Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Equipment Title:
Tag Nos.:
Equipment Title:
Tag Nos.:
37AF-00016_R00 A15_Siemens cover sheet Any print of this document is an uncontrolled copy.
TABLE OF CONTENTS
1. PURPOSE .............................................................................................................................................. 4
2. SCOPE ................................................................................................................................................... 4
3. REFERENCE ......................................................................................................................................... 4
4. ABBREVIATIONS/DEFINATIONS ..................................................................................................... 4
5. RESPONSIBILITIES ............................................................................................................................. 5
6. PLANT AND EQUIPMENT.................................................................................................................. 5
7. PROCEDURE ........................................................................................................................................ 6
7.1 INSTALLATION METHOD FOR HYDRANT SYSTEM .............................................................. 6
7.1.1 PREPARATION OF WORKS ....................................................................................................... 6
7.2 INSTALLATION OF UNDER GROUND PIPES ........................................................................... 6
7.3 INSTALLATION OF ABOVE GROUND PIPES............................................................................ 7
7.4 PRESSURE TEST: ........................................................................................................................... 7
7.5 DEPRESSURIZING ........................................................................................................................ 8
7.6 PRESSURE GAUGES ..................................................................................................................... 9
7.7 ACCEPTANCE CRITERIA ............................................................................................................. 9
7.8 FLUSHING OF THE PIPE WORKS ............................................................................................... 9
7.9 UNDERGROUND PIPE WRAPPING AND COATING ................................................................ 9
7.10 INSTALLATION OF VALVES, HYDRANTS AND ACCESSORIES ......................................... 9
8. PROJECT CONTROL ......................................................................................................................... 10
8.1QUALITY CONTROL ................................................................................................................... 10
8.2 HSE ................................................................................................................................................ 10
8.3 WORKING HOURS ...................................................................................................................... 10
8.4 EMERGENCY PROCEDURE & CONTACT NUMBERS ........................................................... 10
9. ATTACHMENT ................................................................................................................................... 10
GLOSSARY OF TERMS
GA General Arrangement drawings
CEMP Construction Environmental Management Plan
COP Code of Practices
DUBAL Dubai Aluminium
EGA Emirates Global Aluminium
TRA Task Risk Assessment
RA Receiving authority
IA Issuing Authority
HSE Health safety and environment
TBT Tool Box talks.
QA/QC Quality assurance/Quality control
FQP Field Quality Plan
1. PURPOSE
To specify the method for installing and commissioning of Hydrant System which include the
installation of Fire Water Network piping in underground and above ground with Isolation
valves, Hydrants, Tie in point for different Fire protection system for H-Class combined power
plants in compliance to the requirements of the EGA project specification and relevant NFPA
standards/FM Standards.
2. SCOPE
This method statement applies to Installation of Fire Water Network (Hydrant) System by
Carbon Steel Pipes and fittings for H- Class Combined Cycle Power Plant at Dubai Aluminum
as per EGA project specification and relevant NFPA standards/FM Standards.
3. REFERENCE
IFC drawings
Safety booklet (EGA Green Book)
Dubai Code of Construction Safety Practices
NFPA Standards
FM Global Standards
EGA Standards
local UAE and Dubai regulations
Project technical specification
Approved FQP
Project EHS Manual and Site Instructions
MP7S/MEC/011/ JAS101-TK4004P-A15-6033
4. ABBREVIATIONS/DEFINATIONS
The Project Manager is in charge of the competent and timely execution of all Tyco
projects in UAE. He is coordinating the works with the Site Managers/Engineer in charge
and is advising on technical and contractual matters.
The Construction Manager is responsible for compliance/implementation of the EHS
requirements, monitoring and implementation of scope of work as related to construction
and accordance with approved project schedule.
The Site Engineer personnel on site are directly responsible for the
compliance/implementation of the EHS requirements and controlling the activities of the
skilled employees. They play an effective role in the implementation of the Safety
Program as they have direct contact with the workers. They plan safety activity with the
same care and effort as they do in their other work Programs i.e. production and quality.
The Site Manager is reporting directly to the Construction Manager. He will have the
overall responsibility for the compliance/implementation of the EHS requirements,
competent and timely execution and monitoring of the Ground Improvement Works. He is
representing the company in meetings with the client. His responsibilities are further to
supervise sub-contractor(s) and suppliers, to ensure that the works are being installed in
a safe and proper manner and to coordinate and delegate works through the authorities
falling under him.
The Site Supervisor/ foreman shall report to the Site Manager. He shall organize the daily
works, assign the required manpower and report on the equipment status to his line
manager. Further it is his responsibility to compliance/implementation of the EHS
requirements stock and spot-check on all delivered materials, to monitor the proper use
of plant and equipment and to record the progress in the Daily Production Reports.
The Surveyor shall perform duties related to land surveying for identifying land ownership
and property boundaries Conduct standard calculations to identify areas, elevation and
volumes of field survey notes. Provide consistent and superior quality documents for
survey, design and building projects for all clients in region.
The HSE Manager/Officer will be responsible to ensure and monitor the compliance of
the site EHS requirements of all Tyco and its subcontractors with the project safety
regulations and the company’s safety policy. The Safety Officer can report directly to the
Construction Manager/ Project Manager and will be independent of other site activities.
The QA/QC manager shall oversee all activities, to ensure all activities are executed as
per QA/QC Plan and Project specifications.
The QA/QC Engineer reports to the Quality manager. He is supervising and coordinating
the QA/QC activities on site and assists the quality manager in analyzing the test results.
The Workers will be responsible to maintain the work places, maintain provided plant and
systems, following instructions, attending mandatory trainings and work safely as per the
site requirements.
Flagman is responsible for control working equipment, pedestrians and forewarns drivers
of up-coming works.
Crane and any other lifting equipment with third party certification as approved of EGA. All
crane operators shall possess valid third-party certification and a Green Card issued by EGA
EHS after assessing the competence of the operator for a particular crane.
Welding Machine
Diesel Welding Generator
Diesel Power Generator
Gas cutting set as required
Mobile Crane
Boom Truck as required
Trailer
Air Compressors
Measuring tape
Power tools
Electric Drill Machine
Mobile Scaffold, Lifting tools-belts, chains, chain blocks, shackle, hydraulic jacks, ropes
etc.
Hand Tools
Grooving equipment
Grinding Machine
Surveying Equipment
Pressure relief valve
Static hydro pump
Calibrated pressure gauges
Certified Manifold
Isolation valve
Pipe threading machine
Scaffolding Materials.
7. PROCEDURE
Before commencing the installation of the Main Fire Water Network (Hydrant) system the
following shall be carried out
On receipt of pipes & fittings, storage shall be arranged at site as per manufacturer’s
recommendations so as to prevent any physical damage to the material.
Check approved materials are available for installation.
Check all the drawings are approved by client to start installation activities.
Ensure necessary work permit is obtained for commencement of work.
TBT to be conducted prior to start work
Ensure that work area is clean and safe for work with adequate lighting provided.
Ensure all site personnel have undergone EGA safety induction, SIEMENS/SEPCOIII
Site Specific Safety Induction.
Ensure that installation work is undertaken by trained and experienced personnel
Ensure work area is properly barricaded and demarcated.
Ensure proper re-routing plan of foot and vehicle traffic is in place and mitigated to all
concerns as and if required.
The 10”, 8” & 6” Carbon Steel pipes from the supplier will be delivered at the specified
area at site or at storage yard and shall be stacked in a safe way.
The pipes will be offloaded by fixing the suitable capacity lifting slings on the pipes
The pipes/pipe spools would be hauled to the work location by suitable sized truck
/trailer/pickups as needed and shall always be handled by means of mobile crane or
crane truck and trailers which are suitable for the specific pipe size being handled.
Pipe shall be cut in to the required spool length as per approved layout drawings for
fabrication.
Trench Excavation / pipe bed preparation / backfilling will be done by SEPCO as per the
approved drawing
Trench, concrete blocks, protection sleeves shall be provided as per approved
drawing/MSRA
Pipe shall be laid in the trench using crane on sand bags or wooden blocks with the soft
sheets on top for the fit-up, welding and Holiday test
Ensure Proper accesses to the trench and check the condition of Excavation.
Pipes shall be welded for required lengths as per approved welding procedure.
Welding Pits will be prepared for the joints inside the trench.
Once welding joints are visually accepted, 10% RT to be carried out as applicable as per
approved RT Procedure
Separate MSRA will be provided for RT
Internal cleanliness: do not allow foreign material and water to enter the pipe during
installation. At times when pipe laying is not in progress, close the open ends of pipe by
temporary cap.
Determine the position of the pedestal supports for the above ground pipe with an
elevation of 1mtr from ground level as per the approved network drawings. Pre-
Fabricated Pipes shall be laid on the pedestal supports and fixed using U-Bolts/approved
design.
Suitable scaffolding shall be provided for installation of pipes in pipe rack and high
elevation location
If the pipes are running through the existing structures/ concrete walls, determine the
position and fix supports using anchor bolts and ensure all fixings are tight and secure.Use
Proper scaffolding for activities at height.
Drill holes in the concrete/Structure using portable electric drilling machine ensuring
correct drill bit size is used.
Place pipes, in position, if required using lifting hoists / straps and chain blocks
Ensure appropriate Gaskets and bolts are used for assembling of the pipes.
After installation of the pipe works, check for correct levelling, position and alignment.
Internal cleanliness: do not allow foreign material and water to enter the pipe during
installation. At times when pipe laying is not in progress, close the open ends of pipe by
temporary cap.
All Above Ground Piping shall be welded Joints with Flanged ends and it shall be painted
in RED as per Project Specification (MP7S/MEC/011/ JAS101-TK4035P-A33-0001).
7.5 DEPRESSURIZING
As soon as possible after completion of the pressure test, the test medium shall be
completely drained from the system to the nearest Drain. Vents and other high point
connections in the piping system and connected equipment shall be opened prior to
commencement of draining. Particular care shall be taken with the venting of equipment
during draining to avoid damage resulting from the creation of excessive vacuum.
Before releasing hydro tested water, nearest drain pit/provision to be identified by
concerned in charge in coordination with contractor/client.
Proper PPE should be used prior to commence the depressurizing process and extra
safety measures to be followed for the ease operation.
On completion of hydro test, the pipes shall be completely drained and dried.
Isolation Valves should be kept close
7.6 PRESSURE GAUGES
On the system a minimum of two pressure gauges (1 No at the high point and 1 No at the
low point) shall be used for pressure testing so that it is readily visible to the operator
controlling the pressure.
Each pressure gauge shall have a serial or identification number permanently attached
along with a calibration due date sticker.
Pressure gauge used in testing shall have dials graduated over a range about double the
intended maximum test pressure, but in no case shall be less than 1 ½ times and not
more than 4 times of the test pressure.
All indicating pressure gauge shall be calibrated against a standard dead weight tester or
calibrated master gauge. The calibration of the pressure gauge shall be done by 3rd party
and the validity of the certificate should be within 12 months of the date of hydrostatic
test.
The pressure test is only acceptable when no leakage is observed and no deviation in the
test pressure other than that is caused due to temperature variation.
After pressure testing of the pipe works, the complete piping shall be flushed clean by
potable water.
Potable water should be used for flushing activity and quantity/ Length of pipe will be
based on loops selected for hydro test.
The water used for flushing will be discharged at the system drain point. The drain water
will be collected in barrels and disposed in designated location.
Underground pipe shall be wrapped with Serviwrap R30B materials -Tropical grade, black
in color and consisting of an extruded PVC backing bonded to a self-adhesive bituminous
rubber compound with a total thickness of approximately 1.65mm. It shall be supplied in
nominal 15m rolls for hand-wrapping.
Refer the attached Wrapping and Coating Materials Data sheet and application
guidelines.
Prior to backfilling, the wrapped pipes shall be holiday tested using an approved holiday
tester set at 5kV per mm of tape thickness to a maximum of 10Kv as per Manufacturing
Standard.
After completion of Holiday testing, pipes should be backfilled as per the drawing
Isolation Gate valve with post Indicators in Underground line and NRS Gate valve in
above ground line shall be installed as per the locations identified on the approved
drawings
Hydrants, Hose Box and Accessories shall be installed as per the locations identified on
the approved drawings.
8. PROJECT CONTROL
8.1QUALITY CONTROL
The QC Inspector shall inform the relevant Site Engineer as to the suitability of the
material. The QC inspector will ensure that all work is executed according to Project
Drawing & Specification.
All quality acceptances shall be performed and signed in accordance with the
corresponding FQP.
8.2 HSE
All personnel involved will use necessary PPE as required such as safety helmet, glasses,
shoes, gloves, ear plugs, dust mask etc.
The workers must go through the relevant special training before the corresponding
activities.
Material or equipment should be maintained in an orderly manner and labelled in
accordance with statutory requirements and use in safe manner.
The workers will be made aware of HSE requirements related to this activity through daily
toolbox talk.
All efforts shall be made to keep the Environment clean.
Crane and lifting tools should have valid certificate.
Daily pre-work checklist must be done by PTW receiver and supervisor.
All the works must meet the requirements of EGA green book.
All the crane operators must have the Green Card issued by EGA
All above ground pipes which is to be installed in high level should be installed only after
scaffolding works and scaffolds should have approval tags.
Working hours will be from 7.00Hrs to 19.00 Hrs. in general and will be intimated in
advance if there any changes of work timings. In case of emergency situation (Fire, spill,
etc.) until and unless occur in site clearance received from relevant authority from
DUBAL.
Night work shall be carried out as if there is any change in work plan, and required
arrangements for night work shall be carried out by applying permission from SIEMENS /
EGA engineering and from SIEMENS / EGA operations. Required lighting shall be
provided in the area of work.
As per UAE law mid-day break timing will be followed during summer time.
9. ATTACHMENT
TRA
Technical Data Sheet / Safety Data sheet for Wrapping and Coating Material
Application Guidelines for Wrapping and Coating Material
CAPITAL PROJECTS CONTRACTOR TASK RISK ASSESSMENT (TRA) FORM -
EGA.SAF.GEN.03.01.F04
6. TASK:
Area: EGA PLANT
Location: Fire Fighting System Main Ring
EGA SAFETY PROCEDURE · EGA.SAF.GEN.03.01.F04
Risk Residual
Category Initial Risk Accepted?
If ‘yes’ Risk
move to
Additional Control
People
Environment
Asset
Reputation
Likelihood
Severity
Total (L x S)
Likelihood
Severity
Total (L x S)
next
Sr. No Activity in sequence Hazard Risk Existing Control Measures activity if measures
‘no’
(Use Hierarchy of Controls)
continue
with
additional
controls
pass.
FIELD.
worn.
Damage equipment, damage All electric powered tools to be equipped with disconnected when not in
Damage hoses and body parts Use electric powered tool of 110V. Safety devices (Dead-man
cables injury Power supply to power hand tools must be centre switch/Latching) switch to be
Electricity Electric shock tapped giving 55 V to earth. checked before staring the
Pre-use inspection of tools, cables and hoses to be educate them on the risks
procedures.
plugs,
electric grinders.
Failure of pressurized Air Compressor to be have a valid test certificate Physical inspection to be
equipment Personal Injury and Inspected before entering at site and air carried of all safety guards,
Compressed air Hose Hand injury receiver to be certified by third party. hoses and joint connection
X x X 3 3 9 NO 1 3 3
disconnect / burst Explosion All equipment and tools to be inspected and color before commencing the
equipment Compressed air hose to be secured with whip EHS coverage and
hair and ling jewelry Rotating parts to be protected by suitable guards. during the course of work
used
disposed.
site.
Supervisor to ensure
Trailer details to be recorded and authorization will
loading/ unloading of
be issued by security staff.
equipment’s in sequence to
Access pass to be used to trailer drivers.
Personal Injury prevent any damage to
Site induction training to be provided to personnel
Unauthorized access (collision & equipment and injury to
entering at site.
of vehicle and being struck by personnel hit by the
Gate access pass to be issue upon completion of
equipment moving equipment.
induction training.
Unauthorized entry of x x x vehicle)/ 3 3 9 No Restrict access to 1 3 3
Speed limit and other road safety signage to be
personnel Traffic loading/unloading area.
07 Lifting Work displayed at site.
Poor Site traffic accidents/ Ensure that sufficient room
Site traffic rules to be followed
management Property for vehicle movements.
Flagman to be deployed to control traffic
damage Always ensure to minimize
movement while offloading the equipment.
personnel’s while loading &
Reverse beeper and flashing beacon lights should
reversing.
be fitted to the vehicles and in working condition
while in operation.
Injury to person All lifting equipment (Crane) to be selected as per Pre-planned maintenance to
Mechanical failure of x x Damage to task specification- (Capacity of lifting equipment to 2 3 6 No be ensuring to check the 1 3 3
Incompetent operator Overturn of EGA approved rental companies crane to be hired safety devices.
Parking of crane and equipment Mobile crane must be having 3rd party certification Last Minute Check to be
unstable ground moving trucks Crane to be inspected and sticker to fixed before Continuous supervision and
Lifting equipment Crane operator must have UAE valid license and ensured.
safety devices failure 3rd party competency certificate. Always ensure to minimize
Low Bed trailer and crane must be sited on level personnel’s while loading &
operations.
Lifting accessories All lifting accessories to be 3rd party certified by Last Minute Check to be
Unidentified weight of Property All lifting accessories to be identified with unique Continuous supervision and
lifting items, anchor damage ID, SWL and safety color coding. EHS coverage to be
gravity x x damage Load should be secured and lifting/anchor points 2 3 6 No Unidentified and defective 1 3 3
unsecure load Center of gravity of the load to be identified. removed from site.
Incorrect rigging and 3rd party certified riggers to be appointed. Specific task base training to
sling of lifting items Wight of load lifting accessories should not higher be provided.
Failure of lifting than 75% of the working load acc. to Load Chart TBT to be conducted before
operator error or Loads to be slung correctly by competent riggers Always ensure to minimize
lifting outside the to prevent damage when lifting. personnel’s while loading &
ensured.
possible
vest/helmets color.
control measures.
exceeds 30 KM/H even less if it the cane operator obtained from government
activities.
of waste.
languages.
Unsecured work Site specific induction and specific work training to Lifeline to be installed by
using scaffold (include Unauthorized entry Personal PTW to be obtained before commencing the work. EHS coverage to be ensure
scaffold erection, underneath Injuries Platform based on trestle must be fully boarded during course of work.
10 x x x 3 3 9 No 1 3 3
modification and Insufficient access Property with edge protection included handrail, TBT to be conducted by prior
dismantling) or other and egress Damage intermediate rails and toe boards. to work commencement to
platforms Manual Handling Scaffold to be erected by EGA approved educate the team on risks
Lifting bags to be used to shift the material on top. secured to avoid falling form
Safe and suitable means of access and egress to should be present on the
If scaffold or other means are not applicable, then underneath where work at
competent person.
working at platform.
on scaffolding Platform.
ongoing.
non-slip feet.
the time.
area.
Cable pulling Slip, trip and fall System to be isolated and tag out. switches should be protected
Incompetent from same level Competent & certified electricians to handle all and fully enclosed (and
Fire
Pinch point equipped with Earth Leakage Circuit Breakers Only competent electrician
12 Electrical work Sharp edge of cables x x x x Property damage (ELCB) 3 3 9 No will be allowed to access the 1 3 3
Sharp edge tools Standard Waterproofed industrial plugs and switchboards and panels.
Electric shock
Unsecure cable sockets to be used. All safety devices (ELCB,
connections. Damage to Electric safety signages to be posted on all DBs. Fuses, Earthing) to be
Connecting to live equipment Plug and sockets to be used to eliminate the cable checked on regular basis
immediately. marked
cables.
metal/ surface Ensure all Hot work/welding operations are carried by supervisor to ensure that
Naked flame Injury to out by trained, competent persons area is safe for hot work.
Compressed gas person/cuts & Check equipment before use-specifically electric All Safety devices (flash back
cylinders laceration cables, plugs and any compressed gas equipment arrestor, non-return valves,
Use of power tools hand crushed/ All combustible material to be removed from hot etc.) must be checked before
Hot works (welding, cutting
13 Faulty equipment x x x x bruises work areas if not possible cover with fire blankets. 3 3 9 No using the equipment. 1 3 3
grinding)
Damage electric Ensure any Compressed gas cylinder to be fitted with flash Removal of guards or
produced by welding Personal area-away from heat source as possible. All Defective equipment must
process. Injuries Hot work area to be barricaded and identified by have isolated and tagged to
Trailing cable Eye Damage Adequate cable management to be ensured. from work location
Inadequate PPE problem. Ensure suitable fire extinguisher equipment is EHS coverage to be ensure
generated by welding Heat stress Trained Fire watcher to be deployed during hot Fire extinguisher to be
site-specific PPEs.
use
provided
Handling of personnel Obtain necessary permit to work NDT supervisor must ensure
14 NDT Test 3 3 9 No 1 3 3
radioactive source injury Only 3rd Party Trained and Certified NDT no other activites are goin on
inhalation of fumes radiation injury technician / supervisor must perform this activity under the classified area
during MPI test sickness Radiographers must wear valid TLD film badge proper illumination to be
chemicals on body Warning lights to be installed and the area to be Sign bords to be placed and
in MSDS
Cool and shaded area to be provided for rest. Provide proper ventilation
Cold and fresh water along with Hydrolyte drink to Provide frequent breaks to
be provided. workers
Heat rashes,
Availability of water close to the work area will be Do not expose to direct
High atmospheric Heat cramps,
ensured. sunlight, work from shade
temperature Heat
Individual water thermoses to be provided to Team to be educated on to
15 Working in Summer season High humidity X X Exhaustion 2 3 6 No 1 3 3
contain water oily, heavy and spicy food,
Expose to direct sun Dehydration,
Body-body system to be implemented- alone increase fruit and
light Sunburn
worker not allowed to work in hot climate. Job vegetables, reduce
Heat stroke
rotation to be implemented to reduce the exposure consumption of alcohol, tea,
heat stress.
Injury to A well compacted and level working platform will Segregation of people and
Uncompacted and personnel be provided for all load test operations. plant to be ensure where
Uneven ground Damage to Sufficiently graded and compacted roads and possible.
surface equipment ramps will be provided to allow safe access and Numbers of persons to be
Simultaneous equipment Coordination with all other parties working in same control the equipment
to the area muscle strain, Area to be barricaded to avoid unauthorized vest in vehicle movement
movement body pain Material to be stored, stacked and barricade Adequate supervision and
(bending, reaching, Avoid manual handling, if possible and Forklift during course of work.
PPEs to use.
Unauthorized Barricade the area where the hydrostatic test Ensure that the hydraulic
personnel in load cell activities will go on & provide safety signage. pump is inspected once per
failure (snap) Competent person certified by third party to handle Hydraulic pump exposed to
Over pressure of Injury to All pumps to be certified by 3rd party. be supplied with adequate
system persons Prior to pressuring all pressure scope pipeline antifreeze liquid.
Check for leak or damaged pipe and flange. must be examined for
Prior to applying any load the Test Supervisors, Pre-task/test brief TBT to be
components of the test equipment are as per the team member regarding
masks.
hazard
Electrical Spark / Ensure approved holiday tester to conduct the test.
equipment.
20 Holiday testing X Personal Injury ensure that all precaution adhered to. 2 2 4 Yes
activity.
coveralls.
Epoxies
Application Guidelines
1.0 SCOPE
This document contains general instructions and recommended practices for the
application of the SERVIWRAP cold applied tape coating system. The various coating
grades discussed in this document are used for the corrosion protection of piping, girth
wields, fittings, pipe reconditioning and pipe fabrication for above or below grade
environments. The specifics of where the product can be used are detailed in Section 2.0.
For assistance in coating selection, surface preparation, application or inspection, please
contact a Chase Protective Coatings Representative.
2.0 MATERIALS
2.1 Primer AB – A quick drying adhesive used with all SERVIWRAP tapes except for
M30 and Outerwrap. Can be used for both Temperate and Tropical products.
2.4 Servishield and Outerwrap – Mechanical protection layers that can be added over
the SERVIWRAP tapes. The Servishield is a non-bonded, plastic grid to provide added
impact resistance to below grade coatings. The Outerwrap is a bonded tape to provide
added mechanical and UV protection for above and below grade coatings.
3.2 All products should be stored in dry, cool, well-ventilated conditions, out
of direct sunlight and other major sources of heat. The temperature should not
exceed 30°C.
3.5 Handle cartons with care to avoid damage. Take special care that the
cartons are not dropped.
3.6 All flammable materials should be stored according to local hazard regulations.
AG-COLD-APPLIED-BITUMEN-SERVIWRAP-REV3-Jun16 1
Cold Applied Tapes
Bitumen Adhesive
4.1.2 Hand Tool Cleaning in accordance with SSPC SP2or Swedish Standard St.2
(Scrapers, files and wire brushes),
4.1.3 Power Tool Cleaning in accordance with SSPC SP3 or Swedish Standard
St.3 (Power brushes and grinders),
4.1.5 Near White Metal Blast Cleaning in accordance with SSPC SP10/NACE No. 2
or Swedish Standard Sa. 2 ½,
4.1.6 Power Tool Cleaning to Bare Metal in accordance with SSPC SP11.
Important to note: Clean the grit or shot off the pipe surface after blasting.
4.2 All surface imperfections such as slivers, scabs, weld spatter and other
protrusions shall be removed or made smooth by wire brushing and / or grinding.
4.3 The coating must be applied as soon as practical after cleaning to keep dirt and
rust bloom from re-contaminating the pipe surface.
5.0 APPLICATION
5.1 Primer
5.1.1 Stir the primer well before application. When not in use keep the
containers tightly sealed.
5.1.2 Apply primer by brush, roller or spray in an even coat over the pipe
surface, working well into welds and seams. Ensure surface is free from runs, drips
and bare spots.
5.1.3 The primer coat should not be less than 25 microns Dry Film Thickness
(DFT) and not greater than 50 microns DFT.
5.1.4 The primed pipe surface shall be free from any foreign substances such as
sand, dirt, grease or oil. Any contaminant should be removed and the affected area
re-primed.
AG-COLD-APPLIED-BITUMEN-SERVIWRAP-REV3-Jun16 2
Cold Applied Tapes
Bitumen Adhesive
5.1.5 The primed surface should then be allowed to dry thoroughly before any
attempt is made to apply the SERVIWRAP Tape. The primed surface should remain
E pTape.
clean and dust free immediately before the application of the SERVIWRAP oxies
5.2.2 The tape should be applied spirally with sufficient tension to ensure
consistent conformity to the pipe surface and without any narrowing or wrinkling of
the PVC backing film. The overlap shall be as specified by Chase Protective
Coatings or as defined in the project specification documents or similar
specifications covering the project. The tape overlap will typically either be 55% or
25mm. The roll joins shall be overlapped by a minimum 150mm onto the previously
applied roll-end to ensure adequate continuity of the coating.
5.2.3 A tight and smooth tape coating must be maintained throughout the
application with an absence of any puckers, voids, breaks, wrinkles or folds.
5.3.1 The tape coating adjacent to any fittings or attachments should be feather
trimmed at the edges wherever possible, any existing Tape or coating material not
firmly bonded to the pipe surface should be removed. The fitting should be
thoroughly cleaned in accordance with Section 4.0.
5.3.2 The cleaned, dust free prepared fitting should be primed in accordance
with Section 5.1 and the primer allowed to dry.
5.3.4 SERVIWRAP Tape should be applied over the profiled fitting at a minimum
overlap of 50% using sufficient tension to ensure adequate conformity with the
fitting and profiling compound. A tight and smooth tape coating should be
maintained throughout the application with no puckers, voids, breaks, wrinkles or
folds.
5.4.2 NOTE: All electrical inspection for continuity must be completed prior to
the application of the outerwrap.
AG-COLD-APPLIED-BITUMEN-SERVIWRAP-REV3-Jun16 3
Cold Applied Tapes
Bitumen Adhesive
6.3.1 All tape coated pipes and fittings shall be 100% electrically tested for
continuity of the coating using a suitable holiday detector. The inspection
procedure and voltage levels shall be in accordance with NACE RP-0274. Any
holidays detected shall be repaired in accordance with Section 7.0 of this
document. The repaired areas shall then be holiday detected to confirm that the
repair has been effective.
6.4.1 This test may be carried out at the discretion of the site engineer /
inspector to confirm the coating has bonded to the pipe surface. Note that it is not
a suitable test for fittings.
6.4.2 The test should be carried out approximately 48 hours after the SERVIWRAP
tape has been applied.
6.4.3 Two parallel cuts should be made into the tape approximately 25mm apart,
one end should then be cut free and gently pried from the pipe surface. A spring
balance should then be attached to the free end of the coupon and then the spring
balance pulled away from the pipe surface at an angle of 180o to the pipe surface.
The spring balance should be pulled gently at a steady rate and not jerked.
6.4.4 Note that ambient temperature of the coating on the site should be taken
into account when comparing data generated by this method. It should be noted
that the specification documents issued by specifiers refer to completing the test
under ideal laboratory conditions. An onsite test is used to give an indication that
tape is stuck or not stuck, not a definitive value for adhesion. The site test is
affected by, the rate of pull, the force to pull, the angle of pull, and the pipe
temperature which may be greater than the ambient due to the effects of direct
sunlight.
6.4.5 The area tested in this manner will require repair according to Section 7.0
of this procedure
7.1 Repair should be made to all sections of damaged coating that have been
identified by any method of inspection. All coating materials used in the repair work
shall be of the same specification as the original material specification.
AG-COLD-APPLIED-BITUMEN-SERVIWRAP-REV3-Jun16 4
Cold Applied Tapes
Bitumen Adhesive
7.2 All holiday areas shall be prepared by carefully removing the applied coating that
has been damaged; the area should then be cleaned with a power wire brush to the
surface. Edges of the original coating should be bevelled. Epoxies
7.3 The exposed area shall then be primed as described in Section 4.0 of this
procedure; all exposed metal should be covered by the primer.
7.4 The SERVIWRAP Tape should be spirally (as described in Section 5.0 of this
procedure) applied over the damaged area ensuring that this covers the original coating
by at least 50mm on all sides of the damaged area. Under certain circumstances it may
be necessary to apply a “patch” of tape to the damaged area before the spiral
application of tape is made.
7.5 The repair coating should be applied so that it is tight to the pipe surface without
puckers, voids, wrinkles or breaks. The repair should then be inspected as described in
Section 6.0 of this procedure.
8.2 Booms, hooks, forklifts, skids and all other devices used to move or handle
coated pipe must be padded to prevent damage to the coating. Chains and steel bands
should not be used.
8.3 Pipe should be shipped with sufficient padding or dunnage to adequately protect
the pipe coating.
9.0 BACKFILL
9.1 Backfill should be free of large rocks, stones, scrap, and debris that could
damage the coating.
9.2 Additional Mechanical layers can be used to protect the coating when it is
determined that backfill, handling or installation could be detrimental to the integrity
of the coating.
AG-COLD-APPLIED-BITUMEN-SERVIWRAP-REV3-Jun16 5
Primer AB
Primers
DESCRIPTION Serviwrap Primer AB is used with all Serviwrap tapes except for M30 and
Outerwrap. Primer AB can be used with both Temperate (A) and Tropical (B)
tape systems. Primer AB is a quick drying, liquid adhesive that creates a
permanent bond between the tape and the substrate. Primer AB can be used
for in service temperatures up to 75°C. Primer AB is available as a liquid that
is applied via brush, roller or spray equipment.
A 25-50 micron wet film thickness of Primer AB should be applied and allowed
to dry prior to application of the tape.
SUBSTRATE COMPATIBILITY Steel, Stainless Steel, Ductile Iron, Other Metals, FBE, PE, Plastic Pipe
RECOMMENDED USE Required for most Serviwrap Tapes. May be used for other tapes if the
compatibility is confirmed through testing.
SURFACE PREPARATION The surface to be wrapped should be as clean as possible. Remove metal burrs
and other projections, and all loose matter, any existing coatings, dirt, rust
and foreign debris. Ensure all oil and grease is removed with solvent.
Inspect old pipework or factory coatings and remove any loose coating back to
sound material with wire brushing. Where new or existing steelwork has been
subjected to chemical attack, salt spray, fungi or bacteria other
methods may be used.
TYPICAL DATA
Property Metric US Customary Test Method
Colour Black Black
Dry time <5 minutes at 21°C <5 minutes at 70°F
Flash Point 23°C 73°F Cleveland Open Cup
Service Temperature Range -20°C to +75°C -4°F to +167°F
TDS-Primer AB-REV1-Dec13
Technical Data Sheet
RECOMMENDED USE A high-performance, cold-applied PVC pipe wrap for use on buried and
submarine line pipe. For field welds, fabrications, bends and fittings.
SUBSTRATE COMPATIBILITY Steel, Stainless Steel, Ductile Iron, Other Metals, FBE, PE, Plastic Pipe
SURFACE PREPARATION The surface to be wrapped should be as clean as possible. Remove metal
burrs and other projections, and all loose matter, any existing coatings, dirt,
rust and foreign debris. Ensure all oil and grease is removed with solvent.
Inspect old pipework or factory coatings and remove any loose coating back
to sound material with wire brushing. Where new or existing steelwork has
been subjected to chemical attack, salt spray, fungi or bacteria other
methods may be used.
PRIMER Serviwrap R30 requires a primer to allow for permanent adhesion. Serviwrap
Primer AB should be applied and allowed to dry prior to application of the
tape. See the application guideline for more details.
REFERENCE Serviwrap R30 meets all of the performance criteria listed in the most recent
revision of:
NACE SP0109 (Cold-Applied Laminate Polymeric Tapes)
TDS-R30-REV2-Nov17 1
Typical Data
Water Vapor Permeability 0.36 g/(24h*m2) 0.025 g/(24h*100 in²) ASTM E96
Procedure B
Water Absorption <0.5% <0.5% ASTM D570
Insulation Resistance 1012 Ohms/cm2 1012 Ohms/cm2 ASTM D257
Storage Temperature Range <30°C <86°F
Application Temperature Range
R30A Temperate +5°C to +35°C +41°F to +95°F
R30B Tropical +5°C to +60°C +41°F to +140°F
Service Temperature Range -20°C to +75°C -4°F to +167°F
ORDERING INFORMATION
Dimension Sizes Available
Width 50, 100, 150, 225, 300, 450 mm
Length 15 - 60 m
TDS-R30-REV2-Nov17 2
SAFETY DATA SHEET
according to 1907/2006/EC, Article 31
Page 1/4
Copyright © 2013 ChemSoft Limited. All rights reserved. Print date 2013-03-27
Powered by
Page 2/4
State Solid
Colour Black
Copyright © 2013 ChemSoft Limited. All rights reserved. Print date 2013-03-27
Powered by
Page 3/4
Copyright © 2013 ChemSoft Limited. All rights reserved. Print date 2013-03-27
Powered by
Page 4/4
Copyright © 2013 ChemSoft Limited. All rights reserved. Print date 2013-03-27
Powered by
SAFETY DATA SHEET
according to 1907/2006/EC, Article 31
Page 1/5
Serviwrap Primer AB
Revision 0
Revision date 2012-08-24
Copyright © 2012 ChemSoft Limited. All rights reserved. Print date 2012-10-23
Powered by
Page 2/5
Serviwrap Primer AB
Revision 0
Revision date 2012-08-24
3.2. Mixtures
67/548/EEC / 1999/45/EC
Chemical Name Index No. CAS No. EC No. REACH Registration Conc. Classification
Number (%w/w)
Xylene (Xylene, o-,m-,-p-or mixed 601-022-00-9 1330-20-7 215-535-7 01-2119486136-34 40 - 50% R10 Xn; R20/21 Xi; R38
isomers)
Bitumen 64742-93-4 40 - 50% Xn; R68 R10
Copyright © 2012 ChemSoft Limited. All rights reserved. Print date 2012-10-23
Powered by
Page 3/5
Serviwrap Primer AB
Revision 0
Revision date 2012-08-24
8.2. Exposure controls
Copyright © 2012 ChemSoft Limited. All rights reserved. Print date 2012-10-23
Powered by
Page 4/5
Serviwrap Primer AB
Revision 0
Revision date 2012-08-24
Disposal methods
Can be incinerated if in compliance with local regulations. Contact a licensed waste disposal
company. Dispose of in compliance with all local regulations.
14.1. UN number
UN1263
14.2. UN proper shipping name
PAINT RELATED MATERIAL
14.3. Transport hazard class(es)
ADR/RID 3
Subsidiary risk -
IMDG 3
Subsidiary risk -
IATA 3
Subsidiary risk -
14.4. Packing group
Packing group III
14.5. Environmental hazards
Environmental hazards No
Marine pollutant No
ADR/RID
Hazard ID 33
Tunnel Category (D/E)
IMDG
EmS Code F-E S-E
IATA
Packing Instruction (Cargo) 366
Maximum quantity 220 L
Packing Instruction 355
(Passenger)
Maximum quantity 60 L
Serviwrap Primer AB
Revision 0
Revision date 2012-08-24
Labelling
R68 - Possible risk of irreversible effects.
Safety phrases S36/37 - Wear suitable protective clothing and gloves.
Copyright © 2012 ChemSoft Limited. All rights reserved. Print date 2012-10-23
Powered by