Plastering Thickness 12 mm
Plastering Area 100 m2

Plastering Ratio
Cement 1
Sand 6

Sand Bulkage 35 %
Wastage 20 %

Calculation

Volume of Mortar 1.2 m3


Volume of Mortar with bulkage
&wastage 1.86 m3

Required Cement 7.66 bags


Sand Required 1.59 m3
Rubble Work in 1:5 Cemnt Sand Mortar

Width of Rubble 0.45 m


Height of Rubble 0.6 m
Length of Rubble 50 m

Volume of Rubble 13.5 m3

Required Rubble 17.55 m3

Required cement 23.85 bags

Required Sand 1.50 m3


Height of Block 0.065 m
Length of Block 0.215 m
Width of Block 0.1025 m
Thickenes of Mortar 0.01 m
Total Area of Block Work 90 m2
Wastage of Blocks 5%

Cemnet Sand Ratio


Cement 1
Sand 5

Area of 4 Blocks (2 row & 2 Column) 0.0675 m2

No of Blocks per m2 59.26 Nr


No fo Block with Wastage per m2 62.22 Nr
No of Blocks 5600.0 Nr
Volume of Mortar 0.0012 m3
Total Required Volume 1.58533333333 m3

Assume that for 1 Cu of dry volume required 1.33 Cu of cement and 1.33 Cu of sand
of wet volume. Which means to create a 1 Cu of a dry mortar volume is required
1.66 Cu of a wet mortar volume.

Total Volume of Sand 2.19 m3

Total No. of Cement 12.64 bags


Cement 1
Sand 2
Aggregate 4
W/C Ratio 0.55
Density of Sand 1600 kg/m3
Density of Aggregate 1450 kg/m3
Concrete Density 2400 kg/m3

Required Cement 0.03448276 m3


Required Sand 0.06896552 m3
Required Aggregate 0.13793103 m3

Required Cement 50 kg
Required Sand 110.344828 kg
Required Aggregate 200 kg
Water 27.5 kg

Weight of Concrete from 1 Bag Cement 387.844828 kg


Volume of Concrete from 1 Bag Cement 0.16160201 m3

No of Cement per m3 Concrete 6.18804179 bags 5352.65615


Volume of Sand per m3 Concrete 0.4267615 m3 1910.12216
Volume of Aggregate per m3 Concrete 0.85352301 m3 4222.37529
Water 170.171149 l
11485.1536