PROJECT QUALITY ASSURANCE PLAN

CHECK LIST FOR REINFORCEMENT


Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar
ICB No: BR/PD/DCP/ADB/ICB/2016/WD1:LOT-1
EMPLOYER: CONSULTANT: CONTRACTOR:
BANGLADESH RAILWAY SMEC, CANARAIL, SYSTRA, ACE-JV with STRATEGI CREC-TOMA JV
Spec. Item : High Yield Deformed Steel Reinforcement Bar Structure Identification : Pile Cap of A2
Pay. Item : D-7.1 Name of Bridge : BR - 07
Drg No : DCRP/LOT-01/BR-07/RD/A2/14 Location : CH. 03+475

Bar Bending Schedule for Pile Cap


Bar Bar Dia Distribution Spacing No. of No. of Total Unit Wt.
Sl. Description Total No. Shape of Bar Length (m) Weight(kg) Remarks
Mark (mm) Length (mm) (mm) Bar Item length(m) (kg)

Long directional rebar at


1 2-1 25 5525.00 150 38 1 38 1200 1200 11.650 442.700 3.850 1704.400
bottom mesh
9250

Long directional rebar at


2 2-2 25 5525.00 150 38 1 38 9.200 349.600 3.850 1346.000
bottom mesh
9200

Short directional rebar at


3 1-2 25 9225.00 150 63 1 63 1200 1200 7.950 500.850 3.850 1928.300
bottom mesh
5550

Short directional rebar at


4 1-1 25 9225.00 150 63 1 63 5.500 346.500 3.850 1334.100
bottom mesh
5500

Long directional rebar at


5 4-1 20 5525.00 150 38 1 38 1200 1200 11.650 442.700 2.470 1093.500
top mesh
9250
Total Quantity of Reinforcement = 7,406.300 kg
Total Quantity of Reinforcement, A = 7.407 Ton

Conclusion:
INSPECTED BY: CREC-TOMAJV INSPECTED BY: ENGINEER IN CHARGE ON SITE
SIGNATURE: SIGNATURE:
NAME: NAME:
DATE: DATE:
Form No:DCRP/CTJV/Q/QAP01/AP-54-REV.D Page 1 of 3
PROJECT QUALITY ASSURANCE PLAN
CHECK LIST FOR REINFORCEMENT
Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar
ICB No: BR/PD/DCP/ADB/ICB/2016/WD1:LOT-1
EMPLOYER: CONSULTANT: CONTRACTOR:
BANGLADESH RAILWAY SMEC, CANARAIL, SYSTRA, ACE-JV with STRATEGI CREC-TOMA JV
Spec. Item : High Yield Deformed Steel Reinforcement Bar Structure Identification : Pile Cap of A2
Pay. Item : D-7.1 Name of Bridge : BR - 07
Drg No : DCRP/LOT-01/BR-07/RD/A2/14 Location : CH. 03+475

Bar Bending Schedule for Pile Cap


Bar Bar Dia Distribution Spacing No. of No. of Total Unit Wt.
Sl. Description Total No. Shape of Bar Length (m) Weight(kg) Remarks
Mark (mm) Length (mm) (mm) Bar Item length(m) (kg)

Short directional rebar at


6 4-2 20 9225.00 150 63 1 63 1200 1200 7.950 500.850 2.470 1237.100
top mesh
5550

7 Long directional face bar 7 16 10 2 20 1200 1200 11.650 233.000 1.580 368.200
9250

8 Short directional face bar 3 16 10 2 20 5.550 111.000 1.580 175.400


5550
300
Near face vertical bar at
9 5 32 7800.00 150 53 1 53 300 5685 6.285 333.110 6.310 2102.000
stem wall

300
Near face vertical bar at
10 5 16 7800.00 150 53 1 53 300 5685 6.285 333.110 1.580 526.400
stem wall

Total Quantity of Reinforcement = 4,409.100 kg


Total Quantity of Reinforcement, B = 4.410 Ton

Conclusion:
INSPECTED BY: CREC-TOMAJV INSPECTED BY: ENGINEER IN CHARGE ON SITE
SIGNATURE: SIGNATURE:
NAME: NAME:
DATE: DATE:
Form No:DCRP/CTJV/Q/QAP01/AP-54-REV.D Page 2 of 3
PROJECT QUALITY ASSURANCE PLAN
CHECK LIST FOR REINFORCEMENT
Single Line Dual Gauge Railway Track from Dohazari to Cox’s Bazar
ICB No: BR/PD/DCP/ADB/ICB/2016/WD1:LOT-1
EMPLOYER: CONSULTANT: CONTRACTOR:
BANGLADESH RAILWAY SMEC, CANARAIL, SYSTRA, ACE-JV with STRATEGI CREC-TOMA JV
Spec. Item : High Yield Deformed Steel Reinforcement Bar Structure Identification : Pile Cap of A2
Pay. Item : D-7.1 Name of Bridge : BR - 07
Drg No : DCRP/LOT-01/BR-07/RD/A2/14 Location : CH. 03+475

Bar Bending Schedule for Pile Cap


Bar Bar Dia Distribution Spacing No. of No. of Total Unit Wt.
Sl. Description Total No. Shape of Bar Length (m) Weight(kg) Remarks
Mark (mm) Length (mm) (mm) Bar Item length(m) (kg)
300
Far face vertical bar at
11 6 25 7800.00 150 53 1 53 300 5685 6.285 333.110 3.850 1282.500
stem wall

Far face vertical rebar at


12 20 12 4050.00 150 28 2 56 300 300 8.485 475.160 0.888 422.000
wing wall
7885

Far face vertical rebar at


13 20 12 1050.00 150 8 2 16 300 300 7.585 121.360 0.888 107.800
masking wall
6985

Near face vertical rebar


14 21 25 2700.00 150 19 2 38 500 500 6.585 250.230 3.850 963.400
at wing wall
5585

15

Total Quantity of Reinforcement = 2,775.700 kg


Total Quantity of Reinforcement, C = 2.776 Ton
Grand Total for Pile Cap (A+B+C) = 14.593 Ton

Conclusion:
INSPECTED BY: CREC-TOMAJV INSPECTED BY: ENGINEER IN CHARGE ON SITE
SIGNATURE: SIGNATURE:
NAME: NAME:
DATE: DATE:
Form No:DCRP/CTJV/Q/QAP01/AP-54-REV.D Page 3 of 3