REV DATE REVISION BY CHECKED APPROVED
ITEM NO. 87-C-08 87&lh&08 SHEET 1 OF 2
FORMAT NO.3-1646-0113 REV.1 (22.12.2009) A3-420 X 297
Page 89 of 434
$ Mh ,l vks
Page 90 of 434
NOZZLES AND CONNECTIONS GENERAL NOTES SPECIFICATIONS DESIGN DATA
MARK QTY
NOM.
SCH./THK
FLANGES PROJECTION PAD
SERVICE
UNLESS STATED OTHER WISE X DENOTES APPLICABLITY CODE ASME SEC. VIII DIV.1 2010+ADDENDA 2011
DIA CLASS TYPE FACING NOTE-4 WxT 1 ALL DIMENSIONS ARE IN MM.UNLESS STATED OTHER WISE WORKING PRESSURE (kg/cm2g) TOP 14.8 BOT _
INT:
2 ALL ANCHOR BOLT HOLES TO STRADDLE N/S CENTRE LINE. DESIGN PRESSURE (kg/cm2g) 23 EXT _
F 1 80 160 300 WN RF 940 55X20 INLET 0
TOP/
3 NORTH DIRECTION WHEREVER SHOWN IS WITH RESPECT TO PLAN VIEW. WORKING TEMPERATURE ( C) TOP 40 BOT _
4 (A) FOR NOZZLES ON SHELL PROJECTIONS ARE REFERRED FROM VESSEL JACOBS SPECIFICATIONS DESIGN TEMPERATURE
0
( C) 85
B 1 80 160 300 WN RF 940 55X20 BOTTOM OUTLET CENTER LINE TO FLANGE CONTACT FACE.
X GENERAL SPECIFICATION FOR PRESSURE VESSELS 44NC-4600-0000-V.02.-0101-A4 MDMT (0C) (-) 27
D 1 40 160 300 WN RF
SEE
_ DRAIN
4 (B) FOR NOZZLES ON HEAD PROJECTIONS ARE REFERRED FROM HEAD T.L TO X GENERAL SPECIFICATION FOR SHOP & FIELD PAINTING 44NC-4600-0000-V.02.-0111-A4 CORROSION ALLLOWANCE (MM) 3
DWG. FLANGE CONTACT FACE. GENERAL SPECIFICATION FOR INSULATION 44NC-4600-0000-V.02.-0112-A4 TYPE OF HEAD 2:1 ELLIPSOIDAL
V 1 50 160 300 WN RF
SEE
_ VENT
5 THE INDICATED THICKNESS IS THE MINIMUM ACCEPTABLE AFTER X GENERAL SPECIFICATION - MATERIAL SPECIFICATIONS 44NC-4600-0000-V.02.-0114-A4 JOINT EFFICIENCY SHELL 1.0 HEAD 1.0
DWG. CONSTRUCTION.
X STANDARD SPECIFICATION FOR BQ CS PLATES 44NC-4600-0000-V.02.-0117-A4 RADIOGRAPHY (NOTE-10 & 19) SHELL FULL HEAD FULL
SV 1
101.6
- 300 LWN RF
SEE
_ SAFETY VALVE
8 ID OF WELD NECK FLANGES SHALL MATCH WITH CORRESPONDING ID OF X GENERAL TOLERANCES FOR PRESSURE VESSELS IND VSD 001 WIND SPECIFICATION IS 875
I/D (H) DWG. NOZZLE PIPE. X MANWAY DAVIT (FOR VERTICAL /HORIZONTAL MANHOLE) IND VSD 002/003 SEISMIC IS 1893 & SITE SPECTRA
CONDITIONS: SUPPORTS FOR INTERNAL FEED PIPE IND VSD 046/047 INTERNAL PARTS (WELDED) SA 516 GR.60 * @
X LIFTING LUG TOP HEAD TYPE IND VSD 048 INTERNAL PARTS (BOLTED) SS 316
(i).THE WET SAND DENSITY SHALL BE CONSIDERED AS 1600 KG/M3. LIFTING LUG FOR HORIZONTAL VESSEL IND VSD 050 CLIPS & ATTACHMENTS ((EXT.) DIRECTLY WELDED SA 516 GR.60 @
(ii).THE VESSEL IS FULL OF LIQUID OF DENSITY 519 KG/CM .
3
X TYP. NOZZLE FLANGE TO NECK JOINT IND VSD 051 CLIPS & ATTACHMENTS (EXT.) WELDED OVER PAD IS 2062 Gr.B
(iii).THE PRESSURE DROP SHALL BE CONSIDERED AS 0.3 KG/CM
2
FOR DIRTY X RECOMMENDED WELD EDGE PREPARATION FOR BUTT WELDS IND VSD 052 PAD FOR EXTERNAL CLIPS ATTACHMENTS SA 516 GR.60 @
SERVICE & 0.15 KG/CM3 FOR CLEAN CONDITION.(HOLD) ALLOY LINER DETAIL (2SHEETS) IND VSD 053 DEMISTER/GRID -
(iv)THE GRID SUPPORT RING SHALL BE MIN 22 THK. SUPPORT RING AND BOLTING BAR IND VSD 055 PIPE DAVIT SA 106 GR.B/SA 53
22 THE NOZZLE "B" SHALL BE ORIENTED UNDER THE BAFFLE X SUPPORT RING SIZES FOR PACKED TOWERS IND VSD 056 WEAR PLATE -
23 SUPPLIERS OF PROFILE WIRE SCREEN (GRID): (HOLD) INSULATION SUPPORTS FOR VERTICAL VESSEL IND VSD 057 NAME PLATE SS 304
A).JOHNSON SCREEN INSULATION SUPPORTS FOR HORIZONTAL VESSEL IND VSD 058 NAME PLATE BRACKET SA 516 GR.60
B).NAGAOKTA INTL. CORPORATION,JAPAN X FIRE PROOFING SUPPORT IND VSD 062 SUPPORT GRID FOR SAND BED SS 304
C).EURO SLOTS X INLET DEFLECTOR BAFFLE IND VSD 064 BEAMS FOR GRID SS 304
D).OR EQUIVALENT X EARTHING LUG IND VSD 080 WIRE MESH SS 304
24 DESIGN OF ALL INTERNALS SHALL BE CARRIED OUT AS CONSIDERING BRACKET SA 516 GR.60
LOADS AS SPECIFIED IN NOTE-21 ABOVE. EIL REFERENCE DRAWINGS MANWAY DAVIT
ALL OTHER PARTS IS 2062 Gr.B
A).ALLOWABLE STRESSES IN BENDING SHALL BE 0.66 OF YIELD STRESS AT NOZZLE ORIENTATIONS LIFTING LUGS IS 2062 Gr.B
DESIGN TEMPERATURE. LADDERS/PLATFORM CLEATS EARTHING LUGS IS 2062 Gr.B
B)ALLOWABLE DEFLECTION OF BEAM SHALL BE L/360. PIPE SUPPORT CLEATS
DEMISTER DATA SHEET NA
25 ALL STAINLESS STEEL SURFACES SHALL BE PICKLED AND PASSIVATED AS MONKEY LADDER
APPROVAL PER ASTM A380. PROCEDURE SHALL BE SUBMITTED FOR JACOBS REVIEW * NACE + HIC ( REFER NOTE-13 & 20)
PMC REVIEW "@" IMPACT TESTED (REFER NOTE-18 & 26)
RECORDS 26 ENERGY VALUE AND IMPACT TEST TEMPERATURE FOR PLATES SHALL BE AS
PER TABLE A2.15 OF SA-20.
DBE 20500 3250 X SUPPORT HEIGHT X LADDER/PLATFORM CLEATS ERECTION 7,100 OPERATING 22,700
SEISMIC X DETAILS OF INTERNALS TRAY SUPPORT/BOLTING BARS
Page 91 of 434
Page 92 of 434
lSUM fQYVj QWkj
Document No.
VENDOR DATA REQUIREMENTS A133-086-16-46-VDR-6141
FOR Rev. A
CS VESSELS Page 1 of 4
Page 93 of 434
Document No.
VENDOR DATA REQUIREMENTS A133-086-16-46-VDR-6141
FOR Rev. A
CS VESSELS Page 2 of 4
The following drawings/documents marked " " shall be furnished by the bidder.
POST ORDER
S. WITH WITH
N DESCRIPTION FOR FOR DATA REMARKS
BID
O. REVIEW RECORD BOOK
(FINAL)
1. RADIOGRAPHIC EXAMINATION REPORTS Vendor to store these
for 5 years.
WITH FILMS @.
2. CODE CERTIFICATES (INCLUDING Documents shall be
INSPECTION CERTIFICATE, HYDROSTATIC submitted within 1
TEST CERTIFICATE, LOCAL CODE week after final
REQUIREMENTS, RUBBING OF CODE inspection.
@.
STAMP AND NAME PLATE ETC.)
3. MATERIAL TEST CERTIFICATES Documents shall be
submitted within 1
week after final
inspection.
@.
4. DESTRUCTIVE AND NON-DESTRUCTIVE Documents shall be
submitted within 5 to 8
TEST REPORTS weeks of issue of PR.
@.
5. PACKING AND FORWARDING
INSTRUCTIONS
6. WELDING PROCEDURES AND Documents shall be
submitted within 5 to 8
QUALIFICATION TEST REPORTS weeks of issue of PR.
@.
7. INSPECTION AND TESTING PLAN Documents shall be
submitted within 5 to 8
weeks of issue of PR.
@.
8. GENERAL ARRANGEMENT DRAWING
INDICATING DESIGN DATA FABRICATED Documents shall be
EQUIPMENT WEIGHT, GENERAL NOTES, submitted within 3 to 5
NOZZLE SCHEDULE, DETAIL OF SHELL, weeks of issue of PR.
HEADS, SUPPORTING ARRANGEMENT, Plate cutting layout is
not required.
MAIN WELD SEAMS, NOZZLE ORIENTATION
PLAN, CUTTING LAYOUT ETC.
9. DETAIL OF NOZZLES, MANHOLES, Documents shall be
submitted within 3 to 5
ACCESSORIES ETC weeks of issue of PR.
10. DETAIL OF INTERNAL DISTRIBUTOR. Documents shall be
submitted within 3 to 5
weeks of issue of PR.
11. DETAIL OF EXTERNAL CLIPS SUCH AS Documents shall be
submitted highlighting
LADDER, PLATFORM, PIPE SUPPORT. areas of discrepency
or fouling, etc. within
10 to 15 weeks of
issue of PR.
12. DETAIL OF INSULATION, FIRE PROOFING Documents shall be
submitted highlighting
areas of discrepency
or fouling, etc.within 10
to 15 weeks of issue of
PR.
Page 94 of 434
Document No.
VENDOR DATA REQUIREMENTS A133-086-16-46-VDR-6141
FOR Rev. A
CS VESSELS Page 3 of 4
POST ORDER
S. WITH WITH
N DESCRIPTION FOR FOR DATA REMARKS
BID
O. REVIEW RECORD BOOK
(FINAL)
13. DETAIL OF PIPE DAVIT Documents shall be
submitted highlighting
areas of discrepency
or fouling, etc. within
10 to 15 weeks of
issue of PR.
14. DETAIL OF LIFTING LUG,TRUNION AND Documents shall be
submitted highlighting
TAILING LUG ETC. areas of discrepency
or fouling, etc. within
10 to 15 weeks of
issue of PR.
15. CERTIFIED 'AS BUILT' DRAWINGS Documents approved
by inspector shall be
INCORPORATING ACTUAL DIMENSIONS submitted within 2
AND MATERIAL USED, DULY CERTIFIED BY weeks after dispatch of
THE INSPECTOR equipment.
@.
16. DATA FOLDER AS PER SPECIFICATION Documents approved
by inspector shall be
submitted within 2
weeks after dispatch of
equipment.
@.
17. HEAT TREATMENT PROCEDURE AND TIME Documents shall be
submitted within 1
TEMPERATURE CHARTS week after final
inspection.
@.
18. DETAIL OF INTERNAL DISTRIBUTOR AND Documents shall be
submitted highlighting
ITS SUPPORT,VORTEX BREAKERS, etc. areas of discrepency
or fouling, etc.within 8
to 10 weeks of issue of
PR.
19. DETAILS OF PACKING SUPPORT,
GRATINGS, AND GRATING SUPPORTS.
POST ORDER
S. WITH WITH
N DESCRIPTION FOR FOR DATA REMARKS
BID
O. REVIEW RECORD BOOK
(FINAL)
1. Assembly & Installation Details Documents shall be
submitted within 12 to
16 weeks of issue of
PR. Documents shall
be approved by EIL
before shipment. @
2. Hydrotest procedure & foundation monitoring Documents shall be
submitted within 12 to
procedure 16 weeks of issue of
PR. @
3. Erection drawings including weights, C.G. & Documents shall be
submitted within 1
slinging facilities, etc. week after final
inspection.
Documents shall be
approved by EIL
before shipment.
4. Detail of Structural Platforms etc. Documents shall be
submitted highlighting
areas of discrepency
or fouling, etc.
Page 95 of 434
Document No.
VENDOR DATA REQUIREMENTS A133-086-16-46-VDR-6141
FOR Rev. A
CS VESSELS Page 4 of 4
Notes :
1. Quality requirements as mentioned in Job Specification of columns.
2. Refer 44NC-4600-0000/N.02/0040/A4+Annexure- I to V for quality management system
3. Bidder to submit 6 nos. hard copy of each drawing/document at drawing review stage along with soft copy in
eDMS. Final documentation shall be submitted in hard copy (15 prints) and soft (4 CDs/DVDs) in addition to
submission through EIL eDMS.
4. "TICK" denotes applicability.
5. Post order, drawing / document review shall commence only after approval of Document Control Index (DCI).
6. All post order documents shall be submitted / approved through EIL eDMS portal.
7. Post order- The schedule of drawing / data submission shall be mutually agreed between EIL & the bidder /
contractor / supplier during finalization of Document Control Index (DCI).
8. "@" indicates submission of documents to Inspection Agency.
9. Bill of Material shall form part of the respective drawing.
10. All drawings & documents shall be submitted in A4 or A3 paper sizes. Documents in higher paper size shall
be submitted in exceptional circumstances or as indicated in the MR/Tender.
Page 96 of 434
DOCUMENT No.
UNIT RATES FOR
ADDITION/DELETION A133-16-46-UR-6141
Rev. A
Page 1 of 7
UNIT RATES
FOR
ADDITION/DELETION
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
Page 97 of 434
DOCUMENT No.
UNIT RATES FOR
ADDITION/DELETION A133-16-46-UR-6141
Rev. A
Page 2 of 7
1. Offer shall contain the sheets given below & the subsequent sheets for addition / deletion
of nozzles duly filled in, else offer will be rejected. Please note that the same EIL sheets
as given below shall be filled in and enclosed in the offer. Bidder shall not enclose his
own sheets.
2. It is understood that
a) The quoted price includes for the “HOLDS “details of which are indicated on
respective equipment Engineering Drawing.
b) The weights indicated on EIL Engineering Drawings do not form the basis for
offer, since these are approximations only.
c) Spares as included in clause no. 2.3 in Scope of Supply are quoted.
d) The rates to be quoted below shall be paid on finished weight basis only.
- SA 516 Gr 70
- SA-516 Gr. 60
- 100 NB Sch.80
- 150 NB Sch.40
- 150 NB Sch.80
- 200 NB Sch.40
- 200 NB Sch.80
- 250 NB Sch.40
- 250 NB Sch.80
- 300 NB Sch.40
- 300 NB Sch.80
- SA-516 Gr.70
- SA-240 Gr.316
- SA-240 Gr.316L
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
Page 98 of 434
DOCUMENT No.
UNIT RATES FOR
ADDITION/DELETION A133-16-46-UR-6141
Rev. A
Page 3 of 7
- SA-516 Gr.60
- SA-516 Gr.70
- SA-106 Gr B
- SA 516 Gr.60 (NACE)
- SA 516 Gr.60 (NACE + HIC)
- SA 106 Gr. B (NACE)
- SA 106 Gr. B (NACE + HIC)
ix) Change in self reinforced nozzle sizes per kg.
Basis
- SA-105
- SA-105 (HIC+NACE)
- SA-105+ SS 304L Weld Overlay
- SA -350 LF2 CL1
In case of change in size, vendor shall submit
design calculation, details and weights of the
previous size also for EIL review at the time of
extra claims.
- SA 234 WPB
- SA 234 WPB + SS 410S WO
- SS 410S
- SS 316
- SA 234 WPB (NACE)
- SA 234 WPB (NACE + HIC)
- SA-105
- SA-105 + SS 410 S WO
- SA 105 (NACE)
- SA 105 (NACE + HIC)
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
Page 99 of 434
DOCUMENT No.
UNIT RATES FOR
ADDITION/DELETION A133-16-46-UR-6141
Rev. A
Page 4 of 7
- SA-516 Gr.60
- SA-516 Gr.60 + SS 410 S CLAD
- SA-516 Gr.70
- SA 516 Gr.60 (NACE)
- SA 516 Gr.60 (NACE + HIC)
- SA 516 Gr.60 (NACE + HIC) Impact
Tested
- SA-516 Gr. 60
- SA-516 Gr. 70
- SA 516 Gr.60 (NACE)
- SA 516 Gr.60 (NACE + HIC)
- SA-240 Gr. 304
- SA 240 Gr. 316
- SA 516 Gr.60 (NACE + HIC) Impact
Tested
- SA-106 Gr. B
- SS 304
- SA 106 Gr. B (NACE)
- SA 106 Gr. B (NACE + HIC)
- SS 316
- SS 316 L
- Up to 10 mm
- 11 mm to 20 mm
- 21 mm to 25 mm
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
Page 100 of 434
DOCUMENT No.
UNIT RATES FOR
ADDITION/DELETION A133-16-46-UR-6141
Rev. A
Page 5 of 7
TABLE-1(A)
SCHEDULE OF RATES FOR ADDITION/DELETION OF NOZZLES
SL.NO. NOMINAL SIZE WITHOUT BLIND WITH BLIND WITHOUT BLIND WITH BLIND WITHOUT WITH BLIND REMARKS
NB FLANGE FLANGE FLANGE FLANGE BLIND FLANGE FLANGE
1 25
2 40
3 50
4 80
5 100
6 150
7 200
8 250
9 300
10 350
11 400
12 450
13 500
14 600
15 650
16 700
17 750
18 800
19 850
20 900
21 950
22 1050
23 1200
24 1350
25 1400
26 1450
27 1500
NOTES :-
1. MATERIAL SPECIFICATION FOR NOZZLE COMPONENTS SUCH AS NOZZLE NECK, FLANGE, REINFORCEMENT PAD, NOZZLE STIFFENER,
STUDS, NUTS AND GASKETS SHALL BE AS PER ENGINEERING DRAWING. NOZZLE REINFORCEMENT AND PROJECTION DETAIL SHALL
BE AS PER ATTACHED STANDARD. BIDDER SHALL NOTE THAT EXTRA CLAIM FOR INCREASE IN NOZZLE PROJECTION UPTO
100MM W.R.T ATTACHED STANDARD SHALL NOT BE PAYABLE.
2. SCOPE OF SUPPLY OF NOZZLE COMPONENTS SHALL BE AS PER MATERIAL REQUISITION.
3. THE RATES QUOTED SHALL INCLUDE SUPPLY OF NOZZLE NECK, FLANGE, STIFFENER, STUDS, NUTS AND GASKETS (WHEN SUPPLIED
WITH BLIND FLANGE) AND ASSOCIATED FABRICATION AND TESTING.
4. PRICES INDICATED ABOVE SHALL BE IRRESPECTIVE OF NOZZLE THICKNESS.NO EXTRA CLAIM ON THIS ACCOUNT WILL BE
ENTERTAINED AT A LATER DATE.
5. THE SCHEDULE OF RATES EXCLUDES COST OF REINFORCEMENT PAD
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
Page 101 of 434
DOCUMENT No.
UNIT RATES FOR
ADDITION/DELETION A133-16-46-UR-6141
Rev. A
Page 6 of 7
TABLE-1(B)
SCHEDULE OF RATES FOR ADDITION/DELETION OF NOZZLES
FLANGE MATERIAL :- SA 105 (NACE + HIC) / SA 105 (NACE + HIC+ Impact Tested)
NOZZLE NECK MOC :- SA 106 Gr. B (NACE + HIC) / SA 106 Gr. B (NACE + HIC+ Impact tested) /SA 516 Gr. 60 (
NACE + HIC)/ SA 516 Gr. 60 (NACE + HIC +Impact tested)
ANSI B 16.5/ ANSI B 16.47 (SERIES B)
CLASS 150 (WN RF FLG.) CLASS 300 (WN RF FLG.) CLASS 600 (WN RF FLG.)
SL.NO. NOMINAL SIZE WITHOUT BLIND WITH BLIND WITHOUT BLIND WITH BLIND WITHOUT WITH BLIND REMARKS
NB FLANGE FLANGE FLANGE FLANGE BLIND FLANGE FLANGE
1 25
2 40
3 50
4 80
5 100
6 150
7 200
8 250
9 300
10 350
11 400
12 450
13 500
14 600
15 650
16 700
17 750
18 800
19 850
20 900
9
21 9 950
22 1050
23 1200
24 1350
25 1400
26 1450
27 1500
NOTES :-
1. MATERIAL SPECIFICATION FOR NOZZLE COMPONENTS SUCH AS NOZZLE NECK, FLANGE, REINFORCEMENT PAD, NOZZLE STIFFENER,
STUDS, NUTS AND GASKETS SHALL BE AS PER ENGINEERING DRAWING. NOZZLE REINFORCEMENT AND PROJECTION DETAIL SHALL
BE AS PER ATTACHED STANDARD. BIDDER SHALL NOTE THAT EXTRA CLAIM FOR INCREASE IN NOZZLE PROJECTION UPTO
100MM W.R.T ATTACHED STANDARD SHALL NOT BE PAYABLE.
2. SCOPE OF SUPPLY OF NOZZLE COMPONENTS SHALL BE AS PER MATERIAL REQUISITION.
3. THE RATES QUOTED SHALL INCLUDE SUPPLY OF NOZZLE NECK, FLANGE, STIFFENER, STUDS, NUTS AND GASKETS (WHEN SUPPLIED
WITH BLIND FLANGE) AND ASSOCIATED FABRICATION AND TESTING.
4. PRICES INDICATED ABOVE SHALL BE IRRESPECTIVE OF NOZZLE THICKNESS.NO EXTRA CLAIM ON THIS ACCOUNT WILL BE
ENTERTAINED AT A LATER DATE.
5. THE SCHEDULE OF RATES EXCLUDES COST OF REINFORCEMENT PAD.
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
Page 102 of 434
DOCUMENT No.
UNIT RATES FOR
ADDITION/DELETION A133-16-46-UR-6141
Rev. A
Page 7 of 7
TABLE-1(C)
SCHEDULE OF RATES FOR ADDITION/DELETION OF NOZZLES
SL.NO. NOMINAL SIZE WITHOUT BLIND WITH BLIND WITHOUT BLIND WITH BLIND WITHOUT WITH BLIND REMARKS
NB FLANGE FLANGE FLANGE FLANGE BLIND FLANGE FLANGE
1 25
2 40
3 50
4 80
5 100
6 150
7 200
8 250
9 300
10 350
11 400
12 450
13 500
14 600
15 650
16 700
17 750
18 800
19 850
20 900
9
21 9 950
22 1050
23 1200
24 1350
25 1400
26 1450
27 1500
NOTES :-
1. MATERIAL SPECIFICATION FOR NOZZLE COMPONENTS SUCH AS NOZZLE NECK, FLANGE, REINFORCEMENT PAD, NOZZLE STIFFENER,
STUDS, NUTS AND GASKETS SHALL BE AS PER ENGINEERING DRAWING. NOZZLE REINFORCEMENT AND PROJECTION DETAIL SHALL
BE AS PER ATTACHED STANDARD. BIDDER SHALL NOTE THAT EXTRA CLAIM FOR INCREASE IN NOZZLE PROJECTION UPTO
100MM W.R.T ATTACHED STANDARD SHALL NOT BE PAYABLE.
2. SCOPE OF SUPPLY OF NOZZLE COMPONENTS SHALL BE AS PER MATERIAL REQUISITION.
3. THE RATES QUOTED SHALL INCLUDE SUPPLY OF NOZZLE NECK, FLANGE, STIFFENER, STUDS, NUTS AND GASKETS (WHEN SUPPLIED
WITH BLIND FLANGE) AND ASSOCIATED FABRICATION AND TESTING.
4. PRICES INDICATED ABOVE SHALL BE IRRESPECTIVE OF NOZZLE THICKNESS.NO EXTRA CLAIM ON THIS ACCOUNT WILL BE
ENTERTAINED AT A LATER DATE.
5. THE SCHEDULE OF RATES EXCLUDES COST OF REINFORCEMENT PAD.
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
Page 103 of 434
TECHNICAL COMPLIANCE SHEET DOCUMENT NO.
A133-16-46-TQS-6141
Rev A
Page 1 of 2
Format No. EIL 1641-1924 Rev. 1 Copyrights EIL – All rights reserved
THIS FORM MUST BE DULY FILLED-IN AND RETURNED WITH THE QUOTATION. QUOTATION WITHOUT
THIS FORM DULY FILLED-IN SHALL BE DEEMED AS INCOMPLETE AND NOT TO BE EVALUATED.
Format No. EIL 1641-1924 Rev. 1 Copyrights EIL – All rights reserved
Page 105 of 434
DOCUMENT No.
INSTRUCTIONS TO BIDDERS A133-16-46-TR-6141
Rev. A
Page 1 of 9
INSTRUCTIONS TO BIDDERS
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
Page 106 of 434
DOCUMENT No.
INSTRUCTIONS TO BIDDERS A133-16-46-TR-6141
Rev. A
Page 2 of 9
Bidding Instructions
A) Category-II MR
1. Vendor to note that bid evaluation may be carried out without any post-bid correspondence.
2. Vendor shall furnish quotations only for those items (as per attached vendor list) which he
can supply strictly as per MR specifications including fulfillment of BQC criteria as per MR.
3. If the bid does not include complete scope, technical / performance data, proven track record
etc. required to be submitted with the bid, the offer shall be liable for rejection.
B) It is understood that
1. The quoted price includes for the “HOLDS” details of which are indicated on the Drg.
2. The weights indicated on EIL Engineering Drgs. do not form the basis for offer, since these
are approximations only.
3. Spares included in of doc. A133-16-46-SS-6141 are included in the quoted price.
4. Any decrease/ increase in weights shall be recovered/ paid as per Doc.No. A133-16-46-UR-
6141.
1. The equipment having length more than 20 m and / or forming ‘Gross vehicle weight
(Weight of equipment and the weight of vehicle clubbed together) more than 49 MT
shall be transported by Hydraulic axles only with compliance to all statutory norms of
authorities concerned.
2. Prime mover of the vehicle to have GPS tracking system to monitor the movement of
consignment.
Technical Instructions
1. The shape of dished end/toricone, profile of conical reducer, knuckle radius, cone angle and
overall height shall be as per engineering drawing. Minimum thickness of shell, cone and
dished end shall be achieved taking into account thinning and scaling etc.
2. Dished ends and hot formed pressure parts shall have 10% or 2mm (whichever is higher)
allowance for scaling and thinning, in order to achieve minimum thickness specified on the
drawing.
3. a) Wherever hot forming and subsequent heat treatment is involved, adopted procedure shall
not impair the mechanical properties of the material beyond the limits specified in respective
material specification.
b) For low temperature equipment and hot formed parts, number of production coupons and
the tests thereon shall be as per requisition.
4. Post weld heat treatment and all non destructive testing like radiography, ultrasonic testing,
magnetic particle/dye penetrant examination etc. shall be conducted as per requisition.
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
Page 107 of 434
DOCUMENT No.
INSTRUCTIONS TO BIDDERS A133-16-46-TR-6141
Rev. A
Page 3 of 9
5. The vessels shall be transported in single piece except for Burried vessel Tag no. 86-C-51.
7. Pickling and passivation of internal surfaces of stainless steel shall be carried out as per
ASTM A-380/Job specification no. A133-08-16-46-SP-11 as applicable as per respective
MDS. Procedure shall be furnished for approval/review.
8. For IBR vessels, approval of drawings, documents, stagewise inspection and final
certification of the equipment by Inspectorate of Boilers shall be included in bidder’s scope.
Complete design of equipment as per IBR shall be carried out by vendor.
responsibility of bidder.
10. The main equipment shall not be subcontracted, however bought out items/ components can
be subordered or subcontracted to approved vendors/sub-contractors only. Refer commercial
section and attached vendor list for approved vendors for complete equipment, all raw
material and bought out components.
11. Demister /Agitator shall be procured from approved vendors only ( Refer vendor List attached
in commercial section)
12. Fabricator to supply template for checking the orientation of anchor bolts on foundation and to
ensure matching of base plate that is drilled in advance. The template for foundation shall be
box type and height of template shall be equal to anchor chair base ring, top ring, washer and
nuts. The schedule of supply of template at site shall be 8 weeks from FOA.
13. Gaskets used for hydrotesting of vessels shall be of the same specification as service
gaskets and the fabricator shall supply new gaskets for manholes and nozzles with blind
flanges apart from spares. Gaskets used for hydrotest shall not be used for actual hook up.
14. While transporting vessels, fabricator shall provide suitable type and no. of supports so that
no deformation of any part of the equipment takes place.
15. Fabricator shall exercise utmost care during fabrication so that no damage to any part of the
equipment occurs. Suitable type and no. of supports shall be provided for supporting the
vessels.
16. Fabricator shall also design and provide suitable stiffening arrangement at the base anchor
chair locations so that deformation/buckling of base and bottom zone does not occur at the
time of lifting while the vessels are being erected.
17. Fabricator shall design and provide lugs/trunnions for handling and assembly of vessel
sections.
18. Number of temporary attachments/cleats, lifting lug/trunnion used for site assembly should be
kept minimum. Temporary attachments / cleats shall be removed by fabricator after complete
execution of work if desired by engineer-in-Charge leaving 12mm from the shell & grinding of
all cut edge burrs.
19. If the equipment is to be transported via sea routes (marine transportation), the following shall
be provided by bidder and included in the quoted price:
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
Page 108 of 434
DOCUMENT No.
INSTRUCTIONS TO BIDDERS A133-16-46-TR-6141
Rev. A
Page 4 of 9
After completion of all testing and inspection, the inside of complete equipment shall be
thoroughly drained and dried out. Equipment shall be completely dried by passing hot air for
sufficient time until no further increase in relative humidity of outgoing air is observed. After
drying, the equipment shall be purged and filled with dry N2 at 0.25 kg/cm 2. The equipment
section shall be provided with pressure gauge to monitor N2 pressure and ½ “ non-return
valve. All threaded holes other than tell tale holes for testing shall be suitably protected with
steel bar plugs. All nozzles not provided with blind flange shall be provided with steel covers,
temporary gaskets and bolts. All external surfaces shall be properly protected / covered
against sea environments.
20. Erection weight given in equipment data sheet is approximate. Vendor shall calculate the
actual equipment weight and furnish calculation. Erection weight furnished in vendor drawing
shall be based on fabricator’s calculation. Calculation of Centre of Gravity (C.G.) of the
equipment shall also be done by vendor and marked on the equipment & in the fabrication
GA drawing.
21. For internal distributor pipes, internal flanges shown are minimum required. It is vendor’s
responsibility to provide required number of flanges to ensure removability through nearest
manway.
All production welding shall be examined by RT. In case vendor want to perform UT by TOFD
technique in lieu of RT, the same is acceptable subject to the following:
b) With Code Case 2235, Automated UT incorporating TOFD and pulse echo probes or
TOFD and Phased Array mounted on the same chassis that automatically traverses
along the joints to be inspected and displaying both results simultaneously on a single
screen may be considered in lieu of RT.
c) Calibration block of similar material/thickness shall be used. Calibration block shall have
suitable notches to simulate longitudinal as well as transverse cracks on outside and
inside surface. Setup should be capable of detecting defects on outside as well as
inside while scanning from one surface only.
23. Steel structure to be fabricated in modular forms including electroforged galvanized grating,
handrails, stairs, toe guard at vendor’s shop. Platforms shall be transported to site with
identification & match marking for assembly and erection at site. Installation and erection of
platform is excluded from bidder’s scope. Shot blasting, and primer shall also be completed
at shop for platform components as applicable.
General Instructions
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
Page 109 of 434
DOCUMENT No.
INSTRUCTIONS TO BIDDERS A133-16-46-TR-6141
Rev. A
Page 5 of 9
1. Stage wise & final inspection of the vessel shall be by Third Party Inspection Agency
(Refer commercial documents for list of approved agencies). Fabrication shall not commence
before their approval except as noted at Sl. No. 2 & 3.
2. Raw material procurement may proceed prior to approval of vendor drawings on the basis of
Material Requisition and all testing and agency for testing shall be arranged by Vendor.
3. Shell rolling/welding and dished - head fabrication shall commence without awaiting
fabrication drawing approval. Inspection shall be carried out in accordance with Purchase
Requisition documents till approved fabrication drawings are available.
4. Material for shell, dished ends and skirt shall be considered as major raw material wherever
identification of major raw material is one of the payment milestones.
5. Purchase requisition shall be issued within two weeks of Fax of intent (FOI). Final nozzle
sizes (without any holds) shall be issued along with purchase requisition or latest within one
month of Fax of intent (FOI).
6. Nozzle orientation of the equipment shall be issued latest by mid of contractual delivery
period reckoned from date of issue of Fax of intent (FOI) .
7. Pipe support/structural clip details shall be issued latest by three months before contractual
delivery date.
8. Approved for construction (AFC) drawings of platforms shall be issued latest by three months
before contractual delivery date.
9. Minimum course width shall be 1 metre. Maximum no. of longitudinal seams shall be as
follows:
(a) vessels upto 2 metre diameter : 1 seam
(b) vessels from 2 metre upto 4 metre dia. : 2 seam
(c) vessels from 4 metre upto 6 metre dia. : 3 seam
(d) vessels from 6 metre upto 10 metre dia. : 9 seam
In any case, distance between two longitudinal seams shall not be less than 3 meters. .
10. If any discrepancy is found during design and fabrication stages, the fabricator shall inform
EIL immediately and shall obtain necessary clarification/approval before proceeding with that
portion of the job any further. EIL's review of fabricator's drawings and documents must not
be considered as a check and shall not relieve the fabricator of his responsibilities to supply
equipment as per requisition. Fabricator shall remain responsible for conflicts between his
drawings/documents and EIL drawings/documents.
11. English language and metric units shall be used in all documents. Drawings shall be prepared
in prescribed sizes as standardised by bureau of indian standards (BIS) and shall be
preferably in the sizes such as 210 x 297, 297 x 420, 420 x 597, 597 x 841, 841 x 1189 mm.
12. All fabricator's drawings submitted to EIL shall be based on purchase requisition and shall
bear reference number and revision of the corresponding EIL drawings. It shall indicate the
following in the lower right hand corner. All revisions shall be clearly marked by encircling
with revision marks.
Item Number
Owner name and logo. (attached with MR)
PMC name and logo. (attached with MR)
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
Page 110 of 434
DOCUMENT No.
INSTRUCTIONS TO BIDDERS A133-16-46-TR-6141
Rev. A
Page 6 of 9
a). Vendor shall prepare Document Control Index (list of those drawings, which are to be
submitted to EIL along with the submission dates for each drawing) within 15 days of
placement of FOI. Successful bidder to submit DCI (document control index) and all
the vendor data through vendor portal (http://edocx.eil.co.in:7001/vportal) and refer
general note-3 of Vendor data requirements document (Doc. No. A133-086-16-46-VDR-
6135). The detail guidelines for uploading the documents on vendor portal are
available on the site itself. Successful bidder to submit all the documents as
scheduled documents only.
b). Vendor to note that unscheduled documents (documents which are not listed in DCI)
shall not be accepted by EIL. All vendor drawings/documents shall be submitted as
scheduled document only.
15. All drawings shall be thoroughly checked and duly signed by fabricator. Unchecked drawings
and drawings without revisions clearly marked shall be returned without review. Successive
review of the same fabricator's drawing shall apply only to EIL's latest data sheet/comments
on the previous revision. Drawings and documents returned to fabricator for revision shall be
resubmitted preferably within ten days of receipt.
16. Dimensions of all flanges shall be as per ANSI B16.5 for nozzle sizes 24"NB and below and
as per ANSI B16.47 Series B for sizes greater than 24"NB, unless otherwise stated.
Stage-I
- General arrangement drawing indicating design data, fabricated equipment's weight,
general notes, nozzle schedule, detail of shell, heads, skirt/supporting arrangement, main
weld seams, nozzle orientation plan, cutting layout (in case of free issue material) etc.
- Bill of material for each item showing part size, quantity, material specification, scope of
supply and weight etc.
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
Page 111 of 434
DOCUMENT No.
INSTRUCTIONS TO BIDDERS A133-16-46-TR-6141
Rev. A
Page 7 of 9
Stage-II
- Detail of internals such as tray support ring and bolting bar.
- Detail of external clips for ladder, platform, pipe support, insulation, fire proofing, pipe davit,
lifting lugs etc.
- Bill of material for each item showing part size, quantity, material specification, scope of
supply and weight etc.
- In case of owner's free issue plate material, fabricator shall submit plate cutting diagram for
EIL's approval.
18. After receipt of order, fabricator shall submit to EIL, the planning of fabrication which shall
indicate the details and scheduled date of:
- Sub orders.
- Purchase of materials such as plates, pipes, forged flanges, bolting, gaskets, etc.
- Start of fabrication of dished ends and shell, welding of shell and heads.
This planning shall be established to extend from purchasing of equipment components to the
end of fabrication and delivery of equipment.
19. All drawings shall be drawn in AUTOCAD R-14.No hand drawn drawings shall be accepted.
All residual calculations shall be computerised.
20. Documents and letters shall be furnished in electronic format. The software used shall be as
follows.
a) MS OFFICE 97 or above
b) ADOBE ACROBAT 4.0 & ABOVE
21. In case of owner's free issue plate material, fabricator shall tabulate each plate detail as per
following table:
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
Page 112 of 434
DOCUMENT No.
INSTRUCTIONS TO BIDDERS A133-16-46-TR-6141
Rev. A
Page 8 of 9
22. Words “fabricator”, “vendor”, “contractor” appearing any where in the MR/Specifications/
Standards etc. shall be read as “bidder”.
23. Further to pt. No. 9 of General Instructions; Bidder to note that interference of nozzles
with circumferential seams is not acceptable. However, vendor to take suitable care to
avoid fouling of external/internal attachments with C-seams. Vendor to submit shell
development for checking above in the 1st submission.
24. Vendor shall note that the vendor drawing for the following standard components shall not be
reviewed by EIL. It shall be solely vendor's responsibility to ensure the correctness of these
drawings as per EIL Standards and Drawings. If any discrepancy / mistake is found at a later
date the vendor shall rectify the same at his time and cost.
However, all these above listed drawing shall be submitted in a separate drawing for
information to EIL ensuring adherence to all the respective EIL Standards and Drawings.
Clarifications (if any) shall be obtained by Vendor from EIL before fabrication.
25. Standard Inspection and test plans are attached with requisition for guidance. Vendor shall
submit inspection test plans for the approval of visiting inspection engineer. Inspection shall
take care of all the requirements of specifications. Inspection engineer has the authority to
modify the plan depending on the criticality of the item.
26. In the event of conflict, most stringent requirement in following order of precedence shall
govern:
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
Page 113 of 434
DOCUMENT No.
INSTRUCTIONS TO BIDDERS A133-16-46-TR-6141
Rev. A
Page 9 of 9
However in event of conflict it shall be the duty of the Vendor to bring it to EIL’s attention for
resolution and resolve it before proceeding with the manufacture. EIL’s comments shall be
final and binding on vendor without any cost and delivery implications.
ADDITIONAL REQUIREMENTS:
1.0 The following formats are attached with the MR. The same shall be filled by vendor with
each transmittal, submitted to EIL for approval/review or records.
2.0 Vendor shall furnish itemized price list for 2 years normal operation and maintenance
spares, if any.
3.0 Access to Client/TPIA/EIL/PMC shall be provided at all times for inspection at fabrication
yard during execution of the job.
4.0 FOR PRESERVATION AT SITE: Non stick/washable coating of approved make shall be
applied inside the complete equipment to protect/preserve the equipment. The coating shall
be completely removable by water. The coating shall be suitable for protecting the
equipment at least for 6 months.
Vendor to apply the coating before dispatching the equipment. Localized coating at location
of site seam to be performed at site.
5.0 SPIR form duly filled shall be furnished by vendor after code-2 approval of the drawings.
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
Page 114 of 434
LIST OF APPLICABLE DOCUMENT No.
SPECIFICATIONS AND A133-16-46-LL-6141
STANDARDS Rev. A
Page 1 of 6
LIST OF APPLICABLE
SPECIFICATIONS & STANDARDS
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
SCOPE OF SUPPLY
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
SCOPE OF SUPPLY
1. Owner
[] Shell
[] Skirt
[] Manhole neck, nozzle neck 300 NB and above in carbon steel and 125 NB and above
in stainless steel
[] Reinforcement pad
[] Wrapper plate
[] Internal piping
[] Insulation support
[] Lifting lugs
[] Baffle
[] Demister support
[] Pipe fitting
[] Gasket
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
[] Brick lining
[] Refractory lining
[] Spray nozzles
[] Tower packing & associated internals including distributor (as indicated in respective
MDS), feed pipes, support grid / plates, retaining grid / bed limiters etc associated
with packing.
[X] Thermowells
2. VENDOR
2.1 Boiler quality/low alloy/stainless steel/ clad steel / Monel plate conforming to
specification as indicated in respective vessel mechanical data sheets for :-
[X] Shell
[X] Dished head/intermediate head/cone / toricone.
[X] Sump and sump head
[X] Skirt (part)/ Anchor chair/ Base plate/Lug/ intermediate skirt
[X] Manhole neck, nozzle neck above 300 NB in carbon steel and 125 NB and above in
stainless steel & 350 NB and above and in clad steel shall be fabricated from clad
plate.
[X] Reinforcement pad / Insert plate
[X] Wrapper plate
[X] Plate type flange
[X] Internal piping
[ ] Tray support ring/bolting bar/seal pan and their supports welded to the vessel
[X] Pad for external attachment
[X] Fire proofing and insulation support
[ ] Saddle support/bracket/leg support
[X] Lifting lug/ trunions
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
[X] Vacuum stiffening rings, structural & Piping cleats (welded directly over shell / head)
[X] All welded support for packing, distributors, chimney trays, other internals etc
[X] All plate fabricated welded/removable attachments like manhole in partition baffle,
supporting members etc.
2.2 Structural steel section and plate conforming to IS:226/IS:2062 Gr.B / SA-283 Gr.C
for
[ ] Shell
[X] Skirt/anchor chair/base plate/saddle and bracket support
[ ] Internals
[X] Insulation support/fire proofing support over BQCS pad or on skirt (IS 2062 portion)
[ ] Flat cover
[ ] Manway flange/cover
[ ] Tailing lug in skirt portion /Trunion with BQCS pad
[X] Structural/Piping clips welded over BQCS pad or on skirt (IS 2062 portion)
[ ] Section for stiffeners for skirt base/anchor block
[ ] Leg supports and base plate
[X] Studs/bolts and nuts for manway/handholes/internal flanges /nozzles with matching
flange/shell flange, including jack bolts for manway
[X] Gasket for manway/handhole/internal flange/shell flange/ nozzles shown with blind
flanges
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
[X] Seamless nozzle neck 300 NB and below in carbon steel & weld overlayed nozzles
[ ] Spray nozzle
[ ] Internal packing
[ ] Light and sight glass assembly with 4 sets of spare glasses for each size
[X] All other metallic and non-metallic parts, consumables and gases not covered under
1 and 2 but required to complete fabricated equipments including inspection, testing
and supply of equipments as per this requisition
[X] Mandatory spares - 10% of fasteners (minimum two numbers for each size) and two
sets of gaskets for each nozzle shown with blind flange/for each shell flange/for all
internal flanges
[X] Commissioning spares - 10% of fasteners (minimum two numbers of each size) and
one set of gaskets for each nozzle shown with blind flange/for each shell flange/for
all internal flanges
[ ] Spares( demister) - 10% (min. 4 nos. Of each size/type) extra fasteners (bolts,nuts,
clamps, spacers etc.) as required for holding the demister
[X] The Monkey ladder inside the skirt.
[X] Supply of all materials, fabrication of all platforms, ladders, cage ladders,
hand railing, hot dip electroforged galvanized grating and other structural
works as per schedule of quantities attached with MR.
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
PART : V
SECTION : 3.4
TABLE OF CONTENTS
1.0 SCOPE
2.0 DEFINITIONS
7.0 MARKING
8.0 ATTACHMENTS
8.1 TYPICAL POSITIVE MATERIAL IDENTIFICATION REPORT FORM – ALLOY STEEL BULK
MATERIAL
1.0 SCOPE
1.1 This specification applies to the requirements for Positive Material Identification (PMI) to be
performed at vendor’s works on Metallic Alloy Materials procured either directly by Vendor or
indirectly through their sub-vendors. Any deviations from this specification must be approved by
Purchaser in the deviation / Waiver permit format. This specification shall also be read in
conjunction with positive material identification at site.
1.2 This Specification covers the procedures and methodology to be adopted to assure that the
chemical composition of alloy material is consistent with the material specification as specified in
purchase documents using alloy analyser at the time of final inspection before despatch.
1.3 The scope of this specification shall include but not limited to Positive Material identification (PMI) to
be performed on Alloy Piping Materials listed below :
However all grades of materials including stainless steel are subjected to PMI verification / test after
receipt at site.
2.0 DEFINITIONS
2.1 Vendor : Any supplier or manufacturers on whom an order is placed for supply of referred piping
items. This definition shall also include any sub-vendor or manufacturers on whom a sub-order is
placed by the vendor.
2.2 Inspection Lot : A group of items offered for Inspection covered under same size, heat and heat
treatment lot.
2.3 Alloy Material : Any metallic material (including welding filler materials) that contains alloying
elements such as chromium, nickel, molybdenum, vanadium, etc which are intentionally added to
enhance mechanical or physical properties and/or corrosion resistance.
3.1 The Vendor shall submit a procedure of PMI to comply with the requirements of this Specification.
Approval of PMI procedure shall be obtained from Purchaser prior to commencing manufacturer /
inspection of product.
3.2 PMI examination of alloy materials is independent of any certification, markings of colour coding that
may exist and is aimed at verifying that the alloy used are as per specified grades.
3.3 The Vendor shall identify all incoming alloy materials and maintain full traceability of all alloy
materials, including all off-cuts. Transfer of identification marks shall be undertaken prior to cutting
to ensure maintenance of identification on off-cuts.
3.4 The Vendor shall ensure that all materials are segregated and stored in separately identified
locations to prevent the mix-up of materials of different alloy specifications or alloy material with
carbon steel. Non-ferro-magnetic materials shall be segregated at all times from ferro – magnetic
materials.
3.5 PMI examination is subject to surveillance inspection by Vendor / Jacobs / Third Party Inspection
Agency / Purchaser as specified in Quality Assurance Plan.
4.1 The Method used for PMI examination shall provide a quantitative determination of the alloying
elements like Cr, Mo, Ni, V in Alloy Steel items. For Non-Ferrous alloys quantitative determination of
appropriate alloying elements shall be verified.
4.2 Instruments or methods used for PMI examination shall be of those that will provide quantitative,
recordable, elemental composition results for positive identification of alloying elements present.
4.3 The acceptable instrument for alloy analyser shall be either “Portable X-ray fluorescence” or “Optical
Emission Spectro Analyser” type capable of verifying the percentage of alloy elements within
specified range.
4.4 Chemical spot testing, magnets, alloy sorters and other methods using eddy current methods are
not acceptable for PMI examination.
4.5 The PMI instrument used shall have the sensitivity to detect the alloying elements in the specified
range.
4.6 Each analyser must be calibrated according to the manufacturer’s specification at the beginning and
end of each shift. Instrument must be checked against known standard for each alloy type to be
inspected during the shift.
4.7 Certified samples with full traceability of “known” alloy materials shall be available for use as a
random spot check on the instrument calibration.
4.8 The surface to be examined shall be prepared by light grinding or abrasive paper and solvent
cleaner. Evidence of arc burn resulting from examination shall be removed by light grinding or
abrasive paper.
4.9 Alloy steel type joint gaskets shall only be inspected by using portable X-ray fluorescence
instrument.
4.10 Testing shall be done as per the procedures outlined by the manufactures of alloy analyser being
used. Modification of these procedures if any, must be approved by Purchaser.
4.11 The persons performing PMI shall demonstrate their capabilities to the satisfaction of
Owner/Jacobs/Third Party Inspection Engineer. If the vendor has qualified operator in his rolls, he
may perform the examination. Otherwise PMI examination shall be sub contracted to an
independent testing agency.
4.12 Whenever materials, items and welds are identified as not meeting requirements by the visiting
engineer a rejection note shall be issued. The above shall be marked with a red “R” pending
resolution.
Following sampling plans shall be applicable for PMI examination of various alloy items.
The results of PMI examination shall be recorded in the PMI Report Form as enclosed with this
specification.
7.0 MARKING
7.1 All alloy materials tested by PMI shall be identified using either of the following methods by
indicating “AV”
a) Electro – etching
b) A low stress stamp marking
c) Hologram Sticker
d) Vibro – etching
e) Colour Coding
Location of markings will be near to vendor’s monogram, material specification, heat number / cast
number, welders stamp, etc as applicable.
8.0 ATTACHMENTS
As enclosed.
ATTACHMENT 8.1
TYPICAL POSITIVE MATERIAL IDENTIFICATION REPORT : ALLOY STEEL
Page ….of ….
BULK MATERIALS
Project : Client : Job No. :
Source Age
Instrument Type / ID
Source dt.
Last Service Date :
PMI Examination Approved by
Witnessed by
by : Vendor
Company
1"1' 0
125
M IS NAME OF MANUFACTURER
DESIGNED BY I I OWNER I
cs,
ITEM NO. I I JOB NO. I rs,
, P.O. NO. I I YEAR OF FABRICATION I
(.1
D in CODES I INSPECTED BY I ,
IN N. I
DESIGN PRESSURE I I DESIGN TEMPERATURE I
CORROSION ALLOW. I I RADIOGRAPHY I
cs,
TEST PRESSURE I I EMPTY WEIGHT I
rs,
4,st- I
4" DATE OF TEST I
el
5R
4.50 HOLE 2
28 26 28
BRACKET
NAME /
PLATE
NOTES
ALL DIMENSIONS ARE IN mm UNLESS OTHERWISE SPECIFIED.
ALL LETTERS, BLOCKS AND BORDERS SHALL BE RAISED POLISHED FACE.
BACKGROUND SHALL BE BLACK.
NAME PLATE SHALL BE TACK—WELDED TO THE BRACKET. WHERE NOT POSSIBLE
IT MAY BE RIVETTED.
NAME PLATE SHALL BE OF STAINLESS STEEL OF 2mm THICK.
BRACKET MATERIAL SHALL BE SAME AS SHELL MATERIAL.
4
3
31.08.2011
12.10.2006
REAFFIRMED AND REISSUED AS STANDARD
REAFFIRMED AND REISSUED AS STANDARD
POREL
POREL
A41
KT
RKG
A.D‘>)
kAAr914/1"/
KM / SC
AKM
DM
VC
Rev. Prepared Checked Stds. Committee Stds. Bureau
Date Purpose Convenor Chairman
No. by by
Approved by
Page 137 of 434 Copyright EIL - All rights reserved
Format No. 8-00-0001-F4 Rev.0
Page 138 of 434
Page 139 of 434
ANNEXURE - I
QUALITY PLAN (Design Function) Document Number
Organisation DIVISION / Document Number
DEPARTMENT : Revision Number Sheet of
Under present constraints, requested waiver / deviation is most optimum for the project and does not involve any security and
safety hazard
Date Signature
Contractor / Vendor(With Seal) / Jacobs
Decision on waiver / deviation with remarks, if any, on time / cost implications
(To be filled by the department / division in Jacobs responsible for conveying to the originator)
Signature : _________________________
Date : _____________
Name : _____________________________
FORWARDED TO __________________
(Target Resolution Div / Dept./Group)
PART : III
SECTION : B.12
TABLE OF CONTENTS
1.0 General
2.0 Scope
3.0 Codes & Standards
4.0 Equipment
5.0 Surface Preparation
6.0 Paint Materials
7.0 Paint Systems
7.1 Pre-erection / Pre-fabrication and shop priming for carbon steel, low temperature carbon
steel & low alloy steel, un-insulated and insulated steel structures, piping and equipment,
etc.,
7.2 Repair of pre-erection /fabrication and shop priming after erection / welding for carbon steel,
low temperature carbon steel & low alloy steel uninsulated and insulated items in all
environments.
7.3 Repair of all weld joints and damages of galvanized steel, carbon steel and alloy steel
structures, piping and equipment after erection on above ground / overhead areas at site.
8.0 Field paint system for normal corrosive environment (for carbon steel, low temperature
carbon steel and low alloy steel)
9.0 Field paint system for corrosive areas in plant (for carbon steel, low temperature carbon
steel and low alloy steel)
10.0 Field paint system for highly corrosive areas in plant (for carbon steel, low temperature
carbon steel and low alloy steel)external surfaces of piping & equipment
11.0 Field paint system for carbon steel storage tanks (internal & external) for all environment
and areas
12.0 Coating system for external side of underground carbon steel plant piping and tanks
13.0 Painting under insulation for (hot, cold & safety) Carbon Steel plant piping and tanks
14.0 Internal protection of Carbon Steel water boxes and tube sheets of cooler condensers
15.0 Field painting system for GI towers / Non-Ferrous tueb sheet
16.0 Shop & Field painting system for Effluent treatment plant
17.0 Storage
18.0 Color code for piping as per CPCL
19.0 Identification of vessels, piping, etc.,
20.0 Painting for civil defence requirements
21.0 Inspection and testing
22.0 Guarantee
23.0 Qualification criteria of painting contractor
1.0 GENERAL
1.1 These technical specifications shall be applicable for the work covered by the contract and
without prejudice to the various codes of practice, standard specifications, etc. It is understood
that Contractor shall carry out the work in all respects with the best quality of materials and
workmanship and in accordance with the best engineering practice and instructions of Engineer-
in-Charge.
1.2 1 Wherever it is stated in the specification that a specific material is to be supplied or a specific
work is to be done, it shall be deemed that the same shall be supplied or carried out by the
contractor. Any deviation from this standard without written deviation permit from appropriate
authority will result in rejection of job.
2.0 SCOPE
2.1 Scope of work covered in the specification shall include, without being limited to the following
2.1.1 This specification defines the requirements for surface preparation, selection and application of
paints on external surfaces of equipment, vessels, machinery, piping, ducts, steel structures,
external & internal protection of storage tanks for all services. MS chimney without refractory
lining and flare lines etc. The items listed in the heading of tables of paint systems is indicative
only, however the contractor is fully responsible for carrying out all the necessary painting,
coating and lining on external and internal surfaces as per the tender requirement.
2.2.1 The following surfaces and materials shall require shop, pre-erection and field painting :
a. All un-insulated C.S & A.S equipment like columns, vessels, drums, storage tanks, heat
exchangers, pumps, compressors, electrical panels and motors etc., and tanks and
equipment in ETP plant.
b. All un-insulated carbon and low alloy piping fittings and valves (including painting of
identification marks), furnace, ducts and stacks.
d. All structural steel work, pipe, structural steel supports, walkways, handrails, ladders,
platforms, etc.
f. Identification color bands on all piping as required including insulated aluminum clad,
galvanized, SS and nonferrous piping.
i. Supply of all primers, paints and all other materials required for painting other than Owner’s
supply.
k. Painting under insulation for carbon steel, alloy steel and stainless steel as specified. 1
l. Repair work of damaged / pre-erection / fabrication shop primer and weld joints at field.
2.2.2 The following surfaces and materials shall not require painting in general. However, if there are
any specific requirement by the Owner, the same shall be painted as per the relevant
specifications:
2.3 Unless otherwise instructed final painting on pre-erection / shop primed pipes and equipments
shall be painted in the field, only after the mechanical completion, testing on systems are
completed as well as after completion of steam purging wherever required.
2.4 Changes and deviations required for any specific job due to clients requirements or otherwise
shall be referred to Jacobs for deviation permit.
3.1 Without prejudice to the provision of Clause 1.1 above and the detailed specifications of the
contract, the following codes and standards shall be followed for the work covered by the
contract.
Color coding Color coding inspection manual for piping issued by CPCL (Ref.
Annexure-2) 1
ASA A 13.1-1981 Scheme for identification of piping systems: American National Standards
Institution.
3.2.1 Swedish Standard – SIS-05 5900-1967 (surface preparation standards for painting steel surfaces)
This standard contains photographs of the various standards on four different degrees of rusted
steel and as such is preferable for inspection purpose by the Engineer-in-Charge.
3.2.2 Steel Structures Painting Council, U.S.A (Surface Preparation Specifications (SSPC-SP).
3.2.5 Various International Standards equivalent to Swedish Standard for surface preparations are
given in Table-I.
3.3 The contractor shall arrange, at his own cost, to keep a set of latest edition of above standards
and codes at site.
3.4 The paint manufacturer’s instructions shall be followed as far as practicable at all times.
Particular attention shall be paid to the following :
4.0 EQUIPMENT
4.1 All tools, brushes, rollers, spray guns, blast material, hand power tools for cleaning, inspection
instruments, e.g. surface profile gauges, holiday detectors, pin hole detectors, dry film thickness
gauges, etc. and all equipments, scaffolding materials, shot blasting equipments like hooper, grit
etc & air compressors, etc., required to be used shall be suitable for the work and all in good
order and shall be arranged by the Contractor at site and in sufficient quantity. 1
4.2 Mechanical mixing shall be used for paint mixing operations in case of two pack systems except
that the Engineer-in-Charge may allow the hand mixing of small quantities at his discretion.
5.1 General
5.1.1 In order to achieve the maximum durability, blast cleaning is considered the most desirable
method to achieve required profile however one or more of following methods of surface
preparation shall be followed, depending on conditions of steel surface and as instructed by
Engineer-in-Charge. Adhesion of the paint film to surface depends largely on the degree of
cleanliness and surface profile of the metal surface. Proper surface preparation contributes more
to the success of the paint protective system.
5.1.2 Mill scale, rust, rust scale and foreign matter shall be removed fully to ensure that a clean and dry
surface is obtained. The minimum acceptable standard in case of manual or hand tool cleaning
shall be St. 2 or equivalent, in case of mechanical or power tool cleaning it shall be St. 3 or
equivalent in case of blast cleaning it shall be Sa 2-1/2 OR equivalent as per Swedish Standard
SIS-055900-1967 or equivalent. Where highly corrosive conditions exist, then blast cleaning shall
be Sa 3 as per Swedish Standard.
Remove all other contaminants, oil, grease, etc. by use of an aromatic solvent prior to surface
cleaning.
5.1.3 Blast cleaning shall not be performed where dust can contaminate surfaces undergoing such
cleaning or during humid weather conditions having humidity exceed 85%.
5.1.4 Irrespective of the method of surface preparation, the first coat of primer must be applied by
airless spray gun on dry surface No brush shall be used except for touchup. This should be done
immediately and in any case within 4 hours of cleaning of surface. However, at times of
unfavorable weather conditions, the Engineer-In-Charge shall have the liberty to control the time
period, at his sole discretion and / or to insist on re-cleaning, as may be required, before primer
application is taken up. In general, during unfavorable weather conditions, blasting and painting
shall be avoided as far as practicable. 1
5.1.5 The external surface of RCC chimney to be painted shall be dry and clean. Any loose particle of
sand, cement, aggregate etc., shall be removed by scrubbing with soft wire brush if necessary
acid etching with 10-15% HCl solution for about 15 minutes shall be carried and surface must be
thoroughly washed with water to remove acid & loose particles then dry completely before
application of paint.
The surfaces shall be blast cleaned using one of the abrasives Al2O3 particles chilled cast iron or
malleable iron and steel at pressure of 7 Kg /cm2 at appropriate distance and angle depending of
nozzle size maintaining constant velocity and pressure. Chilled cast iron, malleable iron and steel
shall be in the form of shot or grit of size not greater than 0.055” maximum in case of steel and
malleable iron and 0.04” maximum in case of chilled iron. Compressed air shall be free from
moisture and oil. The blasting nozzles should be venturi style with tungsten carbide or boron
carbide as the materials for liners. Nozzles orifice may vary from 3/16” to ¾”. On completion of
blasting operation, the blasted surface shall be clean and free from any scale or rust and must
show a grey white metallic luster. Primer or first coat of paint shall be applied within 4 hours of
surface preparation. Blast cleaning shall not be done outdoors in bad weather without adequate
protection or when there is dew on the metal, which is to be cleaned. Surface profile shall be
uniform to provide good key to the paint adhesion (i.e. 35 to 50 microns). If possible vacuum
collector shall be installed for collecting the abrasives and recycling.
Environmental, health and safety problems associated with abrasive blast cleaning limit the
application of Air Blast Cleaning in many installations. In such case water blast cleaning is
resorted to.
Water Blast Cleaning can be applied with or without abrasive and high pressure water blasting.
The water used shall be inhibited with sodium chromate / phosphate. The blast-cleaned surface
shall be washed thoroughly with detergents and wiped with solvent and dried with compressed
air. For effective cleaning abrasives are used. The most commonly used pressure for high
pressure water blast cleaning for maintenance surface preparation is 3000 to 6000 psi at 35-45
lit/minute water volume and pressures upto 1000 psi and water volume at 45 lit/minute provide
maximum cleaning.
The water blast cleaned surface shall be comparable to SSPC-SP-12/nace No. 5. The operation
shall be carried out as per SSPC guidelines for water blast cleaning. The indicative values for
sand injection is :
Special equipments for water blast cleaning with abrasives, now available, shall be used.
Power tool cleaning shall be done by mechanical striking tools, Chipping hammers, grinding
wheels or rotating steel wire brushes. Excessive burnish of surface shall be avoided as it can
reduce paint adhesion. On completion of cleaning, the detached rust mill scale etc. shall be
removed by clean rags and / or washed by water or stream and thoroughly dried with compressed
air jet before application of paint.
Manual or hand tool cleaning is used only where safety problems limit the application of other
surface preparation procedure and there is approach problem in certain areas and hence does
not appear in the tables of paint systems.
Rust, mill scale spatters, old coatings and other foreign matter, shall be removed by hammering,
scrapping tools, emery paper cleaning, wire brushing or combination of the above methods. On
completion of cleaning, loose material shall be removed from the surface by clean rags and the
surface shall be bushed, swept, dusted and blow off with compressed air/steam to remove all
loose matter. Finally the surface may be washed with water and dried for effective cleaning.
The compatibility of finishing coat should be confirmed from the paint manufacturer. In the event
of use of primer such as zinc rich epoxy, inorganic zinc silicate etc., as shop coat, the paint
system shall depend on condition of shop coat. If the shop coat is in satisfactory condition
showing no major defect, the shop coat shall not be removed. However a non-compatible primer
shall have to be removed before application of compatible paint system for the environment. The
touch up primer and finishing coat(s) shall be identified for application by Engineer-in-Charge.
5.4 Shop coated (coated with primer & finishing coat) equipment should not be repainted unless paint
is damaged.
5.5 Shop primed equipment and surfaces will only be ‘spot cleaned’ in damaged areas by means of
power tool brush cleaning or hand tool cleaning and then spot primed before applying one coat of
field primer unless otherwise specified. If shop primer is not compatible with field primer then
shop-coated primer should be completely removed before application of selected paint system for
particular environment.
5.6 For Package units / equipment, shop primer should be as per the paint system given in this
specification. However, manufacturer’s standard can be followed after review.
5.7.1 Surface shall not be coated in rain, wind or in environment where injurious airborne elements
0
exists, when the steel surface temperature is less than 5 F above dew point when the relative
0
humidity is greater than 85% or when the temperature is below 40 F.
5.7.2 Blast cleaned surface shall be coated with one complete application of primer as soon as
practicable but in no case later than 4 hrs. the same day.
5.7.3 To the maximum extent practicable, each coat of material shall be applied as a continuous film
uniform thickness free of probes. Any spots or areas missed in application shall be recoated and
permitted to dry before the next coat is applied. Applied paint should have the desired wet film
thickness.
5.7.4 Each coat shall be in proper state of cure or dryness before the application of succeeding coat.
Material shall be considered dry for recoating when an additional coat can be applied without the
development of any detrimental film irregularities, such as lifting or loss of adhesion of the under
coat. Manufacturer instruction shall be followed for inter-coat interval.
5.7.5 When the successive coat of the same color have been specified, alternate coat shall be tinted,
when practical, sufficiently to produce enough contrast to indicate complete coverage of the
surface. The tinting material shall be compatible with the material and not detrimental to its
service life.
5.7.6 Deleted 1
5.7.7 Airless spray application shall be in accordance with the following procedure : as per steel
structure paint Manual Vol. 1 & Vol. 2 by SSPC, USA. Air less spray relies on hydraulic pressure
rather than air atomization to produce the desired spray. An air compressor or electric motor is
used to operate a pump to produce pressures of 1000 to 6000 psi, paint is delivered to the spray
gun at this pressure through a single hose within the gun, a single paint stream is divided into
separate streams, which are forced through a small orifice resulting in atomization of paint without
the use of air. This results in more rapid coverage with less over spray. Airless spray usually is
faster, cleaner, more economical and easier to use than conventional air spray.
Airless spray equipment is mounted on wheels, and paint is aspirated in a hose that sucks paint
from any container, including drums. The unit shall have inbuilt agitator that keep the paint
uniformly mixed during the spraying. The unit shall consist of inbuilt strainer. Usually very small
quantity of thinning is required before spray. In case of high build epoxy coating (two pack), 30:1
pump ratio and 0.020-0.023” tip size will provide a good spray pattern. Ideally fluid hoses should
not be less than 3/8” ID and not longer than 50 ft. to obtain optimum results.
a. Brushes shall be of a style and quality that will enable proper application of paint.
b. Round or oval brushes are most suitable for rivets, bolts, irregular surface and rough or pitted
steel. Wide flat brushes are suitable for large flat areas, but they shall not have width over
five inches.
5.7.9 Manual application by sling (where 6 o’ clock position of pipe is not approachable)
A canvas strip (alternatively a tinplate strip) about 450mm wide and 1.5m long is held under the
pipe by two men holding this sling move it up and down and walk slowly forward while fresh
coating is poured on the pipe and they manipulate the sling so that an even coating is obtained all
round the bottom. This work shall be done very carefully and by experienced personnel. There
shall not be any formation of “Whiskers” and holes in the coating. The coating film shall be
inspected by mirror.
5.7.10 For each coat the painter should know the WFT corresponding to the specified DFT and
standardize the paint application technique to achieve the desired WFT. This has to be ensured
in the qualification trial.
5.8.1 No coat shall be applied until the preceding coat has dried. The material shall be considered dry
for re-coating when another coat can be applied without the development of any film irregularities
such as lifting or loss of adhesion of undercoats. Drying time of the applied coat should not
exceed maximum specified for it as a first coat; if it exceeds the paint material has possibly
deteriorated or mixing is faulty.
5.8.2 No paint shall be force dried under conditions which will cause checking, wrinkling, blistering
formation of pores, or detrimentally affect the conditions of the paint.
5.8.3 No drier shall be added to paint on the job unless specifically called for in the manufacturer’s
specification for the paint.
5.8.4 Paint shall be protected from rain, condensation, contamination, snow and freezing until dry to
the fullest extent practicable.
5.9 Repair of damaged paint surface
5.9.1 Where paint has been damaged in handling and in transportation, the repair of damaged coating
of pre-erection / fabrication shall be as given below.
5.9.2 Repair of damaged inorganic zinc silicate primer after erection / welding.
Quickly remove the primer from damaged area by mechanical scrapping and emery paper to
expose the white metal. Blast clean the surface if possible. Feather the primer over the intact
adjacent surface surrounding the damaged area by emery paper.
0 0
5.9.3 Repair of damaged pre-erection and shop priming in the design temperature of –90 C to 400 C
• One coat of F-9 shall be applied wherever damage was observed on pre-erection / pre-
fabrication / shop primer of inorganic zinc silicate coating (F-9).
5.10.1 Shop priming / pre-erection priming with F9 or F12 shall be done only on blasted surface.
5.10.2 Shop priming / pre-erection priming with F9 shall be done only with airless spray.
5.10.3 For large flat surface field painting shall be done by airless spray otherwise brush can be used.
5.11 Documentation
5.11.1 A written quality plan with procedure for qualification trials and for the actual work.
5.11.2 Daily progress report with details of weather conditions, particular of applications, no. of coats
and type of materials applied, anomalies, progress of work versus program.
5.11.3 Results of measurement of temperatures relative humidity, surface profile, film thickness, holiday
detection, adhesion tests with signature of appropriate authority.
5.11.4 Particulars of surface preparation and paint application during trials and during the work.
Paint manufacturers shall furnish the characteristics of all paints materials on printed literature
along with the test certificate for all specified characteristics given in this specification. All the paint
materials shall be on first quality and conform to the following general characteristics. As per the
tables 6.1, 6.2 and 6.3.
Sr.
Description P-2 P-4 P-6
No.
2. Type and Single pack, air drying Two pack Two component polyamide
composition chlorinated rubber based polyvinyl butyral cured epoxy resin medium-
medium plasticised with resin medium pigmented with zinc
unsaponifiable plasticizer, cured with phosphate.
pigmented with zinc phosphoric acid
phosphate solution
pigmented with
zinc tetroxy
chromate
2. Type and Two-pack Single pack Two pack Two pack polyamide
composition aliphatic plasticized polyamine (F- cured epoxy resin
isocynate cured chlorinated rubber 6A) / polyamide blended with coaltar
acrylic finish based medium (F-6B) cured medium, suitably
paint with chemical and epoxy resin pigmented.
weather resistant medium suitably
pigments pigmented
9. Over coating Min : Overnight Min : Overnight Min : Overnight Min. : 24 hrs.
interval (12 hrs.) Max. : Unlimited Max : 5 days Max. : 5 days
(approx.) Max. : Unlimited
10. Pot life 6-8 hrs. Not applicable 4-6 hrs. 4-6 hrs.
(approx) at
0
30 C for two
component
paints (approx.)
1. Technical Name Self priming type Inorganic zinc Heat resistant Heat resistant silicone
surface tolerant silicate coating synthetic medium aluminum paint suitable
0 0
high build epoxy based on two pack upto 500 C / 550 C dry
coating (complete Aluminum paint temp.
rust control suitable upto
0
coating) 250 C dry temp.
2. Type and Two-pack epoxy A two pack air Heat resistant Single pack silicone resin
composition resin based drying self curing synthetic medium based medium with
suitable solvent based based two pack Aluminum flakes.
pigmented and inorganic zinc Aluminum paint
capable of silicate coating suitable upto
0
adhering to 250 C
manually
prepared surface
and old coating.
9. Over coating interval Min : 10 hrs Min : 8 hrs at Min : 16 hrs Min. : 16 hrs
0
(approx.) Max. : 6 months 20 C & 50% RH Max : Unlimited Max. : Unlimited
Max. : Unlimited
10. Pot life (approx) at 90 min 4-6 hrs Not applicable Not applicable
0
30 C for two
component paints
(approx.)
0 0
11. Temperature - - 250 C 500 C
Resistance
2 Type and Specially formulated Two pack ambient Amercoat 738 from Ameron
composition polyamine cured temperature curing Products, USA/ Berger 938 from
coal tar epoxy epoxy phenolic coating Berger Paints Ltd., Kolkata or
suitable for suitable for application Intertherm 751 CSA from Akzo
application under under insulation Nobel coating, Bangalore.
insulation
0 0
F-14 Specially formulated polyamide cured Coal-tar epoxy suitable for –45 C to 125 C for application
under insulation.
0 0
F-15 Two pack ambient temperature curing epoxy phenolic coating suitable for –45 C to 125 C for
application under insulation.
F-16A Engineered polysiloxane coating : Amercoat 738 from Ameron Products, USA
F-16B Engineered poly siloxane coating : Berger 938 from Berger Paints Ltd., Kolkatta
NOTES
1 Covering capacity and DFT depends on method of application. Covering capacity specified above
are theoretical. Allowing the losses during application, min. specified DFT should be maintained.
2. All primers and finish coats should be ambient temperature curing and air drying unless otherwise
specified.
3. All paints shall be applied in accordance with manufacturer’s instructions for surface preparation,
intervals, curing and application. The surface preparation, quality and workmanship should be
ensured.
4. Technical data sheets for all paints shall be supplied at the time of submission of quotations.
The paints shall conform to the specifications given above and best quality in their products range of
manufacturers listed in Annexure-I.
The paint system should vary with type of environment envisaged in and around the plants. Three
types of environment as given below are considered for selection of paint system. The paint system
is also given for specific requirements.
PRIMERS
F-6A : High build epoxy finish coating cured with polyamine hardner
F-6B : High Build epoxy finish coating cured with polyamide hardner
7.1.2 401 to 500 SSPC-SP-10 1 coat of F-12 40-50 Finish coat at site
TABLE 7.3 : REPAIR OF ALL WELD JOINTS AND DAMAGES FOR STRUCTURES, PIPING
AND EQUIPMENT AFTER ERECTION ON ABOVE GROUND OVERHEAD AREAS
AT SITE
Materials : GALVANIZED STEEL, CARBON STEEL AND ALLOY STEEL
TYPE : UNINSULATED AND INSULATED
NOTE 1 : For external surfaces of MS chimney with or without refractory lining 8.3, 8.4 and 8.5 shall
be followed.
NOTE 2 : For external surfaces of RCC chimney: 2 coats of F-6B @ 100µ DFT/Coat to obtain
2x100=200 µ DFT shall be applied after making surface preparation as per guidelines in
5.1.5. The DFT on concrete surfaces can be checked by Tool Gauge or by applying the
same coating system simultaneously on a carbon steel panel of 12"x12" size and measure
the DFT by normal Magnetic gauges/digital electronic gauges for ferrous surfaces.
NOTE 3 : Wherever required S.No.8.3 shall be used for -14°C to 80°C and S.No.8.2 will be deleted.
TABLE 9 : FIELD PAINT SYSTEM FOR HIGHLY CORROSIVE AREAS IN PLANT AREA
EXTERNAL SURFACES OF UNINSULATED COLUMNS, VESSELS, HEAT
EXCHANGERS, BLOWERS, PIPING, PUMPS, TOWERS, COMPRESSORS,
STRUCTURAL STEEL ETC.
Materials : CARBON STEEL, LOW TEMPERATURE CARBON STEEL & LOW ALLOY STEEL
Surface : Un-insulated
Note : Exposed to spillage or fumes of HCL, H2SO4, salty water, water impingement,
chloride etc
Sl. Design Surface Paint System Total DFT Remarks
No. Temperature Preparation In
in°C Microns
(min.)
Field Primer Finish Paint
10.1 -90 to -15 SSPC-SP-10 Repair of pre- None 65-75 Repair procedure of
fabrication primer pre-erection/fabri
1c o at of F- 9 @ cation primer shall be
65-75u DFT/coat followed. No
overcoating is
allowed.
Surface preparation is
required only for
repairing of damaged
pre-erection/
fabrication primer.
TABLE 10 : PAINTING UNDER INSULATION FOR INSULATED (HOT, COLD & SAFETY) PIPING,
STORAGE TANKS AND EQUIPMENTS IN ALL ENVIRONMENT
Materials : CARBON STEEL, LOW ALLOY STEEL, LOW TEMPERATURE CARBON STEEL &
STAINLESS STEEL
Surface : Insulated
Paint System
Sr. Design Surface Field Primer Finish paint Total Remarks
No. Temperatur Preparation DFT in
0
e in C Microns
(min.)
9.1 Insulated carbon steel, low alloy steel and LTCS piping and equipment and tanks
9.2.1 Below 00C Aluminium sheeting with aluminium foil and “Chloride free mineral If the piping &
to all minus sealant coating barium chromate” shall be applied. equipments are already
temperature erected then surface
shall be prepared by
cleaning with emery
9.2.2 0 to 120 SSPC-SP-10 None 2 coats of F-14 @ 250 or
paper and wash / flush
(15-25µ surface 125 µ DFT / coat 240
with chloride free DM
profile) = 2x125 = 250 or 3
water followed by wiping
coats of F-15 =
with organic solvent.
3x80=240
All the coating materials
9.2.3 121 to 400 SSPC-SP-10 None 3 coats of F-12 60 for SS shall be free from
@20µ DFT /Coat = leachable chlorides.
3x20=60 or 1 coat
of Poly siloxane or
coating (F-16 A/B)
@ 75 microns
DFT/coat
TABLE 12.0 COATING SYSTEM FOR EXTERNAL SIDE OF UNDERGROUND CARBON STEEL
PLANT PIPING AND TANKS
12.2.2 221 to 400 SSPC-SP-10 1CoatofF-16@ 75 1 Coat of F- 175 Cold and hot insulation
µ DFT/coat 16@ 100µ shall be provided
DFT/coat
Note: No Coating and Wrapping systems are available for underground high temperature services
TABLE 13.0 PAINTING UNDER INSULATION FOR INSULATED (HOT, COLD & SAFETY) CARBON
STEEL, LOW ALLOY STEEL, LOW TEMPERTURE CARBON STEEL & STAINLESS STEEL
PIPING, STORAGE TANKS AND EQUIPMENTS IN ALL ENVIRONMENT.
13.1 Insulated carbon steel, low alloy steel and LTCS piping and equipment & tanks
13.1.1 -45 to 125 SSPC-SP-10 Repair of 2 coats of F- 315 For other temperature ranges no
pre- 14 @125 µ painting is required under
fabricatio DFT/coat = insulation F-12 shall be ambient
n primer 2x125=250 temperature curing type till
F-9 @ 65- OR 3 coats of operating temperature is attained
75 µ DFT. F-15= for full curing. F-16 is completely
3x80=240 ambient temperature curing.
13.1.2 Operating SSPC-SP-10 Repair of 2 Coats of 125-135
temperature pre- F-12 @20 µ
-45 to 125°C fabricatio DFT/coat
but design n primer 3x20=60 (or)
temperature F-9 one coat of
126-400°C @65-75 µ Poly-siloxane
DFT coating @ 75
µ DFT/coat
13.3 No painting is required for insulated Monel, Incoloy and Nickel lines.
TABLE 14.0 INTERNAL PROTECTION OF CARBON STEEL WATER BOXES AND TUBE SHEETS OF
COOLERS / CONDENSERS
Water boxes, channels, partition plates, end covers and tube sheets etc.
15.1 Upto 80 SSPS-SP-3 1 coat of P-4 @ 2 coats of F-2 130 Shade as per
8-10 µ DFT/coat @40 µ defence
+ 1 coat of P-6 @ DFT/coat Requirements.
40u DFT/coat 2x40=80
TABLE 16.0 SHOP & FIELD PAINTING SYSTEM FOR EFFLUENT TREATMENT PLANT
17.0 STORAGE
1 All paints and painting materials shall be stored only in rooms to be arranged by
contractor and approved by Engineer-in-charge for the purpose. All necessary precautions
shall be taken to prevent fire. The storage building shall preferably be separate from adjacent
building. A signboard bearing the word "PAINT STORAGE - NO NAKED LIGHT - HIGHLY
INFLAMABLE" shall be clearly displayed outside.
20.1 Following items shall be painted for camouflaging if required by the client.
a. All columns
b. All tanks in off sites
c. Large Vessels
d. Spheres
20.2 Two coats of selected finishing paint as per defence requirement shall be applied in a
particular pattern as per 20.3 and as per the instructions of Engineer-In-Charge.
20.3.1 Disruptive painting for camouflaging shall be done in three colors in the ratio
of
5:3:2 (all matt finish).
21.1 All painting materials including primers and thinners brought to site by contractor for
application shall be procured directly from manufactures as per specifications and
shall be accompanied by manufacturer's test certificates. Paint formulations without
certificates are not acceptable.
21.2 Engineer-In-Charge at his discretion may call for tests for paint formulations. Contractor
shall arrange to have such tests performed including batch-wise test of wet paints for
physical & chemical analysis. All costs there shall be borne by the contractor.
21.3 The painting work shall be subject to inspection by Engineer-In-Charge at all times. In
particular, following stage-wise inspection will be performed and contractor shall offer the
work for inspection and approval of every stage before proceeding with the next stage. The
record of inspection shall be maintained in the registers. Stages of inspection are as
follows:
In addition to above, record should include type of shop primer already applied on equipment
e.g. Red oxide zinc chromate or zinc chromate or Red lead primer etc.
Any defect noticed during the various stages of inspection shall be rectified by the contractor
to the entire satisfaction of Engineer-In-Charge before proceeding further. Irrespective of the
inspection, repair and approval at intermediate stages of work, contractor shall be
responsible for making good any defects found during final inspection/guarantee
period/defect liability period as defined in general condition of contract. Dry film thickness (D
F T)) shall be checked and recorded after application of each coat and extra coat of paint
should be applied to make-up the DFT specified without any extra cost to owner, the extra
cost should have prior approval of Engineer-in-charge.
After surface preparation, the primer should be applied to cover the crevices, corners, sharp
edges etc. in the presence of inspector nominated by Engineer-In-Charge.
21.4.1 The shades of successive coats should be slightly different in color in order to ensure
application of individual coats, the thickness of each coat and complete coverage should
be checked as per provision of this specification. This should be approved by
Engineer-In-Charge before application of successive coats.
21.4.2 The contractor shall provide standard thickness measurement instrument with appropriate
range(s) for measuring.
Dry film thickness of each coat, surface profile gauge for checking of surface profile in case
of sand blasting. Holiday detectors and pinhole detector and protector whenever required
for checking in case of immersion conditions.
21.4.2 Prior to application of paints on surfaces of chimneys, the thickness of the individual coat
shall be checked by application of each coat of same paint on M.S.test panel. The
thickness of paint on test panels shall be determined by using gauge such as
'Elkometer'. The thickness of each coat shall be checked as per provision of this
specification. This shall be approved by Engineer-In-Charge before application of paints on
surface of chimney.
21.4.3 At the discretion of Engineer-In-Charge, the paint manufacturer must provide the expert
technical service at site as and when required. This service should be free of cost and
without any obligation to the owner, as it would be in the interest of the manufacturer to
ensure that both surface preparation and application are carried out as per their
recommendations.
21.4.4 Final inspection shall include measurement of paint dry film thickness, Adhesion, Holiday
detection check of finish and workmanship. The thickness should be measured at as
many points/ locations as decided by Engineer-In-Charge and shall be within + 10% of the
dry film thickness, specified in the specifications.
21.4.5 The contractor shall arrange for spot checking of paint materials for Sp.gr., glow time (ford
cup) and spreading rate.
22.0 GUARANTEE
22.1 The contractor shall guarantee that the chemical and physical properties of paint
materials used are in accordance with the specifications contained herein/to be
provided during execution of work.
22.2 The contractor shall produce test reports from manufacturer regarding the quality of the
particular batch of paint supplied. The Engineer-in-Charge shall have the right to test wet
samples of paint at random for quality of same, as per the paint materials specification.
Batch test reports of the manufacturer's for each batch of paints supplied shall be
made available by the contractor. The contractor shall stand guarantee for carrying
out the rectification/repair/re-painting of the defects/ failures of painting found during the
execution of painting job and till the expiry of the defect liability period of total project as
per the directions of the Engineer-in-Charge of CPCL/JE
Painting contractor who is awarded the job under this standard must have necessary
equipments, machinery, tools and tackles for surface preparation, paint application and
inspection. The contractor mush have qualified, trained and experienced surface
preparator, paint applicator, inspector and supervisors. The contractor's supervisor,
inspector, surface preparator and paint applicator must be conversant with the
standards referred in this specification. The painting job shall be carried out by the approved
agencies of paint manufacturers and supervised by the approved paint manufacturers own
representative or paint manufacturer their scheme( supply and apply basis).
ANNEXURE-I
Indian Vendors
Foreign Vendors
The following are approved vendors for speciality items (phosphating chemical) only.
Annexure-II
Paint Color Code for Piping & Equipment given by CPCL Document No. 00-ES-100-004, Rev. 5
dated 24/12/2006 to Specification No.6782-0642-PT-L06 Rev.2
This section of the standard deals with the color coding to he given to in service piping for easy
identification bused on the liqui d contained in the line.
1. Where ever paint is required for piping external surfaces, the finish coat color shall be as follows
except for paragraph 2, Type of paint, surface preparation. DFT etc. shall he as per the
painting specification.
Insulated and austenitic stainless steel lines will he having only color coding for fluid
discrimination as given in 3 below.
2. Fire water lines shall he painted " Red '" as per IS 536 through out the line.
3. All lines, in general, shall he provided with discrimination color coding mark over the final coat or
on the cladding / jacketing surface of insulated piping as mentioned in 1 above . as
well as on the surfaces on which any paint is not provided. The color coding shall be as per the
attachment to this standard and in the following manner. Color codes on Austenitic SS lines should
he done only wit chloride free paint suitable for application on stainless steel surfaces.
As far as possible, paint used for color bands should he of the same specification as the finish
coat. If for some reason a deviation is required for this, then enamel paint can be used over finish
coat after taking approval from the ‘engineer In - Charge'
3.1 The system of color coding shall consist o f a primary identification color band and other color
hand (s) superimposed on the primary band. All the bands shall be painted circumferential!;
around the line.
The primary color hand identifies the basic nature of the fluid carried in the line. The second and
the third color hands will identify the exact fluid carried in the line. The various primary color
bands included in t h i s standard are explained below:
3.2.1 Primary colorblind / color band ( s ) (see Fig I) arc required to be located at
3.2.2 Primary color band shall he intermittently coated along respective lines with primary color
bands of 2V1 length with the following maximum center to center distance between two
adjacent color bands.
Center to center distances at lesser intervals may be given. if" so desired by unit head.
3 AIR
Plant Air Sky Blue Silver Grey
Instrument Air Sky Blue French Blue
Process air ( ex: bitumen, Sky Blue Signal Red
Mereox)
5 AC IDS
6 LIQUID HYDROCARBONS
Notes : 1) Wherever Dark Admiralty Grey is not available due to the nature of the final coat of
paint ( eg: Coal Tar epoxy in high H2S environments ) . Black can be used.
2) Canary Yellow for ladders etc. has been selected for visibility.
1. Equipment number shall be stenciled in black (after initial painting if any) on each vessel,
column, equipment, machinery till a visible location as directed by the "Engineer - in -
charge "'
Rotating equipment shall have tin arrow showing the direction of rotation painted on the
equipment.
Additional stenciling of line numbers and service will be required and shall be provided on
the lines at the direction of “Engineer- In - Charge"
80- 150 mm 40 mm
150-250 mm 60 mm
> 250 mm 90 mm
Auxiliary piping in packaged units or on base plates of pumps / compressors wilh in the
scope of vendors do not need numbering at site.
• Tank number
• Reference height
• Stile filling height
• Critical /one ( in ease of floating roof tanks only )
• Dale of commissioning
• Date of last cleaning
4. The following details are to be painted on the tank shell near the top landing platform of the
staircase, in letter size 50 mm high, black color.
• Reference height
• Sale filling height
• Critical zone ( in case of floating roof tanks only )
5. The following details shall he painted on the kink at 2!3 the height of the tank at a
location facing the road, from where normal approach lo the Tank is provided. In addition,
the same details shall be provided on two additional points in the lank 120 degrees apart.
Tank number
• Capacity
• Service.
The size of the above lettering shall be 500 mm for 20 M high tanks and 300 mm for
smaller tanks.
DGCA requirements for a l l shall be followed in addition to the above.
1.0 The part of the standard covers the method of identification of STORED piping material by
color coding. This standard is applicable to storage during project Stage as well.
2.0 General guide lines of identification by color coding:
a) Piping shall be painted with one color or a combination of two color as
enclosed.
b) Color identification is not required on galvanized material and mm ferrous
material such as Copper. Aluminum etc. because of their peculiar color and
character
e) Special items l i k e bellow, strainers, steam Imps etc. should be lagged and hence do
mil require color identification.
d) Color identification of Austenitic Stainless Steel is not desirable due to r i s k
of contamination from paint material.
e) Ends of piping to be welded shall not be painted. The color band shall start
2" from the pipe ends.
f) Width of color strips shall be 25 mm for .V nominal pipe dia and above. Secondary
color strip where required, shall be half the size of primary strips. For less than 3" size
color strip shall be 12 mm < 1/2") or maximum practical.
Carbon Steels
Alloy Steels
P1, F1. WP1, WP1W etc. Green / Red
P12, F12, W12 etc Green / Yellow
P22, F22, WP22. etc Green / Silver
P11, F11, WP11 etc. Green / Orange
P5, F5, WP5 etc. Green / Blue
P9, F9, WR9 etc. Green / Pink
to
4=1
w
0 50
z
50 FOR NOZZLES UPTO 250 NB
AND 80 FOR NOZZLES ABOVE
250 NB
TYPE — 1A TYPE — 2A
FOR NOZZLE NB 100
3D0
TYPE — 1B TYPE — 2B
FOR NOZZLE NB < 100
NOTES
ALL DIMENSIONS ARE IN mm UNLESS OTHERWISE STATED.
IN CASE OF CONFLICT ENGINEERING DRAWING SHALL GOVERN.
3.a) FOR ALLOY LINED VESSELS, THE BAFFLE MATERIAL SHALL BE SAME AS ALLOY LINING.
b) FOR CONCRETE LINED VESSELS, THE BAFFLE MATERIAL SHALL BE ALLOY AS SPECIFIED
IN ENGINEERING DRAWING.
REFER ENGINEERING DRAWING FOR DIMENSION 'B'.
DENOTES NOMINAL BORE SIZE OF SUBJECT NOZZLE.
PART : V
SECTION : 3.4
TABLE OF CONTENTS
6.0 MATERIAL SPECIFICATION FOR PARTS OF LOW ALLOY STEEL (1¼Cr-1/2Mo) EQUIPMENT
7.0 MATERIAL SPECIFICATION FOR PARTS OF LOW ALLOY STEEL (2 ¼ Cr-1 Mo) EQUIPMENT
11.0 MATERIAL SPECIFICATION FOR PARTS OF LOW ALLOY STEEL ( 1 ¼ Cr-1/2 Mo)
EQUIPMENT WITH SS 347 CLAD
12.0 MATERIAL SPECIFICATION FOR PARTS OF LOW ALLOY STEEL ( 2 ¼ Cr-1 Mo) EQUIPMENT
WITH SS 347 CLAD
13.0 MATERIAL SPECIFICATION FOR PARTS OF HIGH THICK (>50 MM) C.S. EQUIPMENT
1. Introduction
Intention of this specification is to state minimum requirements for various materials to be used
for plant equipment.
In case of conflict with any of Licensor documents, requirements specified in Licensor documents
will govern.
In case of conflict with any of code requirements, stringent of the requirements specified herein
and code will govern.
PLATES
− Carbon steel plates conforming to SA-516 Gr. 60 shall be supplied in normalised condition
FORGINGS
PIPES
− Seamless carbon steel pipes shall conform to SA-106 Gr. B and hardness shall not exceed
190 BHN.
BOLTINGS
− Internal bolting and bolting exposed to H2S environment shall conform to SA 193 B7M/SA-
194 Gr. 2HM
PLATES
− Carbon steel plates conforming to SA-516 Gr. 60 shall be supplied in normalised condition.
The steel shall be killed and shall conform to fine austenitic grain size as per SA-20.
− Carbon content ≤ 0.2%. Carbon equivalent (Ceq) ≤ 0.42% for t < 2” and 0.45% for t ≥ 2”
Materials shall pass the NACE standard TM 0284 but using the acidified test solution specified
in NACE TM 0177 with:
− Through thickness tension testing of plates 25mm thick and above shall be carried out as per
SA-770, S-3 and minimum reduction area shall be 35%.
a. Plates having thickness 16mm to 50mm (both inclusive) shall be examined ultrasonically
as per SA 435
b. For thicknesses above 50mm ultrasonic examination shall be carried out as per SA 578
and shall have acceptance standard of Level – 1
c. For quenched and tempered steel plates, ultrasonic examination shall be done after the
heat treatment of plates
The steel shall be specially produced as HIC resistant steel at the specified HIC resistant
level, tested originally by the Steel Producer.
PIPES
− Seamless carbon steel pipes conforming to SA-106 Gr. B shall have following chemistry
requirement on product
FORGINGS
BOLTINGS
Internal bolting and bolting exposed to H2S environment shall conform to SA 193 B7M/SA-194
Gr. 2HM
Carbon steel forging shall conform to SA-266 Gr.2 with the following requirements:
The HIC resistance of these forgings shall be verified in the HIC test in accordance with NACE
TM-0284 but using the acidified test solution specified in NACE TM 0177. The acceptance
criteria of the material shall be as follows:
All licensor requirements shall be complied with. However in case of any contradiction
same to be resolved in consultation with the Owner/Jacobs/Licensor
MATERIAL SPECIFICATION FOR PARTS WHEN SHELL/DISHED HEAD IS SA 516 GR. 60/70
Reinforcement Pad/Pad for external Same as shell material
attachment
Flanges SA 105
Couplings SA 105
Skirt support for min. top 1m (Top 2m in case Same as shell material
0
of design temp. ≥ 400 C)
* MDS shall be referred for material of external bolts / nuts and in case of discrepancy between this
material specification and PMS, the same shall be referred to OWNER/Jacobs for clarification.
MATERIAL SPECIFICATION FOR PARTS WHEN SHELL/DISHED HEAD IS SA 516 GR. 60 WITH
NACE/HIC REQUIREMENTS (See Note 1)
Reinforcement Pad / Pad for external Same as shell material / use self reinforced nozzles if
attachment required as per design
Flanges SA 105
Couplings SA 105
Skirt support for min. top 1m (top 2m in case Same as shell material
0
of design temp. ≥ 400 C)
* MDS shall be referred for material of external bolts / nuts and in case of discrepancy between this
material specification and PMS, the same shall be referred to OWNER/Jacobs for clarification
MATERIAL SPECIFICATION FOR PARTS WHEN SHELL/DISHED HEAD IS SA 516 GR. 70 + SA 240 Gr.
316L CLAD (In case of a different SS cladding, the same shall be applicable )
Reinforcement Pad/Pad for external SA 516 Gr. 70
attachment
Nozzles & Pipes ** SA 106 Gr. B (Seamless) + SS 316L Weld overlay <
8” NB
** For smaller size if weld overlay is not possible in seamless pipe (3” NB & below) it shall be cut in
two pieces and after weld overlay & proper finish these two pieces shall be welded and weld
Seams shall be fully radiographed.
Skirt support for min. top 1m (top 2m in case Same as shell material
0
of design temp. ≥ 400 C)
* MDS shall be referred for material of external bolts / nuts and in case of discrepancy between
this material specification and PMS, the same shall be referred to OWNER/Jacobs for
clarification.
6. MATERIAL SPECIFICATION FOR PARTS OF LOW ALLOY STEEL (1¼ Cr-1/2 Mo) EQUIPMENT
0
External Bolts & Nuts SA 193 Gr. B7/SA 194 Gr. 2H upto 343 C
0
*SA 193 Gr. B16/SA 194 Gr. 4 for temp. > 343 C
Skirt support for min. top 1m (top 2m in case of Same as shell material
0
design temp. ≥ 400 C)
* MDS shall be referred for material of external bolts / nuts and in case of discrepancy between this
material specification and PMS, the same shall be referred to OWNER/Jacobs for clarification.
7. MATERIAL SPECIFICATION FOR PARTS OF LOW ALLOY STEEL (2 ¼ Cr-1 Mo) EQUIPMENT
MATERIAL SPECIFICATION FOR PARTS WHEN SHELL/DISHED HEAD IS SA 387 Gr. 22 Cl. 2
Reinforcement Pad / Pad for external SA 387 Gr. 22 Cl. 2
attachment
Flanges SA 182 F 22
Fittings SA 234 WP 22
Couplings SA 182 F 22
External Bolts & Nuts *SA 193 Gr.B7 / SA 194 Gr. 2H upto 343°C
* SA 193 GR. B16/ SA 194 Gr.4 for temp. >343°C
* MDS shall be referred for material of external bolts / nuts and in case of discrepancy between this
material specification and PMS, the same shall be referred to OWNER/Jacobs for clarification.
Hand railing, Stairway, Platform IS 1239 Cl.1 as per standard / SA 53/IS2062 Gr.A/B
* MDS shall be referred for material of external bolts / nuts and in case of discrepancy between this
material specification and PMS, the same shall be referred to OWNER/Jacobs for clarification.
Nozzles & pipes ** SA 106 Gr. B + Monel 400 Weld overlay <8” NB.
“Same as shell material” for 8” NB and above (with full
radiography of weld joints)
* MDS shall be referred for material of external bolts / nuts and in case of discrepancy between this
material specification and PMS, the same shall be referred to OWNER/Jacobs for clarification.
** For small size if weld overlay is not possible in seamless pipe (3” NB & below) it shall be cut in two
pieces and after weld overlay and proper finish these two pieces shall be welded and weld seams
shall be fully radiographed.
Note : In case of Monel weld overlay ferrite content shall be checked and the same shall be limited
to 2.5% at the depth of 3 mm cladding.
10. PICKLING & PASSIVATION PROCEDURE FOR SURFACE CLEANING ON MONEL CLAD
SURFACE
Water : 1 gal.
Time : 5 Sec.
Water : 1 gal.
Time : 5 Sec.
1.4 Neutralisation by swabbing 1-2% soda ash followed by hot water rinse.
11. MATERIAL SPECIFICATION FOR PARTS OF LOW ALLOY STEEL (1¼ Cr-1/2Mo) EQUIPMENT
WITH SS347 CLAD
MATERIAL SPECIFICATION FOR PARTS WHEN SHELL/DISHED HEAD IS SA 387 GR. 11 CL.1 + SS
347 CLAD
Reinforcement Pad/Pad for external SA 387 Gr. 11 Cl. 1
attachment
* MDS shall be referred for material of external bolts / nuts and in case of discrepancy between this
material specification and PMS, the same shall be referred to OWNER/Jacobs for clarification.
* For smaller size if weld overlay is not possible in seamless pipe (3” NB & below) it shall be cut in two
* pieces and after weld overlay and proper finish these two pieces shall be welded and weld seams
shall be fully radiographed .
12. MATERIAL SPECIFICATION FOR PARTS OF LOW ALLOY STEEL (2¼ Cr-1 Mo) EQUIPMENT
WITH SS347 CLAD
MATERIAL SPECIFICATION FOR PARTS WHEN SHELL/DISHED HEAD IS SA 387 GR. 22 CL.2 + SS
347 CLAD
Reinforcement Pad / Pad for external SA 387 Gr. 22 Cl. 2
attachment
Skirt support for min. top 1m (top 2m in case Same as shell material
0
of design temp. ≥ 400 C)
* MDS shall be referred for material of external bolts / nuts and in case of discrepancy between this
material specification and PMS, the same shall be referred to OWNER/Jacobs for clarification.
** For smaller size if welded overlay is not possible in seamless pipe (3” NB & below) it shall be cut in
two pieces and after weld overlay and proper finish these two pieces shall be welded and weld
seams shall be fully radiographed.
13. MATERIAL SPECIFICATION FOR PARTS OF HIGH THICK (>50 MM) C.S. EQUIPMENT
MATERIAL SPECIFICATION FOR PARTS WHEN SHELL/DISHED HEAD IS SA 516 Gr. 60 / 70 / SA
266 Gr.2
Pad for external attachment Same as shell material / SA516 Gr. 70
Pipes (Except for nozzles directly welded to SA 106 Gr. B (Seamless) < 12” NB.
vessels “Same as shell material” for 12” NB and above (with full
radiography of weld joints)
External Bolts & Nuts * SA 193 GR. B7/SA 194 Gr. 2H upto 343°C
* SA 193 GR. B7/SA 194 Gr. 4 Temp. > 343°C
Skirt support for min. top 1m (top 2m in case Same as shell material
0
of design temp. ≥ 400 C)
External cleats with pad (same as shell / SA 283 Gr. C upto 343°C
head material Same as shell material / SA516 Gr.70 for temp > 343°C
* For welded internal parts of clad portions of equipment, refer to respective material specifications /
Mechanical Data sheet.
PART : V
SECTION : 3.4
Rev No. Issue Date Pages Rev Description Prepared Checked Approved
By By By
CONTENTS
1.0 PURPOSE
2.0 GENERAL
1.0 PURPOSE
This specification covers requirements for carbon steel plates intended primarily for pressure
vessels / heat exchangers. The steel plates shall meet the requirements of ASME Section II
(latest). This is intended to supplement the minimum applicable requirements of the material
specification indicated in the purchase requisition.
2.0 GENERAL
2.1 Plates supplied to this specification shall conform to specification SA-20 with additional
requirements mentioned herein.
2.2 The tolerance on thickness of steel plates shall be positive only. Final Rolling shall be
lengthwise.
2.3 The plates shall be free from injurious defects and shall have workman like finish.
Reconditioning / repair of plates by welding shall not be permitted. Surface conditions shall
meet requirements of EN 10163 Class A Subclass 3.
3.1 All plates shall be supplied in normalised condition except when the applicable material
specifications require supply of plates in quenched and tempered condition.
3.2 a. One product analysis of each heat shall be carried out and reported. Chemical analysis
shall be as per applicable specification.
Additionally, one of the following requirements for carbon equivalent based on heat
analysis, shall also be satisfied.
Equation – 2 shall be used when applicable material specifies the above elements or
restricted chemical requirements are specified or supplementary requirements S19 and
S21 of SA-20 are specified in purchase requisition.
c. For quenched and tempered steel plates, ultrasonic examination shall be done after the
heat treatment of plates.
The following heat treatment shall be conducted on the test coupons representative of heat-
treated plates before the specified mechanical testing like tensile, bend, impact tests, etc.
For plates above 16 mm thickness : One normalising * + One stress relieving as per
intended for hot rolling / hot forming UCS-56 of ASME Sec. VIII Div. 1
0 0
(I) Soaking temperature: 900 C to 1000 C
(ii) Holding time one hour per 25 mm thickness but shall not less than half an hour
3.6 If specified in the purchase requisition, charpy V-notch impact test as per supplementary
requirement S5 of specification SA-20 at temperature indicated in the purchase requisition shall
be conducted, for low temperature service.
3.7 If specified in the purchase requisition, plates shall meet the requirements of Indian Boiler
Regulations (IBR).
ii) Acceptance criteria and test temperature for impact testing of non listed material of
Table A2.15 of SA-20 shall be as specified in purchase requisition.
d. Simulated heat treatment of test coupons for all plates as per Clause 3.4 mentioned
above.
The supplier shall furnish 7 copies of the following certificates / documents inclusive of all tests
required as per specification duly certified by the Inspecting Authority before shipment of plates.
The actual values obtained shall be recorded in the test certificates / documents. Material
certificates shall conform to DIN 50049 Type 3.1 B/EN 10204 Type 3.1 B.
a. Chemical Analysis
b. Mechanical Tests
c. Data of heat treatment i.e. initial temperature, heating rate, soaking temperature, cooling
rate, etc
d. Simulated Heat Treatment of Mechanical Test coupons (S3 of SA-20) at indicated Heat
Treatment Cycle (if specified in the requisition or whenever applicable)
f. Charpy V-notch impact tests (S5 of SA-20 if specified in the requisition or whenever
applicable)
No painting / coating of any kind is permitted on the steel plates, except stencil marking.
6.1 Material test certificate duly certified by Mill’s quality assurance / quality control department is
acceptable. However, if third party inspection is specified in requisition, all test certificates and
documents shall be duly certified by the third party.
EPCC-1 : COKER BLOCK : DELAYED COKER UNIT & LPG CFC TREATING UNIT
PART : I
SECTION : 9
TABLE OF CONTENTS
1.0 INTRODUCTION 3
2.0 DEFINITIONS 3
5.0 CONFLICT 7
ANNEXURES
ANNEXURE – I : QUALITY PLAN FORMAT – DESIGN FUNCTIONS
ANNEXURE – II : QUALITY PLAN FORMAT – PROJECT SERVICES
ANNEXURE – III : QUALITY PLAN FORMAT – PROCUREMENT
FUNCTIONS
ANNEXURE – IV : QUALITY PLAN FORMAT – CONSTRUCTION
ACTIVITIES
ANNEXURE – V : QUALITY PLAN FORMAT – WAIVER / DEVIATION
REQUEST
1.0 INTRODUCTION
This Quality Management System requirements are to be met by the LSTK Contractor during
execution of contracted Scope of Work.
It is preferred by Owner / PMC, that Contractor has a fully documented and certified (by a third
party, internationally accredited certification agency) quality system such as ISO 9001:2000.
2.0 DEFINITION
2.3 Contractor
For the purpose of this specification, the work “Contractor” means the person(s), firm, company
or organisation who is either under the process of being contracted or contracted by Owner /
PMC for delivery of some products (Including service). The work is considered synonymous to
supplier, bidder or tenderer.
2.4 Quality Manager – Shall mean quality assurance manager dedicated to this project.
2.5 Third Party - Shall mean an independent organisation carrying out assessment on behalf of
Owner / PMC to assess Contractor’s compliance with quality system.
The LSTK contractor shall provide a detail of plan for his total scope of work along with the Bid.
This is required to assure Owner / PMC that he has understood the work and has required
capabilities to carry out the work. Following documents are required to be submitted along with
the bid to enable assessment of above stated requirements,
3.1.1 Brief description of the quality system used by the contractor for carrying out the following
activities:
¾ Project management
¾ Licensor / Technology Slection
¾ Engineering
¾ Procurement including inspection and expediting
¾ Planning and controls
¾ Construction
¾ Commissioning
¾ Subcontracting
¾ Training
¾ Quality Management
3.1.2 Details indicating the plan for all activities, required to be done by the contractor, to accomplish
offered scope of work. These quality plans must be made on enclosed forms, complete in all
respects. The quality plans shall be assumed to be detailing contractors understanding and
planning for the contract / offered scope of work. It is the responsibility of the contractor to
ensure complete harmony between deliverables covered under quality plan(s) and other
documents of the contract.
3.2.1 Various documents submitted by the Contractor during the pre-award stage shall be finalised in
consultation with PMC / Owner. It shall be presumed that once an offer is made, the contractor
has understood the requirements given in this specification and agrees to comply with them in
totality unless otherwise categorically so indicated during pre-award stage by Owner / PMC.
3.2.2 Owner / PMC will review all the quality documents including quality manual and contractor is
obliged to incorporate all comments as per this specification.
3.2.3 It is obligatory on the contractor to obtain approval on every quality document (documents
demanded by this specification and / or in the quality plans) before using a particular document
for delivery of contracted scope of work.
3.3.1 The LSTK contractor is expected to fully comply with all quality documents submitted and
finalised / agreed against the requirements of this specification. Approval of PMC / Owner on all
these documents shall be sought before start of work.
3.3.2 The LSTK contractor shall be producing sufficient quality records on controlled forms such that
requirements given in this specification can be objectively demonstrated..
3.3.3 The LSTK contractor shall facilitate PMC / Owner during quality audits / surveillance at his office
works / sites to demonstrate compliance to any / all requirements of this specification. PMC /
Owner may institute audits at its sole discretion.
3.3.4 The LSTK contractor shall discharge all responsibilities towards enforcement of this
specification on all the sub-contractors for any part of the work that is sub-contracted by the
contractor.
4.2 The LSTK contractor shall clearly establish the responsibilities and authorities of senior
functionaries such that PMC / Owner has total clarity about the concerned person depending
upon nature of the issue. The contractor shall provide adequate manpower and material
resources as per the agreed quality plans.
4.3 The contractor is required to review the contract at all appropriate stages to evaluate its
capability vis-à-vis contract scope of work. All major / critical aspects must be evaluated before
acceptance of the contract. It is expected that the contractor completely plans the contract scope
of work on quality plan formats such that no major variation is expected during delivery of
contract scope of work. Contractor shall plan the type of resources, including various work
methodology and strategies that are to be utilised for delivery of contract scope of work and form
the basis for the costing. The resources shall be planned and deployed based on good industry
practices and as per the job need.
4.4 The scope of the audit shall cover but not limited to the following areas of the project:
4.4.2 Procurement
4.4.4 The quality requirements shall address the activities / procedures associated but not limited to
following personnel / disciplines.
- Home office activities
- Project team consisting of managers from various disciplines such as process, mechanical,
electrical, civil, instrument, procurement etc.
- All functional disciplines
- Site Construction etc.
4.5 All design activities, if any, performed during delivery of contract scope of work shall be so
controlled that the output is efficient and reliable. It is expected that during development of
design, the contractor shall take recourse to detailed checking, inter departmental reviews and
documented verification methods. Demonstrable objectives evidence for these measures shall
be retained. For all design activities (including verification and review), the contractor shall use
duly qualified personnel as per good industry practices
4.6 A system which assures that latest / required version(s) of the documents(s) are available at all
locations / point of use.
4.7 In case the contractor decides to sub-contract any part of the contract scope of work (with in the
frame-work of main contract), the contractor shall ;
4.7.1 Evaluate the sub-contractor(s) before awarding them with any work.
In case, a sub-contractor may not have a system meeting requirements of this specification, the
contractor may lend his system to sub-contractor for the contract such that sub-contractor
effectively meets the requirements of this specifications.
4.8 All outputs delivered against the contract scope of work shall be suitably identified in such a
manner that either through identification or some other means, sufficient traceability is
maintained which permits effective resolution of any problem reported in the outputs. By this, the
intention is that when some problems are found in the outputs, the root cause can be traced
back through available marking on the output such that effective preventive action is feasible.
4.9 For all critical activities, contractor is expected to have documented methodologies that are to be
utilized for delivery of contract scope of work. Wherever it is difficult to fully inspect or verify the
output (special process), contractor shall pre-qualify the performers and methodologies.
4.10 All inspections carried out by the contractor’s surveillance / inspection staff shall be in conformity
to quality plans and / or inspection and test plans. All inspections results shall be duly
documented on controlled forms such that results are traceable to specific product, that was
inspected / tested. All inspections shall be carried out by duly qualified personnel as per industry
norms or applicable standards.
4.11 All Inspection, Measuring & Test Equipment (IMTE) shall be duly calibrated as per national,
international standards / codes and only duly calibrated and so certified IMTEs shall be utilised
for inspection / testing of contract scope of work.
4.12 All outputs / products delivered against contract scope of work shall be duly marked such that
their inspection / control status is clearly evident during all stages / period of the contract.
4.13 All non-conformities found by contractor’s inspection / surveillance staff shall be duly recorded
including their disposal action. Effective corrective and preventive action shall be implemented
by the contractor for all repetitive non-conformities.
4.14 All non-conformities found by PMC / Owner representative shall be duly recorded on a controlled
form. Such non-conformities shall be analyzed by the contractor and effective and appropriate
correction, corrective and preventive actions shall be implemented. Contractor shall intimate
PMC / Owner of all such corrective and preventive actions implemented by him. Effectiveness of
implemented corrective and preventive action shall be monitored till next two audits.
4.15 Contractor shall establish appropriate methodologies for safe and effective handling, storage,
preservation of various materials / inputs encountered during delivery of contract scope of work.
4.16 Contractor shall prepare sufficient records for various processes carried out by him for delivery
of contract scope of work such that requirement of this specification can be objectively
demonstrated. Various records produced during performance of any activity shall be specified in
the quality plans. In case PMC / Owner finds that enough objective / recording is not available for
any particular process, contractor shall be obliged to make additional records so as to provide
sufficient objective evidence. The decision of PMC / Owner shall be final and binding on such
issues.
4.17 The contractor shall carry-out internal quality audit for the contract scope of work including this
specification after every three months. Audits shall be scehduled such that each element of
contractor’s quality system applicable to each major activity areas viz., design / engineering,
project management, procurement, construction and commissioning is audited. An independent
team having appropriate qualification shall be appointed for this purpose. The findings of such
assessment shall be duly recorded and appropriate corrective and preventive actions
established and acted upon, the complete report / copy of these shall be sent to PMC / Owner
for information / review.
4.18 The contractor shall institute second part audits on all subcontractors after every three months to
establish compliance to this specification. PMC / Owner reserves the right to nominate their
representatives during such audits. Records of findings and actions shall be maintained.
4.19. For all special, verification and critical processes, contractor shall deploy only qualified
performers. Wherever PMC / Owner find any deficiency, the contractor shall be obliged to impart
necessary training / qualifications to the performer(s) before any further delivery of work.
5.0 CONFLICT
In case of any conflict between the main contract and requirements given in this specification or
any document finalised based on this specification, the requirements / provisions of the main
contract shall prevail.
6.1 Management Review Meetings shall be carried out scheduled quarterly or on as needed basis at
sufficient intervals.
6.2 The Management shall address in these meetings the feed back received from audit findings,
non-conformities and the feed back from Owner / PMC.
6.3 There shall be total involvement and commitment by the Management to enhance Owner’s
satisfaction through continual improvement of the system and assurance of conformity to
Owner’s and applicable regulatory requirements.
PART : V
SECTION : 3.4
Rev No. Issue Date Pages Rev Description Prepared Checked Approved
By By By
TABLE OF CONTENTS
1.0 PURPOSE
2.0 DESIGN
3.0 ELECTRODES
4.0 FABRICATION
1.0 PURPOSE
This supplementary specification indicating additional requirements for fusion welded carbon steel
vessels shall form addenda to General Specification for Pressure Vessels No. 44MM-2800-00-
V.02-0101-A4
2.0 DESIGN
2.1 Reinforcement for nozzle openings shall be integral type when required by the applicable
codes/standards or when the nominal thickness of vessel part exceeds 50mm. Self-reinforcing
type nozzles of size 3” NB and above shall be `set in’ type.
2.2 Design calculations for self reinforced nozzles/self reinforced weld ends shall be submitted by
Vendor.
3.0 ELECTRODES
3.1 Electrodes conforming to following specification shall be used. In case of any deviation, prior
approval from Jacobs shall be obtained.
2. Pressure Parts :
a. Steels with UTS upto 70,000 psi : ASME IIC SFA 5.1 E7016/ E7018
b. Steels with UTS upto 80,000 psi : ASME IIC SFA 5.5 E8016-X/
E8018-XX depending upon the alloy
element
3.2 All electrodes and fluxes shall be properly baked / dried as per manufacturer’s recommendation
before use.
3.2.1 All bare electrodes and fluxes shall be selected as per ASME IIC. All weld metal shall have equal
or better mechanical properties than the parent metal.
4.0 FABRICATION
4.1.1 Forming of shell plates and heads shall be carried out by machine, either hot or cold, in such a
way so as to preserve the specified material properties and to produce a regular finish.
4.1.2 Magnetic particle / Dye penetrant examination shall be carried out on the outside and inside
surfaces including edges of torispherical or elliptical heads in knuckle zone, after forming, for
detection of cracks.
4.2.1 The preparation of edges to be welded shall be done by machining, chipping, grinding, cold
shearing, Oxy-acetylene flame cutting or a combination of these.
4.2.3 Oxy-acetylene flame cutting done in any circumstances shall be followed by machining or grinding
to eliminate any discoloration of material affected.
4.2.4 All welding edges shall be checked by Magnetic particle/Dye penetrant examination for detection
of cracks, laminations or segregations.
0
4.2.5 No welding shall be carried out when ambient temperature is less than 10 Celsius unless
preheating is carried out.
4.3.1 Heat treatment of formed parts shall be carried out as per following:
(a) Cold formed dished ends or knuckles up to 16 mm nominal thickness shall be stressed
relieved.
(b) Cold formed dished ends or knuckles above 16 mm nominal thickness shall be
normalised
(c) Hot formed dished ends or similar parts, which have not been uniformly heated in the
normalising range in the final stages of manufacturing shall be normalised.
(d) When the completed vessel involves post weld heat treatment, heat treatment
recommended in (a) above shall not be applicable.
4.3.2 Vessels in caustic service, amine or sour service shall be stress relieved.
Production weld tests shall be applicable for vessels above 50 mm nominal thickness or when
required by the applicable code. The following shall apply:
a) Two production test plate coupons representative of one longitudinal and another
circumferential seam shall be provided for each procedure, position and thickness in
each vessel shell.
b) One production test plate representative of the weld seams shall be provided for each
procedure, position and thickness for welded dished ends/cones.
c) The production test plate shall be from material of the same heat and thickness as of
shell/head. During and after welding, the test plates shall be subjected to same heat
treatment as and together with the course they represent. Extra coupons shall be
preserved to take care of eventuality of retests.
d) The tests mentioned below shall be carried out as per methods of testing in governing
codes:
(ii) Two side bend tests with weld located in the centre of bend.
(iii) Hardness test on production test coupon weld & HAZ (The hardness value shall not
exceed 200 BHN)
b) For vessel over 50 mm nominal thickness used for warmer service, the test
0
temperature shall be lower of 0 C or lowest ambient temperature of the site.
c) The acceptance criteria for energy absorption shall be as per Table A 2.15 of
SA 20 or the Design Code whichever is more stringent.
4.5 For vessels required to meet stress corrosive conditions (such as caustic service, H2S service,
amine, etc.), one Brinell hardness reading shall be taken on the inside of each shell section, head
longitudinal weld, circumferential weld and nozzle longitudinal weld after final post weld heat
treatment. The value shall be limited to the specified value as per requisition.
PART : V
SECTION : 3.4
TABLE OF CONTENTS
1.1 CODES
5.0 SUPPLY
6.0 FABRICATION
1.1 CODES
The following applicable codes and laws of India and their applicable standards in their
latest edition including latest addenda shall be followed unless otherwise specified for the
design, fabrication, inspection and testing of Vessels, Columns, Reactors, Storage Tanks,
Steel Flare/ Vent Stacks :
ASME SEC. VIII DIV. 2 For Pressure Vessels (as specified in bid package for
high shell wall thickness of equipment)
ASME SEC. VIII Div. 1 For workmanship of Vessels not categorised under
any other code
National laws and statutory requirements such as of Indian Boiler Regulations and
requirements of Department of Explosives, Nagpur, India together with any local by-laws for
the state shall be complied with. Static and Mobile Pressure Vessel (SMPV) rules and
Petroleum rules, Directorate (OISD) etc. as applicable shall also be complied with.
NACE MR 0103 Sulphide Stress Cracking Resistant Metallic Materials for Oil Field
Equipment
NACE MR 0284 Evaluation of Pipeline and Pressure Vessel Steel for Resistance
to Hydrogen Induced Cracking
WRC Bulletin # 107 Local Stresses in Spherical & Cylindrical Shells due to External
Loadings
WRC Bulletin # 297 Local Stresses in Cylindrical Shells due to External Loadings on
Nozzles
All equipment shall be designed in accordance with the latest design codes, and
applicable standards/ specifications. Design calculations shall be made considering all
loads for Erection, Operating and Hydrotest conditions (ref. Para.3.1.2)
All equipment columns, clad/lined vessels, vessels (including thickness ≥ 50 mm), tanks,
bullets & all others vessels shall be sized on the basis of internal diameter only.
2.2.1 For columns of carbon and low alloy steel, minimum thickness shall be 8mm (including
corrosion allowance up to 3mm).
The minimum thickness of carbon and low alloy steel vessels shall be 6.0 mm (including
corrosion allowance not exceeding 3.0 mm) but shall not be less than calculated as per
following formula:
Wall thickness = Dia / 1000 + 1.5 + Corrosion Allowance, for Dia. less than 2400 mm.
Wall thickness = Dia / 1000 + 2.5 + Corrosion Allowance, for Dia. 2400 mm and more.
All dimensions are in mm. Above formula is applicable for both columns & vessels.
2.2.2 For columns of stainless steel and high alloy steel, minimum thickness shall be 5mm.
Corrosion allowance shall be added in this minimum thickness as specified in process
data sheet.
The minimum thickness of stainless steels & high alloy vessels shall be 3.0 mm but shall
not be less than calculated as per following formula:
Wall thickness = Dia / 1000 + 2.5 + Corrosion Allowance, for Dia. more than 1500 mm.
2.2.3 Tangent to tangent height (H) to diameter (D) ratio (H/D) greater than 5 shall be
considered as column and designed accordingly.
2.3.1 2:1 semi-ellipsoidal dished end shall be used for pressure vessels unless otherwise
specified. Seamless dished ends shall be used for specific services as per process
licensor requirement.
2.3.2 Unless specified otherwise, hemispherical ends shall be used when the thickness of shell
exceeds 70 mm.
2.3.4 For vessels diameter < 600 mm, without any internals, pipe caps may be used.
2.3.5 Dished ends, after forming, shall be heat treated as per following applicable details:
Dished ends with nominal thickness > 16mm shall be normalized. Recommended
normalizing cycle:
0 0
• Soaking temperature: 900 C to 1000 C
• Holding time one 2.4 min per mm thickness but shall not less than half an
hour
• Cooling in still air
2.3.5 Vessels and columns with diameter up to 1000 mm shall be provided with 500 NB
manhole. Vessels and columns with diameter greater than 1000 mm and up to 1500
mm shall be provided with 500 NB manhole. However, if required, vessels and
columns with diameter above 1500 mm shall be provided with 600 NB manhole.
Trays and other column internals installation shall be given consideration in deciding the
size and location of manholes, hand holes or body flanges as the requirements may be at
the initial design itself.
High pressure reactor manholes i.e. HCGO/OHCU Reactor etc. shall be on I.D. basis.
Size shall be as per Licensor drawing.
2.3.6 All process vessels that have a manhole will also be specified to have a vessel vent to
provide ventilation for maintenance. This vessel vent will be located at the top, or a
minimum distance from top of vessel. Size of this vent shall be as follows.
Vertical vessel not having any nozzle on the top shall be provided with 50 NB nozzle for
conducting hydro test in vertical conditions.
All vent and drain lines of light Hydrocarbons like MS, naphtha, LPG, propylene, and H2
shall be provided with double isolation valves with end flanges as per OISD. Dia11/2 in
NB (40 NB) and above drain lines shall be provided with end flanges.
2.3.7 If the equipment process data sheet indicates sour service (alkaline or wet H2S service),
the equipment materials, their testing, their post weld heat treatment and any other
recommendations of the NACE materials recommended by the licensor and pertinent
publications like NACE MR 175 shall be complied without exception.
Design pressure shall be calculated as per the following unless otherwise specified
elsewhere.
2.4.2 Design pressure shall be at the top of vertical vessel or at the highest point of horizontal
vessel.
2.4.3 The design pressure at any lower point shall be calculated by adding the highest operating
liquid head and any pressure drop within the vessel.
2.4.4 Equipment with steam out condition shall be designed for full vacuum condition.
2.4.5 Equipment operating under vacuum / partial vacuum shall be designed for an external
2
pressure of 1.055 kg/cm g (15 psi g)
2.4.6 Vessels shall be designed for steam out conditions if specified on process data sheet. For
steam out conditions equipment shall not be designed for Full vacuum.
2.4.7 Minimum design pressure shall be 3.5 kg/cm2 g for any equipment except API storage
tanks.
For vessels operating at ATM pressure minimum design pressure shall be ATM
2.4.8 All storage tanks shall be designed as per code considering full height & using specific
gravity 1.0 if not specified.
2.4.9 Pressure chambers of combination units in equipment shall be designed for testing
independently without pressure in the adjacent chamber in corroded condition.
2.5.2 Minimum Design Metal Temperature (MDMT) shall be lower of minimum atmospheric
temperature and minimum operating temperature encountered during operation.
Un-insulated vessels containing LPG and similar fluids shall be designed for maximum &
minimum temperature as recommended by SMPV rules.
2.6.1 Equipment shall be hydro tested in the fabricator’s shop as per applicable design code &
specification requirements. However care shall be taken that hydrostatic temperature shall
be at least 6 degree centigrade higher than critical exposure temperature (CET) for vessel
thickness up to 50 mm and minimum 17 degree centigrade higher than the CET where CET
id minimum design metal temperature (MDMT). However, if code requirement is found to be
stringent, than the same shall be followed.
2.6.2 All vertical vessels, columns and horizontal vessels (in full corroded condition) shall also be
designed for site testing of the equipment with water at the test pressure on the top of the
equipment considering 33% wind load.
2.6.3 All equipment foundation shall be designed and constructed for water full condition when
equipment is new with 33% wind load.
2.6.4 Open atmospheric vessels shall be tested by filling water up to the top curb angle.
2.6.5 Pressure chambers of combination units that have been designed to operate independently
shall be hydro tested to code test pressure as separate vessels i.e., each chamber shall be
tested without pressure in the adjacent chamber.
When pressure chambers of combination units have their common elements designed for
maximum differential pressure, the common elements shall be subjected to test pressure
equivalent to the differential pressure multiplied by a factor as per applicable design code.
Hydro test pressure shall be equal to 1.3 x design pressure x temperature correction factor
as specified in ASME SEC. VIII DIV.1 (Clause UG-99) at top of column unless specified
otherwise. If column is tested in horizontal position, hydro test pressure shall be increased
in order to take the effect of water head.
After taking precautions as suggested in para 2.21.5, an IBR equipment may be tested to
meet IBR’s hydrostatic test requirements.
2.6.7 Unless otherwise specified in applicable design code allowable stress during hydro test in
tension shall not exceed 90% of yield stress point.
2.7.2 No corrosion allowance for stainless steel columns & vessels shall be used unless
otherwise specified.
2.7.3 If it is agreed to develop the cladding by weld overlay method, then it shall be ensured to
have undiluted chemistry of the cladding upto specified thickness of cladding. Surface
texture requirement if applicable shall also be ensured.
2.7.4 For storage tanks, minimum corrosion allowance shall be as follows unless otherwise
specified:
Bottom plate : 1.5 mm,
First shell course : 3 mm,
Subsequent shell courses : 1.5 mm
Floating roof/fixed roof : 1.0 mm.
2.7.5 Corrosion allowance for nozzles including manholes shall be equal to that specified for the
vessel. No corrosion allowance is required for standard flange face.
2.7.6 Corrosion allowance for girth/ body flange faces shall be used equal to that specified for
vessel.
2.7.7 Corrosion allowance for support skirts of columns & vertical vessels shall be 1.5 mm
(minimum) unless specified otherwise.
Wind load for equipment including anchor chair shall be calculated on the basis of IS 875 / site
data for skirt supported equipments, storage tanks, spheres, flare stacks and air coolers.
For seismic design consideration of new equipments which are replaced on the existing old
foundation, Earthquake loads shall be calculated in accordance with IS: 1893- 1984/Site data.
For seismic design consideration of new equipments on totally new foundations (i.e. skirt
supported equipments, storage tanks, spheres and air coolers) Earthquake loads shall be
calculated in accordance with IS:1893 (Latest), if site specific acceleration spectra is not
specified in the project specification.
Capacity shall be specified as Nominal capacity and stored capacity. Nominal capacity for
fixed roof tanks shall be volume of cylindrical shell.
Stored capacity for fixed roof tanks shall be equal to nominal capacity minus free board
volume (equivalent to 500mm of shell height) or location of fixing of lowest roof structure
member
Nominal capacity (also the stored capacity) for floating roof tanks shall be volume of cylindrical
shell minus free board volume. (Equivalent to minimum 1500mm of shell height)
Nominal capacity (also the stored capacity) for fixed cum floating roof tanks shall be volume of
cylindrical shell minus free board volume. (Equivalent to minimum 2500 mm of shell height).
2.10 SUPPORTS
2.10.1 Skirt supports shall be provided for all vertical vessels, columns and reactors. Small vertical
vessels may be supported on legs or brackets.
2.10.2 All Cr-Mo steel reactors shall be supported on skirts. Welding of external cleats on Cr-Mo steel
reactors shall be avoided wherever possible.
Corrosion allowance of total 1mm minimum shall be considered for skirt unless otherwise
specified in the project specifications to achieve final thickness of skirt shell.
2.10.4 Columns with diameter 1000 mm & larger shall be self supported unless the process data
sheet indicates a guide supported design.
2.10.5 Columns with diameter less than 1000mm shall be supported by superimposed structure
around the column covering the entire height. Guy wires shall not be used to support any
equipment. Supporting of columns by superstructure require prior approval from Jacobs
2.10.6 In special cases, columns with diameter up to 1000mm and height not exceeding 10m
(including skirt height) can be self-supported and heights exceeding 10m shall be supported
by super imposed structure around the column covering the entire height.
2.10.7 Flare and vent stacks shall be supported structurally by superimposed structure around for
complete height.
2.10.8 Buried vessels shall be suitably anchored to prevent the uplift due to water table. Anchor bolts
shall have corrosion allowance of 6mm. Buried vessels shall be supported on concrete
saddles with bracket support at the centerline of the vessel.
2.12 Nozzles and manholes including self-reinforced type shall be “set in” type attached to vessel
with full penetration welds unless otherwise specified.
2.13 FLANGES
2.13.1 Nozzle flanges up to 600 NB shall be as be ASME / ANSI B16.5 and above 600 NB shall be
as per ASME / ANSI B 16.47 (SERIES ‘B’).
2.15.2 Nozzle flanges shall be welding neck flanges unless specified otherwise.
2.15.3 Slip on flanges shall not be used in Lethal, Hydrogen, Amine, Caustic, severe cyclic service,
sour service, HIC (Hydrogen induced cracking) service and corrosive service where corrosion
allowance is more than 3 mm.
2.14 INTERNALS
All removable internals shall be bolted type and bolting shall be SS type 304 unless specified
otherwise.
2.15 GASKETS
Service gaskets supplied shall not be used for hydro testing purpose. Gasket used for hydro
testing of equipment shall be of same specification as that of service gaskets for all nozzles,
manholes and body/girth flanges. Gasket seating face of flanges shall have finish as per
gasket specified.
All columns and Vertical vessels with internals & safety valve shall be provided with pipe davit
as per Jacobs’s standard. Weight of the valve or item to be handled shall be advised for
selection of configuration.
2.17 Spares
Plugs 10%
Belts 50%
MP Connection for PG/TI
ii) Air Cooler One on one of the inlet & one on one of the outlets of each
header, size 40NB nozzle with BF etc. If it is not possible to
provide on process nozzle then it shall be provided on header.
Rating shall be same as process nozzle.
2.18.1 All vessels and columns shall be designed considering design pressure; maximum
operating liquid head and any pressure drop within the vessels/columns.
2.18.2 All columns and vessels shall be capable of withstanding water full condition during system
testing.
2.18.3 Vessels and columns shall be hydro tested at shop at pressure calculated as per applicable
code in new and cold condition.
2.18.4 Seismic design shall be carried out based on design requirement for earthquake.
2.18.5 Equipment covered under the purview of IBR (Indian Boiler Regulations) shall be designed
as per IBR regulations. However, design of components not covered in IBR Regulations
shall be designed in accordance with ASME SEC. VIII Div-1 by multiplying the allowable
stress at design temperature by 0.8667 (1.3/1.5 which is the ratio of minimum multiplying
factor for hydro test for ASME sec VIII div-1 and IBR). This way the equipment can be safely
tested to meet ASME as well as IBR requirements.
2.18.6 Detail stress analysis, local load analysis for loads due to piping and supported equipment
etc. shall be carried out for all equipment. Critical equipment shall be analysed by using
finite element analysis methods (FEM) as defined in job specifications & reports shall be
submitted for Jacobs review. For allowable nozzle loads refer Jacobs’s standard
specification attached with Bid package.
2.18.7 All nozzle necks, all nozzle flanges and blind flanges shall be of weld overlay construction
for clad equipment. Loose liners on nozzle necks and blind flanges are not permitted.
2.18.8 All vertical vessels and columns shall be provided with 2 lifting lugs/Lifting trunions. Lifting
lugs shall be designed with impact factor of two.
2.18.9 Mechanical design of self supporting Tall columns / tower shall be carried out for various
load combinations as per Clause 3.1
2.18.10 Material of various parts of equipment shall be selected as per table given in TABLE– 3
unless otherwise stated on process data sheets. In case the suggested basic material
system for equipment does not meet the temperature applicability requirement, it shall be
brought to the notice of Jacobs and clarification obtained at enquiry stage itself.
2.18.11 Local Stress analysis shall be carried out for nozzle to shell junction using maximum shear
stress theory for vessels and columns. Allowable stress intensity shall be as per ASME
SEC. VIII Div. 2 and non-destructive examinations shall be carried out for shell to nozzle
junction as per ASME SEC. VIII Div. 2.
2.18.12 Stress analysis of shell to skirt junction shall be carried out using maximum shear stress
theory for vessels and columns designed as per ASME Sec. VIII Div. 2. In case skirt shell
joint is of butt-welded construction, the same shall be 100% radiographed.
2.18.13 All vessel, columns and tanks shall be provided with earthing bosses as per Jacobs’s
standard. Body flanges of equipment shall have provision to provide jumpers for earthing.
2.18.14 Permanent fixed ladders shall be provided inside the skirt of columns/vertical vessels for
inspection of dome / dished end.
2.18.15 ODC / Very heavy equipment shall require special considerations for handling,
transportation and erection by Contractor.
2.18.17 All equipment requiring insulation shall be provided with insulation support rings /cleats as
per Jacobs’s specifications.
Mechanical design of self-supporting column and its anchorage block shall be carried out
considering combination of various loads.
3.1.1 Loadings:
The loadings to be considered in designing a self supporting column / tower shall include:
b. Self weight of column inclusive of piping, platforms, ladders, manholes, nozzles, trays,
welded and removable attachments, insulation and operating liquid etc. The weight of
attachments to be considered shall be as per Table–1
c. Other loadings as specified in UG-22 of ASME SEC. VIII Div. 1 wherever applicable
e. Basic wind pressure and wind velocity (including that due to winds of short duration as
in squalls) for the computation of forces / moments and dynamic analysis respectively
shall be in accordance with site data for the project (Refer Clause 2.8 above).
Additional wind loading on column due to external attachments like platforms, ladders,
piping and attached equipment should be given due consideration.
(b) Operating condition: Column in (corroded condition) under design pressure, including
welded items, trays, removable internals, piping, platforms,
ladder, reboiler mounted on column, insulation and operating
liquid etc., plus full wind on insulated column with all other
projections open to wind or earthquake forces.
(c) Test conditions Column (in corroded condition) under test pressure, filled with
water plus 50% of specified wind load on uninsulated column
including all attachments shall be considered.
Maximum allowable deflection at top of column shall be equal to total height (including skirt
height) of the column divided by 200 but shall not exceed 300 mm in any case.
3.1.3.1 If the deflection of column exceeds the above allowable limit, the thickness of skirt shall be
increased as first trial upto a maximum value equal to the column thickness and this exercise
shall be stopped if the deflection falls within allowable limit.
3.1.3.1 If the above step is inadequate, skirt shall be gradually flared to reduce the deflection. Flaring of
skirt shall be stopped if the deflection falls within limits or half angle of cone reaches maximum
limit of 9°.
3.1.3.3 If the above two steps prove inadequate in limiting the deflection within allowable limits, the
thickness of shell courses shall be increased one by one starting from bottom course above skirt
and proceeding upwards till the deflection falls within allowable limits.
3.1.3.4 For tall equipment fabricated from stainless steels and other exotic materials, it shall be
examined if an external guide will be helpful in controlling the required thickness such that the
equipment along with its guide structure cost is economical than a free standing design
The stresses due to design pressure, weights, wind/seismic loads shall be combined using
maximum principal stress theory for ASME SECTION VIII Div.1. Thickness is accordingly
chosen to keep the stresses within limits as per Table-2.
Base supporting including base plate, anchor chairs, compression ring, foundation bolting etc.,
shall be designed based on over-turning moment (greater of seismic or wind). Minimum size of
anchor bolts shall be M24.
44NC-4600-0000-V.02-0101-A4 General Spec for Pressure vessels.doc
A minimum number of 8 foundation bolts shall be provided. Numbers of foundation bolts shall be
in multiple of four. Skirt thickness shall also be checked to anchor chair reaction forces.
Anchor bolts shall be so spaced that there is no interference between fixing arrangement, Anchor
bolt sleeves and trailing lug etc.
Dynamic analysis of each column shall be carried out for stability under transverse wind induced
vibrations as per standard design practice and calculations for each column shall be submitted to
Jacobs for approval.
The recommended magnification factor for unlined towers / column shall be taken as 70 and
allowable dynamic amplitude shall be limited to tower diameter divided by 5.
4.1 General
4.1.1 All materials and accessories required for the fabrication, inspection, testing etc. of the vessel
shall be supplied by the Vendor unless otherwise stated. Whenever some material is to be
supplied by the Owner, this shall be so indicated as Free Issue Material and the supplementary
specifications in this regard shall be complied with.
4.1.2 In addition to the requirements of materials as per material specifications, material shall also
meet the requirements mentioned in this specification and other specifications enclosed with the
requisition. All materials shall be certified for compliance with IBR requirements for the term(s)
so specified.
While procuring materials, Vendor shall stipulate additional requirements such as limits on
hardness, ultimate tensile strength (UTS), yield strength, chemical composition, heat treatment
and any other specific requirements to ensure that final requirement as per specification and
Code are met with.
4.1.3 All materials for pressure parts and parts welded to pressure parts including materials in the
scope of sub-vendors shall be accompanied with mill test certificates duly certified by a reputed
third party inspection agency. In the absence of mill test certificate the material shall get tested
from a reputed third party inspection agency like Jacobs, Lloyds, BV, DNV etc. and test results
shall be submitted in lieu of mill test certificate.
All cost towards such testing and inspection shall be borne by the Vendor. All materials shall be
inspected at Vendor’s and sub-vendor’s shop for verification prior to use on the job. The decision
of Authorized Inspector to accept or reject materials on the basis of such testing shall be final.
4.1.4 Wherever simulated heat treatment of test specimens is required as per code or specification,
the simulation cycle shall include one extra cycle of stress relieving for any eventuality of repair
at site by Owner during the life of the equipment.
0
4.1.5 The exchanger’s minimum design metal temperature (MDMT) shall be taken as 0 C or the
design temperature specified in drawing or datasheet whichever is lower, unless specified
otherwise in design basis or datasheets or drawings.
All Carbon steel (CS), low temperature carbon steel (LTCS) and low alloy steel (LAS) materials for
0
pressure parts and attachments to pressure parts having MDMT below 0 C shall be impact tested.
The test temperature shall be minimum of MDMT and impact test temperature as specified in
applicable materials specification or as given in job specification whichever is lower. Unless
specified otherwise, impact values shall be more stringent of the values as per UG 84 or applicable
material specification
In addition to the tests done at the mill, one impact test (three specimens) per heat shall be repeated
after receipt of materials at vendor shop, with the test temperature same as given above.
If the test results do not meet the impact energy requirements given above, the material shall be
rejected.
4.1.6 PLATES
4.1.6.1 Pressure parts having thickness 16 mm to 50 mm (both inclusive) shall be ultrasonically tested as
per SA – 435.
4.1.6.2 Pressure parts having thickness greater than 50 mm shall be ultrasonically tested as per SA-578
Level B.
4.1.7 FORGINGS
Forgings to SA-105 and SA - 266 above 75 mm thickness, all tube sheet forgings and all forgings of
other materials except standard nozzle flanges up to 8” NB and small forgings shall be 100%
ultrasonically tested as per SA-388. Acceptance standard shall be as per para AM 203.2 of ASME
Section VIII Division 4.
4.1.8 PIPES
Pipes shall be seamless and sizes above 1 ½ “ NB shall be hot finished. Dimensions and
tolerances shall be in accordance with ANSI 36.10 or ANSI 36.19 applicable as per material
specification.
4.2 Specific material requirements (Pressure parts and parts welded to pressure parts)
d) Plates above 50 mm thickness shall meet following additional requirements of SA- 20.
i) Vacuum treatment shall be as per the supplementary requirement S1. If vacuum degassing
is not reported in the test certificate, then through thickness tests as per SA 770 shall be
conducted and minimum reduction in area of 35% shall be ensured.
ii) Charpy V-notch test shall be as per supplementary requirement S5. Test temperature shall
0 0 0
be minus 29 C for MDMT greater than or equal to 0 C. For MDMT less than 0 C refers
clause 4.1.5 above. Impact energy values shall be as per Para UG-84 of Code, or as per
applicable material specification, whichever is higher. Orientation of test bar shall be
transverse to rolling direction.
e) Unless specified otherwise in requisition or bid document. All CS materials specified, as HIC
tested shall meet the following requirements.
i) Carbon equivalent shall be restricted to 0.43% max. Nickel content shall be 0.2% max.
ii) Sulphur content shall be 0.002% max for plates and 0.01% for pipes and forgings.
iii) Hardness of plates and pipes shall not exceed 200 BHN, and that of forgings shall not
exceed 187 BHN.
iv) Plates shall be to SA 516 Gr. 60/70 only. The plates shall contain calcium or other rare
earth elements to create spherical inclusions instead of stringers. The plates shall be
tested in accordance with NACE TM-02-84 using the test solution of NACE TM-01-77.
The acceptance criteria shall be crack length ratio 10% maximum.
f) All LTCS and CS charpy plate material shall be to fine grain practice and the austenitic grain
size shall be measured and reported in the mill test certificate.
g) CS pipes shall be SA-106 Gr.B. LTCS pipes shall be seamless conforming to SA 333 Gr. 1 or 6
h) Non-standard forgings (SA 266, SA 350 etc.) shall be in normalized and tempered condition.
a) All LAS plates, pipes, forgings and fittings shall be in normalized and tempered condition. Use
of C-½ Mo materials is prohibited.
b) For 1-¼ Cr- ½ Mo materials the maximum room temperature tensile strength of all pressure
containing components, materials and welds shall be 100000 psi.
c) For LAS tubes (SA-199, 209 and 213) hardness test shall be performed on outside of the tubes
as per SA-450.
d) For LAS plates above 50 mm thickness, following supplementary requirements of SA-20 shall
also apply:
ii) Charpy V-notch impact test as per supplementary requirement S5 with impact values as
0 0
per UG 84 of Code. Test temperature shall be lower of MDMT or -18 C (0 C for 5Cr- ½
Mo) whichever is lower. Orientation of test bar shall be transverse to the direction of
rolling.
a) All SS material (300 series) shall be in the solution heat treated (fully annealed) and pickled
condition. All stabilized grades of SS (SS 321, SS 347 etc.) shall be given stabilization heat
treatment, in addition to solution annealing.
b) All SS (300 series) plates shall be hot rolled and shall have No.1 finish on both sides.
c) SS (300 series) materials for all components shall be procured with the IGC test as per ASTM
A-262 (test shall be carried out, after the specified heat treatment and sensitization per
specification) with acceptable corrosion rate and practices as under.
i) For all services except nitric acid service, Practice E shall be followed Specimen after
exposure shall be bent as per requirements mentioned in A262 Practice E and shall be
inspected under magnification of 200X. The bent specimen shall be free of any cracks or
grain dropping. The microstructure shall be submitted to the Authorized Inspector for
approval.
ii) For Nitric acid service: Practice C with corrosion rate not greater than 25 mils per year.
iii) For straight chrome (13% Cr.) material, maximum carbon content shall not exceed
0.08%. Hardness of UNS No.S41000 and S41008 shall not exceed 75 RB and that of
S40500 shall not exceed 80 RB.
a) Cladding shall be integrally and continuously metallurgically bonded to the base metal. All
clad plates shall be rolled-on or explosion bonded type.
b) Clad plates shall be ultrasonically examined from the cladding surface in accordance with SA-
578. Scanning shall be 100% of the plate surface. Acceptance standard shall be level B.
Clad plates shall meet the supplementary requirements of S7 of SA-578. All ultrasonic
testing shall be undertaken after specified heat treatment of clad plates.
c) Both base material and clad material shall meet the specification of the respective materials
as stipulated in this specification.
d) Alloy clad steel plates shall be as per SA 263 or SA 264 or SA 265. Bond between cladding
and the base metal shall be checked for a minimum strength of 14 kg/mm2 in shear for alloy
clad steel plates, by conducting shear test as per applicable material specification.
e) For copper alloy clad plates, the bond between cladding and base metal shall be checked for
a minimum strength of 10 kg/mm2 in shear by conducting shear test.
f) During tension test of clad plates the cladding shall be removed and the tensile properties of
the base material shall meet the Code material requirements.
g) For austenitic SS clad plates the SS surface shall be acid pickled as per ASTM A-380. For
Chromium steel clad surfaces the pickling shall be as per Vendor’s established procedure.
h) For all clad plates used in Hydrogen or H2S service with design temperature greater than 350
0
C, Hydrogen dis-bonding test shall be carried out. The test condition shall be representative
of the actual design conditions and the procedure shall be submitted to Authorized Inspector
for approval.
4.3.1 CS plates shall be minimum IS-2062 Gr. B/C or SA 283 Gr. C or equivalent. Pipes shall be to IS
1239 or SA 53 or equivalent.
0
4.3.2 Saddle material shall be same as that of shell for design temperature greater than 350 C.
The materials for various components in a vessel shall be as per Owner or Jacobs’s requirement.
This does not preclude use of equivalent or better materials. However, these deviations should be
clearly indicated in the prescribed format. If an equivalent material sought by the Vendor is to a
specification, other than IS or ASTM or ASME, it is necessary for the Vendor to submit the
specifications of the equivalent material with complete details in English for approval.
5.0 SUPPLY
Supply shall be in accordance with requisition or bid documents to which this specification is
attached. It shall, however, include the following:
5.3.2 Earthing lugs shall be provided on each vessel and shall be located in such a way as to avoid any
fouling with the exchanger foundation bolts at site.
5.3.3 Vendor to supply one set of torque wrenches for bolt size M45 (1¾“) to M56 (2¼”) and a set of bolt
tensioner device for bolt sizes greater than M56 (2¼”) in case these bolt sizes are being used in
exchangers covered in the requisition. BTD capacity shall be 40% more than the maximum load
required for hydro test condition. BTD pump shall be pneumatically and manually driven. Vendor
shall supply one pump unit, required load cells and 4 heads of each size. Torque values for
tightening the bolts shall be mentioned in the fabrication drawings.
5.3.5 Additions like cleats for piping, ladder, platform, insulation cleats etc. which may be required shall be
provided.
6.0 FABRICATION
6.1.1 For CS, the preparation of edges for welding shall be done using machining, chipping, cold
shearing, oxy-acetylene flame cutting or a combination of these. Chipping or cold shearing shall be
followed by grinding to a smooth and regular surface. Oxy-acetylene flame cutting shall be followed
by machining or grinding to eliminate any discoloration of material affected.
6.1.2 For LAS, the edges for welding shall be made by oxy-acetylene flame cutting or by machining. Cold
shearing may be used for cutting thickness up to 10 mm. Oxy-acetylene flame cutting shall be used
with preheat and shall be followed by machining or grinding to eliminate any discoloration of material
affected.
6.1.3 For austenitic SS, the edges shall be prepared using plasma arc; however, cold shearing may be
adopted for thickness up to 15 mm. In all cases the cut edges shall be ground back or machined
back by 2 to 3 mm.
6.1.4 All welding edges after cutting shall be Dye Penetrant (DP) or Magnetic Particle (MP) examined for
laminations, cracks or segregation. Additionally UST shall be carried out within twice the material
thickness of edge for LAS materials or when the service is low temperature or hydrogen or HIC.
6.1.5 The paragraphs NF7 and NF14 in part UNF of Code are mandatory. This applies to non-ferrous
cladding and weld overlay.
6.2.1 Rolling
Rolling for bending and forming of plates shall be in the longitudinal direction of the plates. This
direction shall be clearly marked on the plates.
Re-rolling after welding is not normally recommended. However, if for large diameter shells, re-
rolling of welded shell course is inevitable, procedure for re-rolling along with extent of non-
destructive tests (NDT) shall be submitted for approval of the Authorized Inspector.
All welds on the section to be re-rolled must be ground flush. After re-rolling all the welds on the re-
rolled section must be DP checked. Such welds shall then be subjected to radiography as required
by drawings and Code.
6.2.2 Dishing
All dished heads shall preferably be of single piece construction. However dished ends with one
chordal seam are acceptable for shells with diameter greater than 1 m. In such cases, the chordal
seam shall preferably be in the middle one-third of the blank.
Dished ends shall preferably be 2:1 ellipsoidal or tori-spherical (knuckle radius 15 % of the outside
diameter and crown radius 80% of outside diameter).
Dished heads shall be subjected to DP test on knuckle portions (both inside and outside) and weld
edges after heat treatment. Vendor to ensure adequacy of indicated thinning allowance for dished
head. If nominal thickness indicated is not adequate then the nominal thickness should be increased
accordingly, keeping minimum thickness as per equipment drawing.
A straight face of 38 mm or 3 times the nominal thickness of dished end, whichever is less shall be
provided. However, if larger straight face is specified, it shall be ensured.
6.3 Welding
6.3.1 All welding and weld overlays shall be done with electrodes, fillers and fluxes of reputed make with
Austenitic SS consumables of low carbon and stabilized grade shall also be IGC tested as per
ASTM A262 Practice E. Straight chrome materials shall be welded with electrode that produces an
austenitic chromium nickel weld deposit or a non-air hardening nickel –chromium-iron weld deposit.
6.3.2 All welding procedures shall be submitted for approval by Authorized Inspector giving all relevant
details. Welding qualification records shall indicate hardness values of weld metal. HAZ and parent
0
metal and also results of impact tests when design temperature are below 0 C or when specifically
indicated for materials being welded. No welding shall be undertaken until the welding procedure
and welder’s qualification have been approved by the Authorized Inspector.
All welding procedures and welders shall be qualified for the particular type of welding and material
in accordance with the ASME Section IX. Vendor shall be responsible for the quality of the welds
performed.
6.3.3 Pressure holding joints shall be full penetration welds. Root pass of single side welded joints shall
be done with GTAW process. Backing strip for single side welded joints is not permitted.
For LTCS materials both inside and outside of welds shall be ground flush or dressed smooth. All
internal welds in the shell shall be ground flush in order to insert and remove tube bundle. Also all
internal welds shall be ground flush to the extent of facilitating draining of complete equipment.
6.3.4 Longitudinal seams shall be staggered with the circumferential distance between the centers of
welds being at least 5 times the thickness of the thicker-plate. Weld seams shall be located so as to
avoid interference with weld seam of nozzles and external attachments.
6.3.5 Attachment to pressure part shall be of same quality as the pressure part. All LAS weld
attachments to pressure retaining component shall be with full penetration weld and ground to a
smooth concave contour.
External attachments like lugs, supports, etc. of CS shall not be welded directly to high alloy or
austenitic SS vessel components. These attachments should be of the same material as the vessel
components.
If this is not so, intermediate pad plates of the same material type as the vessel component may be
used. These pads shall be at least 100 mm wider and longer than the attachment and shall be at
least 5 mm thick. Welding of CS or LAS to austenitic SS shall be done with austenitic SS electrodes
or filler wire (AWS – ASTM – E 309L or E-309 Mo.L only).
Wrapper plates, reinforcing pads or stiffeners of higher thickness than specified can be used
provided there is no change in basic dimensions and with the approval from Jacobs.
6.3.6 When impact tests are required on material as per Code or specification the welds shall also be
qualified for impact test. In such case following special requirement shall apply to the welding
procedure qualification:
i) Qualification tests shall be made on plates of the ASME specification as specified for the
exchanger using welding electrodes of AWS or SFA specification and wire & flux of the
ii) Welding current and travel speed shall be considered essential variables in order to ensure
that production welding is substantially equivalent to the procedure qualification.
iii) Welded test plates shall be subjected to a total thermal cycle sequence similar to the finished
equipment. Specifically, test plates shall be held at intermediate and final stress relief
temperatures for approximately the same length of time as the finished exchanger. Final
cooling rate shall be approximate to that expected for the finished exchanger.
iv) Charpy V-notch impact tests shall be made on the weld and HAZ of the test plate for each
welding procedure to be qualified. Test procedure shall be as per UG 84 of Code. Test
temperature shall not be higher than MDMT. Impact energy requirements shall be as per
Table 2.15 of SA 20 of ASME Section II Part A or UG 84 of Code whichever is higher.
6.3.7.1 Weld deposit overlay shall be done by a qualified welding procedure and surface shall be properly
machined or ground flush after overlay. Minimum thickness of finished weld deposit shall be as
indicated in the drawings or specifications.
In case a higher deposition thickness and multiple weld layers are required to achieve the minimum
specified undiluted deposit metal, the same shall be done only after taking prior approval from
Jacobs.
Minimum thickness of undiluted finished weld overlay from top shall be 3 mm or as specified in the
drawings. For non-ferrous weld deposit, the iron dilution should be restricted to 2.5% (maximum) in
the finished undiluted layer (thickness defined above).
6.3.7.2 The weld overlay procedure shall be qualified on base metal of the same composition as the
exchanger component and meeting the requirements of ASME Section IX.
6.3.7.3 The weld overlay shall be relatively smooth with no notches and undercuts that would act as stress
raisers. All cracks, fissures and circular defects greater than 1/16” diameter shall be removed.
Repaired areas shall be DP checked.
Weld overlay shall be applied to base metal, which has been grit blasted and is smooth and clean
so as to ensure full bonding. Welding overlay cladding shall be applied after any normalizing but
before the post weld heat treatment (PWHT). The weld overlay shall consist of at least 2 layers.
6.3.9.4 The alloy cladding shall be cut back at all seams to permit back welding of the base metal. Weld
metal shall be ground flush and fully covered with the applicable weld deposit.
The weld joint in base plate shall be 100% DP tested for detection of cracks and flaws before
welding from clad side. The weld deposit shall be at least as thick as the cladding.
6.3.7.5 Shells, cones and dished heads formed from clad plates shall be UST after forming for a minimum
of 10% of the clad surface, including no less than one square feet in each 10 square feet or fraction
thereof.
Unbonded areas that cannot be encompassed by a 3“ diameter circle shall be repaired by weld
overlay. When repairs in excess of 5% of the total examined area are required, the complete
Repaired areas and weld deposit overlay at weld seams shall be DP examined. UST shall be
repeated for dished heads after heat treatment. All UST shall be in accordance with SA 578 S6 for
spot examination and SA 578 S7 for 100% examination
6.3.7.6 All weld overlays shall be 100% DP examined in accordance with the method described in ASTM-E-
165. The barrier layer shall be 100% examined.
When the overlay involves multiple passes (layers) and the procedure uses an intermediate heat
treatment with cooling to room temperature prior to applying the subsequent layer, each layer shall
be examined.
Where overlay is to be machined such as for flange facing, machined surface shall be 100%
examined after PWHT. If 100% of overlay is examined prior to the final PWHT, overlay shall be spot
examined (not less than 10% of the surface) after heat treatment.
6.3.7.7 Samples of the weld overlay shall be taken to perform chemical analysis to the required depth as
specified. The number and location of samples shall be at the discretion of Authorized Inspector.
However, they shall be representative of each exchanger component for each type of welding
process. Report of this chemical analysis shall be submitted to Authorized Inspector for approval.
6.3.7.8 For all weld overlays used in hydrogen or H2S service with design temperature greater than 3500 C.
Hydrogen disbonding test shall be carried out. The test condition shall be representative of the
actual design conditions and the procedure shall be submitted to Authorized Inspector for approval.
6.4 Production test coupons (PTC) are required for CS welds above 50 mm thickness, for LAS welds
above 25 mm or when required by the Code. For PTC the following shall apply:
a) Two PTCs representative of one longitudinal and another circumferential seam shall be
provided for each procedure, position and thickness.
b) PTC shall be from material of the same heat and thickness as of parent metal. During and
after welding PTC shall be subjected to same heat treatment as and together with the course
they represent, extra PTC shall be preserved to take care of eventuality of retests.
c) The tests mentioned below shall be carried out as per methods of testing in Code:
ii) Two side bend tests with weld located in the center of bend
iii) One hardness test on PTC weld and HAZ. The acceptable limits are 200 BHN for CS, 225
BHN for P3 and P4 materials and 235 BHN for P5
vi) For LAS, charpy V notch tests on weld and HAZ shall be carried out for 25 mm thickness
and above or when specified in requisition. Test temperature and acceptance criteria shall
be as per clause 2.2.2 (d) (ii) above.
Hardness limitation for materials wherever specified on drawings or datasheets and LAS materials
shall be as per Jacobs Spec. 44NC-4600-0000-V.02-0110-A4-General Spec for hardness
requirements. Hardness limitation for tube to tubesheet welding shall be established on a mock-up
with simulation heat treatment. Hardness of straight chrome materials in the cold-formed state, HAZ
and welds shall not exceed 88 RB.
6.6.1 Flanges
Unless otherwise indicated, dimensions, drilling, facing and tolerance for nozzle flanges (and blind
covers if required) shall be as per ASME B 16.5 (for size up to 24” NB) and ASME B 16.47 series B
(for sizes above 24” NB) for the respective class. Weld overlays, wherever specified or required,
shall be in addition to the thickness as per these standards. Bolt holes on these nozzle flanges shall
straddle principal vertical and horizontal centerlines of equipment. If the component to which
nozzles are attached is subsequently stress relieved, it shall be Vendor’s responsibility to maintain
true gasket faces by machining or otherwise. If distortion expected is considerable, final machining
operation should be done after stress relieving; sufficient machining allowance for this purpose
should be available. Gaskets for flanges to ASME B16.5 and B16.47 shall be as per ANSI B16.20.
6.6.2 Nozzles
6.6.2.1 Nozzle pipes shall be attached to the vessel components by full penetration welds. Attachment
welds using only inner and outer fillet welds are not permitted. Unless otherwise indicated on the
datasheets or drawings, necks of all nozzles shall be flush with the inside of vessel component.
Inside corners of nozzle pipes at shell and channel inside diameter shall be radiused. All nozzles 2”
NB and below except long weld neck, shall have two stiffeners (40 mm x 6 mm) at right angles.
6.6.2.2 Whenever nozzle inside is required to be over-layed, these shall be done by weld overlay or
cladding. Minimum nozzle ID before weld depositing shall be 50 mm in such cases. Loose liners
are not acceptable.
Reinforcing pads whenever required as per drawings or Code shall be of the same material as the
vessel component to which it is welded. All reinforcing pads shall be provided with two 1/8” (3 mm)
0 2
NPT tapped holes located 180 apart for air soap solution test with a pressure of 1.25 kg/cm (g).
This test shall also be required to be carried out for slip on flanges.
Higher test pressure are not recommended because of accompanying risks and also because the
soap bubbles have a chance to blow off. Tell-tale holes in reinforcing pads shall be plugged with
hard grease unless otherwise indicated after the hydro test of the exchanger.
6.7.1 All inch bolting and threading shall conform to ANSI B 1.1 except for size 1” and above where it shall
be 8 threads per inch. Metric bolting and threading shall conform to ISO – R261 except for size
M24 and above, where it shall have 3 mm pitch.
6.7.2 Studs shall extend beyond the nut by about 10 mm and shall be threaded full length except when
square ends are required for use with bolt tensioner, in which case the extension shall be as per bolt
tensioner manufacturer’s recommendation. The studs for extended tubesheet and the studs for use
with connecting piece shall also have square ends. The extended portion of the stud shall be
provided with a suitable protection cap to avoid clogging / rusting of stud threads.
6.7.3 All nuts shall be of heavy series only and nut-seating faces shall be machined or spot faced.
6.7.4 Threads on external bolting, plugs etc. shall be lubricated with graphite grease for working
temperature unto 200 0C and with Molybdenum Disulphide for higher temperatures.
6.8.1 Vendor shall be responsible for taking adequate preventive measures to ensure the quality and
finish of materials and to avoid any rusting.
6.8.4 ‘T’ wherever indicated on drawings, denotes match mark for assembly and shall be punched on all
mating parts.
6.8.5 Lifting lugs shall be provided as per standard for lifting of channels, channel covers, shell covers,
test rings, test flanges etc.
6.9 De-scaling, pickling and passivation shall be done for all SS parts of vessels in accordance with
ASTM A-380. The Vendor shall supply details of the procedure for approval to the Authorized
Inspector.
6.10.1 The dimensional tolerances shall be within the limits indicated on Jacobs’s drawings and standards.
Where tolerances are not specified, these shall be in accordance with the requirements of TEMA
and Code.
6.10.3 Finish of all machined components shall be minimum 12 microns (500 RMS) unless otherwise
indicated. Parts subjected to UT shall have minimum finish of 6 microns.
7.1 All the NDT procedures shall be submitted to the Authorized Inspector for approval. For all NDT
activities, only qualified NDT technicians shall be deployed with the approval of Authorized
Inspector.
7.2 The extent of radiography shall be as specified on the datasheets or drawings or job specifications.
In no case it shall be less than that required in the Code.
7.3 Minimum extent of radiography shall be spot, unless full radiography is specified in the drawings or it
is required as per specification or Code. Spot radiography shall mean that at least 10% of the total
welded length must be radiographed. Further, all “T” joints must be radiographed and at least one
shot must be taken on each longitudinal and circumferential seam. This requirement shall
supplement the ones specified in Code. The Authorized Inspector shall be consulted in marking the
area to be radiographed.
7.4 Full radiography when specified shall imply 100% radiography of all butt welds.
7.5 All nozzles fabricated from plate, irrespective of thickness of plate and radiography specified, shall
be 100% radiographed.
7.6 Weld seams of formed heads shall be 100% radiographed after forming and heat treatment, if any.
7.7 All nozzles to shell welds shall be DP or MP checked at the root run and final weld.
7.8 For LAS welds, radiography shall be done after final PWHT. All welds which cannot be fully
radiographed such as nozzle to shell weld etc. shall be 100% ultrasonically tested after final PWHT.
Regarding fillet welds and welds which can not be radiographed or ultrasonically tested (i.e. pass
partition plate to channel and floating head joint etc.), the root run shall be DP checked and the
welds should finally be MP checked after stress relieving.
7.10 Acceptance standards for radiography shall be as per Code unless stated otherwise.
8.1 PWHT shall, in general, be done as required by datasheets, drawings, specifications, Code etc.
PWHT when mentioned on the drawings shall be over and above the requirements of specifications
or Code. No welding or heating is permitted after PWHT operation.
All matching operations shall preferably be carried out after heat treatment (Also refer clause 4.6.1.
above). It shall be the responsibility of the Vendor to leave sufficient allowance for this purpose.
Vendor shall submit all the procedures for PWHT to Authorized Inspector for review.
8.3 Heat treatment of SS clad assemblies shall be at reduced temperature to avoid sensitization of SS
materials. The soaking time shall be increased accordingly as per Code.
8.4 Heat treatment of non-ferrous clad assemblies, if required, shall be performed with extra care, if
required at reduced temperatures to avoid differential thermal expansion. The soaking time in such
a case shall be increased accordingly as per Code.
ii) Cold formed floating head cover up to 16 mm thick if fiber stretch exceeds 5%.
i) Hot formed dish head and floating head dish if not formed in normalizing range.
ii) Cold formed dish heads for thickness greater than 16 mm.
This heat treatment need not be given if same heat treatment is given subsequently on sub-
assembly.
ii) Hardness value of dished heads after cold forming exceeds 235 BHN.
iii) Hot formed shells, cones, dished heads.
After any heat treatment on austenitic SS, IGC test shall be carried out as per clause 2.2.3 (c)
above.
8.8 For LAS materials, preheating procedure shall be established in the welding procedure and got
approved by the Authorized Inspector. Preheating by resistance or induction heating method is
preferred. Preheating shall extend uniformly to at least three times the thickness of joint but not less
than 50 mm on both sides of the weld. Temperature indicating crayons shall be used for
assessment of correct pre-heat temperature.
8.9 All Low Alloy Steel pressure containing welds shall be PWHT.
9.1 Inspection
9.1.1 The inspection shall be carried out by Authorized Inspector. The materials, fabrication and testing of
exchangers shall be open to inspection by the Authorized Inspector in addition to any inspection
required by the specified Code or by local authorities having jurisdiction over the installation.
9.1.2 Inspection shall be carried out both during fabrication and before delivery and also for sub-ordered
materials. If any, in addition to final inspection and certification by Authorized Inspector during the
course of manufacture, Authorized Inspector’s written approval shall be obtained by the Vendor at
various stages of fabrication. For this purpose, Vendor shall prepare his Quality Assurance Plan,
defining the stages of fabrication, hold points for his own inspection and that by the Authorized
Inspection or Code or statutory Authorities Inspection etc.
The Quality Assurance Plan shall be discussed with Authorized Inspector before start of job and
mutually agreed. The various stages of fabrication to be inspected (by Vendor or the Authorized
Inspector) shall include but not limited to the following.
g) Profile and thinning of dished ends and toriconical pieces after forming
h) Review of NDT reports and any other specified test such as for leak, corrosion and hardness.
9.1.3 The presence of the Authorized Inspector shall not modify or reduce the obligation of the Vendor to
carry out his own tests and control. Should any material and / or equipment be found not in
compliance with the requirements specified, the Authorized Inspector or his delegate shall be
entitled to irrevocably reject them, even if such non-compliance has not been evidenced in the
course of inspections and/or tests.
9.1.4 The Authorized Inspector will, at the time of initial visit, set up with the Vendor actual details of
inspection stages to be witnessed or carried out: the schedule of future visits and subsequent
inspection notices can be arranged between the Authorized Inspector and the Vendor.
9.1.5 The Vendor shall notify the Authorized Inspector sufficiently in advance of any fabrication operations
to permit him to arrive at the Vendor’s shop in time to witness the operations.
9.1.6 The Vendor shall provide to the Authorized Inspector, free access to his shops at all times. He shall
also supply all tools and tackles to the Authorized Inspector for carrying out the inspection. The
Vendor shall also arrange for similar facilities at this sub-contractor’s shops.
9.1.7 The Vendor must satisfy the Authorized Inspector that the welding procedures, welders, electrodes,
fluxes, welding wires etc. are in accordance with the requirements of the Code and specifications.
Further the welder’s qualification test must be carried out in the presence of the Authorized
Inspector.
9.1.8 Prior to final inspection, all slag, weld spatters, loose scale, dirt, grit, paint, grease, oil and other
foreign matter shall be removed in order to facilitate inspection. All reinforcing pads and slip on type
flange welds shall be pressure tested with air and soap solution before and after heat treatment (if
any) and before final hydro test.
9.1.9 A dimensional checking of equipment shall be carried out taking into account the tolerances shown
on job drawings and standards, design specification or Code; the more stringent values shall
govern. Dimensional checks are to be taken of the internal measurements of equipment together
with external ones and these are to be recorded on a copy of the drawings as being the “As Built”
dimensions.
9.2.1 Hydrostatic tests shall be witnessed by the Authorized Inspector. When hydrostatic tests are
performed the indicating gauge shall be connected to the upper most parts of the equipment.
Testing water shall be clean potable water. Seawater shall not be used.
For SS equipment water used for these tests shall not contain more than 25 ppm chlorides.
0
Minimum metal temperature during hydrostatic tests shall be 20 C.
Test pressures shall be maintained for at least one hour. Shell and tube sides shall be tested
separately, unless otherwise mentioned on the drawing.
10.1 After completion of all testing and inspection, the inside of complete equipment shall be thoroughly
drained and dried out. Equipment shall be completely dried by passing hot air for sufficient time
until no further increase in relative humidity of outgoing air is observed.
Dry out shall be done simultaneously on both shell and tube sides. After drying, the equipment shall
2
be purged and filled with dry N2 at 0.25 kg/cm . The equipment shall be provided with pressure
gauge to monitor N2 pressure, and a ½” non-return valve.
All threaded holes; other than tell tale holes for testing, shall be suitably protected with steel bar
plugs. All nozzles not provided with blind flange shall be provided with steel covers and temporary
gaskets and bolts adequate to maintain nitrogen pressure as above.
All CS and LAS external surfaces other than gasket faces and other machined surfaces shall be
given one coat of primer paint. Surfaces to be painted shall be prepared for painting by removing
loose mill scale, loose rust, oil, grease and other films or substances harmful to the adhesion of
paint by an approved method such as shot blast cleaning.
The surface shall be prepared to near white finish as per SSPC-SP-10 [SA 2 ½ Swedish standard
(SIS-05-5900)]. The shop primer shall be inorganic zinc silicate with 65-75 microns dry film
thickness, unless stated otherwise.
10.3 The equipment item number, Purchase Order (PO) number and Owner name and address shall be
painted in bold white paint letters written with stencil, on the vessel.
Vessels shall be securely anchored for dispatch in order to prevent any shifting and damage during
transportation. Expansion joints and bellows, wherever used shall be suitably protected against any
possible damage by providing tie bars before boxing up.
Packaging shall be suitable for rail or road transport and also sea worthy if transported by sea.
Spares shall be dispatched separately in a box and marked with PO number, item number and
Owner’s name and address.
Sling mark identification shall be provided by Vendor on all vessels with respect to center of gravity
of the equipment.
No equipment shall be dispatched until a written clearance is obtained from Owner or Jacobs
regarding Piping Clips and Structural Cleats on individual equipment.
The Vendor shall be completely responsible for the compliance to Code requirements, residual
design, detailing, fabrication, materials and workmanship of the exchangers as per the stipulations
of the requisition and its attachments. In this regard, it may be noted that review by Owner or
Jacobs shall not relieve the Vendor of his responsibility of meeting all requirements and ensuring
satisfactory performance of the equipment. Guarantee period shall be as per Purchase Condition of
Owner.
TABLE – 1
TABLE-2
ALLOWABLE STRESS FOR COMBINED LOADING
Where
S = Basic allowable tensile stress as per Clause UG 23(a) of ASME SEC.VIII Div.1
K = Factor for increasing basic allowable value when wind or seismic load is present
TABLE- 3
The following table gives general guidelines for material selection chart for various pressure parts / non
pressure parts of the equipment:
Design Plate Pipe (See Forging Bolts / Structural Interna Studs /
0
Temp. C note 8) Studs / attachment l pipes Bolts /
Nuts welded to Nuts
External pressure parts Internal
CRYOGENIC
From – SA240 SA312 SA182, Gr. F SA320, Gr.B8, 8C, 8T strain
254 up to Gr.304L, Type 304 304, 304L hardened
–195 304, 316, 304L, 316, 316, 347, SA 194 Gr.8, 8C, 8T
316L, 347 316L, 347 316L
(impact
tested)
Same as pressure parts
Above SA240, SA312, SA182 Gr.F SA320, Gr.B8, 8C, 8T strain
–195 up Gr.304L, Type 304, 304 F304L, hardened
to –80 304, 316, 304L, 316, F316L SA194 Gr.8, 8C, 8T
316L, 316L, 321,
321, 347. 347.
LOW TEMPERATURE
Above – SA203 SA 333 SA 350 SA 320 L7 SA 203 Gr.E SA333 SA193 Gr.B8
80 Gr.E Gr.3, 4 Gr. LF3 SA 194 Gr.3, 4 SA194 Gr.8
Up to – impact Gr.4 or Gr.7
60 tested
(see note-
1)
Above – SA537 SA333 SA350 SA320 L7 SA537 Cl.1 SA333 SA193, Gr.B8,
60 Cl.1 Gr.3 Gr.LF3 SA194 Gr.4 Gr.3 SA194 Gr.8
Up to – impact Or GR 7
45 tested
(see note-
1)
Above-45 SA516 SA333 SA350 SA320 Gr.L7 SA516 (in all SA333 SA193, Gr.B8,
upto –29 (All Gr.6 or Gr.LF2 SA194 Gr.4 grades) Gr.6 , SA194 Gr.8
grades) Gr.1 or Gr.7 1
impact
tested
(see note-
1)
Above SA516 SA106, SA105 / SA193 SA516 (in all SA106, SA-193, Gr.B8,
-29 upto (all Gr.B (see SA266 (see Gr.B7 grades) Gr.B SA194, Gr.8
0 grades) note 3) note 3) SA194
(See note Gr.2H
3)
ELEVATED TEMPERATURE
Above SA387 SA335 P11 SA182 SA193 Gr.B16 Same as Same as SA193
427 Up Gr.11, Cl.1/ SA335 P12 Gr.F11, SA194 Gr.4 Pressure parts Pressure Gr.B8.
to 538 Cl.2, SA182 parts SA194
SA387 Gr.F12 Gr.8
Gr.12, Cl.1/
Cl.2
NOTES
1. Pressure vessel steel plates are purchased to the requirement of the standard ASME SA-20
which requires testing of individual plates for low temperature service. Carbon steel material is
ordered to meet the impact requirements of supplement S5, of standard ASME SA 20. Typical
material specification is as follows. SA516 Gr.60 normalised to meet impact requirements per
o
supplement S5 of SA 20 AT -50 F.
2. All permanent attachments welded directly to 9% nickel steel should be of the same material or
of an austentic stainless steel type which can not be hardened by heat treatment.
3. Check for impact testing requirement as per UCS-66 for coincident temperature and part
thickness.
5. This table is not applicable for atmospheric / low pressure storage tanks. Materials shall be
selected as per API 650 / API 620 as applicable.
6. Materials for caustic service, sour service, or sour service + HIC shall be selected based on
specific recommendation of process licensor & considering chemical composition, hardness,
Vacuum degassing requirements & heat treatment requirements.
7. Material for pressure vessels designed according to ASME SEC VIII DIV. 2 shall be given special
consideration as per code.
9. Non-ferrous material and super alloys are not covered above and shall be selected based on
specific recommendation.
10. Material for vessel / column skirt shall be the same material as of vessel / column shell for upper
part with a minimum of 1000mm.
11. Materials used for IBR equipment shall meet all requirements of Indian Boiler Regulations.
TABLE 4:
NOZZLE LOADING DATA FOR NOZZLES ON CYLINDRICAL SHELLS
2
(Not applicable for High Pressures > 75 kg/cm )
Y
FA
FY=FA
MT
Z X
ML MC
FZ=FT FX=FL
FT FL
C Y L IN D R IC A L E N D S
FA
MB
Y MT
Z X
FR = RESU LTAN T
D IS H E D / F O R M E D E N D S
(NOTE: LOADS INDICATED IN THE TABLES TO BE CHECKED FOR BOTH POSITIVE AND NEGATIVE
CONDITIONS)
41114) el I kiwi
Thr-4U 7-4 kitc111c-Ich chief
STANDARD SPECIFICATION
CIVIL AND STRUCTURAL WORKS
'Eirft.T
GENERAL SCOPE
Standards Standards
Conimittee Bureau
Rev. Prepared Checked
Date Purpose Convenor Chairman
No by by
Approved by
Abbreviations:
IS : Indian Standards
1 These specifications establish and define the material and constructional requirements for
CIVIL and STRUCTURAL WORKS.
2. Methods of measurements are indicated in these specifications; where not so specified, latest
revision of IS:1200 shall be applicable.
3. Providing and operating all necessary measuring and testing devices/ equipments including all
materials and consumables are included in the scope of work. No separate measurement or
payment for testing the quality of work and materials shall be made; rates quoted for various
items shall be deemed to include the cost of such tests which are required to ensure
achievement of specified quality.
5. Wherever referred to in the tender document, only the latest revision of Specifications, Codes
of Practice and other publications of Bureau of Indian Standards shall be applicable.
6. Wherever the Contractor executes civil and structural works involving buildings, equipment
foundations, supporting structures, pipe racks, etc., the following works are deemed to have
been included in the quoted rates for various works.
7. The provisions of Schedule of Rates, specifications and drawings shall be read in conjunction
with each other and in case of conflict amongst them, clarification shall be obtained from the
Engineer-in-Charge whose decision shall be final and binding. However, the following
procedure may generally be followed:
- Description of items in schedule of rates shall be followed when provisions therein are
different from those in specifications.
Where the description of item does not call for some specific requirement but the
same is given in specifications, the specifications shall be followed in addition to the
requirement given in description of item.
Where drawings call for requirements different from or additional to those given in
item description and specifications, the decision of the Engineer-in-Charge shall be
obtained as to what shall be followed.
STRUCTURAL STEELWORK
Rev No. Issue Date Pages Rev. Description Prepared Checked Approved
By By By
CONTENTS
1.0 PURPOSE
5.0 ATTACHMENTS
1.0 PURPOSE
The purpose of this document is to state the requirements of material, workmanship and
construction procedure to be followed during the execution of structural steelworks.
This specification covers the requirements for material, storage, fabrication, assembly,
testing/examination, transportation and erection of all types of bolted and welded structural steel
work for general fabrication work. Fabrication of structure shall also include fabricating .
3.1 GENERAL
a. The requirements set forth in IS 800 for general construction in steel and IS 9595 cold formed
light sections are not allowed to be used. IS 806 for use of steel tubes in general building
construction for the design, fabrication and erection of structural steel for buildings shall be
followed for structural steel work, unless otherwise specified.
b. In cases of conflict between this specification and the above Indian Standards, this specification
shall govern conflict between design basis and job specification & this specification , the former
shall govern.
3.2 MATERIALS
The Structural steel shall conform to IS:2062-2006 (Weldable quality) unless specified otherwise.
Carbon steel pipes shall conform to IS:1161-1998 of Grade YST-240 or higher , IS : 1239-2004
(PART-1). & IS :1239-Part 2 -1992.
Wide flange sections conforms to Is: 12278 whenever applicable shall be used.
Covered electrodes for metal arc welding of structural steel shall conform to IS:814-2004.
Bare wire electrodes for submerged arc welding of structural steel shall conform to IS: 7280. The
combination of wire and flux shall comply with IS: 3613.
Filler rods and wires for gas welding shall conform to IS: 1278. Filler rods and bare electrodes for
gas shielded arc welding of structural steel shall conform to IS: 6419.
Bolts and nuts (including lock nuts) shall conform to IS:1363-2002, IS:1364-2002 (property class -
4.6) , IS:1367-2002, IS:3460, IS:6623 and IS:6639 as applicable. Washers shall conform to
IS:5369, IS:5370, IS:5372, IS:5374, IS:6610 and IS:6649 as applicable.
High strength bolt shall conform to IS : 3757-1985.
All sections shall be checked on receipt to ensure that they are free from surface defects such as
pitting, twists, cracks and laminations. They shall be arranged by grade and quality and by lot.
Every section shall be marked for identification and the manufacturers certificate for every lot
giving details of chemical analysis and mechanical characteristics shall be kept in record.
Welding wires and electrodes shall be segregated by quality and lots and stored inside a dry,
enclosed room as per recommendations of IS:9595. All care shall be taken to keep the
electrodes in perfectly dry condition to ensure weld metal soundness and satisfactory operations.
Manufacturers certificates for electrodes shall also be logged into the records.
Bolts, nuts and washers shall be sorted out by grade, type and diameter and the manufacturers
quality / test certificates shall be maintained for record purpose.
The contractor is required to provide manufacturers quality certificate for every item of material
supplied by him. In case such certificates are not available, the contractor shall at his own cost
carry out all such tests as are required by Owners / consultant at an approved Test House and
submit the test results for approval. The approval of such material shall however be entirely at
the discretion of the Owner / Consultant.
The Contractor shall ensure that all materials brought to site are duly approved. Rejected
materials shall not be used and shall be removed from site. Any material doubtful in quality for
which specific tests are to be carried out as per the instruction of Owner / Consultant, shall be
separately stacked and properly identified and shall not be used.
The storage yard for fabricated steel parts shall be prepared in advance and got approved by the
Owner / Consultant before the steel structures start arriving from the shop.
All materials shall be set at least 150 mm clear from ground on wooden or steel blocks for
protection against direct contact with the ground and to permit drainage of water.
Steps shall be taken to prevent warping of items during handling at all stages.
3.2.7 Deviations
Use of materials other than those specified above shall be allowed, with prior approval, only
where Contractor can prove technical advantage to the Owner.
Fabrication and erection shall be carried out based on drawings thoroughly checked, stamped
“Approved for Fabrication” and signed by the contractors own responsible engineer. Unchecked
and unstamped drawings shall not be used for purpose of proceeding with the work
B
The contractor shall directly issue to site / shop the fabrication and erection drawing in the correct
order, simultaneously submitting required copies (specified elsewhere)copies to Owner /
Consultant for their review. The Owner / Consultant shall at his sole discretion review part or
whole of all, some or none of the drawings.
Review of drawings by Owner / Consultant shall in no way relieve the contractor of his
responsibility for correctness in the execution of the work, and the contractor shall be required to
modify / rectify the structure at any stage of the work in case owner / consultant bring to his
attention any mistake / omission in the fabrication drawing and the fabrication based on this
drawing or that the work does not conform to good engineering practice. All such modifications /
rectifications shall be made at no extra cost to the owner.
Fabrication drawings shall be drawn to scale and shall convey the information clearly and
adequately. Following information shall be furnished on such drawings :
– Reference to design drawing number (along with revision number) based on which fabrication
drawing has been prepared.
– Structural layout, elevations and sections (with distinct erection marking of all members).
– Layout and detailing of rain water pipes and gutters showing all necessary levels, connections
and provisions wherever required.
– Detailing of shop / field joints, connections, splices for required strength and erection.
– Quality of structural steel, plates etc., welding electrodes, bolts, nuts and washers to be used.
– Erection assemblies identifying all transportable parts and sub-assemblies with special
erection instructions, if required.
The Contractor shall additionally ensure accuracy of the following and shall be solely responsible
for the same :
Connections, splices and other details where not shown on the design drawings shall be suitably
designed and shown on the fabrication drawings based on good engineering practice developing
full member strength. Design calculations for such connections/splices shall be submitted to the
Owner / Consultant, if called for.
Any substitution or change in section shall be allowed only when prior written approval of the
Owner / Consultant has been obtained. Fabrication drawings shall be updated incorporating all
such substitutions/changes by the Contractor at no extra cost.
In case during execution of the work, the Owner / Consultant on review of drawings considers any
modifications/substitutions necessary to meet the design parameters/good engineering practice,
these shall be brought to the notice of the Contractor who shall incorporate the same in the
drawings and works without any extra cost to the Owner. The Contractor will be totally
responsible for the correctness of the detailed fabrication drawings and execution of the work.
Contractor shall incorporate all the revisions made in the design drawings during the course of
execution of work in his fabrication drawings and resubmit the drawings at no extra cost. All
fabrication shall be carried out only as per the final AFC drawings.
The Contractor shall supply two prints each of the final / as built drawings alongwith their
transparencies to Owner / Consultant for reference and record.
The contractor is required to update the fabrication drawings to include revisions made in design
drawings during the course of work at no extra cost. The Contractor shall also supply two prints
of as built drawings, along with their transparencies at no extra cost.
3.4 FABRICATION
3.4.1 General
All fabrication shall be done as per specifications, IS:800, IS:9595 and other relevant IS codes on
the basis of stamped and signed “Good for Construction” fabrication drawings.
The contractor shall prior to starting any fabrication ensure that the fabrication yard is levelled and
firm enough to take weight of structures and equipment.
Any defective fabrication or material pointed out at any stage shall be replaced by the contractor
free of cost.
3.5.1 Straightening
All materials shall be straight and free from twists. If straightening or flattening is necessary, it
shall be done by a process approved by the Owner / Consultant, and in a manner that will not
damage the material properties. Sharp kinks or bends shall be a cause for rejection. The
specified camber wherever necessary shall be provided.
Bending of rolled steel section and plates shall be done by Cold Process to shapes, as shown in
drawings.
Tolerance as per IS: 7215.
3.5.2 Clearance
The erection clearance for members having end cleats or plates shall not be more than 2 mm at
each end, whereas for other types of end connections it shall not be more than 3 mm at each
end. If for any reason a greater end clearance is required, suitable seating, approved by Owner /
Consultant shall be provided.
3.5.3 Cutting
Prior to cutting, all members shall be properly marked showing the requisite cut length / width,
connection provisions e.g., location and dimensions of holes, welds, cleats, etc. Marking for
cutting shall be done judiciously so as to avoid wastages or unnecessary joints as far as
practicable. Marking shall be done by placing the members on horizontal supports/pads in order
to ensure accuracy. Marking accuracy shall be limited to + 1 mm.
Template shall be used for full scale layout incase of critical joints connection.
Cutting may be affected by shearing, cropping or sawing. Gas cutting by mechanically controlled
torch shall be permitted for mild steel. Hand flame cutting may be permitted subject to the
approval of the Owner / Consultant.
Except where the material is subsequently joined by welding, no loads shall be transmitted into
metal through a gas cut surface.
Shearing, cropping and gas cutting shall be clean, square, free from any distortion & burrs and
should the Owner / Consultant find it necessary, the edges shall be ground afterwards, to make
the same straight and uniform at no extra cost to the Owner.
3.5.4 Holing
Holes for compound or built up section passing through more than one thickness shall preferably
be drilled after the members are assembled and tightly clamped or bolted together. In case the
thickness of metal for each component is less than 16 mm, the holes may be punched prior to
assembly provided the holes are punched 3 mm smaller in diameter than the required size and
reamed after assembly to the required diameter. Dynamically loaded structures shall not be
holed by punching. In case the material is not more than 12 mm thick and the connection is not a
splice, the hole may be punched full size except in holes for close tolerance bolts or barrel bolts.
Holes may be drilled in one operation through two or more parts and the burrs removed from
each part after drilling. Holes not drilled through all the thicknesses in one operation shall be
drilled to a smaller size and reamed out after assembly.
Holes for close tolerance bolts and barrel bolts shall be drilled through all the thicknesses in one
operation and subsequently reamed to size after firmly holding the parts together with the aid of
tacking bolts or clamps.
Finished holes for black bolts of high strength and high strength friction grip bolts shall not have a
diameter more than 2 mm the diameter of the bolt passing through them or as specified in
fabrication drawings.
To facilitate the grouting, holes shall be provided in column base / seating plates exceeding
300 mm width for the escape of entrapped air.
To avoid accumulation of water inside column base or boxed type construction suitable
reverse U-type holes shall be provided at junction of base plate and column section in vertical
gusset plates to drain collected water out.
3.5.5 Bending
Bending of plates, flats and sections shall be carried out on bending rolls or in presses.
Cold process bending may be accepted when bending radius is equal to or more than
Accuracy of bending operations shall be checked by means of templates and the clearance
between member and template shall not be more than + 1 mm.
Bent member shall not have cracks or deep indentations from bending equipment.
3.5.6 Assembly
The component parts shall be aligned and assembled in such a fashion that they are not twisted
or damaged in any way and have the prescribed camber. The clamps, jigs and other fixtures
shall be placed so as to cause no imbalance which would result in twisting / incorrect positioning
of members. Due attention shall be paid to welding shrinkage and distortion.
3.5.7 Bolting
All turned and fitted bolts shall be parallel throughout the barrel within the tolerance of 0.125 mm,
unless otherwise specified and faces of heads and nuts bearing on steel work shall be machined.
All such bolts shall be provided with washers not less than 3 mm thick, so that when the nut is
tightened, it shall not bear the unthreaded body of the bolt and the threaded portion of the bolt
should not be within the thickness of the parts bolted together. The threaded portion of each bolt
shall project through the nut by at least one thread. Square tapered washers shall be provided for
all heads and nuts bearing on bevelled surface. Flat washers shall be circular in shape. The
bolts, nuts and washers, etc., shall be thoroughly cleaned and dipped in linseed oil.
All nuts and bolts shall be tightened in a staggered pattern and where more than four bolts in any
joints they shall be tightened from centre to outwards. Every bolted connection shall have atleast
2 bolts.
3.5.8 Bracings
Guys wires and temporary bracing shall be used wherever necessary to withstand the loads due
to erection. Such members shall be left in place as long as may be required for safety.
3.5.9 Welding
a. General
Welding of steel shall be in accordance with IS:816-1969, IS:819, IS:1024, IS:1261, IS:1323 and
IS:9595-1996 as applicable. Welds shall be made only by Qualified Welding Operators who have
been previously qualified by tests by the Owner / Consultant. Evidence of welder’s qualification
tests shall be produced if required by the Owner / Consultant. Owner / Consultant may reject any
welder found not suitable during actual work.
Welding wire and electrodes shall be sorted separately by quantities and lots inside a dry and
enclosed room, and as per instruction given by the Owner / Consultant. Electrodes shall be low
hydrogen type.
Both the structural members and the welding operation / process shall be adequately protected
from rain, strong winds or snow during welding. The Contractor shall provide necessary
supervision to ensure that all welding is carried out in conformity with the specification and
relevant IS codes. The contractor shall make all necessary infrastructure available such as
requisite number of welding sets, cutting and grinding equipment, test equipment and all
consumables as required.
Edge preparation of fusion faces for welding shall be carried out as per details given in IS: 9595
or as shown on drawings. All tolerances for such work shall be as per IS: 9595. The bevelling of
such faces shall be checked by the Owner / Consultant.
Surfaces to be welded shall be cleared to ensure that they are free from loose scales, slag, rust,
grease, paint and other foreign matter, and shall be maintained.
Preheating of members shall be necessary when the base metal temperature (based on ambient
temperature) is less than the temperature required for that welding procedure. The preheating
shall be done in such a manner that the part on which weld metal is to be deposited is above the
specified temperature for a distance of 75 mm on either side of the weld line. The temperature
shall be measured on the face opposite to the face being heated. In case access is limited to
only the face being heated, the source of heat shall be removed and sufficient time allowed to
elapse for heat equalisation prior to measurement. (1 minute per 25 mm of plate thickness).
Column splices and butt joints of compression members shall be accurately ground and close
butted over the entire section to ensure full contact for load transmission. The tolerance for such
work shall be maximum 0.2 mm. In the case of column bases and caps the ends of the section
along with connected gussets, stiffeners, angles, channels etc. shall be ground so as to ensure a
minimum contact area of 90%. The fitting of angles and channels should be sufficiently accurate
to limit the reduction in thickness on account of grinding to 2 mm. The ends of bearing stiffeners
shall be ground so as to fit tightly at both top and bottom. Slab bases and cap plates shall be
accurately ground over bearing surfaces to ensure minimum 90% contact area with columns.
c. Welding Processes
Argon welding process shall be done where working in an existing working plant building. Where
welding operation is carried out in restricted working plant areas , it shall only be conducted only
if required by the Owner/consultant in specified areas. See Annexure 1 for details on Argon
welding.
The Contractor shall submit the welding procedure and the consumables proposed to be used to
the Owner / Consultant for approval. Combination of processes or electrodes may be permitted
only with the specific approval of the Owner / Consultant.
The Contractor shall satisfy the Owner / Consultant that the welders are suitable for the work
upon which they will be employed. For this purpose the welders shall have satisfied the relevant
requirements of IS: 7318. If the welders will be working to approved welding procedures, they
shall have satisfied the relevant requirements of IS: 7310.
Adequate means of identification shall be provided to enable each weld to be traced to the welder
by whom it was made. The Contractor shall intimate the Owner / Consultant sufficiently in
advance, the commencement of tests, to enable him to be present to witness the same.
The Contractor shall carry out procedure tests in accordance with IS:7307 to demonstrate by
means of a specimen weld of adequate length on steel , that the welder can make welds with the
welding procedure to be used for the work to the complete satisfaction of the Owner / Consultant.
The test weld shall be as per weld details required for the actual work and should simulate the
work conditions likely to be encountered in the actual work in terms of sit up electrode condition
etc. The test weld shall be held at ambient temperature for a minimum period of 72 hours prior to
testing to IS: 7307
After establishing the welding method, the Contractor shall finally submit to the Owner /
Consultant for his approval of the welding procedure specification in standard format given in IS:
9595 before starting the fabrication.
f. Sequence of Welding
i. The direction of welding shall be from points relatively fixed with respect to each other
towards points having more flexibility.
ii. Welding shall be carried out continuously to completion with the required number of runs.
iii. For compound section splices, each component part shall be spliced prior to welding with
other component parts.
iv. Welds shall progress in a sequence that will balance the applied heat so as to reduce
distortion.
v. Joints having more shrinkage shall be welded prior to joints having less shrinkage.
g. Welding Technique
The fusion faces shall be properly aligned and the gap set to the distance specified. The root
pass of butt joint shall be done such that full penetration is achieved as also complete fusion of
root edges.
On completing each run the weld and the parent metal shall be cleared by wire brushing and light
chipping to remove all slag and splatters. Visible defects if any such as cracks, cavities etc. shall
be removed to sound metal prior to depositing subsequent run of weld.
All full penetration butt welds shall be completed by gouging / chipping the back of the joint and
depositing a seal run of weld metal. Alternatively a backing strip shall be provided.
All care shall be taken to prevent any kind of movement, shock or vibration of components during
welding to prevent weld cracks.
The method of inspection shall be according to IS:822 and extent of inspection and testing shall
be in accordance with the relevant applicable standard or, in the absence of such a standard, it
shall be done as specified by the Owner / Consultant. Welds shall not be painted or otherwise
obscured until they have been inspected, approved and accepted.
The Owner / Consultant or his representative shall have access to the Contractor’s work at all
reasonable times and the Contractor shall provide him with all facilities necessary for inspection
during all stages of fabrication and erection with, but not limited to, the following objectives.
i. To check the conformity with the relevant standards and suitability of various welding
equipments and their performance.
iv. To check whether shop/field welding being executed is in conformity with the relevant
specifications and codes of practice.
Inspection and testing of all fabricated structures shall be carried out by the Contractor by any, or,
a combination of all the following methods as directed by the Owner / Consultant and no separate
payment shall be made, unless otherwise mentioned, for inspection and testing of
welds/fabricated structures:
i. Visual Inspection
100% welds shall be visually inspected to ascertain absence of the following defects.
- Surface cracks in weld or parent metal, or undercut, burning, overheating of parent metal.
- Defects in the profile such as excessive convexity or concavity, unequal leg lengths
incompletely filled grooves, excessive penetration beeds, root grooves etc.
Tensile load test, bend tests, impact tests etc. shall be carried out as per the standard.
Radiographic examination shall be carried out only in special cases for random joints as
directed by the Owner / Consultant. The Contractor shall not be paid any extra for such
examination. The Contractor shall make necessary arrangement at his own expense for
providing the radiographic equipment, films and all other necessary materials required for
carrying out the examination. The tests shall be carried in the presence of the Owner /
Consultant by employing approved testing procedure in accordance with IS:822. The
Contractor shall fulfil all the statutory safety requirements while handling X-ray and Gamma-
ray equipment and provide the Owner / Consultant all the necessary facilities at site such as
dark room, film viewer etc., to enable him to examine the radiographs. When full strength
butt weld / full penetration bevelled weld shall be tested minimum 10% joints / length of weld
can be considered for testing.
The examination shall be done at random as directed by the Owner / Consultant. Whenever
such tests are directed, the tests shall be carried out on joints chosen by owner / consultant .
The tests shall be carried out by employing approved testing procedure in accordance with
IS: 822.
i. Repair of Welds
No repair of defective welds shall be carried out without proper permission of the Owner /
Consultant and his approval for the corrective procedure.
Welds not complying with the acceptance requirements (as specified by IS codes & the Owner /
Consultant), as revealed during inspection & testing of welds or erection or in-situ condition, shall
be corrected either by removing & replacing or as follows :
In removing defective parts of a weld, gouging, chipping, oxygen cutting or grinding shall not
extend into the parent metal to any substantial amount beyond the depth of weld penetration,
unless cracks or other defects exist in the parent metal. The weld or parent metal shall not be
undercut in chipping, grinding, gouging or oxygen cutting.
Any fabricated structure or its component which, in the opinion of Owner / Consultant, is defective
and/or beyond any corrective action shall be removed forthwith from the site as instructed by the
Owner / Consultant without any extra claim. The Owner reserves the right to recover any
compensation due to any loss arising out of such rejections.
3.5.10 Splicing
Splicing of built up / compound / latticed sections shall be done in such a fashion that each
component of the section is joined in a staggered manner.
Where no butt weld is used for splicing, the meeting ends of two pieces of joist/channel/built up
section shall be ground flush for bearing on each other and suitable flange and web splice plates
shall be designed and provided for the full strength of the flange / web of the section and welds
designed accordingly.
Where full strength butt weld is used for splicing (after proper edge preparation of the web and
flange plates) of members fabricated out of joist/channel/angles/built up section, additional flange
and web plates shall be provided, over and above the full strength butt welds, to have 40%
strength of the flange and web.
Where a cover plate is used over a joist/channel section the splicing of the cover plate and
channel/joist sections shall be staggered by minimum 500 mm. Extra splice plate shall be used
for the cover plate.
Prior approval shall be obtained by the Contractor for locations of splices where not shown on
design drawings. Only a single splice at approved locations shall be allowed for members up to a
length of 6 to 7 m. Maximum two numbers of splices shall be allowed for members exceeding
this length.
In case full strength butt weld is used to connect opposing ends at a joint, additional flange and
web splice plates shall be provided capable of carrying 20% strength of the flange and web.
The steel work shall be temporarily erected in the shop to determine the accuracy of the fit. The
extent of erection shall be either complete or as directed by Owner / Consultant.
Materials and workmanship at all times shall be subject to inspection by the Owner / Consultant.
All inspection as far as possible shall be made at the place of fabrication and the contractor shall
co-operate with the Owner / Consultant’s Inspector and permit access for inspection to all places
where work is being done. The contractor shall supply free to the Owner / Consultant all
necessary gauges and templates necessary for inspection. However, such inspection shall not
relieve the contractor of his responsibility to furnish satisfactory work.
The contractor shall obtain approval from the Owner / Consultant of all fabricated items prior to
commencement of their erection. However, any such approval shall not absolve the Contractor
from his responsibility of correctness and workmanship of the entire work.
Loading and transportation shall be done in accordance with transport rules prevailing at that
location. Items shall be packed to protect them from damage / distortion. Small parts shall be
securely wired to their main members.
Loose items such as Bolts, nuts and washers shall be packed in crates.
The suitability and capacity of all plant and equipment used shall be to the complete satisfaction
of the Owner / Consultant.
All steel work shall be so stored and handled at site so that the members are not subjected to
excessive stresses and any damage.
Setting Out
Prior to setting out of the steel work, the Contractor shall get himself satisfied about the
correctness of levels, alignment, location of existing concrete pedestals/columns/brackets and
holding down bolts/pockets provided therein. Any minor modification in the same including
chipping, cutting and making good, adjusting the anchor bolts etc., if necessary, shall be carried
out by the Contractor at his own expense. The positioning and levelling of all steel work including
plumbing of columns and placing of every part of the structure with accuracy shall be in
accordance with the drawings and to the complete satisfaction of the Owner / Consultant.
Tolerances
Tolerances for erection of steel work shall be in accordance with Table given below & IS:7215
whichever is more stringent.
ERECTION TOLERANCES
Tolerances allowed in the Erection of Structural Steel Buildings frames shall be as follows :
- in Longitudinal direction + 5 mm
- in Lateral direction + 5 mm
c) Deviation in straightness in
longitudinal and transverse + 10 mm or + H/1000
planes of column at any ( whichever is less )
point along the height.
Crane, Gantry, Girders and Shift in the centre line of crane rail + (half web thickness
Rails with respect to centre line of web of plus 2 mm)
gantry girder
i) Supports 15 mm
ii) Midspan 20 mm
The CONTRACTOR shall comply with IS: 7205 for necessary safety and adhere to safe erection
practices and guard against any hazardous as well as unsafe working conditions during all stages
of erection.
During erection, the steel work shall be securely bolted or otherwise fastened and when
necessary, temporarily braced/guyed to provide for all loads to be carried by the structure during
erection till the completion, including those due to the wind, erection equipment and its operation
etc., at no extra cost to the Owner. For the purpose of guying, the Contractor shall not use other
structure in the vicinity without prior written permission of the Owner / Consultant.
No permanent bolting or welding shall be done until proper alignment has been achieved.
Proper access, platform and safety arrangement shall be provided for working and inspection, (at
no extra cost to the Owner) whenever required.
Field Bolting
Field bolting shall be carried out with the same care as required for shop bolting.
Field Welding
All field assembly and welding shall be executed in accordance with the requirements for shop
assembly and welding. Holes for all erection bolt – where removed after final erection shall be
plugged by welding. Alternatively, erection bolts may be left and secured.
3.13 GROUTING
After final alignment and plumbing of the structure, the forms shall be constructed alround and
joints made tight to prevent leakage. Grouting (under the base plates/shoe plates including
grouting of sleeves & pockets) shall be done on dry cleaned concrete surface with non-shrink
2
grout having compressive strength (28 days) not less than 40 N/mm . Non shrink grout shall be
of free flow premix type and of approved quality and make. It shall be mixed with water in
proportion as specified by the manufacturer. Ordinary 1:2 cement/sand mortar grout with non-
shrink admixture in to the cement grout mix in shall be used only for small, isolated structures
e.g., operating platforms not supporting any equipment not exceeding 2 m heiht, pipe supports
not exceeding 1.5 m height, cross overs, & ladders. The thickness of grout shall be as shown on
the drawings but not less than 25 mm or more than 50 mm in any case.
The grout mixture shall be poured continuously (without any interruption till completion) by
grouting pumps from one side of the base plate and spread uniformly with flexible steel strips and
rammed with rods, till the space is filled solidly and the grout mixture carried to the other side of
the base plate.
The grout mixture shall be allowed to harden for a period as per manufacturer’s specification
decided by the Owner / Consultant. At the end of this period, the shims/wedges/pack plates may
be removed and anchor bolts tightened uniformly. The alignment of the structure shall now be
rechecked and if found correct, the voids left by the removal of shims/wedges/pack plates (if
removed) must be filled up with a similar mixture of grout. In case after checking, serious
misalignment is indicated, the grout shall be removed completely and fresh grouting done after
making appropriate correction of alignment.
5.0 ATTACHMENTS
Annexure -1
ANNEXURE-1
Material:
Technical Requirements:-
a. The welding should be done by experienced and qualified Tungsten inert gas
(Argon) welder.
b. Starting the arc by touching the tungsten electrode to the work piece must be
avoided as it contaminates and wears out the electrode tip, and gives rise to
tungsten Inclusions in the weld deposit and thereby degrading the weld metal
properties.
c. Gas pre-flow is must for good quality fig welding, as it removes air from the torch
and gas hose before the arc strikes and ensures complete and perfected
shielding of the electrode and base metal even before the arc is struck and
during arc striking.
d. Joints to be welded should be free from paint grease oil, oxide film and scale
and free of sulphur lead.
e. While welding the welder must watch the puddle at all times to see that it is built
up to a uniform height and form a smooth bead with only traces of a ripple.
f. The welder must be careful to prevent the electrode from making contact with the
sides of the joints and molten puddle.
g. While welding with tungsten electrodes the arc tip should be only hot part of the
electrode, the remainder should be kept as cool as possible.
h. Electrodes should be kept in original package and kept clean; without broken electrodes.
1. "Supplying, Fabricating, transporting fabricated items to site, unloading & storing bolted and/ MT
or welded STRUCTURAL STEEL WORKS of Grade E250A (confirming to IS:2062 at all
locations and levels) including all builtup sections/ compound sections made out of rolled
sections and/or plates/ bent plates in beams, brackets, bracings, ladders (with or without
cage), safety chain brackets, staircases and platforms of any shape and size (excluding
chequered plates/ gratings), on vertical and/ or horizontal equipments, in miscellaneous
valve operating platforms, pipe supports etc, cutting to required size, straightening/ bending
if required, edge preparation, cleaning, preheating, bolting/ welding of joints, (including
sealing the joints of box sections with continuous welding and plugging any open ends &
holes of box sections), finishing edges by grinding, including preparation and submission of
detailed fabrication drawings, preparing the surface for painting (SSPC-SP-10) and applying
pre-erection/ shop primer (1 coat of Inorganic Zinc Sulphate (F-9) coating @ 65-75 micron
DFT) as per Specification No. 44NC-4600-0000-V.02-0111-A4 after fabrication etc. all
complete as specified and directed. (SUPPLY OF ALL MATERIAL IN CONTRACTOR'S
SCOPE.)
3. Supplying, Fabricating, transporting fabricated items to site, unloading & storing 1050mm M
high HORIZONTAL HAND RAILING (for platforms, walkways, etc. or any other location as
directed) consisting of top rail with 32mm nominal diameter medium grade MS Tubes
conforming to IS:1239, mid rail with L50x50x6 & vertical posts (Maximum spacing 1200mm
c/c) with L90x90x8 confirming to IS:2062 (Grade A), including straightening if required,
cutting, bending, welding, bolting, cleaning, preparing the surface for painting (SSPC-SP-
10) and applying pre-erection/ shop primer (1 coat of Inorganic Zinc Sulphate (F-9) coating
Template NoPage
5-0000-0001-T3
369 of 434 Rev 1 Copyrights EIL – All rights reserved
SCHEDULE OF RATES FOR ADDITION AND DELETION Document No.
FOR LADDER & PLATFORMS A133-086-16-48-SOR-6141
87-C-08 & 87-C-09 Rev No A
Page 3 of 3
_____________________________
Template NoPage
5-0000-0001-T3
370 of 434 Rev 1 Copyrights EIL – All rights reserved
SCHEDULE OF QUANTITIES Document No.
FOR PLATFORMS & LADDER FOR A133-086-16-48-SOQ-6141
87-C-08 & 87-C-09 Rev No A
Page 1 of 3
STRUCTURAL
1. "Supplying, Fabricating, transporting fabricated items to site, unloading & storing bolted and/ or welded
STRUCTURAL STEEL WORKS of Grade E250A (confirming to IS:2062 at all locations and levels) including all
builtup sections/ compound sections made out of rolled sections and/or plates/ bent plates in beams, brackets,
bracings, ladders (with or without cage), safety chain brackets, staircases and platforms of any shape and size
(excluding chequered plates/ gratings), on vertical and/ or horizontal equipments, in miscellaneous valve operating
platforms, pipe supports etc, cutting to required size, straightening/ bending if required, edge preparation, cleaning,
preheating, bolting/ welding of joints, (including sealing the joints of box sections with continuous welding and
plugging any open ends & holes of box sections), finishing edges by grinding, including preparation and submission
of detailed fabrication drawings, preparing the surface for painting (SSPC-SP-10) and applying pre-erection/ shop
primer (1 coat of Inorganic Zinc Sulphate (F-9) coating @ 65-75 micron DFT) as per Specification No. 44NC-4600-
0000-V.02-0111-A4 after fabrication etc. all complete as specified and directed. (SUPPLY OF ALL MATERIAL IN
CONTRACTOR'S SCOPE.)
1.1 EQUIPMENT NO. 87-C-08 MT 2.6
1.2 EQUIPMENT NO. 87-C-09 MT 2.5
2. Supplying and fabricating ELECTROFORGED GALVANISED GRATING TYPE-I (purchased from approved
manufacturer by the Contractor) conforming to Standard No. 44NC-4600-0000/S.01/0008/A4 (Sheet 1 of 8 to sheet
8 of 8) (in walkways, platforms, stair treads etc.) including cutting to required size, shape, making holes, notches,
openings of required size, nosing, straightening if required, making the edges smooth, removing the burrs, supplying
manufacturer's supplied galvanised clamps, preparation and submission of fabrication drawings, all complete as
specified and directed (SUPPLY OF ALL MATERIALS IN CONTRACTOR'S SCOPE).
2.1 EQUIPMENT NO. 87-C-08 MT 1.7
2.2 EQUIPMENT NO. 87-C-09 MT 1.6
3. Supplying, Fabricating, transporting fabricated items to site, unloading & storing 1050mm high HORIZONTAL HAND
RAILING (for platforms, walkways, etc. or any other location as directed) consisting of top rail with 32mm nominal
diameter medium grade MS Tubes conforming to IS:1239, mid rail with L50x50x6 & vertical posts (Maximum
spacing 1200mm c/c) with L90x90x8 confirming to IS:2062 (Grade A), including straightening if required, cutting,
bending, welding, bolting, cleaning, preparing the surface for painting (SSPC-SP-10) and applying pre-erection/
shop primer (1 coat of Inorganic Zinc Sulphate (F-9) coating @ 65-75 micron DFT) as per Specification No. 44NC-
Template NoPage
5-0000-0001-T3
372 of 434 Rev 1 Copyrights EIL – All rights reserved
SCHEDULE OF QUANTITIES Document No.
FOR PLATFORMS & LADDER FOR A133-086-16-48-SOQ-6141
87-C-08 & 87-C-09 Rev No A
Page 3 of 3
4600-0000-V.02-0111-A4 after fabrication and submission of fabrication drawings etc., all complete as specified,
shown and directed. (SUPPLY OF ALL MATERIALS IN CONTRACTOR'S SCOPE). (Complete handrail work shall
be measured as length of top rail only and not length of each element fixed).
3.1 EQUIPMENT NO. 87-C-08 M 50
3.2 EQUIPMENT NO. 87-C-09 M 50
_____________________________
Template NoPage
5-0000-0001-T3
373 of 434 Rev 1 Copyrights EIL – All rights reserved
TECHNICAL SPECIFICATIONS DOCUMENT No.
(CIVIL-STRUCTURAL) FOR A133-086-16-48-SOW-6141
Rev. A
PLATFORMS & LADDER FOR
87-C-08 & 87-C-09 Page 1 of 7
TECHNICAL SPECIFICATIONS
(SCOPE OF WORK/ SUPPLY
AND SPECIFIC REQUIREMENTS)
(CIVIL-STRUCTURAL)
FOR
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
Page 374 of 434
DOCUMENT No.
TECHNICAL SPECIFICATIONS A133-086-16-48-SOW-6141
(CIVIL-STRUCTURAL) FOR Rev. A
PLATFORM & LADDER FOR
87-C-08 & 87-C-09 Page 2 of 7
CONTENTS
SL TITLE PAGE
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
Page 375 of 434
DOCUMENT No.
TECHNICAL SPECIFICATIONS A133-086-16-48-SOW-6141
(CIVIL-STRUCTURAL) FOR Rev. A
PLATFORM & LADDER FOR
87-C-08 & 87-C-09 Page 3 of 7
1. SCOPE OF WORK
The scope of work under this contract shall include in general, but not limited to supply,
fabrication, transportation etc. for all relevant structural works (excluding erection at site) for
platforms (circular or any shape) on vertical vessels 87-C-08 & 87-C-09 in LPG CFC unit at
CPCL, Manali, Chennai including supply of all materials (as defined in scope of supply), tools
& tackles, labour, etc., as per the detailed scope of work, scope of material supply, schedule of
quantities, specifications, standards, drawings included in this Document (including
addendums/ amendments) and the directions of Engineer-in-charge and as per approved for
construction (AFC) drawings (including subsequent revisions) made available to the
successful bidder.
Major structural activities involved shall include but not be limited to the following :
1.1 Structural steel works with rolled steel or tubular/ hollow sections, including supply,
transportation, fabrication and preparation of detailed fabrication drawings for all types
of structures at all locations and heights.
1.2 For scope of other civil-structural works, refer Doc. No. A133-16-46-SS-6141 attached
elsewhere in the bid document.
Any other structural work, not specifically mentioned herein, but required for the
satisfactory and successful completion of the project as per directions of the Engineer-in-
Charge shall also be in the scope of the contractor.
2. SCOPE OF SUPPLY
NIL.
2.2.1 All items consumables/ non consumables required to complete the job as per
Specifications, standards, drawings & instructions of Engineer-in-Charge.
2.2.2 All labor, tools tackles, plant machinery etc to complete the job.
2.3 Approved manufacturer/ vendor list for Electro-forged galvanized grating for use in
Structural works is as follows:
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
Page 376 of 434
DOCUMENT No.
TECHNICAL SPECIFICATIONS A133-086-16-48-SOW-6141
(CIVIL-STRUCTURAL) FOR Rev. A
PLATFORM & LADDER FOR
87-C-08 & 87-C-09 Page 4 of 7
3. SPECIFIC REQUIREMENTS
Note: In case of any contradiction between these Specific Requirements and Requirements/
Specification specified elsewhere in the tender document, the Specific Requirements given
below shall have precedence.
3.1 All works shall be done to the entire satisfaction of the Engineer-in-Charge/ TPI. Any
work not carried out in accordance with the instructions shall be dismantled and made
good without any extra cost and time implication to the owner.
3.2 Assembly & Shop erection of platforms as per specification shall be ensured before
supplying to site.
3.3 The contractor shall ensure proper co-ordination / co-operation with other agencies,
while working in the unit area, without affecting others work front areas.
5.1. Prices for quantities of items mentioned in SOQ (Doc. No. A133-086-16-48-SOQ-6141)
shall be included in the quoted prices. Unit rate quoted against each SOR item (as per Doc.
No. A133-086-16-48-SOR-6141) shall be applicable for any addition and deletion during
execution of the project.
6. ADDENDUM TO SPECIFICATIONS
6.1.1. The payment terms shall be read in conjunction with the Specification No. 44NC-4600-
0000/C.02/0015/A4.
6.1.2. Payment for structural steel works shall be made on the basis of admissible weight in
metric tons (determined as described in Clause 6.1.3 and 6.1.4) of the structure accepted
by the Engineer-in-Charge. The rate shall include supplying (as per supply conditions
given in the Tender) fabricating, testing/examining (excluding radiography only) of
bolted and/or welded structural steel works of all types (including all built up/compound
sections made out of rolled sections and/or plates) including all handling, transporting,
storing, straightening if required, cutting, edge preparation, preheating, bolting and
welding of joints (including sealing the joints of box sections with continuous welding),
finishing edges by grinding/machining as shown, preparation of fabrication drawings,
preparation and submission of as built drawings, preparing the surfaces for painting, and
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
Page 378 of 434
DOCUMENT No.
TECHNICAL SPECIFICATIONS A133-086-16-48-SOW-6141
(CIVIL-STRUCTURAL) FOR Rev. A
PLATFORM & LADDER FOR
87-C-08 & 87-C-09 Page 6 of 7
applying the primer as specified after fabrication, etc. all complete for all the operations
mentioned in the foregoing clauses.
6.1.3. The weight for payment shall be determined from the fabrication drawings and
respective bill of materials prepared by the Contractor. The bill of materials shall be
checked and approved by the Engineer-in-Charge before making the payment. The
Contractor shall prepare full scale template in order to supplement/verify the actual
cutting dimensions where so directed by the Engineer-in-Charge. The weight shall be
calculated on the basis of BIS Hand Book wherever applicable. In case sections used are
different from BIS sections, then Manufacturers' Hand Book shall be adopted. No
allowance in weight shall be made for rolling tolerances.
6.1.4. Welds, bolts, nuts, washers, shims, pack plates, wedges, shop painting shall not be
separately measured. The quoted rate shall be deemed to include the same.
6.1.5. The rate shall include all expenses related to safety & security arrangements and all
plants & tools required for fabrication & transportation.
6.2.1. The payment terms shall be read in conjunction with the Specification No. 44NC-4600-
0000/C.02/0025/A4.
6.2.2. Payment shall be made on the basis of admissible weight in metric tons (determined as
described in clause 6.2.4) of the gratings accepted by the Engineer- incharge.
6.2.3. The rate shall include supplying & fabricating M.S. gratings (purchased from approved
manufacturer) including transporting, handling, cutting to required size and shape,
making holes/notches/openings, smoothening the edges, fabricating clamps, preparing
detailed fabrication drawings, surface cleaning, removal of rust, scale, grease and
galvanising as required, all complete.
6.2.4. The weight for payment shall be determined from the fabrication drawings and
respective bill of materials prepared by the Contractor. The bill of materials shall be
checked and approved by the Engineer-incharge before making the payment. The
weight, shall be calculated on the basis of BIS Handbook as mentioned above. No
allowance in weight shall be made for rolling tolerances.
6.2.5. Welds, bolts, clamps, nuts and washers shall not be measured. The quoted rate shall be
deemed to include the same.
6.3.1. The payment terms shall be read in conjunction with the Specification No. 44NC-4600-
0000/C.02/0025/A4.
6.3.2. Payment shall be made on the basis of measured length in meters (m) of top rail only
(Horizontal and/or inclined lengths). The rate shall include preparation of fabrication
drawings, supply of all materials, handling, transporting, straightening if required,
cutting to required size, bending, welding, bolting, surface cleaning, removal of rust,
scale, grease and applying one coat of primer as per Specification no. 44NC-4600-
0000/V.02/0111/A4, after fabrication etc. all complete.
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
Page 379 of 434
DOCUMENT No.
TECHNICAL SPECIFICATIONS A133-086-16-48-SOW-6141
(CIVIL-STRUCTURAL) FOR Rev. A
PLATFORM & LADDER FOR
87-C-08 & 87-C-09 Page 7 of 7
6.3.3. The rate shall include making suitable notches in floor plates/gratings for fixing the
vertical posts.
Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved
Page 380 of 434
Page 1 of 6
TABLE OF CONTENTS
1.0 PURPOSE
2.0 SCOPE
1.0 PURPOSE
2.0 SCOPE
The work covered consists of providing & installing all miscellaneous metal work in strict
accordance with the specifications and the applicable drawings. The following work shall normally
be covered under the specifications.
Work included under the Specifications shall be fabricated and installed by the contractor at the
proper time, and as rapidly as progress of the adjacent & connecting work will permit. Work to be
installed by the contractor shall be delivered when required. The contractor shall consult with the
various Agencies installing adjoining work, regarding the methods to be employed in connecting
the several materials. Holes and connections for the work of other trades shall be provided as
necessary. All work shall be erected and secured plumb and true to line, and finished smooth and
free from noticeable irregularities of file marks.
The contractor shall verify all measurements in the field, for the fabricated work to fit the actual
conditions at site. Before starting work, all adjoining work shall be examined. Application of
corrective measures to the adjoining work, may be necessary to make the work comply with the
specifications.
3.1 MATERIALS
The materials for fabrication work covered in the specifications shall be supplied by the
contractor. The M.S. materials shall conform to IS 2062 / IS 432 for tubular sections conform to
IS: 1161and IS:1239 (Part 1), IS : 1239 (Part 2) , for welding conform to IS: 814 , IS:816, IS :
9595 ,IS : 813.
Steel ladders with cage and rungs shall be provided and installed wherever indicated and as
detailed in the drawings. Necessary accessories, such as base plates, anchor bolts shall also be
provided.
Anchor bolts shall be made out of steel or iron rod, with pipe sleeves, bent ends or anchor plates
as shown and specified in drawings. Bolts shall be provided with hexagonal head, nuts &
washers. Bolts shall be provided with M.S. sleeves, wherever necessary for adjustment during
erection. The material shall conform to IS 2062 : 2006 Grade ‘B’ ( Fe 410 w ) E250 ( carbon 0.22
% maximum).
3.4 SLEEVES
Sleeves shall be fabricated out of M.S. sheets or YST 25 medium pipes or P.V.C. If load bearing,
they shall be fastened by anchor straps in concrete, and shall be placed at proper elevation as
shown in the drawings. The work shall include providing and fixing sleeves and sealing with
cement grout in manner approved by the owner / consultants.
These shall be provided in underground ducts & roofs as indicated in the drawings. Access
opening covers shall be of steel and painted as required. Air - tight hatches shall be gasketed
suitably.
Metal flashings shall be installed at locations shown in the drawings to provide water-tight
protection. Exposed edges of all flashings shall be folded back 12 mm to provide stiffness. Cap
flashings shall be secured in metal reglects with the groove filled with caulking compound as
shown in the drawings. The materials of flashings will be either G.I., aluminium or copper as
specified.
Steel stairs including cat - walks, wherever shown on the drawings shall be complete with
stringers, treads, risers, cat - walk framing, struts, hangers, bracing, chequered plates, toe plates,
railings and all fastenings and fittings. All work shall be shop fitted and assembled as far as
possible before erection. All work shall be erected square, plumb straight and true. Joints and
intersections shall be accurately fitted and securely braced or anchored.
These shall consist of M.S. angle 50 x 50 x 6mm size with hold-fasts @ 200 mm minimum / c.c.
unless otherwise stated. Hold-fasts shall normally be 8mm M.S. rods approximately 150mm long,
bent to shape and welded within the flanges of the angles.
3.9 M.S.INSERTS
M.S. plate or pipe inserts in concrete or masonry shall be fixed at correct locations and elevations
shown in the relevant drawings. The fabrication of the inserts shall be done in the best applicable
methods to avoid distortion. Hold-fasts shall normally be fully welded unless otherwise specified.
Any parts such as bolts, which are integral part of the insert, shall be carefully handled during
fabrication to avoid damages to threads and shall be accurately positioned prior to and during
welding. The inserts shall be painted with anti –corrosive paint over primer on exposed surfaces
after placement. Any modifications after placement in concrete particularly with gas-cutting shall
be avoided.
This shall consist of M.S. angle / M.S. pipes and two runners at top and mid height of the post.
Wherever necessary, the plates shall be provided. The construction shall be welded type unless
otherwise specified. The vertical posts shall be M.S. angle 50x50x6 / 32 NB or 40 NB ‘B’ class
pipe or as specified in drawings and shall be placed at 1.5M max spacing unless otherwise
specified. The height shall be 1050 mm. The mid rail 32 NB or 25 NB B class pipe / structural
steel shall be welded as shown on the drawing and specified elsewhere.
Fabrication, in general, shall be as shown on the drawings and specified elsewhere. Toe plate of
100 x 6 M.S. flat shall be provided whenever called out. The handrail top shall be wooden or M.S.
pipe fixed as per detail drawing.
The material shall conform to IS 2062 / IS 3502 . The thickness of the chequered plate shall be
as specified in the drawings. The plates shall either be tack-welded / seal-welded to the
supporting structure or shall be fixed by the counter - sunk bolts, as required. The plate shall be
fixed in regular shapes and the intermediate joints shall be welded types. Care shall be taken to
avoid distortion of the plate while welding. The M.S. stiffening angle shall be specifically shown in
the relevant drawings. Openings and cuts shall be provided wherever necessary to allow service
piping and / or cables to pass through. Wherever necessary, vertical edge strips shall be
provided. The rate of chequered plates shall be deemed to include all the work necessary and as
described in the preceding lines and shall also cover one shop coat of red-oxide primer.
These shall be of the best locally available make, and shall be approved by the Consultants
before using the same. The anchor fasteners type, diameter shall be as per the loading for
holding up minor / medium/ heavy structural works and equipments in concrete or masonry as
required. It shall be as per manufacture’s specification.
Grating shall be designed for min. 500 Kg load over 1 sq. m area or as desired by Owner /
Consultant.
Electroforged grating shall conform to BS 4592. The electroforged grating shall have hot dip
galvanized finish as per IS 2629 / ASTM 123 / BS 729. Minimum thickness of galvanizing shall
be 120 microns.
Flats / Twisted cross bars to be pressed and simultaneously resistance welded into solid bearing
flats to obtain perfectly homogeneous forged weld at every intersection without any air gaps to
give the grating panels high stability, maximum strength & optimum load distribution.
The entire manufacturing process shall be programmed & controlled to achieve forge weld that
provide incomparable resistance to twisting and bending distortions along with dimensional
accuracy.
The top surface of the grating should be non-skid / plain. Sprays for the galvanization shall be
used when grating are cut to form openings at site to return the galvanization.
The Vendor shall provide all necessary non-corrosive clamps, fixtures required as per connection
developed.
FRP grating of minimum 30mm thick of Vinylester based resin material of approved make
shall be used where grating would be subjected to acid attack.
The grating shall be manufactured from grey cast - iron conforming to grade 15 of IS - 210. The
cast - iron grating shall conform to IS - 5961 and as specified on the drawing.
PART : III
SECTION : B.12
TABLE OF CONTENTS
1.0 General
2.0 Scope
3.0 Codes & Standards
4.0 Equipment
5.0 Surface Preparation
6.0 Paint Materials
7.0 Paint Systems
7.1 Pre-erection / Pre-fabrication and shop priming for carbon steel, low temperature carbon
steel & low alloy steel, un-insulated and insulated steel structures, piping and equipment,
etc.,
7.2 Repair of pre-erection /fabrication and shop priming after erection / welding for carbon steel,
low temperature carbon steel & low alloy steel uninsulated and insulated items in all
environments.
7.3 Repair of all weld joints and damages of galvanized steel, carbon steel and alloy steel
structures, piping and equipment after erection on above ground / overhead areas at site.
8.0 Field paint system for normal corrosive environment (for carbon steel, low temperature
carbon steel and low alloy steel)
9.0 Field paint system for corrosive areas in plant (for carbon steel, low temperature carbon
steel and low alloy steel)
10.0 Field paint system for highly corrosive areas in plant (for carbon steel, low temperature
carbon steel and low alloy steel)external surfaces of piping & equipment
11.0 Field paint system for carbon steel storage tanks (internal & external) for all environment
and areas
12.0 Coating system for external side of underground carbon steel plant piping and tanks
13.0 Painting under insulation for (hot, cold & safety) Carbon Steel plant piping and tanks
14.0 Internal protection of Carbon Steel water boxes and tube sheets of cooler condensers
15.0 Field painting system for GI towers / Non-Ferrous tueb sheet
16.0 Shop & Field painting system for Effluent treatment plant
17.0 Storage
18.0 Color code for piping as per CPCL
19.0 Identification of vessels, piping, etc.,
20.0 Painting for civil defence requirements
21.0 Inspection and testing
22.0 Guarantee
23.0 Qualification criteria of painting contractor
1.0 GENERAL
1.1 These technical specifications shall be applicable for the work covered by the contract and
without prejudice to the various codes of practice, standard specifications, etc. It is understood
that Contractor shall carry out the work in all respects with the best quality of materials and
workmanship and in accordance with the best engineering practice and instructions of Engineer-
in-Charge.
1.2 1 Wherever it is stated in the specification that a specific material is to be supplied or a specific
work is to be done, it shall be deemed that the same shall be supplied or carried out by the
contractor. Any deviation from this standard without written deviation permit from appropriate
authority will result in rejection of job.
2.0 SCOPE
2.1 Scope of work covered in the specification shall include, without being limited to the following
2.1.1 This specification defines the requirements for surface preparation, selection and application of
paints on external surfaces of equipment, vessels, machinery, piping, ducts, steel structures,
external & internal protection of storage tanks for all services. MS chimney without refractory
lining and flare lines etc. The items listed in the heading of tables of paint systems is indicative
only, however the contractor is fully responsible for carrying out all the necessary painting,
coating and lining on external and internal surfaces as per the tender requirement.
2.2.1 The following surfaces and materials shall require shop, pre-erection and field painting :
a. All un-insulated C.S & A.S equipment like columns, vessels, drums, storage tanks, heat
exchangers, pumps, compressors, electrical panels and motors etc., and tanks and
equipment in ETP plant.
b. All un-insulated carbon and low alloy piping fittings and valves (including painting of
identification marks), furnace, ducts and stacks.
d. All structural steel work, pipe, structural steel supports, walkways, handrails, ladders,
platforms, etc.
f. Identification color bands on all piping as required including insulated aluminum clad,
galvanized, SS and nonferrous piping.
i. Supply of all primers, paints and all other materials required for painting other than Owner’s
supply.
k. Painting under insulation for carbon steel, alloy steel and stainless steel as specified. 1
l. Repair work of damaged / pre-erection / fabrication shop primer and weld joints at field.
2.2.2 The following surfaces and materials shall not require painting in general. However, if there are
any specific requirement by the Owner, the same shall be painted as per the relevant
specifications:
2.3 Unless otherwise instructed final painting on pre-erection / shop primed pipes and equipments
shall be painted in the field, only after the mechanical completion, testing on systems are
completed as well as after completion of steam purging wherever required.
2.4 Changes and deviations required for any specific job due to clients requirements or otherwise
shall be referred to Jacobs for deviation permit.
3.1 Without prejudice to the provision of Clause 1.1 above and the detailed specifications of the
contract, the following codes and standards shall be followed for the work covered by the
contract.
Color coding Color coding inspection manual for piping issued by CPCL (Ref.
Annexure-2) 1
ASA A 13.1-1981 Scheme for identification of piping systems: American National Standards
Institution.
3.2.1 Swedish Standard – SIS-05 5900-1967 (surface preparation standards for painting steel surfaces)
This standard contains photographs of the various standards on four different degrees of rusted
steel and as such is preferable for inspection purpose by the Engineer-in-Charge.
3.2.2 Steel Structures Painting Council, U.S.A (Surface Preparation Specifications (SSPC-SP).
3.2.5 Various International Standards equivalent to Swedish Standard for surface preparations are
given in Table-I.
3.3 The contractor shall arrange, at his own cost, to keep a set of latest edition of above standards
and codes at site.
3.4 The paint manufacturer’s instructions shall be followed as far as practicable at all times.
Particular attention shall be paid to the following :
4.0 EQUIPMENT
4.1 All tools, brushes, rollers, spray guns, blast material, hand power tools for cleaning, inspection
instruments, e.g. surface profile gauges, holiday detectors, pin hole detectors, dry film thickness
gauges, etc. and all equipments, scaffolding materials, shot blasting equipments like hooper, grit
etc & air compressors, etc., required to be used shall be suitable for the work and all in good
order and shall be arranged by the Contractor at site and in sufficient quantity. 1
4.2 Mechanical mixing shall be used for paint mixing operations in case of two pack systems except
that the Engineer-in-Charge may allow the hand mixing of small quantities at his discretion.
5.1 General
5.1.1 In order to achieve the maximum durability, blast cleaning is considered the most desirable
method to achieve required profile however one or more of following methods of surface
preparation shall be followed, depending on conditions of steel surface and as instructed by
Engineer-in-Charge. Adhesion of the paint film to surface depends largely on the degree of
cleanliness and surface profile of the metal surface. Proper surface preparation contributes more
to the success of the paint protective system.
5.1.2 Mill scale, rust, rust scale and foreign matter shall be removed fully to ensure that a clean and dry
surface is obtained. The minimum acceptable standard in case of manual or hand tool cleaning
shall be St. 2 or equivalent, in case of mechanical or power tool cleaning it shall be St. 3 or
equivalent in case of blast cleaning it shall be Sa 2-1/2 OR equivalent as per Swedish Standard
SIS-055900-1967 or equivalent. Where highly corrosive conditions exist, then blast cleaning shall
be Sa 3 as per Swedish Standard.
Remove all other contaminants, oil, grease, etc. by use of an aromatic solvent prior to surface
cleaning.
5.1.3 Blast cleaning shall not be performed where dust can contaminate surfaces undergoing such
cleaning or during humid weather conditions having humidity exceed 85%.
5.1.4 Irrespective of the method of surface preparation, the first coat of primer must be applied by
airless spray gun on dry surface No brush shall be used except for touchup. This should be done
immediately and in any case within 4 hours of cleaning of surface. However, at times of
unfavorable weather conditions, the Engineer-In-Charge shall have the liberty to control the time
period, at his sole discretion and / or to insist on re-cleaning, as may be required, before primer
application is taken up. In general, during unfavorable weather conditions, blasting and painting
shall be avoided as far as practicable. 1
5.1.5 The external surface of RCC chimney to be painted shall be dry and clean. Any loose particle of
sand, cement, aggregate etc., shall be removed by scrubbing with soft wire brush if necessary
acid etching with 10-15% HCl solution for about 15 minutes shall be carried and surface must be
thoroughly washed with water to remove acid & loose particles then dry completely before
application of paint.
The surfaces shall be blast cleaned using one of the abrasives Al2O3 particles chilled cast iron or
malleable iron and steel at pressure of 7 Kg /cm2 at appropriate distance and angle depending of
nozzle size maintaining constant velocity and pressure. Chilled cast iron, malleable iron and steel
shall be in the form of shot or grit of size not greater than 0.055” maximum in case of steel and
malleable iron and 0.04” maximum in case of chilled iron. Compressed air shall be free from
moisture and oil. The blasting nozzles should be venturi style with tungsten carbide or boron
carbide as the materials for liners. Nozzles orifice may vary from 3/16” to ¾”. On completion of
blasting operation, the blasted surface shall be clean and free from any scale or rust and must
show a grey white metallic luster. Primer or first coat of paint shall be applied within 4 hours of
surface preparation. Blast cleaning shall not be done outdoors in bad weather without adequate
protection or when there is dew on the metal, which is to be cleaned. Surface profile shall be
uniform to provide good key to the paint adhesion (i.e. 35 to 50 microns). If possible vacuum
collector shall be installed for collecting the abrasives and recycling.
Environmental, health and safety problems associated with abrasive blast cleaning limit the
application of Air Blast Cleaning in many installations. In such case water blast cleaning is
resorted to.
Water Blast Cleaning can be applied with or without abrasive and high pressure water blasting.
The water used shall be inhibited with sodium chromate / phosphate. The blast-cleaned surface
shall be washed thoroughly with detergents and wiped with solvent and dried with compressed
air. For effective cleaning abrasives are used. The most commonly used pressure for high
pressure water blast cleaning for maintenance surface preparation is 3000 to 6000 psi at 35-45
lit/minute water volume and pressures upto 1000 psi and water volume at 45 lit/minute provide
maximum cleaning.
The water blast cleaned surface shall be comparable to SSPC-SP-12/nace No. 5. The operation
shall be carried out as per SSPC guidelines for water blast cleaning. The indicative values for
sand injection is :
Special equipments for water blast cleaning with abrasives, now available, shall be used.
Power tool cleaning shall be done by mechanical striking tools, Chipping hammers, grinding
wheels or rotating steel wire brushes. Excessive burnish of surface shall be avoided as it can
reduce paint adhesion. On completion of cleaning, the detached rust mill scale etc. shall be
removed by clean rags and / or washed by water or stream and thoroughly dried with compressed
air jet before application of paint.
Manual or hand tool cleaning is used only where safety problems limit the application of other
surface preparation procedure and there is approach problem in certain areas and hence does
not appear in the tables of paint systems.
Rust, mill scale spatters, old coatings and other foreign matter, shall be removed by hammering,
scrapping tools, emery paper cleaning, wire brushing or combination of the above methods. On
completion of cleaning, loose material shall be removed from the surface by clean rags and the
surface shall be bushed, swept, dusted and blow off with compressed air/steam to remove all
loose matter. Finally the surface may be washed with water and dried for effective cleaning.
The compatibility of finishing coat should be confirmed from the paint manufacturer. In the event
of use of primer such as zinc rich epoxy, inorganic zinc silicate etc., as shop coat, the paint
system shall depend on condition of shop coat. If the shop coat is in satisfactory condition
showing no major defect, the shop coat shall not be removed. However a non-compatible primer
shall have to be removed before application of compatible paint system for the environment. The
touch up primer and finishing coat(s) shall be identified for application by Engineer-in-Charge.
5.4 Shop coated (coated with primer & finishing coat) equipment should not be repainted unless paint
is damaged.
5.5 Shop primed equipment and surfaces will only be ‘spot cleaned’ in damaged areas by means of
power tool brush cleaning or hand tool cleaning and then spot primed before applying one coat of
field primer unless otherwise specified. If shop primer is not compatible with field primer then
shop-coated primer should be completely removed before application of selected paint system for
particular environment.
5.6 For Package units / equipment, shop primer should be as per the paint system given in this
specification. However, manufacturer’s standard can be followed after review.
5.7.1 Surface shall not be coated in rain, wind or in environment where injurious airborne elements
0
exists, when the steel surface temperature is less than 5 F above dew point when the relative
0
humidity is greater than 85% or when the temperature is below 40 F.
5.7.2 Blast cleaned surface shall be coated with one complete application of primer as soon as
practicable but in no case later than 4 hrs. the same day.
5.7.3 To the maximum extent practicable, each coat of material shall be applied as a continuous film
uniform thickness free of probes. Any spots or areas missed in application shall be recoated and
permitted to dry before the next coat is applied. Applied paint should have the desired wet film
thickness.
5.7.4 Each coat shall be in proper state of cure or dryness before the application of succeeding coat.
Material shall be considered dry for recoating when an additional coat can be applied without the
development of any detrimental film irregularities, such as lifting or loss of adhesion of the under
coat. Manufacturer instruction shall be followed for inter-coat interval.
5.7.5 When the successive coat of the same color have been specified, alternate coat shall be tinted,
when practical, sufficiently to produce enough contrast to indicate complete coverage of the
surface. The tinting material shall be compatible with the material and not detrimental to its
service life.
5.7.6 Deleted 1
5.7.7 Airless spray application shall be in accordance with the following procedure : as per steel
structure paint Manual Vol. 1 & Vol. 2 by SSPC, USA. Air less spray relies on hydraulic pressure
rather than air atomization to produce the desired spray. An air compressor or electric motor is
used to operate a pump to produce pressures of 1000 to 6000 psi, paint is delivered to the spray
gun at this pressure through a single hose within the gun, a single paint stream is divided into
separate streams, which are forced through a small orifice resulting in atomization of paint without
the use of air. This results in more rapid coverage with less over spray. Airless spray usually is
faster, cleaner, more economical and easier to use than conventional air spray.
Airless spray equipment is mounted on wheels, and paint is aspirated in a hose that sucks paint
from any container, including drums. The unit shall have inbuilt agitator that keep the paint
uniformly mixed during the spraying. The unit shall consist of inbuilt strainer. Usually very small
quantity of thinning is required before spray. In case of high build epoxy coating (two pack), 30:1
pump ratio and 0.020-0.023” tip size will provide a good spray pattern. Ideally fluid hoses should
not be less than 3/8” ID and not longer than 50 ft. to obtain optimum results.
a. Brushes shall be of a style and quality that will enable proper application of paint.
b. Round or oval brushes are most suitable for rivets, bolts, irregular surface and rough or pitted
steel. Wide flat brushes are suitable for large flat areas, but they shall not have width over
five inches.
5.7.9 Manual application by sling (where 6 o’ clock position of pipe is not approachable)
A canvas strip (alternatively a tinplate strip) about 450mm wide and 1.5m long is held under the
pipe by two men holding this sling move it up and down and walk slowly forward while fresh
coating is poured on the pipe and they manipulate the sling so that an even coating is obtained all
round the bottom. This work shall be done very carefully and by experienced personnel. There
shall not be any formation of “Whiskers” and holes in the coating. The coating film shall be
inspected by mirror.
5.7.10 For each coat the painter should know the WFT corresponding to the specified DFT and
standardize the paint application technique to achieve the desired WFT. This has to be ensured
in the qualification trial.
5.8.1 No coat shall be applied until the preceding coat has dried. The material shall be considered dry
for re-coating when another coat can be applied without the development of any film irregularities
such as lifting or loss of adhesion of undercoats. Drying time of the applied coat should not
exceed maximum specified for it as a first coat; if it exceeds the paint material has possibly
deteriorated or mixing is faulty.
5.8.2 No paint shall be force dried under conditions which will cause checking, wrinkling, blistering
formation of pores, or detrimentally affect the conditions of the paint.
5.8.3 No drier shall be added to paint on the job unless specifically called for in the manufacturer’s
specification for the paint.
5.8.4 Paint shall be protected from rain, condensation, contamination, snow and freezing until dry to
the fullest extent practicable.
5.9 Repair of damaged paint surface
5.9.1 Where paint has been damaged in handling and in transportation, the repair of damaged coating
of pre-erection / fabrication shall be as given below.
5.9.2 Repair of damaged inorganic zinc silicate primer after erection / welding.
Quickly remove the primer from damaged area by mechanical scrapping and emery paper to
expose the white metal. Blast clean the surface if possible. Feather the primer over the intact
adjacent surface surrounding the damaged area by emery paper.
0 0
5.9.3 Repair of damaged pre-erection and shop priming in the design temperature of –90 C to 400 C
• One coat of F-9 shall be applied wherever damage was observed on pre-erection / pre-
fabrication / shop primer of inorganic zinc silicate coating (F-9).
5.10.1 Shop priming / pre-erection priming with F9 or F12 shall be done only on blasted surface.
5.10.2 Shop priming / pre-erection priming with F9 shall be done only with airless spray.
5.10.3 For large flat surface field painting shall be done by airless spray otherwise brush can be used.
5.11 Documentation
5.11.1 A written quality plan with procedure for qualification trials and for the actual work.
5.11.2 Daily progress report with details of weather conditions, particular of applications, no. of coats
and type of materials applied, anomalies, progress of work versus program.
5.11.3 Results of measurement of temperatures relative humidity, surface profile, film thickness, holiday
detection, adhesion tests with signature of appropriate authority.
5.11.4 Particulars of surface preparation and paint application during trials and during the work.
Paint manufacturers shall furnish the characteristics of all paints materials on printed literature
along with the test certificate for all specified characteristics given in this specification. All the paint
materials shall be on first quality and conform to the following general characteristics. As per the
tables 6.1, 6.2 and 6.3.
Sr.
Description P-2 P-4 P-6
No.
2. Type and Single pack, air drying Two pack Two component polyamide
composition chlorinated rubber based polyvinyl butyral cured epoxy resin medium-
medium plasticised with resin medium pigmented with zinc
unsaponifiable plasticizer, cured with phosphate.
pigmented with zinc phosphoric acid
phosphate solution
pigmented with
zinc tetroxy
chromate
2. Type and Two-pack Single pack Two pack Two pack polyamide
composition aliphatic plasticized polyamine (F- cured epoxy resin
isocynate cured chlorinated rubber 6A) / polyamide blended with coaltar
acrylic finish based medium (F-6B) cured medium, suitably
paint with chemical and epoxy resin pigmented.
weather resistant medium suitably
pigments pigmented
9. Over coating Min : Overnight Min : Overnight Min : Overnight Min. : 24 hrs.
interval (12 hrs.) Max. : Unlimited Max : 5 days Max. : 5 days
(approx.) Max. : Unlimited
10. Pot life 6-8 hrs. Not applicable 4-6 hrs. 4-6 hrs.
(approx) at
0
30 C for two
component
paints (approx.)
1. Technical Name Self priming type Inorganic zinc Heat resistant Heat resistant silicone
surface tolerant silicate coating synthetic medium aluminum paint suitable
0 0
high build epoxy based on two pack upto 500 C / 550 C dry
coating (complete Aluminum paint temp.
rust control suitable upto
0
coating) 250 C dry temp.
2. Type and Two-pack epoxy A two pack air Heat resistant Single pack silicone resin
composition resin based drying self curing synthetic medium based medium with
suitable solvent based based two pack Aluminum flakes.
pigmented and inorganic zinc Aluminum paint
capable of silicate coating suitable upto
0
adhering to 250 C
manually
prepared surface
and old coating.
9. Over coating interval Min : 10 hrs Min : 8 hrs at Min : 16 hrs Min. : 16 hrs
0
(approx.) Max. : 6 months 20 C & 50% RH Max : Unlimited Max. : Unlimited
Max. : Unlimited
10. Pot life (approx) at 90 min 4-6 hrs Not applicable Not applicable
0
30 C for two
component paints
(approx.)
0 0
11. Temperature - - 250 C 500 C
Resistance
2 Type and Specially formulated Two pack ambient Amercoat 738 from Ameron
composition polyamine cured temperature curing Products, USA/ Berger 938 from
coal tar epoxy epoxy phenolic coating Berger Paints Ltd., Kolkata or
suitable for suitable for application Intertherm 751 CSA from Akzo
application under under insulation Nobel coating, Bangalore.
insulation
0 0
F-14 Specially formulated polyamide cured Coal-tar epoxy suitable for –45 C to 125 C for application
under insulation.
0 0
F-15 Two pack ambient temperature curing epoxy phenolic coating suitable for –45 C to 125 C for
application under insulation.
F-16A Engineered polysiloxane coating : Amercoat 738 from Ameron Products, USA
F-16B Engineered poly siloxane coating : Berger 938 from Berger Paints Ltd., Kolkatta
NOTES
1 Covering capacity and DFT depends on method of application. Covering capacity specified above
are theoretical. Allowing the losses during application, min. specified DFT should be maintained.
2. All primers and finish coats should be ambient temperature curing and air drying unless otherwise
specified.
3. All paints shall be applied in accordance with manufacturer’s instructions for surface preparation,
intervals, curing and application. The surface preparation, quality and workmanship should be
ensured.
4. Technical data sheets for all paints shall be supplied at the time of submission of quotations.
The paints shall conform to the specifications given above and best quality in their products range of
manufacturers listed in Annexure-I.
The paint system should vary with type of environment envisaged in and around the plants. Three
types of environment as given below are considered for selection of paint system. The paint system
is also given for specific requirements.
PRIMERS
F-6A : High build epoxy finish coating cured with polyamine hardner
F-6B : High Build epoxy finish coating cured with polyamide hardner
7.1.2 401 to 500 SSPC-SP-10 1 coat of F-12 40-50 Finish coat at site
TABLE 7.3 : REPAIR OF ALL WELD JOINTS AND DAMAGES FOR STRUCTURES, PIPING
AND EQUIPMENT AFTER ERECTION ON ABOVE GROUND OVERHEAD AREAS
AT SITE
Materials : GALVANIZED STEEL, CARBON STEEL AND ALLOY STEEL
TYPE : UNINSULATED AND INSULATED
NOTE 1 : For external surfaces of MS chimney with or without refractory lining 8.3, 8.4 and 8.5 shall
be followed.
NOTE 2 : For external surfaces of RCC chimney: 2 coats of F-6B @ 100µ DFT/Coat to obtain
2x100=200 µ DFT shall be applied after making surface preparation as per guidelines in
5.1.5. The DFT on concrete surfaces can be checked by Tool Gauge or by applying the
same coating system simultaneously on a carbon steel panel of 12"x12" size and measure
the DFT by normal Magnetic gauges/digital electronic gauges for ferrous surfaces.
NOTE 3 : Wherever required S.No.8.3 shall be used for -14°C to 80°C and S.No.8.2 will be deleted.
TABLE 9 : FIELD PAINT SYSTEM FOR HIGHLY CORROSIVE AREAS IN PLANT AREA
EXTERNAL SURFACES OF UNINSULATED COLUMNS, VESSELS, HEAT
EXCHANGERS, BLOWERS, PIPING, PUMPS, TOWERS, COMPRESSORS,
STRUCTURAL STEEL ETC.
Materials : CARBON STEEL, LOW TEMPERATURE CARBON STEEL & LOW ALLOY STEEL
Surface : Un-insulated
Note : Exposed to spillage or fumes of HCL, H2SO4, salty water, water impingement,
chloride etc
Sl. Design Surface Paint System Total DFT Remarks
No. Temperature Preparation In
in°C Microns
(min.)
Field Primer Finish Paint
10.1 -90 to -15 SSPC-SP-10 Repair of pre- None 65-75 Repair procedure of
fabrication primer pre-erection/fabri
1c o at of F- 9 @ cation primer shall be
65-75u DFT/coat followed. No
overcoating is
allowed.
Surface preparation is
required only for
repairing of damaged
pre-erection/
fabrication primer.
TABLE 10 : PAINTING UNDER INSULATION FOR INSULATED (HOT, COLD & SAFETY) PIPING,
STORAGE TANKS AND EQUIPMENTS IN ALL ENVIRONMENT
Materials : CARBON STEEL, LOW ALLOY STEEL, LOW TEMPERATURE CARBON STEEL &
STAINLESS STEEL
Surface : Insulated
Paint System
Sr. Design Surface Field Primer Finish paint Total Remarks
No. Temperatur Preparation DFT in
0
e in C Microns
(min.)
9.1 Insulated carbon steel, low alloy steel and LTCS piping and equipment and tanks
9.2.1 Below 00C Aluminium sheeting with aluminium foil and “Chloride free mineral If the piping &
to all minus sealant coating barium chromate” shall be applied. equipments are already
temperature erected then surface
shall be prepared by
cleaning with emery
9.2.2 0 to 120 SSPC-SP-10 None 2 coats of F-14 @ 250 or
paper and wash / flush
(15-25µ surface 125 µ DFT / coat 240
with chloride free DM
profile) = 2x125 = 250 or 3
water followed by wiping
coats of F-15 =
with organic solvent.
3x80=240
All the coating materials
9.2.3 121 to 400 SSPC-SP-10 None 3 coats of F-12 60 for SS shall be free from
@20µ DFT /Coat = leachable chlorides.
3x20=60 or 1 coat
of Poly siloxane or
coating (F-16 A/B)
@ 75 microns
DFT/coat
TABLE 12.0 COATING SYSTEM FOR EXTERNAL SIDE OF UNDERGROUND CARBON STEEL
PLANT PIPING AND TANKS
12.2.2 221 to 400 SSPC-SP-10 1CoatofF-16@ 75 1 Coat of F- 175 Cold and hot insulation
µ DFT/coat 16@ 100µ shall be provided
DFT/coat
Note: No Coating and Wrapping systems are available for underground high temperature services
TABLE 13.0 PAINTING UNDER INSULATION FOR INSULATED (HOT, COLD & SAFETY) CARBON
STEEL, LOW ALLOY STEEL, LOW TEMPERTURE CARBON STEEL & STAINLESS STEEL
PIPING, STORAGE TANKS AND EQUIPMENTS IN ALL ENVIRONMENT.
13.1 Insulated carbon steel, low alloy steel and LTCS piping and equipment & tanks
13.1.1 -45 to 125 SSPC-SP-10 Repair of 2 coats of F- 315 For other temperature ranges no
pre- 14 @125 µ painting is required under
fabricatio DFT/coat = insulation F-12 shall be ambient
n primer 2x125=250 temperature curing type till
F-9 @ 65- OR 3 coats of operating temperature is attained
75 µ DFT. F-15= for full curing. F-16 is completely
3x80=240 ambient temperature curing.
13.1.2 Operating SSPC-SP-10 Repair of 2 Coats of 125-135
temperature pre- F-12 @20 µ
-45 to 125°C fabricatio DFT/coat
but design n primer 3x20=60 (or)
temperature F-9 one coat of
126-400°C @65-75 µ Poly-siloxane
DFT coating @ 75
µ DFT/coat
13.3 No painting is required for insulated Monel, Incoloy and Nickel lines.
TABLE 14.0 INTERNAL PROTECTION OF CARBON STEEL WATER BOXES AND TUBE SHEETS OF
COOLERS / CONDENSERS
Water boxes, channels, partition plates, end covers and tube sheets etc.
15.1 Upto 80 SSPS-SP-3 1 coat of P-4 @ 2 coats of F-2 130 Shade as per
8-10 µ DFT/coat @40 µ defence
+ 1 coat of P-6 @ DFT/coat Requirements.
40u DFT/coat 2x40=80
TABLE 16.0 SHOP & FIELD PAINTING SYSTEM FOR EFFLUENT TREATMENT PLANT
17.0 STORAGE
1 All paints and painting materials shall be stored only in rooms to be arranged by
contractor and approved by Engineer-in-charge for the purpose. All necessary precautions
shall be taken to prevent fire. The storage building shall preferably be separate from adjacent
building. A signboard bearing the word "PAINT STORAGE - NO NAKED LIGHT - HIGHLY
INFLAMABLE" shall be clearly displayed outside.
20.1 Following items shall be painted for camouflaging if required by the client.
a. All columns
b. All tanks in off sites
c. Large Vessels
d. Spheres
20.2 Two coats of selected finishing paint as per defence requirement shall be applied in a
particular pattern as per 20.3 and as per the instructions of Engineer-In-Charge.
20.3.1 Disruptive painting for camouflaging shall be done in three colors in the ratio
of
5:3:2 (all matt finish).
21.1 All painting materials including primers and thinners brought to site by contractor for
application shall be procured directly from manufactures as per specifications and
shall be accompanied by manufacturer's test certificates. Paint formulations without
certificates are not acceptable.
21.2 Engineer-In-Charge at his discretion may call for tests for paint formulations. Contractor
shall arrange to have such tests performed including batch-wise test of wet paints for
physical & chemical analysis. All costs there shall be borne by the contractor.
21.3 The painting work shall be subject to inspection by Engineer-In-Charge at all times. In
particular, following stage-wise inspection will be performed and contractor shall offer the
work for inspection and approval of every stage before proceeding with the next stage. The
record of inspection shall be maintained in the registers. Stages of inspection are as
follows:
In addition to above, record should include type of shop primer already applied on equipment
e.g. Red oxide zinc chromate or zinc chromate or Red lead primer etc.
Any defect noticed during the various stages of inspection shall be rectified by the contractor
to the entire satisfaction of Engineer-In-Charge before proceeding further. Irrespective of the
inspection, repair and approval at intermediate stages of work, contractor shall be
responsible for making good any defects found during final inspection/guarantee
period/defect liability period as defined in general condition of contract. Dry film thickness (D
F T)) shall be checked and recorded after application of each coat and extra coat of paint
should be applied to make-up the DFT specified without any extra cost to owner, the extra
cost should have prior approval of Engineer-in-charge.
After surface preparation, the primer should be applied to cover the crevices, corners, sharp
edges etc. in the presence of inspector nominated by Engineer-In-Charge.
21.4.1 The shades of successive coats should be slightly different in color in order to ensure
application of individual coats, the thickness of each coat and complete coverage should
be checked as per provision of this specification. This should be approved by
Engineer-In-Charge before application of successive coats.
21.4.2 The contractor shall provide standard thickness measurement instrument with appropriate
range(s) for measuring.
Dry film thickness of each coat, surface profile gauge for checking of surface profile in case
of sand blasting. Holiday detectors and pinhole detector and protector whenever required
for checking in case of immersion conditions.
21.4.2 Prior to application of paints on surfaces of chimneys, the thickness of the individual coat
shall be checked by application of each coat of same paint on M.S.test panel. The
thickness of paint on test panels shall be determined by using gauge such as
'Elkometer'. The thickness of each coat shall be checked as per provision of this
specification. This shall be approved by Engineer-In-Charge before application of paints on
surface of chimney.
21.4.3 At the discretion of Engineer-In-Charge, the paint manufacturer must provide the expert
technical service at site as and when required. This service should be free of cost and
without any obligation to the owner, as it would be in the interest of the manufacturer to
ensure that both surface preparation and application are carried out as per their
recommendations.
21.4.4 Final inspection shall include measurement of paint dry film thickness, Adhesion, Holiday
detection check of finish and workmanship. The thickness should be measured at as
many points/ locations as decided by Engineer-In-Charge and shall be within + 10% of the
dry film thickness, specified in the specifications.
21.4.5 The contractor shall arrange for spot checking of paint materials for Sp.gr., glow time (ford
cup) and spreading rate.
22.0 GUARANTEE
22.1 The contractor shall guarantee that the chemical and physical properties of paint
materials used are in accordance with the specifications contained herein/to be
provided during execution of work.
22.2 The contractor shall produce test reports from manufacturer regarding the quality of the
particular batch of paint supplied. The Engineer-in-Charge shall have the right to test wet
samples of paint at random for quality of same, as per the paint materials specification.
Batch test reports of the manufacturer's for each batch of paints supplied shall be
made available by the contractor. The contractor shall stand guarantee for carrying
out the rectification/repair/re-painting of the defects/ failures of painting found during the
execution of painting job and till the expiry of the defect liability period of total project as
per the directions of the Engineer-in-Charge of CPCL/JE
Painting contractor who is awarded the job under this standard must have necessary
equipments, machinery, tools and tackles for surface preparation, paint application and
inspection. The contractor mush have qualified, trained and experienced surface
preparator, paint applicator, inspector and supervisors. The contractor's supervisor,
inspector, surface preparator and paint applicator must be conversant with the
standards referred in this specification. The painting job shall be carried out by the approved
agencies of paint manufacturers and supervised by the approved paint manufacturers own
representative or paint manufacturer their scheme( supply and apply basis).
ANNEXURE-I
Indian Vendors
Foreign Vendors
The following are approved vendors for speciality items (phosphating chemical) only.
Annexure-II
Paint Color Code for Piping & Equipment given by CPCL Document No. 00-ES-100-004, Rev. 5
dated 24/12/2006 to Specification No.6782-0642-PT-L06 Rev.2
This section of the standard deals with the color coding to he given to in service piping for easy
identification bused on the liqui d contained in the line.
1. Where ever paint is required for piping external surfaces, the finish coat color shall be as follows
except for paragraph 2, Type of paint, surface preparation. DFT etc. shall he as per the
painting specification.
Insulated and austenitic stainless steel lines will he having only color coding for fluid
discrimination as given in 3 below.
2. Fire water lines shall he painted " Red '" as per IS 536 through out the line.
3. All lines, in general, shall he provided with discrimination color coding mark over the final coat or
on the cladding / jacketing surface of insulated piping as mentioned in 1 above . as
well as on the surfaces on which any paint is not provided. The color coding shall be as per the
attachment to this standard and in the following manner. Color codes on Austenitic SS lines should
he done only wit chloride free paint suitable for application on stainless steel surfaces.
As far as possible, paint used for color bands should he of the same specification as the finish
coat. If for some reason a deviation is required for this, then enamel paint can be used over finish
coat after taking approval from the ‘engineer In - Charge'
3.1 The system of color coding shall consist o f a primary identification color band and other color
hand (s) superimposed on the primary band. All the bands shall be painted circumferential!;
around the line.
The primary color hand identifies the basic nature of the fluid carried in the line. The second and
the third color hands will identify the exact fluid carried in the line. The various primary color
bands included in t h i s standard are explained below:
3.2.1 Primary colorblind / color band ( s ) (see Fig I) arc required to be located at
3.2.2 Primary color band shall he intermittently coated along respective lines with primary color
bands of 2V1 length with the following maximum center to center distance between two
adjacent color bands.
Center to center distances at lesser intervals may be given. if" so desired by unit head.
3 AIR
Plant Air Sky Blue Silver Grey
Instrument Air Sky Blue French Blue
Process air ( ex: bitumen, Sky Blue Signal Red
Mereox)
5 AC IDS
6 LIQUID HYDROCARBONS
Notes : 1) Wherever Dark Admiralty Grey is not available due to the nature of the final coat of
paint ( eg: Coal Tar epoxy in high H2S environments ) . Black can be used.
2) Canary Yellow for ladders etc. has been selected for visibility.
1. Equipment number shall be stenciled in black (after initial painting if any) on each vessel,
column, equipment, machinery till a visible location as directed by the "Engineer - in -
charge "'
Rotating equipment shall have tin arrow showing the direction of rotation painted on the
equipment.
Additional stenciling of line numbers and service will be required and shall be provided on
the lines at the direction of “Engineer- In - Charge"
80- 150 mm 40 mm
150-250 mm 60 mm
> 250 mm 90 mm
Auxiliary piping in packaged units or on base plates of pumps / compressors wilh in the
scope of vendors do not need numbering at site.
• Tank number
• Reference height
• Stile filling height
• Critical /one ( in ease of floating roof tanks only )
• Dale of commissioning
• Date of last cleaning
4. The following details are to be painted on the tank shell near the top landing platform of the
staircase, in letter size 50 mm high, black color.
• Reference height
• Sale filling height
• Critical zone ( in case of floating roof tanks only )
5. The following details shall he painted on the kink at 2!3 the height of the tank at a
location facing the road, from where normal approach lo the Tank is provided. In addition,
the same details shall be provided on two additional points in the lank 120 degrees apart.
Tank number
• Capacity
• Service.
The size of the above lettering shall be 500 mm for 20 M high tanks and 300 mm for
smaller tanks.
DGCA requirements for a l l shall be followed in addition to the above.
1.0 The part of the standard covers the method of identification of STORED piping material by
color coding. This standard is applicable to storage during project Stage as well.
2.0 General guide lines of identification by color coding:
a) Piping shall be painted with one color or a combination of two color as
enclosed.
b) Color identification is not required on galvanized material and mm ferrous
material such as Copper. Aluminum etc. because of their peculiar color and
character
e) Special items l i k e bellow, strainers, steam Imps etc. should be lagged and hence do
mil require color identification.
d) Color identification of Austenitic Stainless Steel is not desirable due to r i s k
of contamination from paint material.
e) Ends of piping to be welded shall not be painted. The color band shall start
2" from the pipe ends.
f) Width of color strips shall be 25 mm for .V nominal pipe dia and above. Secondary
color strip where required, shall be half the size of primary strips. For less than 3" size
color strip shall be 12 mm < 1/2") or maximum practical.
Carbon Steels
Alloy Steels
P1, F1. WP1, WP1W etc. Green / Red
P12, F12, W12 etc Green / Yellow
P22, F22, WP22. etc Green / Silver
P11, F11, WP11 etc. Green / Orange
P5, F5, WP5 etc. Green / Blue
P9, F9, WR9 etc. Green / Pink
Note : Following modification has been made from the original ITP attached with
Bid Document.
1. In activity :scope of Inspection LSTK contractor has been deleted
2. Activity 4: Shipping drawings of completed equipments has been deleted
3. Activity 5: Summary of all supplementary requirements as specified in the
order/PS/PR deleted
4. Activity 17: Root run DP has been modified as R for TPI
5. Activity 18: DP check after back gouging of weld joints has been modified as R
for TPI
6. Activity 19 : Air test of RF pad has been modified as R for TPI
7. Activity 20 : NDT clearance and RT film review has been modified as H and
balance as R for TPI
8. Activity 22 : PWHT chart review has been modified as R for TPI
9. Activity 24: Hardness check of base metal, weld and HAZ after PWHT been
modified as R for TPI
10. Activity 25 : Visual/dimensional inspection before Hydrotest has been modified as
H/W for TPI , H if not checked before, W if checked before PWHT.
11. Activity 28:Surface preparation painting /pickling etc has been modified as R for
TPI
12. Activity 30 : Spare parts and packing list check have been modified as W for TPI
13. Activities in respect of QAP / ITP and IRN /IC for categories will be as below:
For PMC category A : QAP/ITP approval by EPC , TPIA & PMC.
IRN/IC issued by TPIA and to be endorsed by PMC