HSE Observation Report

Date: 6-4-2020
Action required /
S. No Location Issues Photograph Rectification Close Out Photo
Recommendations

Contractor needs to ensure


that only trained and Penalty issued to the
Found carpenter violator .and informed to
competent scaffolders the scaffold inspector do
1 Water Tank was installing allowed to erect or not allow to incompetent
scaffold structure dismantle the any person for erecting and
scaffolding structures dismantling of scaffold ..

Contractor must ensure


Observed that the
that all electrical DB’s are
Level-2, A05 electrical DB Insulation provided
2 installed properly with
installed without around the cables .
using cable glands. I cable glands in place

Observed that Contractor need to ensure


Damage power cable
operative is using that plugs should be and tools has been
3 Level-1 A05 power tool without maintained for power tools removed and new cable
plug, inserting cable installed by competent
cables person .
directly in the power
socket
HSE Observation Report

Action required /
S. No Location Issues Photograph Rectification Close Out Photo
Recommendations

Contractor needs to
Found and Observed Water tank access has
ensure that all access and
steel rebar were been clear .material
4 Water Tank egress paths are clear and shifted in designated
found and blocking
free from obstruction storage area .
the access

Contractor needs to ensure


Found and Observed that All damaged power Damage power tools
5 modified tools were tools must be removed and has been removed
Level-1 A05
using on site not to use on site from the site .

Contractor need to
Observed Poor
maintained a good
Housekeeping at all
housekeeping all over the Proper housekeeping
6 A02, A05 over the building
building premises is done .
premises
(A02&A05)

Prepared by:
Mohammed Vajid ali