TIME SHEET

COMMISSIONING/TESTING/AMC OF ELECTRIC LOCO TESTING SHED AT ELECTRIC LOCO SHED


(ANGUL) FROM 01/03/2020 TO 20/03/2020 THE DETAILS ARE AS FOLLOWS

Engineer: SACHINDEV MOHAPATRA ZIGMA TECHNOLOGIES (BANGALORE)


SL LOCO DATE OF TIME TIME DAYS EXPLANATION
NO. NO. VISIT IN OUT OF
VISIT

01 -- 01.03.20 -- -- -- SUNDAY

02 28183 02.03.20 8.30 20.00 1 L/ 28183 came to shed for IB inspection ,


data downloaded and no abnormality found.
Mounting bolt tightness checked , blowing
the SIV and cleaning the SIV.

03 28183 03.03.20 19.00 1 L/28183 schedule work done. Under shed


8.30 observation.

04 -- 04.03.20 8.00 17.00 1 Going to shed , meet PPIO section , no loco


at shed.

05 -- 05.03.20 8.30 19.30 1 Going to shed , meet PPIO section , no loco


at shed.

06 -- 06.03.20 8.00 19.30 1 Going to shed , meet PPIO section , no loco


at shed.

Discussed with work section SSE about 5th


quarter joint note and edit the necessary
note.

07 28297 07.03.20 8.00 21.00 1 L/ 28297 came to shed for IC inspection ,


data downloaded and no abnormality found.
Mounting bolt tightness checked , blowing
the SIV and cleaning the SIV.

08 -- 08.03.20 -- -- -- SUNDAY.

09 28297 09.03.20 8.00 20.00 1 L/28297 under shed observation, no loco for
schedule.

10 -- 10.03.20 8.15 16.00 1 Going to shed , meet PPIO section , no loco


at shed.

11 -- 11.03.20 8.15 18.00 1 Going to shed , meet PPIO section , no loco


at shed.

Joint note prepared of 28183 and 28297.

12 -- 12.03.20 8.00 17.30 1 Going to shed , meet PPIO section , no loco


at shed.

13 -- 13.03.20 7.00 18.00 1 Going to shed , meet PPIO section , no loco


TIME SHEET
COMMISSIONING/TESTING/AMC OF ELECTRIC LOCO TESTING SHED AT ELECTRIC LOCO SHED
(ANGUL) FROM 01/03/2020 TO 20/03/2020 THE DETAILS ARE AS FOLLOWS

Engineer: SACHINDEV MOHAPATRA ZIGMA TECHNOLOGIES (BANGALORE)


at shed.

14 27811 14.03.20 8.00 19.30 1 L/ 27811 came to shed for IB inspection ,


data downloaded and no abnormality found.
Mounting bolt tightness checked , blowing
the SIV and cleaning the SIV.

15 -- 15.03.20 -- -- -- SUNDAY.

16 28242 16.03.20 8.00 18.30 1 L/28242 under shed observation and waiting
for IB schedule.

17 28242 17.03.20 8.00 18.00 1 L/ 27811 came to shed for IB inspection ,


data downloaded and no abnormality found.
Mounting bolt tightness checked , blowing
the SIV and cleaning the SIV.

18 -- 18.03.20 8.45 18.30 1 Going to shed , meet PPIO section , no loco


at shed.

19 -- 19.03.20 8.30 18.00 1 Going to shed , meet PPIO section , no loco


at shed.

20 -- 20.03.20 8.30 18.00 1 Going to shed , meet PPIO section , no loco


at shed.

No of days visit - 17

No of days working – 17