Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
-----Original Message-----
From: Buddhika Patikiri [mailto:Buddhika.Patikiri@nakheel.com]
Sent: 28 April 2008 12:40
To: INDRAWANSA SAMARATUN
Subject: Clarification
Is there any requirement of giving notices for any variations by the contractor? Also could we
reject any variation upon not providing such notices?
Please clarify this pursuant to clause 52.2(paragraph two) of FIDIC Conditions of Contract
-----Original Message-----
From: qs_dubai@yahoogroups.com [mailto:qs_dubai@yahoogroups.com] On Behalf Of rajesh
kumar
Sent: 15 April 2008 16:48
To: qsindiagroup
Subject: [qs_dubai] need small help.....clarification
sir
Project : Infrastructure (Pipe Laying & Roadworks)
Division: Storm water Drainage
according to CESMM3 for all other pipeworks like water line, sewerage, Irrigation ....the
rates for pipe laying includes excavation, pipelaying, bedding, backfilling, all
fittings(reducer, bend, tee,.....) etc,...
but especially for storm water drainage, Tee connection will come only where gully &
Inspection port connecting with main perforated pipe
whether rate for TEE is included in pipelaying cost or with the cost for installation of
Inspection port & gully ???????????????????????
kindly reply as soon as possible
Tanaking you in anticipation
R.Rajeshkumar
-----Original Message-----
From: anjalia@thermoproj.ae [mailto:anjalia@thermoproj.ae]
Sent: 30 April 2008 16:39
To: Prof. Sam
Subject: DELETION OF LIGHT FITTINGS
Hi Dr.Sam,
Thanking you
Regards
Anjali Anand
Sr. Quantity Surveyor
-----Original Message-----
From: mohamed salah [mailto:mohamed_sal67@yahoo.com]
Sent: 12 April 2008 10:57
To: sam99@emirates.net.ae
Subject: Nominated subcontractor
-----Original Message-----
From: ShibuKJohn@wadeadams.com [mailto:ShibuKJohn@wadeadams.com]
Sent: 31 March 2008 15:10
To: Prof. Sam
Subject: question
Dear Dr.sam
I would request you to advice me on following situation:
Question 1.
The contractor has a valid claim for extension of time and additional cost due to
additional works instructed by the engineer in one of our RTA contract. The client has
agreed in principle for the extension of time and cost, but nothing in writing. Since the
engineer cannot monitor the progress based on the approved clause 14 programme, he
keeps on requesting for a revised programme incorporating all the additional works.
Is it advisable to submit a revised programme before finalising the claims?
Question 2.
If the consultant did not provide the detailed specification of irrigation works for tender
and as an experienced contractor we priced it . But during execution stage we are in need
of it for the material submittals and other references, can i ask for it officially ?
How can i defend myself if any variation arises due to the new specification ?
regards
----- Original Message -----
From: Lourdes Beato
To: Prof Sam <sam99@emirates.net.ae>
Date: Tue, 15 Apr 2008 00:37:40 -0700 (PDT)
Subject: [No Subject]
Dear Prof. Sam,
If No, why?
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Quantity Surveyor and Registered Arbitrator / Expert
Australian Inst.of Qty.Surveyors-Middle East Representative
PO Box 23461, Dubai, UAE. T +971504588949 F +97143378668
Kind regards,
Lourdes